Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Cauvery Neeravari Nigama Limited vs Sri K Venkatareddy
2025 Latest Caselaw 3479 Kant

Citation : 2025 Latest Caselaw 3479 Kant
Judgement Date : 3 February, 2025

Karnataka High Court

Cauvery Neeravari Nigama Limited vs Sri K Venkatareddy on 3 February, 2025

Author: S.G.Pandit
Bench: S.G.Pandit
                                                  -1-
                                                            NC: 2025:KHC:5094-DB
                                                            RFA No. 428 of 2011




                           IN THE HIGH COURT OF KARNATAKA AT BENGALURU

                             DATED THIS THE 3RD DAY OF FEBRUARY, 2025

                                               PRESENT

                                 THE HON'BLE MR JUSTICE S.G.PANDIT

                                                 AND

                       THE HON'BLE MR. JUSTICE RAMACHANDRA D. HUDDAR

                            REGULAR FIRST APPEAL NO. 428 OF 2011 (MON)

                      BETWEEN:


                      1.     CAUVERY NEERAVARI NIGAMA LIMITED
                             OPPOSITE TO KALAMANDIR
                             VINOBA ROAD, MYSORE-570 001
                             REP. BY ITS MANAGING DIRECTOR
                             NOW REP. BY ITS
                             GENERAL MANAGER (FINANCE)


Digitally signed by
                      2.     THE CHIEF ENGINEER
SHARMA ANAND
CHAYA
                             HEMAVATHI CANAL ZONE
Location: High               TUMKUR-572 101
Court of Karnataka


                      3.     EXECUTIVE ENGINEER
                             HEMAVATHI CANAL ZONE
                             TUMKUR-572 101

                                                                     ...APPELLANTS

                      (BY    SRI. M.R.C. RAVI, SENIOR ADVOCATE FOR
                             SRI. B.R. PRASHANTH, ADVOCATE)
                             -2-
                                       NC: 2025:KHC:5094-DB
                                       RFA No. 428 of 2011




AND:

SRI. K. VENKATAREDDY
S/O SRI. K. JANGAMA REDDY
HINDU, MAJOR
CLASS I PWD CONTRCTOR
AT USHA NILAYA, BESIDE SIDDARODA
ASHRAMA AMARJYOTHI NAGARA
KUNIGAL ROAD,
TUMKUR, PIN CODE-572 101

                                             ...RESPONDENT

(BY SRI. V.B. SHIVAKUMAR, ADVOCATE)

       THIS RFA IS FILED U/SEC.96, OF CPC, AGAINST THE
JUDGMENT     AND   DECREE DATED     30.09.2010   PASSED   IN
O.S.40/2004 ON THE FILE OF THE ADDL. SENIOR CIVIL JUDGE
AND CJM, TUMKUR, DECREEING THE SUIT FOR THE RECOVERY
OF MONEY.


       THIS REGULAR FIRST APPEAL HAVING BEEN RESERVED
FOR JUDGMENT COMING ON FOR PRONOUNCEMENT OF THIS
DAY,    RAMACHANDRA       D.      HUDDAR   J.,   DELIVERED/
PRONOUNCED THE FOLLOWING:


CORAM:      HON'BLE MR. JUSTICE S.G.PANDIT
            AND
            HON'BLE MR. JUSTICE RAMACHANDRA D. HUDDAR
                              -3-
                                       NC: 2025:KHC:5094-DB
                                        RFA No. 428 of 2011




                     CAV JUDGMENT

(PER: HON'BLE MR JUSTICE RAMACHANDRA D. HUDDAR)

This appeal is directed against the judgment and

decree dated 30.09.2010 passed in OS No.40/2004 by the

Senior Additional Civil Judge and CJM, Tumkur.

2. Parties to this appeal are referred to with

reference to the ranks before the trial Court.

3. The defendants are in this appeal.

4. That plaintiff filed a suit against defendants for

recovery of sum of Rs.4,88,07,144/- from the defendants.

It is the case of the plaintiff that he is a Class-I PWD

Contractor and as per the tender invited by defendant no.1

towards construction of cement concrete lining between

100 and 103 kms. of Tumkur Branch Canal, he submitted

a tender which was accepted by the defendants and to that

effect, an agreement was entered into between the

plaintiff and the defendants on 28.02.1996.

NC: 2025:KHC:5094-DB

5. The work order was issued by the defendants

on 05.03.1996 with the condition to complete the work

within six months including rainy season of three months.

Plaintiff mobilised the required equipment, labourers to the

site and camped there. It is stated that on 10.04.1996,

the Superintendent Engineer, did inspection of the work

spot and noticed that the side slopes provided were not

proper and recommended for change of design. On

10.04.1996, plaintiff addressed a letter for clear marking

out and authorised him to construct steeper slopes. But at

the instance of the defendant, the work was stopped from

18.04.1996 on the ground that the approval was sought in

change of design. It is stated that plaintiff went on

addressing letters to the defendants vide letters dated

18.04.1996, 25.04.1996 bringing to the notice of the

defendants seeking approval of change of design and also

brought to the notice of the defendants that gravel is not

available on the site. It was informed to the defendants on

20.05.1996 by a letter stating that the supper passage at

100.5 kms. Is broken and area is getting flooded. The

NC: 2025:KHC:5094-DB

Executive Engineer concerned by his letter dated

20.06.1996 directed to suspend the work for free flow of

water. It was in force till 06.11.1996

6. It is stated that the plaintiff made several

correspondence with defendants and waited for change in

design as directed by the defendants. The Executive

Engineer issued reply admitting several abstractions and

requested the plaintiff to carry over the work wherever

there is no abstraction. Even the plaintiff has listed the

equipments he has stored at the spot after issuing the

work order. It is stated that the plaintiff completed the

work during January 1998 and to that effect, the

defendants preferred bills for Rs.37 lakh only by deducting

the sale tax and income tax.

7. It is alleged by the plaintiff that before the

completion of the work with regard to the concrete line

between 102.4 kms to 103.00 kms. It was collapsed due

to defect in the design. There were several experts given

the report with regard to the defective design including

NC: 2025:KHC:5094-DB

Karnataka Engineering Research Station, Centre for

Scientific and Industrial Consultancy for Indian Institute of

Science. It is observed that the cotton soil is found from

103 kms. and there is Alasina Tank at a distance of 80.00

mts. So also there are irrigated paddy crops on either side

of the canal. As per the reports for the causes of failure is

non providing for reinforcement in the CC lining, non

availing of super passage to drain out stagnated water and

other factors so also, causing uplift pressure in the CC line.

Though the reports suggested remedial measures but

defendant did not care for the same. The said reports

submitted by the aforesaid authorities, did not point out

any defects in the work undertaken by the plaintiff.

8. It is alleged by the plaintiff that he has

completed the work and in the month of June 1998, the

bills were prepared for Rs.63,00,000/- deducting

20,00,000/- towards F.S.T, and Rs.43 lakh were payable

by the defendants. But, defendants paid only 23 lakh. It is

alleged that because of failure on the part of the

NC: 2025:KHC:5094-DB

defendants to pay the amount being submitted as per the

bill submitted by him, after issuance of legal notice, the

plaintiff filed a W.P.No.28793/2000 seeking writ of

mandamus directing for payment of Rs.24,59,658/-. In the

said writ petition, defendants admit that they are liable to

pay Rs.46,83,586/-. An interim order was passed in the

writ proceedings. The plaintiff got issued a legal notice on

20.10.2003 and called upon the defendants to comply the

directions issued by the Hon'ble High Court. But, the Chief

Engineer concerned rejected the claim of the plaintiff vide

letter dated 07.11.2003. Therefore, the plaintiff was

constrained to file the suit claiming the suit claim from the

defendants as tabulated in para 6 of the plaint to the

extent of suit claim stated supra. The defendants are liable

to pay the same. Therefore, it is prayed by the plaintiff to

decree the suit.

9. Pursuant to suit summons, the defendant

appeared before the trial Court and it is defendant Nos.2

to 4 filed the written statement admitting about

NC: 2025:KHC:5094-DB

entrustment of a tender work as stated in the plaint and

also issuance of work order dated 04.03.1996. It is

contended that as per the agreement, a condition is

imposed on the plaintiff that there is a program of work for

allowing water by the end of June 1996 in Tumkur Branch

so as to cater the drinking water to Tumkur Town up to

125 kms. an extension of time would be given as per the

rules but without any extra rate. The other allegation

with regard to the proceedings of the work by the plaintiff

as stated in the plaint, carrying of the equipments and

men etc. is denied. It is contended that the plaintiff fails to

start the work with adequate men and machine though he

was instructed to commence the work immediately but he

went on issuing several notices. So far as change of design

as directed by the Superintendent Engineer, it is not in

dispute. According to the defendants, the said change of

design is in confirmative with Class-13(a)(1) of agreement.

The said change of design would benefit the plaintiff as the

work of excavating the land would decrease considerably.

As per the program of work from quarterly month, the

NC: 2025:KHC:5094-DB

plaintiff has failed to comply the same. Though there was a

proposal for change of design, plaintiff would have

proceeding without removing sheet, excavation of

earthwork and would have done the bed work of the canal.

Therefore, the delay could not have been attributed

against the defendants.

10. It is contended that though there was a collapse

of cement lining, it is plaintiff who is responsible for

draining out the water. The contention that there was a

damage to the super passing because of drain water is

denied. So from the report from K.E.R.S. and I.I.S.C. is

concerned, it is contended that because of improper

maintenance by the plaintiff there was damage. For this

wanton negligence on the part of the plaintiff, the

defendants are not liable. According to the defendants, the

work was to be completed on 04.09.1996. There is latches

on the part of the plaintiff and he actually completed the

work in the year 1998. Now, the claim of the plaintiff is

barred by limitation as per class-8 of the agreement, as

- 10 -

NC: 2025:KHC:5094-DB

computation of date began from 02.02.1997. The

defendants are not liable to pay the amount as claimed

and both plaintiff and defendants are not bound by the

agreement. It is contended that there is no provision in the

agreement for making any separate payment towards

establishment charges. The plaintiff was supposed to quote

his tender rates after taking into consideration of the

element such as materials, labours and establishment

charges. Amongst other grounds, it is prayed by the

defendants to dismiss the suit.

11. Based upon the rival pleading of both the

parties, the learned trial Court framed in all 17 issued and

one additional issue, they read as under:

"1. Whether plaintiff proves that the work was suspended from 18/4/1996.?

2. Whether the plaintiff proves that the period of suspension was not informed to him."

3. Whether the plaintiff proves that suspension was in force till 6/11/96.?

- 11 -

NC: 2025:KHC:5094-DB

4. Whether the plaintiff process that there was several obstructions for the works to be carried on due to change in the design.

5. Whether the defendant proves notwithstanding the change of design which was pending approval and direction not to carry on with the work, the plaintiff could have completed the other works as contended at page no.6 end of para No.3 the written statement?

6. Whether the defendant proves that the work done is not in accordance with the specification and designs issued by the defendant as contended in para 7 page 7 of the written statement.?

7. What is the cause of concrete lining between 102.4. K.M to 103 K.M. to collapse. Whether the lapses is attributable to the plaintiff or the defendant.?

8. Whether the defendant can go back on its chief Engineers finding in his letter dated 15/11/99 as contended in Ist sentence of para.no. 12 page no. 12 of its written statement.?

- 12 -

NC: 2025:KHC:5094-DB

9. Whether the plaintiff proves that he is eligible for the new rates for the work done beyond stipulated period.?

10. Whether the plaintiff proves that, he is entitled for payment of difference in cost of cement.?

11. Whether the plaintiff proves he is entitled for interest.?

12. Whether the plaintiff proves that he is entitled for idle charges.?

13. Whether the plaintiff prove that he is entitled for compensation for longer stay at site.?

14 Weather the defendant proves that it has paid tendered rates it respect of claims under Annexures A to D and consequent upon such payment additional rates can not be demanded as pleaded in para 30 to 33 of its written statement.?

15. Whether the plaintiff proves that he is entitled to equitable rates as claimed in Annexure-E.?

- 13 -

NC: 2025:KHC:5094-DB

16. Whether the defendant proves delay in execution of work is solely attributable to plaintiff and hence, claim under Annexure-F is not maintainable.?

17. To what reliefs the parties are entitled for.?

An additional issue is framed as under,

1. Whether the suit of the plaintiff is barred by Law of limitation.?"

12. Before the learned trial Court, to substantiate

the case of the plaintiff, he himself entered the witness

box as PW1 and got marked Exs.P1-P27 and closed

plaintiff's evidence. To rebut the evidence of the plaintiff,

one Srikanta Murthy an official of the defendant entered

the witness box as DW1 and on behalf of defendants

Exs.D1-26 are marked. Closed defendants evidence.

13. The learned trial Court having heard the

argument of both sides, and on perusal of the evidence

placed on record, answered issues Nos.1, 3 4, 9, 10, 11,

12, 13, 15 in the affirmative and other issues in the

- 14 -

NC: 2025:KHC:5094-DB

negative and ultimately, decreed the suit of the plaintiff

directing the defendants liable to pay Rs.4,34,99,380/- to

the plaintiff together with interest @ 12%p.a. from the

date of suit till realisation fastening the liability on the

defendants joint and several.

14. Now, the defendants have preferred this appeal

challenging the impugned judgment of fastening the

liability on the defendants jointly and severally to pay the

amount so stated in the decree.

15. Trial Court records are secured.

16. The learned counsel for the appellants-

defendants ardently submits that the claim of the plaintiff

itself is barred by limitation as because though the work

was completed in the year 1998 as per the case of the

plaintiff, the plaintiff has filed the suit in the year 2004.

Without any cause of action, the plaintiff has filed the suit

which is time barred. It is further submitted that as per the

conditions stipulated in the tender, the work was stopped

on 20.06.1996 due to letting out of water to Tumkur town

- 15 -

NC: 2025:KHC:5094-DB

and on 06.11.1996, the defendants directed the plaintiff to

resume the work with a request to complete the work

expeditiously. There is no proper adherence to the request

of the defendants by the plaintiff.

17. The learned counsel for the defendants would

further submits that the stoppage of the work was strictly

in accordance with the specific condition of the contract

and now the plaintiff cannot contend that the defendants

were responsible for delay in completing the tender work.

In the month of November 1996, itself the respondents

started correspondence with the plaintiff and even plaintiff

also started addressing letters that defendants should give

revised dates for the work executed beyond the original

tender. This claim of the plaintiff is contrary to the tender

condition. The learned counsel for the defendants would

further submit that the plaintiff is not entitled for any new

rates for the work done beyond the stipulated period and

whatever he is entitled is as per the agreement. Even the

appellant has paid the revised rates for all the items of the

- 16 -

NC: 2025:KHC:5094-DB

work as per the agreed tender conditions as admitted by

the respondent in the cross examination. In view of the

proviso to Section 70 of the Indian Contract Act, the

learned counsel for the defendants would submit that the

work so executed by the plaintiff was under non gratuitous

contract. Therefore, the plaintiff is not entitled for new

rates. Based upon the principles laid down upon the

provision upon 70 of the Indian Contract Act, the principle

of "Quantum meruiut" i.e., if any person does any work

without any agreement and if the said benefit has been

appropriate by the other party, then party who has done

the work is entitled for payment to the extent of benefit

taken by the other party. Therefore, the principle is aptly

applicable to the claim of the plaintiff. There is no

agreement between the plaintiff and the defendants that

benefit is taken by the defendants.

18. The learned counsel for the defendants further

would submit that as per the plaint averments, the plaintiff

has claimed marked rate, but only claiming schedule rate

- 17 -

NC: 2025:KHC:5094-DB

for the works done beyond in excess of the agreement is

not permissible. The quantity of the work done and

equitable rate so claimed by the plaintiff is denied by the

defendants. According to the learned counsel for the

defendants, the scheduled rate and rates of the plaintiff so

claimed by the plaintiff is the own assumption of the

plaintiff. Ex.D20 shows the comparative statement

showing the equitable rates claimed by the plaintiff. It is

not considered by the trial Court. The learned trial Court

adopted a policy of pick and chose in arriving at a

conclusion. The learned counsel for the appellants-

defendants further would submit that rightly the trial Court

has rejected the claim of idle charge of labour, but upheld

the clam of the plaintiff with regard to idle charge of

machinery which is incorrect. There is an admission on the

part of the plaintiff in his cross examination having

incurred an expenses of Rs.35,50,800/- towards idle

charges of the machinery and same is reflected in the

expenditure account. The learned counsel for the

defendants would submits that the trial Court has

- 18 -

NC: 2025:KHC:5094-DB

committed error in arriving at a conclusion that the

plaintiff is entitled for the amounts so decreed. So far as

preparation of the bill with regard to Rs.37,00,000/- the

trial Court has committed error and has wrongly passed an

order to release the said amount. Amongst other ground

including the rate of interest charge on the suit claim, the

learned counsel for the defendants would submit that the

trial Court has committed grave error in decreeing the suit

as prayed for. There is no proper appreciation of evidence

by the trial Court. In addition to submitted fact of the case

as well narration of evidence placed on record, it is

submitted by the learned counsel for the appellants -

defendants to set aside the impugned judgment and

dismiss the suit.

19. In contrast to this submission, the learned

counsel for the plaintiff-respondent justifies the findings of

the learned trial Court as well as reasons given thereon in

decreeing the suit of the plaintiff. According to the

submission of the learned counsel for the plaintiff-

- 19 -

NC: 2025:KHC:5094-DB

respondent, the claim of the plaintiff is not barred by

limitation as there was a continuing cause of auction to file

a suit for recovery of amount. Several correspondence

were made by the plaintiff brining to the notice of the

defendants about the delay being caused in completing the

work because on the lapse of the defendants. At the

instance of the Superintendent Engineer, the design was

sought to be changed and though several correspondence

were made to change the design but defendants did not

comply the request of the plaintiff. Even the Executive

Engineer of the defendants admitted the cause of delay on

the part of the defendants by addressing reply to the

plaintiff.

20. The learned counsel for the plaintiff would

submit that the trial Court has based upon the evidence

and admissions of DW1 has rightly concluded that there is

lapse on the part on the defendant and at the instance,

there is delay and not on the part of the plaintiff. The

learned counsel for the plaintiff would further rely upon the

- 20 -

NC: 2025:KHC:5094-DB

findings of the trial Court and pleadings of the plaintiff

inconsonance of the same the evidence placed on record

both oral and documentary. Therefore, supporting the

reasons assigned by the trial Court, it is prayed by the

learned counsel for the plaintiff to dismiss the appeal by

confirming the impugned judgment.

21. We have given our anxious consideration to the

arguments of both the side. Meticulously perused the

records.

22. In view of the rival submission of both the side,

the following points arise for our consideration:

1) Whether the trial Court has committed any illegality in holding that at the instance of the defendants there was a delay in the completion of the work and thereby plaintiff has to meet additional expenses towards purchase of the materials to complete the work entrusted to him?

- 21 -

NC: 2025:KHC:5094-DB

2) Whether the trial Court has committed any illegality or infirmity in appreciating the evidence placed on record by both the parties in holding that the work was carried out by the plaintiff in accordance with the specification and designs supplied by the defendants?

3) If so whether the trial Court is right in holding that plaintiff is eligible for new rates as a work was done beyond the stipulated period at the instance of the defendants?

4) Whether the judgment and decree of the trial Court suffers from any infirmity or illegality and require interference by this Court?

5) What order?

Point Nos.1 to 3 are discussed together.

23. Before adverting to the other aspects of the

case, let us analyse the admitted facts between both the

parties.

- 22 -

                                             NC: 2025:KHC:5094-DB





i)     Plaintiff   is       a      Class-I          PWD
        Contractor applied as per the
        tender     publication               published
        by       defendant              No.1          for
        construction               of          cement
        concrete lining between 100
        and     103      kms.           Of    Tumkur
        branch canal.

ii)    The tender so submitted by the
        plaintiff was accepted and to
        that effect on 28.02.1996 an
        agreement was entered into
        between              plaintiff               and
        defendants as per Ex.P1.

iii)   As per the agreement, it was
        stipulated that plaintiff has to
        complete the said work within
        six     months           including          three
        months rainy season.

iv)    Plaintiff mobilised the required
        equipments,              labours       to    the
        site.

v)     The      Superintendent               Engineer
        visited the place of work on
                      - 23 -
                                        NC: 2025:KHC:5094-DB





       10.04.1996 and noticed that
       the site slopes provided were
       not proper and recommended
       for change in design.

vi)    There           were               several
       correspondences                   between
       plaintiff       and         defendants
       seeking       approval            of     the
       change in design vide letters
       dated                      10.04.1996,
       18.04.1996,                25.04.1996,
       20.05.1996.

vii)   The work was stopped by the
       defendants on 18.04.1996 on
       the ground of change in the
       design.

viii) Plaintiff           informed              the
       defendants by his letter dated
       20.05.1996              that           super
       passage       at       100.5     kms.     is
       broken and the area is getting
       flooded.

ix)    The         Executive            Engineer
       addressed          a    letter    to     the
                       - 24 -
                                          NC: 2025:KHC:5094-DB





        plaintiff dated 20.06.1996 and
        directed to suspend the work
        for flow of water and the said
        flow of water was in force till
        06.11.1996.

x)     The          Executive             Engineer
        admitted several             obstruction
        brought to his notice by the
        plaintiff    but       requested         the
        plaintiff to carry out the work
        wherever         there            are     no
        obstructions.

xi)    Plaintiff    completed         the       work
        entrusted as per the tender by
        January 1998.

xii)   None of the defendants or any
        superior      officers       or     experts
        found any defects in the work
        done by the plaintiff.

xiii) The claim of the plaintiff was
        rejected      by       the    Executive
        Engineer by his letter dated
        07.11.2003.
                                  - 25 -
                                           NC: 2025:KHC:5094-DB





24. These are all the admitted facts with calendar of

events which have taken place with regard to the

construction of the cement concrete lining between 100

and 103 kms. of Tumkur branch canal so accepted by the

plaintiff.

25. Now, the grievance of the plaintiff is that by

issuing a notice to the defendants he claimed the payment

on revised rates for the works done after the agreement

period, payment of idle charges, payment towards longer

stay at a site of work including the amount held up as FS.D

and EMD. Release of all the amount for the work done

despite the bill prepared by the defendants, different cost

of the cement together with interest at the rate of 12%

p.a. from 19.07.1999 till filing of the suit.

26. The plaintiff has mentioned his claim in para.6

of the plaint as under:

i. Pockline - 1 no.

ii. Mixers & Vibrators - 6 & 12 iii. Tippers - 4 nos.

- 26 -

NC: 2025:KHC:5094-DB

iv. Louring and Crushers - 1 and 2 v. Crushers - 1 no.

          vi. Other Necessary      tools     -   as
              required for he work
         vii. Labourers are plenty - 100 nos.
         viii. Establishment        consists     of
               Managers,       Site      Engineers,

Supervisors, Clerk etc. as required for the construction work at camp.

ix. Camping equipments"

27. PW1- plaintiff throughout his evidence has

stated the entire contents of the plaint averments and also

narrated the placement of equipment/establishment so

also other required machinery at the spot. He is specific in

his evidence about lapse on the part of the defendants in

complying the terms and conditions of the agreement.

According to him, he has claimed only scheduled rates.

28. This PW1 is cross-examined by the defendants

intensively. It is admitted by him that as per the

conditions, he had agreed to stop the work whenever there

is request to provide water to Tumkur town. He denied the

suggestion that he has stopped the work on 04.06.1996.

- 27 -

NC: 2025:KHC:5094-DB

Even he admits that as per condition No.12A, it was fourth

defendant who had powers to change the design. He

further states that, it was defendants who got changed the

design so also he agreed for removal of silt so also digging

at the spot. He further states that, there was further new

agreement in between himself and defendants. He further

states that as per the agreement, he has to take steps to

close the spot for the purpose of flow of the water to the

`Nalas`. It is suggested to PW.1 that on 24.6.1996, the

fourth defendant asked him to repair the super passage.

As per Schedule-B, he has to charge the agreed rate for

the purpose of removing the silt and defendants agreed to

pay for the same. He admits that, as per Schedule-B,

defendants have provided the rate as per the agreement

and as per the Labour Act, he has completed the work. The

suggestion that he has not carried out the work in

accordance with the Labour Act is denied by him. He has

denied all other suggestions directed to him.

- 28 -

NC: 2025:KHC:5094-DB

29. Whereas, DW.1 an official of the defendants

though reiterates the contents of the written statement,

but, in the cross-examination, he has given sufficient/

substantial admissions. He admits that in the counter filed

before this Court in the writ petition, it is admitted by the

defendants that they are due to pay Rs.46,86,586/- to the

plaintiffs. Further, he admits that, even after the

completion of the work, no amount is paid to the plaintiff

and it was told to him that after furnishing the bill it will be

paid. He admits that, plaintiff has carried out sufficient

work as per the directions of the defendants. The account

book containing the particulars of the work carried out by

the plaintiff is with the defendants. He admits that in the

work carried out by the plaintiff, there is a falling of lining

portion and because of that, money is not paid to the

plaintiff. He further admits that after rectification of the

same, they have agreed to pay the amount. He admits

that, the canal lining work was only entrusted to the

plaintiff and prior to him, somebody has done the work.

They have obtained report regarding falling of lining. He

- 29 -

NC: 2025:KHC:5094-DB

admits that, the Karnataka Engineering Research Institute

had inspected the spot and submitted a report as per

Ex.P12 so also their own Engineers have given the report

pointing out no defect in the work carried out by the

plaintiff. He admits that, from month of June till November

in the said canal there is a flow of water to supply the

same to Tumakuru Town. He admits that after April 1996,

plaintiff brought the labours, equipments, machineries and

started the work. There was no excavation. As per the

contract, plaintiff had to use the steel and thereafter it was

informed to him not to use the steel. Thereafter, by

putting the gravel a thickness was made to the extent of

Rs.1.2 mtrs. Even this fact is brought to the notice of

technical sanction committee and based upon the report of

technical committee they took the decision with regard to

slope design by not using the steel etc.. As per his

evidence, the report of Indian Institute of Science as well

as the technical report are true and correct. In the further

cross-examination, he states as under:

- 30 -

NC: 2025:KHC:5094-DB

"DzÀgÉ ¸ÀjAiÀiÁV ªÉÄÊ£ïmÉÊ£ï ªÀiÁqÀzÀ PÁgÀt D jÃw PÀĹ¢zÉ JAzÀÄ

w½¹gÀÄvÁÛgÉ. ªÁ¢AiÀĪÀjUÉ ªÀÄtÚ£ÀÄß vÉUÉAiÀÄ®Ä PÉ®¸À PÉÆnÖ®è. DzÀgÉ ²¯ïÖ (PɸÀgÀÄ

ªÀÄtÄÚ) vÉUÉAiÀÄ®Ä PÉÆnÖzÉÝêÀÅ. PÉ£Á¯ï CUÉvÀzÀ ¸ÀªÄÀ AiÀÄzÀ°è ©zÀÝ ®PÁëAvÀgÀ PÀÆåmÉPï

«ÄÃlgï ªÀÄtÚ£ÀÄß vÉUÉAiÀÄ®Ä PÉÆnÖgÀĪÀÅ¢®è. ªÁ¢AiÀĪÀgÀÄ ªÀiÁrzÀ PÉ®¸ÀzÀ°è

AiÀiÁªÀÅzÉà vÀ¥Àà£ÀÄß EzÀĪÀgÉ«UÀÆ £ÁªÀÅ PÀAr®è. r¸ÉÊ£ï r¥sÉQÖªï CzÀgÀ PÁ®ÄªÉ

PÀĹzÀ DUÀĪÀ ¸ÁzsÀåvÉ EgÀÄvÀÛzÉ JAzÀgÉ ¤d. £ÁªÀÅ PÉÆlÖAvÀºÀ r¸ÉÊ£ï D¥sï

E£ïlÄ M£À DVgÀÄvÀÛzÉ. ¸ÉÆèÃ¥ï eÁ¹Û EzÀÝgÉ lÄ r¸ÉÊ£ï PÉÆqÀ¯ÁUÀÄvÀÛzÉ. E®è

¸ÉÆèÃ¥ï eÁ¹Û EvÀÄÛ £ÁªÀÅ ªÉÆzÀ®Ä PÉÆlÖAvÀºÀ r¸ÉÊ£ï §zÀ¯ÁªÀuÉ ªÀiÁrgÀÄvÉÛêÉ

CzÀÄ JAzÀgÉ D¥sïÀ lÄ M£ï EzÀÝzÀÄÝ । E£ï lÄ | JAzÀÄ ªÀiÁrgÀÄvÉÛêÉ. £ÁªÀÅ

PÉÆlÖAvÀºÀ r¸ÉÊ£ï ªÉÄÃ¯É EArAiÀÄ£ï E£ïìnmÉÊmï D¥sï ¸ÉÊ£ïì AiÀiÁªÀÅzÉà jÃwAiÀİè

CzÀgÀ §UÉÎ nÃQ¹gÀĪÀÅ¢®è. ªÁ¢AiÀĪÀjUÉ ¥ÀÇtð ºÀtªÀ£ÀÄß PÉÆqÀ¨ÉÃPÉAzÀÄ

¸ÀÆ¥ÀjAmÉAqÉAmï EAf¤AiÀÄgï DzÉñÀ ªÀiÁrzÀÝgÀÄ JAzÀgÉ ¤d.

¸ÀÆ¥ÀjAmÉAqÉAmï EAf¤AiÀÄgï ªÀiÁrzÀ DzÉñÀzÀ°è AiÀiÁªÀÅzÉà vÀ¥ÀÅà EgÀ°®è.

ºÁUÁV PÀĹvÀzÀ vÀ¥ÀÅà E¯ÁSÉUÉ §gÀ¨ÁgÀzÀÄ JAzÀÄ vÉÆ¼ÉzÀÄ £ÁªÀÅ zÀÄgÀzÉÝñÀ¢AzÀ

ªÁ¢AiÀĪÀjUÉ ºÀtªÀ£ÀÄß PÉÆnÖ®è JAzÀgÉ ¸ÀjAiÀÄ®è. ¸ÀÆ¥ÀjAmÉAqÉAmï

EAf¤AiÀÄgï ªÀiÁrzÀ DzÉñÀ ¸ÀjAiÀiÁVzÀÝgÀÆ ¸ÀºÀ PÉ£Á¯ï PÀĹzÀ¢zÀÝjAzÀ £ÁªÀÅ

ºÀtªÀ£ÀÄß ªÁ¢AiÀĪÀjUÉ PÉÆnÖgÀĪÀÅ¢®è, ¸ÀÆ¥ÀjAmÉAqÉAmï EAf¤AiÀÄgÀªÀgÀÄ D

PÉ£Á¯ï PÀĹvÀªÁzÀ £ÀAvÀgÀ D jÃw DzÉñÀ ªÀiÁrzÁÝgÉ JAzÀgÉ ¤d."

30. This evidence spoken to by DW.1 goes a long

way to defeat the defence of defendants. The amount

- 31 -

NC: 2025:KHC:5094-DB

deposited as EMD and FSD is still with the defendants. He

further admits that, after trimming the work spot only, it is

possible to put the lining. He further admits that, as the

canal is old, it requires more trimming and further admits

that, because of change in design with regard to the slope,

the work became more with regard to the digging to

construct the sloping. He further admits that, except falling

of the canal sloping almost the plaintiff has completed the

work. He admits that, the work force and men and

machinery came to the spot on 20th 1996 and March until

the completion of the work, they were there and plaintiff

has demanded his claim towards the same. He states that

there was no discussion or thinking of providing the

schedule rate as claimed by the plaintiff and it was not

considered. He admits that as per the schedule rates only,

plaintiff has claimed his claim in the suit. He further admits

that, whatever the report being submitted by the aforesaid

authorities are accepted by his Department.

- 32 -

NC: 2025:KHC:5094-DB

31. On perusal of said reports, the said authorities

have not found any defects or mistake with the execution

of work by the plaintiff. This DW.1 deposed ignorance with

regard to date of the closure of work by the plaintiff. But,

admits that plaintiff has completed the work. He states

that, as per the technical sanction committee report, a

direction was issued not to use the steel but, to make the

thickness by using gravel. He admits that, after

commencement of work by the plaintiff such a decision

was taken not to use the steel. He further states that no

claim is filed by the defendants claiming amount from the

plaintiff. He further states whenever there is alisi pond,

there is no space for leaving the water and even there

were no provision for leaving the water and thus water has

to flow in the Nala. No provision is made for leaving the

water to the pond and no super passage is constructed. He

admits that, part of the amount is given to the plaintiff and

after completion of the work, it was agreed to pay the

amount. He admits about the deposit of EMD and FSD by

the plaintiff.

- 33 -

NC: 2025:KHC:5094-DB

32. While evaluating the evidence adduced by both

the side, the learned trial Court considered issues nos. 1 to

3 together 4 and 5 together and other issues

independently and categorically culled out the admissions

of DW.1 during the course of its discussion. The learned

trial Court has specifically discussed with regard to the

lapse on the part of the defendants. The Executive

Engineer concerned was not examined and it was he who

used to supervise the work entrusted to the plaintiff. It

was agreed in the agreement that if any dispute arises in

between plaintiff and defendants, the decision of

superintending engineer is final. But, there is no evidence

that, the claim of the plaintiff is brought to the notice of

superintending Engineer by the defendants.

33. Throughout the plaint averments, plaintiff is

specific that, because of the directions of the defendants to

stop the work, he had wait along with his all men and

machineries as because, the defendants decided to change

the design and they waited for approval to get the new

- 34 -

NC: 2025:KHC:5094-DB

design. Because of this, he is specific that, he was made to

work beyond the stipulated time, therefore he is entitled

for fresh rates. This assertion and claim of the plaintiff is

denied by the defendants.

34. On scrupulous reading of the documents

produced by the plaintiff i.e. by way of correspondences so

marked in this case do suggest that, there were several

correspondences made by the plaintiff with the defendants

and they are marked at Ex.P3 P4 and P6 P7, 8 and

ultimately Advocates notice at Ex.P15 was issued. Receipt

of these letters is not denied by the defendants. Plaintiff

has also produced three reports Ex.P10, 11 and 12 i.e. of

KERC, IISC and KERC respectively and these reports are

very much silent about any defects in the work carried out

by the plaintiff. Even the Superintendent Engineer

addressed letter as per Ex.P13 bringing to his notice that

the work done by plaintiff is satisfactory. There was some

rectification deed. As because, defendants did not make

any payment, plaintiff filed writ petition as per Ex.P18

- 35 -

NC: 2025:KHC:5094-DB

wherein certain order was passed by writ court. The

defendants categorically admitted about the due towards

plaintiff's work from them. The log books and other

documents are produced by the plaintiff and even the bills

also have been produced by the plaintiffs which are not

denied by the defendants in material particulars.

35. From the evidence of PW.1 and suggestions

directed to him, so also admissions given by DW.1 do

suggest that, the said delay was caused not at the

instance of the plaintiff but, because of the decision being

taken by the defendants to change the design as well

stopping of work to flow the water to Tumakuru town

through the said canal. Thus, as rightly concluded by the

trial Court, there was no fault on the plaintiff to complete

the work beyond the stipulated time.

36. As per clause 13-A(i)(o) of the agreement, it

was Executive Engineer who had power to make any

alterations, omissions, additions, substitutions with regard

to the original specification designs drawings and can give

- 36 -

NC: 2025:KHC:5094-DB

instructions which appear to him necessary. As per this

clause only, the Executive Engineer has suggested certain

change in design and directed the plaintiff to supply the

new design in place of old design which has consumed

sufficient time. Even as per this clause, as per the decision

taken by the Executive Engineer to change the design, the

plaintiff has to carry out the work, in accordance with the

instructions given by the Executive Engineer. This

variations so suggested by the defendants was carried out

by the plaintiff as per the aforesaid three reports. The

learned trial Court has culled out the said clauses in its

judgment and has come to the conclusion that, because of

delay in carrying out the work at the instance of the

defendants, plaintiff had to meet extra expenses. It was

directed to the plaintiff to stop the work. Even DW.1

admits that plaintiff to carry out as per the schedule which

is claimed in the plaint. When there was delay on the part

of the defendants to approve the new design or change or

evidence brought on record, the time stipulated as per the

agreement expired, the plaintiff proceeded with a work as

- 37 -

NC: 2025:KHC:5094-DB

admitted by DW.1 then, no fault can be found with the

plaintiff. When delay is caused at the instance of the

defendants, definitely plaintiff is entitled for schedule rates

for the work carried out by him beyond the stipulated

period as agreed. Though the defendants contend that

plaintiff is not entitled but, the evidence of PW.1 clearly

shows that the tender so accepted provided a rate of

cement at the rate of Rs.124/- per bag and plaintiff had

used 15,000 bags of cement. This fact is not denied by

DW.1 throughout his cross-examination. To that effect,

plaintiff has produced the bunch of bills as per Ex.P44

which are marked without any objections from defendant

side, thereby the plaintiff had to spend Rs.26/- more

towards each cement bag. In addition to the value of

cement per bag, it is not ruled out that, plaintiff had to

meet other incidental expenses also towards loading

charges, transportation etc., Though the learned counsel

for the defendants relied upon various judgments and

evidence but, purchase of the cement at the rate of

Rs.150/- per bag by the plaintiff from various places as

- 38 -

NC: 2025:KHC:5094-DB

stated in Ex.P44 bunch of bills and its loading and

transportation charges is not denied by the defendants. If

that is so, now the defendant cannot escape the liability

towards plaintiff.

37. Even Clause 59 of the agreement, though

specifically states about prohibiting compensation for delay

beyond the contractual period, but, Sec.70 of the Indian

Contract Act, comes to the rescue of the plaintiff wherein,

it states that, it is the obligation of a period enjoin benefit

of non-gratuitous Act. This section says

"Where a person lawfully does anything for another person or delivers anything, not intending to do so gratuitously such other person enjoins the benefit thereof, the latter is bound to make compensation to the former in respect of or to restore, the thing, so done or delivered."

38. Section 70 of Indian Contract Act says, though

there is an agreement, even it need not be expressed in

words to pay the compensation but, it is reasonable and

- 39 -

NC: 2025:KHC:5094-DB

worth to say that, a claim for compensation/rates now

claimed by the plaintiff is to be granted. This Section 70 of

Indian Contract Act comes into operation as it is not based

on any subsisting contract between the parties. Its basis is

that, something had been done by one party from the

other which the other party has voluntarily accepted.

Therefore, Section 70 and para. 3 of Section 73 are based

on the `Doctrine of Restitution' which prevents unjust

enrichment by retaining anything received by a party

which does not belong to him and he must return it to the

person from whom he received it and if action is not

possible pay him in its money value.

39. Based on the provisions of Section 70 of the

Indian Contract Act, the principle of `Quantum meruiut'

i.e., if any person does any work without any agreement

and if the said benefit has been appropriated by the other

party, then party who has done the work is entitled for

payment to the extent of benefit taken by the other party.

- 40 -

NC: 2025:KHC:5094-DB

Therefore, this principle is aptly applicable to the claim of

the plaintiff.

40. Thus, by applying the provisions of Section 70

and 73 of IC Act as admitted by DW.1, certainly

defendants cannot deny the work done by the plaintiff

beyond the stipulated time at their instance and he was

compelled to spend more amount than stipulated in the

agreement and had to incur Rs.26/- more per cement bag.

It is not the case of the defendants that, they entered into

contract with plaintiff without any authority. The plaintiff

met the said expensed who was entrusted with the work

even beyond the period stipulated and he was under legal

compulsion to complete the work and there was a pressure

to complete the work. Therefore, the plaintiff has claimed

the scheduled rates which cannot be denied by the

defendants. Likewise, plaintiff has claimed certain amount

from the plaintiff as stated above towards various claims

and because of that delay and stoppage of the work by the

defendants, the plaintiff was to pay the idle charges, so

- 41 -

NC: 2025:KHC:5094-DB

also other labour charges. Though the defendants deny

about the same, but, it is plaintiff who is ultimately

affected and there is failure to discharge the liability by the

defendants. Therefore, under Section 72 of the Indian

Contract Act, the plaintiff has a right to enforce his claim

and make the defendants liable for the same who are

guilty of delay. Section 73 of the Indian Contract Act

speaks of compensation for loss or damage caused by a

breach of contract. If the provisions of Section 73 of IC Act

is applied to the present facts of the case, the first

paragraph of Section 73 deals with compensation for loss

or damage caused by breach of contract. In this case,

there is no breach of contract and contract is not broken.

But, however, the second paragraph speaks of no

compensation is payable for any remote or loss or

damage. But, the fourth paragraph provides that while

assessing the damage, the existing work carried out has to

be taken into consideration and such plaintiff cannot be

put to any inconvenience and his claim cannot be denied.

Even defendants have not stated that there is a breach of

- 42 -

NC: 2025:KHC:5094-DB

contract. A special right was given to the plaintiff for

extending the time making him to comply the obligations

of completing the work. no notice was issued by the

defendants that they have terminated the work contract.

By Feb. 1999, he completed the work.

41. It is a suit for recovery of money based upon

the contract entered into between the plaintiff and

defendants and the contract is concluded and now the

plaintiff has claimed the scheduled rates. There is no

breach of contract at any point of time. Therefore, as

rightly concluded by the trial Court, as the delay occurred

at the instance of the defendants and in view of the strict

provisions of Indian Contract Act, the defendants are

bound to pay the amount to the plaintiff.

42. On the suit claim, the plaintiff has claimed

interest at the rate of 24% but, the learned trial Court has

granted 12% interest on the same from the date of suit till

its realization by applying the provisions of Sec.34 of CPC

and rightly concluded that defendants are liable to pay the

- 43 -

NC: 2025:KHC:5094-DB

suit claim together with interest at 12% p.a. It has come

in the evidence of PW.1 that, he had employed 100

labourers by paying them Rs.40 per day i.e.Rs.4,000/- per

day and he claimed such amount for 320 days and he has

produced Ex.P31 and 32 giving the particulars of

labourers. Though it is the case of the defendants that, no

proper account is maintained, but, in view of the clauses

mentioned in the agreement, the plaintiff has to subscribe

his workers to the contractor's benevolent fund to the

extent of 0.10 percent and to that effect, amount is to be

calculated. The defendants have to deduct the subscription

furnished by the plaintiff. As rightly discussed by the trial

Court, there is no pleading to that effect by the plaintiff.

Thus, the learned trial Court has concluded about

entitlement of labour charges. The documents produced by

the plaintiff i.e. log books marked at Ex.P25 to 30 shows

the details of machineries and their use by the plaintiff

during the aforesaid days. For the delay caused by the

defendants, plaintiff has claimed the amount for men and

machineries. We do not find any factual error in view of

- 44 -

NC: 2025:KHC:5094-DB

the documents so produced. These documents are

undisputed by the defendants. Though the defendants

contend so many factual aspects but, they admit about the

delay caused by them. There is admission by DW.1 in the

cross-examination that, "if there was no change in the

design approval, the work would have been completed

within the time stipulated in the agreement" itself shows

that, at their instance there was a delay and plaintiff has

to meet extra expenses because of that delay.

43. In view of all these factual features coupled with

admissions of DW.1, it can very well be stated that, the

learned trial court is right in concluding that the plaintiff is

entitled for suit claim.

44. Though the defendants contend that, claim of

the plaintiff is barred by law of limitation but, in view of

the stand taken by the defendants in the written statement

and stand taken by DW.1 in the cross-examination, his

admissions in the cross-examination do establish that

defendants still admit and acknowledge the subsisting

- 45 -

NC: 2025:KHC:5094-DB

liability towards the plaintiff. Therefore, plaintiff can take

the benefit of Section 19 of Indian Limitation Act. That

means when there is acknowledgement of liability by

defendants and by virtue of correspondences made by

defendants' officials acknowledging the work carried out by

the plaintiff and so also expressing their inability to pay

the amount etc., now the defendants cannot contend that

they are not liable to pay the suit claim as it is time

barred. Therefore, we do not find any factual or legal error

committed by the trial Court in decreeing the suit.

Therefore, the claim of the plaintiff is based upon the

factual pleadings and the work carried out by him. Though

the defendants recognize the work of the plaintiff and

appreciate that there are no defects in the work but, have

withheld the amount due to the plaintiff which has made

him to wait till this day to get his own money for which he

is legally entitled. Therefore, the aforesaid points are

answered accordingly.

- 46 -

NC: 2025:KHC:5094-DB

45. In view of our discussion made in the foregoing

paras, appeal fails and is liable to be dismissed with cost of

respondent. Resultantly, we pass the following:

ORDER

i. Appeal filed by defendants is

dismissed with cost of the

respondent/plaintiff.

ii. Judgment and Decree dated

30.09.2010 passed in OS No.40/2004

by the Senior Addl.Civil Judge and

CJM, Tumkur, is hereby affirmed.

iii. Defendants are directed to pay the

decreetal amount with interest to the

plaintiff within two months from the

date of receipt of a certified copy of

the Judgment.

- 47 -

NC: 2025:KHC:5094-DB

iv. Send back the trial Court records

along with a copy of this judgment

forthwith.

Sd/-

(S.G.PANDIT) JUDGE

Sd/-

(RAMACHANDRA D. HUDDAR) JUDGE

SK/CT-VG

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter