Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

N.J.Thomas And Co vs The Principal
2021 Latest Caselaw 3468 Ker

Citation : 2021 Latest Caselaw 3468 Ker
Judgement Date : 1 February, 2021

Kerala High Court
N.J.Thomas And Co vs The Principal on 1 February, 2021
WP(C).No.23073 OF 2020(H)
                                  1

            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

                 THE HONOURABLE SMT. JUSTICE P.V.ASHA

    MONDAY, THE 01ST DAY OF FEBRUARY 2021 / 12TH MAGHA,1942

                      WP(C).No.23073 OF 2020(H)

PETITIONER/S:
                N.J.THOMAS AND CO.
                MATTEETHARA COLONY, Y.W.C.A. LANE, BAKER JUNCTION,
                KOTTAYAM-686 001, REPRESENTED BY THE MANAGING
                PARTNER, SIBY THOMAS.

                BY ADVS.
                SRI.K.L.VARGHESE (SR.)
                SMT.SANTHA VARGHESE
                SRI.RAHUL VARGHESE
                SRI.RANJITH VARGHESE
RESPONDENT/S:

      1         THE PRINCIPAL,
                GOVERNMENT MEDICAL COLLEGE, THRISSUR-680 596.

      2         THE HLL LIFECARE LIMITED
                INFRASTRUCTURE DEVELOPMENT DIVISION, HLL BHAVAN,
                GOLDEN JUBILEE BLOCK, POOJAPPURA P.O.,
                THIRUVANANTHAPURAM-695 012.

      3         THE ENGINEER-IN-CHARGE
                PROJECT ENGINEER (CIVIL), INFRATECH SERVICE LTD.,
                GOLDEN JUBILEE BLOCK, POOJAPPURA,
                THIRUVANANTHAPURAM-695 012.

      4         THE ADDITIONAL CHIEF SECRETARY
                HEALTH AND FAMILY WELFARE DEPARTMENT, GOVT.
                SECRETARIAT BUILDING, THIRUVANANTHAPURAM-695 001.

                R1, R4 BY GOVERNMENT PLEADER
                R2-3 BY ADV. SRI.K.JAJU BABU (SR.)
                R2-3 BY ADV. SMT.M.U.VIJAYALAKSHMI
                R2-3 BY ADV. KUM.T.S.ATHIRA

OTHER PRESENT:

                SRI.K.V.MANOJ KUMAR, SRGP

     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 22-
01-2021, THE COURT ON 01-02-2021 DELIVERED THE FOLLOWING:
 W.P.(C) No.23073 of 2020



                               P.V.ASHA, J.
                    ---------------------------------
                         W.P.(C) No.23073 of 2020
                   ----------------------------------
                Dated this the 01st day of February, 2021


                                      JUDGMENT

Petitioner was awarded the work of "Setting up of

emergency and critical care department at Govt.Medical

College, Thrissur -Construction of Triage Building" as per

Ext.P1 letter of acceptance issued by the 2nd respondent on

24.10.2014. The contract value was Rs.5,47,55,590/- . It is

a deposit work. 2nd respondent, is the consultancy appointed

by the 1st respondent. The 1st and 2nd respondent have

entered into an agreement relating to the said consultancy

work. Pursuant to Ext P1, petitioner and 2 nd respondent

entered into an agreement on 6.11.2014, fixing the time

for completion of work as 11 months from the date of letter

of acceptance. The site was handed over to petitioner on

17.11.2014. As per clause 7 of the agreement, the 2 nd

respondent was to make available the site fixing the plinth

level of the building and for timely supply of structural

and architectural drawing and approval of rates for extra

items and brands of materials to be purchased and consumed; W.P.(C) No.23073 of 2020

the 2nd respondent has to prepare and submit the running

account bills before the 1st respondent within 10 working

days of presentation of the bill for payment to the

contractor; in the event of failure on the part of the

contractor to submit the bill, the Engineer in charge has

to prepare such bills and to make the payment to the

contractor; bills were to be submitted along with the

recorded measurement before the Engineer in charge. It is

stated that the bills were never paid in time, which

affected the progress of the work. The petitioner complains

that payment was never being made within 10 working days

right from 4.6.2015 onwards; payment towards the RA bills

from 18.09.2017 onwards were being made in 2018, 2019, etc;

the delay in making payment affected the completion of the

work; from the stipulated 11 months, when it got delayed to

more than 3 years, petitioner had to stop the work at a

time when 90% work was completed; the remaining 10% work

like electrical, air conditioning, providing medical gas

line, fire fighting etc were to be done, through

specialized agencies; though the work was resumed in

August, 2018, specialized agencies arranged by it were not

willing to undertake the work for the old rates of 2014.

Relying on Ext.P2 letter dated17.2.2018 of the Chief W.P.(C) No.23073 of 2020

Engineer, petitioner submits that the delay in payment for

more than one year is admitted by the 2nd respondent. It is

stated that petitioner had as per in Ext P3 letter dated

20.2.2018 addressed the 2nd respondent pointing out the

delay in completion of work because of the physical

hindrances occurred in carrying out the work as well as

denial of timely payment of bills. It had therefore

requested for enhancement of rate by 50%, informing their

preparedness to foreclose the contract on payment of the

arrears due to them including refund of security

deposit/retention amount and all the bills along with

interest, after assessment of unassured items of work. The

2nd respondent, through its Chief Engineer, thereupon, as

per Ext.P4 e-mail dated 28.02.2018 assured to bring the

matter to the notice of the 1 st respondent. Thereafter a

meeting was convened in the Medical College, Trissur on

22.06.2018 in which the Principal had, as per Ext.P5

minutes, assured to take up the claim for 50% escalation on

the balance 10% work with the DME/Government; however in

Ext.P6 letter dated 7.1.2019 though the Principal had

informed the Government about the demand made by petitioner

and the assurance made by the Principal, it was stated

that the work relating to the triage block was not yet W.P.(C) No.23073 of 2020

started; the Principal had only requested to give necessary

instructions to complete the work. Petitioner submits that

no steps were taken for enhancement of the rate or for any

payment, even after the petitioner submitted Ext.P7

representation to the 3rd respondent on 6.02.2019, Ext.P8

letter to 2nd respondent on 05.06.2019, pointing out the

difficulties faced by it in meeting the expenditure towards

the workers and subcontractors on account of the delay in

payment of bills as well as the refusal to enhance the

rate, the 2nd respondent in Ext P10 letter informed that

they can only act in accordance with the terms of

agreement. In the meanwhile petitioner had also addressed

the Additional Chief Secretary as per Ext.P9 letter dated

20.01.2020 informing that the work had to be stopped for

more than one year due to shortage of funds and refusal to

enhance the rates and requesting for taking immediate steps

to enable the petitioner to resume the work. It is stated

that petitioner had by Exts.P11 and P12 letters intimated

its readiness to complete the balance civil work on

condition that the contract shall be treated as closed

after completion of the civil work and delay in completion

of the work till that time shall be granted without any

penalty and completion of the work shall be recorded and W.P.(C) No.23073 of 2020

security deposit of the work shall be released. However,

by Ext.P13 letter dt.28.7.2020, the DGM informed the

petitioner that they would get the remaining work done by

alternate arrangements, at the risk and cost of the

petitioner and proceedings for the same are in process.

It is stated that even though an on-line meeting was

thereafter held on 30.7.2020 when the petitioner had

offered to complete the balance civil work at the old rate

on condition that the specialised works had to be carried

out without any risk, cost and liability, the 2 nd

respondent has issued Ext.P14 show cause notice on

25.09.2020 proposing termination of work at the risk and

cost of the petitioner and rearrangement of the work. It

is stated that the petitioner has kept a lot of materials

required for the balance work inside the building for which

the petitioner has to incur running expenditure for keeping

watch and ward. Petitioner had thereupon as per Ext.P15

letter dt.10.10.2020, requested for a joint measurement for

the final bill towards the upto date work done before

engaging any other agency. The Writ Petition is filed at

that stage stating that termination of contract as

proposed, at a time when almost 93% of the work is

completed and non completion was on account of the breach W.P.(C) No.23073 of 2020

of contract committed by the 2nd respondent, denying

enhancement even after 6 years of commencement of the work,

is unreasonable. Petitioner has sought for a direction to

the 4th respondent to consider Ext.P6 explanation on

merits. Alternatively it seeks a direction to the

respondents to allow closure of contract without risk

liability and settlement of account after proper

measurements and inventory of materials collected and

available at the stores.

2. 1st respondent has in its counter affidavit stated

that "Commencement of Emergency and Critical Care

Department in Government Medical College, Trichur" is

implemented under a centrally sponsored scheme, at a total

cost of Rs.1459.03 lakhs. The construction of Triage

building was entrusted to the 2nd respondent - M/s.HLL

Lifecare Ltd. as per Ext.R1(a) agreement executed between

the Principal Govt.Medical College, Trichur and the 2nd

respondent on 13.09.2013 fixing the total period of

consultancy as 18 months from the date of execution of the

agreement. It is stated that the petitioner is not a party

to Ext R1(a) agreement between respondents 1 and 2. HLL

awarded the work of the second phase to the petitioner for

Rs.5,47,55,5907/-. A sum of Rs.4,44,82,062/- has been W.P.(C) No.23073 of 2020

released to the 2nd respondent on the basis of the

recommendation of the technical committee (scrutiny of

works/claims in respect of works entrusted to accredited

agencies in DME) against whole bills submitted by the 2 nd

respondent. It is stated that even after 6 years of the

date of execution of agreement with HLL, the works

including construction of corridor, erection of air

conditioners, painting, cleaning etc are yet to be

completed. Several meetings were held and communications

were issued in order to sort out the issues relating to the

completion of the construction at various levels at the

initiative of the Principal of the Medical College as the

completion of the construction is an important and urgent

necessity for the patients admitted in the hospital. It is

stated that the reluctance on the part of the petitioner to

complete the work as per the terms and conditions of the

agreement between the petitioner and 2nd respondent has

resulted in stoppage of the work and denial of an important

life style to the public. Furnishing the time line of the

project undertaken by the petitioner, it is stated that the

work was not completed within the stipulated time; in the

meeting held on 22.6.2018 at the Medical College, Trissur

the petitioner demanded 50% hike on the balance 10% of the W.P.(C) No.23073 of 2020

work; the Principal had informed that the matter would be

taken up with the DME for favourable consideration provided

the work was restarted; but the petitioner did not restart

the work; on 12.09.2018 directions were issued to the 2 nd

respondent to take immediate action for completing the

work. In the meeting convened by the DME on 21.08.2019 the

2nd respondent agreed that the work would be completed

within one month on payment of a sum of Rs.18,13,195.73 to

the contractor directly; though the said amount was

transferred to the contractor directly on 30.11.2019, the

work was not restarted; even after several letters were

issued from January 2019 onwards to the Government, DME,

the 2nd respondent, the District Collector etc requesting

for directions to petitioner and the 2nd respondent to

complete the work, the work is yet to be completed. It is

stated that a bill received from HLL on 15.06.2019 for a

sum of Rs.18,13,195.73 was forwarded to the technical

committee on 28.6.2019 for sanction; in another meeting

held on 21.8.2019 in the Directorate of Medical Education

with the 2nd respondent and the petitioner though a

settlement was arrived at for completion of the work within

a time frame and the amount due to the petitioner was

transferred to it as per the decision in the meeting and W.P.(C) No.23073 of 2020

another meeting was held in the Chamber of the District

Collector on 14.2.2020 with the petitioner and the 2nd

respondent, the work is not restarted despite further

letters issued by Government as well as the DME in

September and October 2020. It is stated that the 1 st

respondent's assurance to take up the demand of petitioner

for 50% hike for the balance 10% of the work, in the

meeting held in the Government Medical College on

22.06.2018, was on condition that the petitioner restarted

the work. It is stated that despite the assurances made by

the 2nd respondent and the payment made directly to the

contractor, the contractor withdrew from its offer. It is

stated that the 1st respondent has never agreed for revision

of rates of the work and that the petitioner cannot have

any valid claim for enhancement, on the basis of an

internal correspondence between the 1st respondent and the

Government to sort out the long delayed issue.

3. The 2nd respondent has filed a counter affidavit

stating that the project was entrusted to it as a deposit

work on cost-plus consultancy charge basis and under clause

(n) of Ext R2(a) agreement between the 1st respondent and

the 2nd respondent, the consultant is to prepare the bill

of quantities for various works, certify the bills of the W.P.(C) No.23073 of 2020

contractors/suppliers, and make timely payments to the

contractors/suppliers from the amount deposited with the

consultant by the client. It is stated that the 2 nd

respondent, after inviting tenders issued letter of award

to the petitioner on 24.10.2014 fixing the period of

completion of work as 11 months. Thereafter Ext R2(c)

agreement was entered into between petitioner and 2nd

respondent on 06.11.2014, as per the Ext R2(C) guidelines

issued by the Central Vigilance Commission. It is stated

that the petitioner had started preconstructional

activities at site on 17.11.2014, the date of handing over

itself and had not raised any objection relating to any

hindrance in the site at the time of handing over. It is

stated that the petitioner started raising running bills

from 4.6.2015 onwards; being a consultant, the 2nd

respondent is solely dependent on the 1st respondent for

payment; as 1st respondent did not release funds, the 2nd

respondent had even made advance payments to the

petitioner, in order to avoid delay. It is stated that as

per Ext.R2(b) Government order dt.3.8.2018 the Government

ordered that funds could be released by the client for all

the projects of Government of Kerala directly to the

contractors based on the recommendation of the consultant W.P.(C) No.23073 of 2020

and therefore the role of the 2 nd respondent was limited to

supervision of bills and certification of bills only in the

Government of Kerala project and therefore payments were

made to the contractor subsequent to the said G.O directly

by the client. It is stated that the petitioner stopped

the work stating delay in payment and demanding enhancement

of rates on balance work; whereas the 2nd respondent is not

vested with project fund for releasing payment to the

petitioner. After the Government issued Ext R2(b) order, 1st

respondent started making payments directly to the

petitioner. When an agreement is executed between the

petitioner and the 2nd respondent, both of them can

only act in terms of the agreement; and the rate of

enhancement other than for extra/substituted items is not

included in the agreement. It is stated that as per the

schedule to the agreement, escalation is not applicable to

the project. It is stated that in view of clause 10B(iv)

of Ext R2(c) agreement dated 6.11.2014 [Ext.R2(c)] and

R2(d) guidelines of Central Vigilance Commission, interest

is charged as per the terms of the contract agreement. The

2nd respondent has furnished the details regarding project

fund received by it from 1st respondent from time to time

and payments made by it to petitioner. It is stated that W.P.(C) No.23073 of 2020

there is no provision for enhancement for 50% under the

terms of the contract or as per CPWD conditions of contract

and the petitioner cannot unilaterally claim any

enhancement. The 2nd respondent has stated that it does not

have any objection for undertaking measurement of the work

at the site; however it is stated that it would not be

possible to measure any item which is not required for the

work. It is stated that 2nd respondent had not made any

assurances for enhancement of rates; the assurance to take

steps for enhancement as per minutes of the meeting was

conditional on restarting of the work. It is their further

case that extension of time can be granted only if the

delay is not on the part of the contractor. The 2 nd

respondent has stated that they can only recommend the

payment to be released by the 1st respondent and the payment

is to be released by the 1 st respondent. It is further

stated that while finalising the extension of time,

eligible extension and all bonafide hindrances if existing

would be considered including delay in payment. Pointing

out Ext.R2(e) proposal dt.01.08.2020 it is stated that it

is for the 1st respondent to approve the proposal for

carrying out the additional work and for its timely

payment. The 2nd respondent has stated that the work W.P.(C) No.23073 of 2020

completed even now is only 90% and majority of mechanical

electrical plumbing (MEP) works are still pending and the

contractor did not show any positive response to complete

the work even after show cause notice was issued.

Producing Ext.R2(f) to (h) it is stated that the 2 nd

respondent has always been requesting the Government, the

DME as well as the Principal to expedite the release of

project fund for making payment and it was only on account

of the continuous follow up action of the 2 nd respondent

that the 1st respondent has released payment in November,

2019. It is further stated that even on 13.05.2020 the 2nd

respondent had as per Ext.R2(i) letter addressed the

financing officer of the DME to expedite the payment due to

the petitioner. It is stated that in case respondents 1

and 4 agree with the proposal submitted by the 2 nd

respondent, the work could be completed, provided there is

a written confirmation regarding the prompt payment for the

balance work. However it is stated that petitioner did not

restart the work even after the payment was released in

November, 2019 which lead to the present situation and the

2nd respondent had to issue notice to the petitioner in

accordance with clause 14 of the agreement.

4. The petitioner has filed a reply affidavit to the W.P.(C) No.23073 of 2020

counter affidavit of the 1st respondent. It is stated that

the estimate of the work was prepared on Delhi Schedule of

rates (DSR 2013) and the work was awarded on 24.10.2014;

the cost was 5,47,55590/- after deduction of Rs.7,19,525/-

from the original quoted value. Pointing out Exts.P3, P5,

P7 and P9 it is stated that petitioner had to encounter

various hindrances on account of delay in finalising

drawing, delay in setting out site, delay in approval for

various items including extra items, inordinate delay in

payment despite clause 7 of Ext R2(c) agreement providing

for payment on 10th day of presentation of the bill. It is

stated that more than 90% of the work was completed within

3 years and total work carried out including cost for

supply of materials would come to 93% if proper measurement

is taken. Pointing out Ext.P2 it is stated that the 2 nd

respondent has admitted that the work had to be stopped for

nearly one year due to shortage of fund and that there was

delay in payment by the 2nd respondent also from the project

fund deposited by the Government. According to petitioner,

the work was awarded as a deposit work and petitioner is

not made aware of any orders like Ext R2(b) based on which

payment is to be made by Government contrary to the terms

of the agreement, based on which the 2nd respondent has to W.P.(C) No.23073 of 2020

ensure payment of running bills within 10 days. It is

stated that even as on 27.10.2017 only 10% of the work

remained to be completed and for that work petitioner had

placed orders for various items including aluminium bars of

different sizes as agreed by the 1st respondent in Ext.P6

and and that 25% of the said work had been completed and

the remaining works were only relating to air conditioning

and the works could have been completed in all respects

within the stipulated time in accordance with the

agreement, in case the rates were enhanced. It is stated

that the work which was restarted in September 2018 had to

be stopped since payment was not made towards RA7 bill.

It is stated that there was a delay of 461 days for its

payment and that too was made in 4 installments. Pointing

out Ext.R2(f) dated 26.7.2019 of the Deputy General

Manager, it is stated that the 2nd respondent has admitted

that bills were kept pending because of paucity of funds.

It is stated that the work of the connection corridor has

to be undertaken by specialised agencies on completion of

subject work using structural steel. It is stated that

Ext.R2(h) letter also would show the request made by

petitioner for withdrawal from the work; it is stated that

though a draft tri-partite agreement for connection W.P.(C) No.23073 of 2020

corridor work was submitted on 21.8.2019, it was not

approved. It is further stated that even if the work is

proceeded, there is no chance for any payment towards the

work done or for escalation of the rate. Therefore, the

petitioner seeks a direction to the 1st respondent for

foreclosure of the contract without risk liability on

either side and settlement of the petitioner's account

after proper measurements of the work done and to grant an

inventory of the materials collected and available at the

site.

5. Heard Sri K.L.Varghese, the learned Senior Counsel

for the petitioner, Shri. Jaju Babu, the learned Senior

Counsel for the 2nd respondent and Smt.Princiy Xavier the

learned G.P for the 1st respondent.

6. It is an admitted fact that the work awarded to

petitioner on 24.10.2014 for which Ext R2(c) agreement was

executed between petitioner and 2nd respondent is not yet

over even after the expiry of more than 6 years. The

purpose of the construction undertaken by the petitioner

through the 2nd respondent, who is the consultant of 1st

respondent/Government is for setting up of emergency

critical care Department in Government Medical College,

Trissur. The delay in completion of the work affects the W.P.(C) No.23073 of 2020

general public who are the beneficiaries of the project,

when the number of patients continue to rise day by day.

7. It cannot be disputed that the terms and conditions

in the agreements are to be respected by the parties to the

agreements. It is also seen that 90% of the work was

already completed within a period of 3 years; though the

agreement was executed stipulating the period of completion

as 11 months, it is seen that extension of time was granted

without imposing any penalty from time to time. According

to the petitioner, the delay in completion of the said 90%

of the work occurred on account of the hindrances at the

site coupled with delay in payment despite the fact that he

had undertaken a deposit work. It is an admitted fact by

all the parties that 90% of the work was already completed

atleast on 22.6.2018 as evident from Ext R1(a) minutes of

the meeting in which the discussion was in respect of the

remaining 10% of the work. Ext.R2(g) also would show that

as on 27.10.2017 itself 90% of work was completed. While

there are provisions for completion of work, provisions are

available for payment towards bills also within the

stipulated time; the various documents produced by the

petitioners as well as respondents would show that there

was delay in payment also; the consultant's version is that W.P.(C) No.23073 of 2020

payment could be made only if funds are made available by

the 1st respondent; however payment is seen made directly to

the contractor from 30.11.2019 onwards, which according to

the 2nd respondent is based on Ext R2(b) order dated

03.08.2018. It is seen that payment was being made only on

recommendation of technical committee. It would appear that

there was delay in payment in contravention of the terms of

the agreements in between the parties. The refusal to

enhance the rate is stated to be absence of a provision in

the agreement. It is seen that the rate fixed for

completing the work was the one which prevailed at the time

of execution of the agreement which was in 2014. When the

petitioner points out that the delay occurred at the

instance of the respondents with respect to the hindrances

at the site as well as the payment, it would appear that

there had been breach of terms of the contract at the

instance of either of the parties to the respective

contracts.

8. According to the petitioner, the work which remains

to be completed is the work to be done through specialized

agencies and the materials are already procured and

stocked. The petitioner has been requesting for foreclosure

of the agreement. One of the grievances raised by the W.P.(C) No.23073 of 2020

petitioner is that measurement of the work is not being

undertaken. The 2nd respondent has stated that it does not

have any objection for the same.

9. Though the 1st respondent is not a party to the

agreement entered into between the petitioner and 2nd

respondent and the petitioner is not a party to the

agreement between respondents 1 and 2 and normally the

grievance of the contracting parties are to be resolved in

tune with the provisions in agreement, it is seen that

several meetings were convened with all the parties in

order to sort out the issue.

10. In the circumstances of the case, taking note of

the fact that the beneficiaries of the project are the

sufferers on account of all these breaches, I deem it

appropriate to direct that a final decision pursuant to

Ext.P13 show cause notice shall be taken after a meeting is

convened by the Government and Director of Medical

Education with the respondents 1 and 2 and the petitioner

and giving sufficient opportunity of hearing to petitioner

taking note of the contentions of all the parties. The

question regarding the materials procured by the petitioner

for the balance work shall also be decided in the said

meeting.

W.P.(C) No.23073 of 2020

The Writ Petition is disposed of accordingly.

Sd/-

                                          P.V.ASHA

rkc                                        JUDGE
 WP(C).No.23073 OF 2020(H)




                            APPENDIX
PETITIONER'S/S EXHIBITS:

EXHIBIT P1           TRUE COPY OF THE LETTER OF ACCEPTANCE DATED

24.10.2014 ISSUED BY TEH 2ND RESPONDENT TO THE PETITIONER.

EXHIBIT P2 TRUE COPY OF THE LETTER DATED 17.2.2018 ISSUED BY THE CHIEF ENGINEER OF THE 2ND RESPONDENT TO THE PETITIONER.

EXHIBIT P3 TRUE COPY OF LETTER NO.NJT/111/HLL/TCR DATED 20.2.2018 ISSUED BY THE PETITIONER TO THE CHIEF ENGINEER OF THE 2ND RESPONDENT WITH COPY TO THE DEPUTY VICE PRESIDENT (TECHNICAL) AND PROJECT MANAGER OF THE 2ND RESPONDENT.

EXHIBIT P4 TRUE COPY OF THE E-MAIL DATED 28.2.2018 SENT BY THE CHIEF ENGINEER OF THE 2ND RESPONDENT TO THE PETITIONER.

EXHIBIT P5 TRUE COPY OF THE MINUTES OF MEETING DATED 22.6.2018 CONVENED AT THE CHAMBER OF PRINCIPAL, GMCTCR.

EXHIBIT P6 TRUE COPY OF THE LETTER DATED 7.1.2019 ISSUED BY THE IST RESPONDENT-PRINCIPAL TO THE 4TH RESPONDENT-ADDITIONAL CHIEF SECRETARY, HEALTH AND FAMILY WELFARE DEPARTMENT.

EXHIBIT P7 TRUE COPY OF THE LETTER DATED 6.2.2019 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT WITH COPY TO OTHER OFFICERS AS ALSO PRINCIPAL OF THE MEDICAL COLLEGE.

EXHIBIT P8 TRUE COPY OF THE LETTER DATED 5.6.2019 ISSUED BY THE PETITIONER TO THE DEPUTY GENERAL MANAGER OF THE 2ND RESPONDENT.

EXHIBIT P9 TRUE COPY OF THE LETTER DATED 20.1.2020 ISSUED BY THE PETITIONER TO THE 4TH RESPONDENT-ADDITIONAL CHIEF SECRETARY, HEALTH & FAMILY WELFARE DEPARTMENT.

EXHIBIT P10 TRUE COPY OF THE LETTER DATED 12.3.2020 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.

WP(C).No.23073 OF 2020(H)

EXHIBIT P11 TRUE COPY OF THE LETTER DATED 4.7.2020 ISSUED BY THE PETITIONER TO THE DGM(IDD) OF THE 2ND RESPONDENT.

EXHIBIT P12 TRUE COPY OF THE LETTER DATED 27.7.2020 ISSUED BY THE PETITIONER TO THE DGM(IDD) OF THE 2ND RESPONDENT.

EXHIBIT P13 TRUE COPY OF THE LETTER DATED 28.7.2020 ISSUED BY THE PETITIONER TO THE DGM(IDD) OF THE 2ND RESPONDENT.

EXHIBIT P14 TRUE COPY OF THE SHOW CAUSE NOTICE DATED 25.9.2020 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.

EXHIBIT P15 TRUE COPY OF THE LETTER DATED 10.10.2020 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT.

RESPONDENT'S/S EXHIBITS:

EXHIBIT R2(A)        TRUE COPY OF THE CONTRACT AGREEMENT DATED
                     13.9.2013   EXECUTED    BETWEEN   THE 2ND
                     RESPONDENT AND THE 1ST RESPONDENT

EXHIBIT R2(B)        TRUE COPY OF THE GO(P) NO.118/2018/FIN
                     DATED 3.8.2018 ISSUED BY THE GOVERNMENT

EXHIBIT R2(C)        TRUE COPY OF THE     RELEVANT    EXTRACT   OF
                     CONTRACT AGREEMENT

EXHIBIT R2(D)        TRUE COPY OF THE OFFICE MEMORANDUM/CIRCULAR

DATED 10.4.2007 VIDE NO 4CC-1/CTE/2 ISSUED BY THE GOVERNMENT

EXHIBIT R2(E) TRUE COPY OF THE PROPOSAL NO HLL/TRIAGE-

TSR/DGM/2020-21/665 DATED 1.8.2020 SUBMITTED BY THE 2ND RESPONDENT TO THE 1ST RESPONDENT

EXHIBIT R2(F) TRUE COPY OF THE LETTER NO HLL/TRIAGE-

                     TSR/DGM/2019-20/1163     DATED    26.7.2019
                     SUBMITTED BY THE 2ND RESPONDENT TO THE
                     DIRECTOR, DME, THIRUVANANTHAPURAM

EXHIBIT R2(G)        TRUE   COPY  OF   THE  LETTER  HLL/TRIAGE-
                     TSR/DGM/2019-20/1163    DATED   27.10.2017

SUBMITTED BY THE 2ND RESPONDENT TO THE 1ST RESPONDENT

EXHIBIT R2(H) TRUE COPY OF THE LETTER NO WP(C).No.23073 OF 2020(H)

HLL/ID/TRIAGE/DGM/2019-20/2211 DATED 12.11.2019 SUBMITTED THE 2ND RESPONDENT TO THE 1ST RESPONDENT

EXHIBIT R2(I) TRUE COPY OF THE LETTER NO HLL/ID/TRAIGE/DGM/2020-21/37 DATED 13.5.2020 SUBMITTED BY THE 2ND RESPONDENT TO THE SENIOR FINANCE OFFICER, DME, THIRUVANANTHAPURAM

EXHIBIT R2(J) TRUE COPY OF THE LETTER NO HLL/ID/TRAIGE-

                     TSR/DGM/2019-20/2819   DATED     8.1.2020
                     SUBMITTED BY THE 2ND RESPONDENT TO THE
                     PETITIONER

EXHIBIT R1(a):       TRUE   COPY   OF   THE   AGREEMENT   DATED
                     13/09/2013.

EXHIBIT R1(b):       TRUE COPY OF THE MINUTES OF THE MEETING
                     HELD ON 22/06/2018.

EXHIBIT R1(c):       TRUE COPY OF THE MINUTES OF THE MEETING
                     HELD ON 25/11/2019.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter