Citation : 2021 Latest Caselaw 16412 Ker
Judgement Date : 5 August, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
THURSDAY, THE 5TH DAY OF AUGUST 2021 / 14TH SRAVANA, 1943
OP(ATE) NO. 4 OF 2021
PETITIONER:
ERA INFRA ENGINEERING LTD.
C-56/41, SECTOR-62, NOIDA-201301, UTTAR PRADESH,
REPRESENTED ITS RESOLUTION PROFESSIONAL, RAJIV
CHAKRABORTY, S/O. SRI. BADAL KUMAR CHAKRABORTY, AGED 47
YEARS, R/O. 12, FF, SUKHDEV VIHAR, NEW DELHI-110025.
G.CHITRA
SUHAIL SEHGAL
RESPONDENT:
NATIONAL INSTITUTE OF TECHNOLOGY,
CALICUT, NIT CAMPUS P.O., CALICUT, KERALA-673601,
REPRESENTED BY ITS REGISTRAR.
THIS OP(ARBITRATION TIME EXTENSION) HAVING COME UP FOR
ADMISSION ON 05.08.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
OP(ATE) NO. 4 OF 2021
2
JUDGMENT
This original petition has been filed by the petitioner
invoking the provisions of Section 29A of the Arbitration and
Conciliation Act, 1996 (for short 'the Act'), with the plea that
the learned Arbitrator - earlier appointed by this Court
through Ext.P3 order - be directed to recommence the
arbitration proceedings, which he has stopped through Ext.P6
order under the provisions of Section 29A(1) of the Act.
2. The petitioner asserts that the learned Arbitrator
could not have stopped proceedings under Section 29A, as is
stood prior to the year 2019, since it was amended with effect
from 09.08.2019, whereby, the period of twelve months
commences only from the date of completion of pleadings
under Section 23(4) of the Act. The petitioner asserts that the
pleadings have not yet been completed and therefore, that the
learned Arbitrator was in error in having concluded
proceedings in the manner as has been done through Ext.P6.
3. I have heard Sri.Suhail Sehgal, the learned counsel
for the petitioner and Sri.Shyam Padman, learned counsel
appearing for the respondent.
OP(ATE) NO. 4 OF 2021
4. Sri.Shyam Padman opposed the afore request of the
petitioner, arguing that, as is evident from Ext.P6, the learned
Arbitrator has found that the entire cause for delay rests
squarely on the petitioner, since they neither completed the
pleadings nor paid the fees, which was agreed, to the
Arbitrator. Sri.Shyam Padman submitted that on account of
the lackadaisical attitude adopted by the petitioner, his client
has been put to unnecessary prejudice and had to expend
large amounts of money; and thus prayed that this Court may
not extend the time frame as sought for by the petitioner any
further, except on appropriate conditions, including that his
client will not shoulder any further responsibility for the
arbitral fees or expenses during the extended period. He
predicated that, in any event of the matter, until the petitioner
pays the agreed fees to the Arbitrator and continues to do so,
this Court may not find favour with their plea and prayed that
this case be ordered only on such terms.
5. I have considered the afore dialectical contentions of
the rival parties and have also examined the order of the
learned Arbitrator stopping proceedings, namely Ext.P6, very
carefully.
OP(ATE) NO. 4 OF 2021
6. The learned Arbitrator has, in paragraph 18 and 19,
explained how the arbitration proceedings were delayed and
has unequivocally found that the petitioner was responsible
for the same. The learned Arbitrator has also recorded that,
in spite of sufficient opportunities have been given to the
petitioner, they had not paid the agreed fees and
consequently, that an order under Section 31A of the Act had
been issued, warning them that if the same is not complied
with, the proceedings would be stopped.
7. The afore conduct of the petitioner, as noticed by the
learned Arbitrator, certainly is deleterious and cannot be
normally condoned. However, taking note of the seriousness
of the disputes raised and the fact that the respondent is an
autonomous educational Institution, I deem it appropriate to
allow this request; however, on the following conditions:
(a) The petitioner will pay the fees of the learned
Arbitrator until today, along with all applicable expenses,
within a period of four weeks from today.
(b) The petitioner will pay the whole of the agreed fees
to the Arbitrator during the extended period of time, without OP(ATE) NO. 4 OF 2021
the respondent being asked to honour the same, albeit on the
specific condition that the learned Arbitrator will make
sufficient provisions for the same in the Award to be finalised
by him.
(c) In the event the petitioners comply with direction (a)
above within the time frame granted herein, the learned
Arbitrator will recommence the proceedings and issue award
within a period of six months from the date on which the
petitioner makes payment in terms of the said direction.
Needless to say, should the petitioner default in any
manner, in making payment as per direction (b) above or be
found not co-operating with the orders of the Arbitrator, the
said Authority will be at full liberty to stop proceedings under
Section 29A appropriately without any further orders from
this Court.
Sd/- DEVAN RAMACHANDRAN JUDGE stu OP(ATE) NO. 4 OF 2021
APPENDIX OF OP(ATE) 4/2021
PETITIONER EXHIBITS
Exhibit P1 TRUE COPY OF THE JUDGMENT DATED 08/05/2018 OF THE NATIONAL COMPANY LAW TRIBUNAL, NEW DELHI PRINCIPAL BENCH IN CP NO. 1B-
190(PB)/2017.
Exhibit P2 TRUE COPY OF THE SUPPLEMENTAL AGREEMENT DATED 13/10/2017 ENTERED INTO BETWEEN THE PETITIONER AND RESPONDENT.
Exhibit P3 TRUE COPY OF THE ORDER DATED 16/01/2018 PASSED BY THIS HONOURABLE COURT IN ARBITRATION REQUEST NO. 03/2017.
Exhibit P4 TRUE COPY OF THE ORDER DATED 02/12/2019 OF THE NATIONAL COMPANY LAW TRIBUNAL, NEW DELHI PRINCIPAL BENCH IN CP NO. IB-190(PB) 2017.
Exhibit P5 TRUE COPY OF THE LETTER DATED 29/05/2019 ISSUED BY THE PETITIONER TO THE LEARNED ARBITRATOR.
Exhibit P6 TRUE COY OF THE ORDER DATED 22/06/2019 OF THE LEARNED ARBITRATOR IN ARBITRATION PETITION NO. 1/2018.
Exhibit P7 TRUE COPY OF THE MINUTES OF THE 16TH MEETING OF THE COMMITTEE OF CREDITORS OF THE PETITIONER HELD ON 24/10/2019 AT 1.00 PM.
Exhibit P8 TRUE COPY OF ORDER DATED 14/11/2019 PASSED BY THE HON'BLE NATIONAL COMPANY LAW TRIBUNAL, NEW DELHI SPECIAL BENCH IN CP NO.1B-190(PB)/2017.
Exhibit P9 TRUE COPY OF THE LETTER DATED 27/03/2019 ISSUED BY THE RESPONDENT TO THE PETITIONER. OP(ATE) NO. 4 OF 2021
Exhibit P10 TRUE COPY OF THE REPLY LETTER DATED 22/05/2019 OF THE PETITIONER TO THE RESPONDENT.
Exhibit P11 TRUE COPY OF THE LETTER DATED 11/02/2020 OF THE PETITIONER.
Exhibit TRUE COPY OF THE LETTER DATED 25/02/2020 OF P11(A) THE RESPONDENT.
Exhibit P12 TRUE COPY OF THE ORDER DATED 10/01/2020 OF THE NATIONAL COMPANY LAW TRIBUNAL, NEW DELHI PRINCIPAL BENCH IN CP NO.1B-190(PB)/2017.
Exhibit P13 TRUE COPY OF THE LETTER DATED 14/03/2016 OF THE PETITIONER.
Exhibit TRUE COPY OF THE LETTER DATED 16/03/2016 OF P13(A) THE PETITIONER ALONG WITH THE MINUTES OF THE MEETING OF THE PROJECT MONITORING COMMITTEE DATED 16/03/2016.
Exhibit TRUE COPY OF THE LETTER DATED 07/04/2016 OF P13(B) THE PETITIONER. Exhibit TRUE COPY OF THE LETTER DATED 04/07/2016 OF P13(C) THE PETITIONER.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!