Citation : 2021 Latest Caselaw 17327 Ker
Judgement Date : 25 August, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE MOHAMMED NIAS C.P.
WEDNESDAY, THE 25TH DAY OF AUGUST 2021 / 3RD BHADRA, 1943
WP(C) NO. 31472 OF 2017
PETITIONER/S:
M/S.VISION MOTORS PRIVATE LIMITED,
N.H.BYEPASS, MANNUTHY,THRISSUR- 680
655REPRESENTED BY ITS HEAD (HR &
ADMINISTRATION)PRASAD.S
BY ADVS.
SRI.A.A.ZIYAD RAHMAN
SRI.LAL K.JOSEPH
RESPONDENT/S:
1 THE THRISSUR MUNICIPAL CORPORATION
REPRESENTD BY ITS SECRETARY,THRISSUR-677 801
2 THE SECRETARY
THRISSUR MUNICIPAL CORPORATION, THRISSUR-677 801
3 THE HEALTH OFFICER
THRISSUR MUNICIPAL CORPORATION,THRISSUR-677 801
BY ADV SRI. SANTHOSH P.PODUVAL, SC, THRISSUR
CORPORATION
OTHER PRESENT:
SNR. GP. SRI.JUSTIN JACOB
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 25.08.2021, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
WP(C) NO. 31472 OF 2017
-2-
JUDGMENT
The petitioner, a dealer of vehicles manufactured by
Honda Cars India Ltd., is conducting a vehicle showroom as
well as a workshop in building bearing No.VI/627/2 within the
respondent-Corporation. The petitioner submits that due to
space constraints they were forced to make some additional
constructions, which according to the Corporation was
unauthorised. A notice, Ext.P1 under Section 406 of the
Kerala Municipality Act was issued, which was challenged by
the petitioner before the Tribunal for Local Self-Government
Institution, Thiruvananthapuram. The Tribunal by Ext.P2
judgment dismissed the appeal, but allowed the petitioner to
apply for regularization of the said structures after making
necessary changes to bring the construction in conformity with
law. The Secretary of the Corporation was directed to dispose
of the said application seeking regularisation within a period of
30 days after its submission. Till a decision was taken, the
implementation of the notice under Section 406 of the Act was WP(C) NO. 31472 OF 2017
also kept in abeyance.
2. The petitioner submits that he has made an application,
Ext.P3, seeking for regularisation as early as on 9.1.2017. The
Corporation informed the petitioner vide letter dated
21.03.2017 that since the unauthorised constructions are not
regularised, the application for D & O licence submitted by the
petitioner cannot be considered. The petitioner, thereafter by
letter dated 31.07.2017, intimated the Secretary of the
Corporation that the temporary sheets made for weather
shades are removed and this letter is acknowledged by the
Corporation on 01.08.2017.
3. The Corporation, later by a notice dated 22.08.2017,
required the petitioner to remit a fee of Rs.20,000/-, possibly
to process the regularization application. The petitioner had
also applied for D & O licence for the year 2017-2019, which is
evidenced by Ext.P7. The challenge in the writ petition is to
Ext.P10 notice 27.09.2017 issued under Sections 447(1) and
532(1) of the Kerala Municipality Act on the premise that the
business is run without the requisite licence. This Hon'ble WP(C) NO. 31472 OF 2017
Court, while admitting the writ petition, granted an interim
order on 3.10.2017 staying the operation of Ext.P10 and the
said order continues to be in force. The Corporation has filed a
counter affidavit pointing out seven defects, which are
extracted below:
"2. The Senior Town Planner upon inspection certain violations in the building numbered VI/627(2) were noted as given below:
i. The backside and other sides were covered using sheet.
ii. Even though the permit is issued for storage occupancy, the building is used as show room, auto mobile workshop and service station. iii. No permission from the Town Planning Department for usage of plot and layout of the building was obtained as per Rule 59(1).
iv. There are violations with respect to coverage and F.A.R. as per Rule 31.
v. There is no parking space as per Rule 34. vi. There is no rain water storage arrangement as per Rule 109(B).
vii. The minimum distance from the road to the side of the building as per Rule 25(1) is not maintained. Even though a notice was issued to cure the defects, the violations mentioned as 6 and 7 were not cured."
WP(C) NO. 31472 OF 2017
4. It is also submitted by the Corporation that a notice
was issued to cure the defects but violations mentioned as
serial Nos.vi and vii were not cured. The petitioner has also
filed I.A.No.14382 of 2018 pointing out that the alleged
unauthorised constructions are removed and stating further
that the landlord of the building has submitted an application
for regularization before the Corporation on 6.07.2018. The
said application dated 24.07.2018 is produced as Ext.P11. The
learned Standing Counsel for the Corporation submits that they
are prepared to conduct an inspection and to hear the
petitioner and will take an appropriate decision, taking into
account the facts mentioned above. It is seen that the
petitioner has not given a reply to Ext.P10 so far. The
petitioner may file a reply to Ext.P10 as also about the
subsequent events. The Corporation has to take a decision on
the issue of regularisation as well as grant of D & O licence
after affording a reasonable opportunity of hearing to the
petitioner. The respondent-Corporation will also intimate the WP(C) NO. 31472 OF 2017
petitioner about the subsisting defects and grant an
opportunity to the petitioner to cure the same. This exercise
shall be done within a period of one month from the date of
receipt of a copy of this judgment. No coercive action shall be
taken against the petitioner pursuant to Ext.P10 till such a
decision is taken and communicated to the petitioner.
This writ petition is disposed of as above.
Sd/-
MOHAMMED NIAS C.P.
Judge STK WP(C) NO. 31472 OF 2017
APPENDIX OF WP(C) 31472/2017
PETITIONER EXHIBITS
EXHIBIT P1 TRUE COPY OF THE NOTICE DATED 9.10.2014.
EXHIBIT P2 TRUE COPY OF THE ORDER DATED 26.11.2016 IN APPEAL NO.1125/2014.
EXHIBIT P3 TRUE COPY OF THE ACKNOWLEDGMENT DATED 9.1.2017
EXHIBIT P4 TRUE COPY OF THE COMMUNICATION DATED 21.3.2017 ISSUED BY THE 3RD RESPONDENT
EXHIBIT P5 TRUE COPY OF THE COMMUNICATION DATED 31.7.2017.
EXHIBIT P6 TRUE COPY OF THE COMMUNICATION DATED 22.8.2017 ISSUED BY THE 3RD RESPONDENT.
EXHIBIT P7 TRUE COPY OF THE APPLICATION DATED NIL SUBMITTED BY THE PETITIONER.
EXHIBIT P8 TRUE COPY OF THE RECEIPT DATED 5.4.2017 EVIDENCING THE COLLECTION OF PROPERTY TAX.
EXHIBIT P9 TRUE COPY OF THE RECEIPTS (2NOS) EVIDENCING THE PAYMENT OF PROFESSION TAX IN RESPECT OF THE EMPLOYEES AND THE INSTITUTION.
EXHIBIT P10 TRUE COPY OF THE NOTICE BEARING NO.
OLK3-3771/2017 DATED 27.9.2017.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!