IA/1/2020 IN RSA 769/2020                     1/2




                       IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                          Present:
                            THE HONOURABLE MR.JUSTICE N.ANIL KUMAR

              Friday,the 9th day of April 2021/19th Chaithra, 1943



            For information       purpose only
                    IA/1/2020 IN RSA/769/2020


AS No.77/2013 of the ADDITIONAL SUB COURT, THALASSERY
OS No.127/2010 of the MUNSIFF COURT, THALASSERY


PETITIONER / APPELLANT


       P. M. KRISHNAN NAMBOODIRI, AGED 63 YEARS,
       S/O. P. M. KRISHNAN NAMBOODIRI, POOJARI AND CUSTODIAN OF
       PINARAYI SREE PARAMESHWARA PARVATHI TEMPLE, PINARAYI AMSOM
       DESOM, THALASSERY TALUK, KANNUR DISTRICT.


RESPONDENTS / RESPONDENTS


1.     KUNHIMADAKKANDY RABEENA, AGED 39 YEARS,
       W/O. P. P. NIYAS, HOUSE NO. 2/433, DARUL AMAN, PINARAYI AMSOM
       DESOM, KETTILEPEEDIKA, POST PINARAYI, THALASSERY, KANNUR
       DISTRICT - 670 104.
2.     P. P. NIYAS
       S/O. MUHAMMED, HOUSE NO.2/433, DARUL AMAN, PINARAYI AMSOM
       DESOM, KETTILEPEEDIKA, POST PINARAYI, THALASSERY, KANNUR
       DISTRICT - 670 104.


      Application praying that in the circumstances stated in the
affidavit filed therewith the High Court be pleased to pass an
Interim Order to stay the operation and all further proceedings
 IA/1/2020 IN RSA 769/2020                    2/2

in    pursuance             of   appellate   Court    decree   &   Judgment    dated
18.12.2019 in A.S. No. 77/2013 on the file of Additional Sub
Court, Thalassery, to the extent it modifying the injunction
granted vide Judgment and Decree dated 29/8/2013 in O.S. No.
127/2010 of Munsiff Court, Thalassery, to the effect construction
in the Plaint 'B' schedule property, pending disposal of the

            For information purpose only
above Appeal, so as to secure the ends of justice.


     This application again coming on for orders upon perusing the
application and the affidavit filed in support thereof, and this
court's order dated 08-01-2021 in IA 1 of 2020 and upon hearing
the arguments of M/S C. P. PEETHAMBARAN, Advocate for the
petitioner and of M/S T. RAMESH BABU, C. K. SREEJITH, Advocates
for the respondents, the court passed the following:


                                         O R D E R

Interim order stands extended by a period of three months.

09-04-2021 Sd/-

N.ANIL KUMAR,JUDGE

/true copy/ Sd/-

ASSISTANT REGISTRAR

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter