Citation : 2024 Latest Caselaw 25763 Kant
Judgement Date : 30 October, 2024
-1-
NC: 2024:KHC:44278
MFA No. 3302 of 2024
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 30TH DAY OF OCTOBER, 2024
BEFORE
THE HON'BLE MR JUSTICE H.P.SANDESH
MISCELLANEOUS FIRST APPEAL NO.3302 OF 2024 (CPC)
BETWEEN:
MR. DHANANJAYA M
S/O LATE MALLIKARJUNAIAH
AGED ABOUT 53 YEARS,
RESIDING AT NO.28, 5TH CROSS,
NEHRU ROAD NEW GUDRADADHALLI,
MYSORE ROAD,
BANGALORE-560026.
...APPELLANT
(BY SRI NAVEENNANDA D T, ADVOCATE)
AND:
Digitally signed M/S ASHRAYA CONSTRUCTIONS
by DEVIKA M REP. BY ITS PROPRIETOR,
Location: HIGH SRI ADARSHA N
COURT OF
KARNATAKA S/O NARAYANAPPA
OFFICE AT NO. 431, 4TH MAIN
4TH CROSS, KENGERI SATELLITE TOWN,
BANGALORE-560060.
...RESPONDENT
(BY SRI DORESWAMY GOWDA E, ADVOCATE)
THIS MFA IS FILED U/O 43 RULE 1(r) OF CPC,
AGAINST THE ORDER DATED 15.04.2024 PASSED ON
I.A.NOS. 1 AND 2 IN OS.NO.8415/2023 ON THE FILE OF
THE X ADDITIONAL CITY CIVIL AND SESSIONS JUDGE,
BENGALURU (CCH-26) AND ETC.
-2-
NC: 2024:KHC:44278
MFA No. 3302 of 2024
THIS APPEAL, COMING ON FOR ADMISSION, THIS
DAY, JUDGMENT WAS DELIVERED THEREIN AS UNDER:
CORAM: HON'BLE MR JUSTICE H.P.SANDESH
ORAL JUDGMENT
This Miscellaneous First Appeal is filed challenging
the order dated 15.04.2024 passed on I.A.Nos.I and II in
O.S.No.8415/2023 by the X Additional City Civil and
Sessions Judge, Bangalore.
2. Heard the learned counsel appearing for the
respective parties.
3. The learned counsel appearing for the appellant
would vehemently contend that the Trial Court has
committed an error in granting the relief of temporary
injunction and fails to take note of the fact that the
appellant/defendant is in actual physical possession of the
suit schedule property and the suit schedule property
belongs to him. The counsel further contend that there
was an agreement for construction of building with the
NC: 2024:KHC:44278
respondent and only right was given to the respondent is
to put up the construction in terms of the agreement. But
the Trial Court fails to take note of the said fact into
consideration and granting the relief of not to interfere
with the plaintiff's possession over the suit schedule
property does not arise. The counsel also submits that the
appellant has already paid an amount of Rs.20 lakh and
only initial construction i.e., putting up of retention wall,
columns and foundation is done and payment ought to
have been made after the first slab but in the meanwhile,
the dispute was raised between the appellant and the
respondent and the respondent/plaintiff also insisting for
further payment and the respondent does not have any
right to get an order of injunction restraining the appellant
from interfering with his property. Hence, the Trial Court
committed a serious error in coming to the conclusion that
the plaintiff has made out a prima facie case and balance
of convenience lies on the plaintiff since it is only a
agreement between the parties for construction of the
building and if any dispute with regard to the payment of
NC: 2024:KHC:44278
the amount spent by the respondent is concerned, he has
to file a suit for recovery of money and not a suit for
injunction restraining the owner from interfering with the
possession of his property and no such exclusive
possession is given to the respondent and only he was
permitted to put up the construction in terms of the
agreement.
4. The counsel also submits that already the
appellant has terminated the agreement on 11.10.2023
and the same was sent through an e-mail on 15.10.2023
as per Annexure-G. The counsel also submits that when
the notice was given terminating the agreement of
construction, the question of granting the interim relief in
favour of the respondent does not arise.
5. Per contra, the learned counsel appearing for
the respondent would vehemently contend that the
appellant also filed the petition before the consumer
redressal forum for the deficiency of service and same was
opposed by the respondent by filing statement of
NC: 2024:KHC:44278
objection. The counsel also submits that the appellant not
dispute the fact that work was entrusted to the respondent
for construction as per the agreement and the Trial Court
taking into note of the material available on record, rightly
comes to the conclusion that the respondent/plaintiff has
made out a prima facie case and granted the relief and
hence, it does not requires any interference.
6. Having heard the learned counsel appearing for
the respective parties and also on perusal of the material
available on record, it discloses that it is not in dispute
that there was an agreement dated 15.06.2023 for
construction. It is important to note that in terms of the
agreement, the cost of construction is Rs.1,02,00,000/-
and in the payment column, it is specifically mentioned
that on what date, the payment has to be made and
description of work also shown in the agreement itself. It
is also not in dispute that the respondent has taken up the
construction work and he had already constructed
retention wall and put up foundation and columns also
NC: 2024:KHC:44278
raised and the appellant has made the payment of Rs.20
lakh. The counsel for the appellant also would vehemently
contend that the report produced by the appellant shows
that even work was not done for having made the
payment of Rs.20 lakhs. The counsel for the respondent
would vehemently contend that more than Rs.35 lakhs
work was done as per the report given by the surveyor.
The counsel for the appellant also relies upon the report of
the valuer with regard to the value of the construction
carried out. The counsel for the respondent submits that
he has also taken the report. Now it is clear that the
dispute is with regard to payment is concerned. When
such being the case, the relief has to be sought in terms of
money and the question of granting the discretionary relief
of restraining the appellant/owner from interfering with
the possession of his property does not arise.
7. It is not in dispute that the property belongs to
the appellant and construction work was entrusted to the
respondent. If there is any dispute between the parties
NC: 2024:KHC:44278
with regard to the payment is concerned, there is a bar
under Section 41(h) of the Specific Relief Act to grant the
relief of temporary injunction. The claim made by the
plaintiff is that he had invested more money for the
construction of the building other than the amount what
he had received. On the other hand, it is the contention of
the appellant/defendant that the respondent did the work
lesser the amount what he had received and the work is
also not the quality work. Hence, dispute raised between
them. When such being the case, the Trial Court ought
not to have granted the relief of temporary injunction
against the owner from interfering with his property. If
there is any dispute with regard to the difference of
amount in respect of the work carried out by the
respondent as well as the work obtained from the
appellant that has to be sorted out and if not, can file a
suit for recovery of money. Even the respondent can file a
suit against the appellant for recovery of amount if he has
spent more amount than what he had received for the
construction and there cannot be an interim order of
NC: 2024:KHC:44278
injunction restraining the owner and no exclusive
possession was given to the respondent and he was only
permitted to put up construction in terms of the contract
entered between the parties. Hence, the Trial Court
committed an error in granting such an interim order by
exercising discretion. No doubt, the Trial Court while
passing the order of injunction restraining the defendant
also made it clear that the said order also subject to
variation, cancellation or modification if necessary and
hence, it is clear that the Trial Court also comes to the
conclusion that the order can be modified. This Court
already comes to the conclusion that there is a bar under
Section 41(h) of the Specific Relief Act in granting of
discretionary relief and the same is payable in terms of
monetary relief. When such being the case, I have
already discussed that if any loss incurred by the
plaintiff/respondent in terms of the contract, he has to
recover the same by filing a suit. Hence, the order
requires to be set aside.
NC: 2024:KHC:44278
8. In view of the discussions made above, I pass
the following:
ORDER
The Miscellaneous First Appeal is allowed.
The impugned order dated 15.04.2024 passed on
I.A.Nos.I and II in O.S.No.8415/2023 by the X Additional
City Civil and Sessions Judge, Bangalore is set aside.
The Trial Court is directed to dispose of the matter
within nine months from today.
The respective parties and their counsel are directed
to assist the Trial Court in disposal of the suit within a time
bound period of nine months.
Sd/-
(H.P.SANDESH) JUDGE
SN
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!