Monday, 01, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Smt Gangavva W/O Hanumantappa ... vs The Special Land Acquisition Officer
2024 Latest Caselaw 19113 Kant

Citation : 2024 Latest Caselaw 19113 Kant
Judgement Date : 31 July, 2024

Karnataka High Court

Smt Gangavva W/O Hanumantappa ... vs The Special Land Acquisition Officer on 31 July, 2024

Author: Shivashankar Amarannavar

Bench: Shivashankar Amarannavar

                                          -1-
                                                     NC: 2024:KHC-D:10797
                                                 MSA No. 100125 of 2022




                  IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH
                        DATED THIS THE 31ST DAY OF JULY 2024
                                       BEFORE
              THE HON'BLE MR. JUSTICE SHIVASHANKAR AMARANNAVAR

                  MISCELLANEOUS SECOND APPEAL NO. 100125 OF 2022
             BETWEEN:

             SMT. GANGAVVA W/O. HANUMANTAPPA NADUVINAHALLI,
             AGE: 60 YEARS, OCC: HOUSEHOLD/AGRICULTURE,
             R/O: DHUPDAL VILLAGE, TQ: SAUNDATTI,
             DIST: BELAGAVI - 591111.
                                                         ...APPELLANT

             (BY SRI. G.N. NARASAMMANAVAR AND SRI.P. V. SAMBARGI,
             ADVOCATES)

             AND:

             1.   THE SPECIAL LAND ACQUISITION OFFICER,
                  MALAPRABHA PROJECT III, DHARWAD,
                  NOW AT SECTOR NO. 60, NAVANAGAR,
                  TQ AND DIST: BAGALKOT - 587103.

             2.   THE EXECUTIVE ENGINEER,
                  KNNL NAVILUTHREETH NO.2,
                  DAM SITE, TQ: SAUNDATTI,
YASHAVANT         DIST: BELAGAVI - 591126.
NARAYANKAR                                                 ...RESPONDENTS
             (BY SMT. GIRIJA S. HIREMATH, HCGP FOR R1;
Location:    SRI. UMESH C. AINAPUR, ADVOCATE FOR R2)
HIGH COURT
OF
KARNATAKA          MSA FILED U/S 54(2) OF LAND ACQUISITION ACT, 1894,
             PRAYING TO ENHANCED THE MARKET VALUE AT THE RATE OF RS.
             5,08,000/- PER ACRE WITH ALL STATUTORY BENEFITS BY
             MODIFYING THE JUDGEMENT AND AWARD PASSED IN LAC
             NO.270/2011 DTD 03.02.2012 PASSED BY THE PRINCIPAL SENIOR
             CIVIL JUDGE SAUNDATTI AND LAC APPEAL NO.2/2018 DTD
             17.09.2022 PASSED BY THE XI ADDITIONAL DISTRICT AND
             SESSIONS JUDGE, BELAGAVI, IN THE INTEREST OF JUSTICE AND
             THIS APPEAL BE ALLOWED WITH COST.
                                  -2-
                                             NC: 2024:KHC-D:10797
                                          MSA No. 100125 of 2022




      THIS APPEAL COMING ON FOR ADMISSION THIS DAY, THE
COURT DELIVERED THE FOLLOWING:
CORAM:      THE HON'BLE MR. JUSTICE SHIVASHANKAR AMARANNAVAR

                          ORAL JUDGMENT

The appellant is claiming enhanced compensation on

the basis of judgment and award passed by the

co-ordinate bench of this Court arising out of the same

notification.

2. With the consent of learned counsels on both

sides, the appeal is taken up for final hearing.

3. The respondent/Government of Karnataka

acquired large extent of land by issuing notification under

Section 4 of the Land Acquisition Act, 1894 (for short, 'the

Act'). Thereafter, declaration under Section 6 of the Act

was issued. The SLAO passed the award determining the

market value at Rs.37,325/- per acre with statutory

benefits. The appellant sought enhancement of the

compensation by seeking reference to the Civil Court. The

reference was made under Section 18 of the Act to the

Civil Court for determination of the market value. The

NC: 2024:KHC-D:10797

reference Court allowed the reference in part and fixed the

market value of the acquired property at the rate of

Rs.1,80,000/- per acre with statutory benefits.

4. The appellant being not satisfied, filed an

appeal under Section 54(1) of the Act before the first

appellate Court. There being a delay in filing the appeal,

the application was filed under Section 5 of the Limitation

Act. The appellate Court having dismissed the application

filed seeking condonation of delay and consequently,

dismissed the appeal. Hence, this appeal under Section

54(2) of the Act is filed.

5. It is the case of the appellant that on account of

her financial condition, illiteracy and dependency on

others, there was delay in filing the appeal before the

District Court. It is submitted on behalf of the appellant is

peasant and illiterate and that by the belated filing of the

appeal, she did not gain anything.

6. It is further submitted that delay being

bonafided and for the reasons beyond their control, it is

NC: 2024:KHC-D:10797

liable to be condoned. It is further submitted that the

Court below is unjustified in refusing to condone the delay

and has erred in dismissing the appeal, despite the appeal

filed by other claimants having been allowed and

compensation payable determined at Rs.3,50,000/- per

acre with statutory benefits. Reliance was placed on the

common judgment passed in MSA No.100012/2016 with

connected matters, decided on 19.07.2016 i.e., for grant

of enhanced compensation and also for condonation of

delay.

7. On the other hand, learned counsel for

respondent No.2 submitted that the delay being

inordinate, having not been satisfactorily explained and

there being negligence and latches on the part of the

appellant, the first appellate Court is justified in refusing to

condone the delay and consequently, dismissing the

appeal. The learned counsel submits that if this Court

comes to the conclusion that opportunity should be given

to the appellant to lead evidence on delay condonation

NC: 2024:KHC-D:10797

application, the matter be remanded to the appellate

Court.

8. Considering the rival submissions and perusing

the record, the points for consideration are:

i. Whether the appellate Court has erred in refusing to condone the delay and dismissing the appeal?

ii. Whether the appellant is entitled for payment of enhanced compensation?

9. Re-point No.1: No doubt, there is long delay in

filing the appeal before the District Court. However, it is to

be seen that the first appellate Court has passed awards in

respect of the appeals filed by other claimants involving

the lands acquired under the same notification and for the

same project. The appellate Court has allowed the appeals

and enhanced the compensation payable at the rate of

Rs.3,50,000/- per acre with the statutory benefits.

10. In the second appeal preferred by the other

claimant, co-ordinate Bench has fixed the market value of

NC: 2024:KHC-D:10797

the acquired property at Rs.5,08,000/- per acre with all

statutory benefits. Thus, there being prima facie case for

consideration, the appellate Court should have kept in

view the fact that the appellant is an agriculturist and

could not prefer the appeal within the period allowed

under law, should have allowed the appeal taking note of

weak financial condition and valuable piece of land held by

the appellant, having been acquired, the compensation in

accordance with law is required to be paid also keeping in

view Article 300-A of the Constitution. At this stage, it

would be appropriate to notice that almost in similar

situation, in the case of Market Committee Hodal V/s

Krishan Murari, (1996) 1 SCC 311, the Hon'ble Apex

Court has condoned delay of 3240 days.

11. The appellant being a woman and not well

educated and being dependent upon others even to put

forth her claim, a lenient approach has to be adopted and

she should not be deprived the just compensation for

acquisition of her land i.e., the payment of compensation

NC: 2024:KHC-D:10797

on par with similarly situated land owners. The appellate

Court has not adopted a pragmatic approach.

12. In the circumstances, equities can be balanced

by denying interest for the period for which she did not

approach the District Court. There can be denial of interest

for the delay period in preferring the first appeal. The

appellate Court ought to have kept in view the principles

enunciated by the Apex Court regarding condonation of

delay, in the case of Collector (Land Acquisition) V/s

Mst. Katiji and Ors. (1987) 2 SCC 107, which was

followed in the case of DDA V/s Bhola Nath Sharma

(2011) 2 SCC 54, wherein, the matter related to the land

acquisition.

13. Having regard to the above, the appellate Court

has committed an error in refusing to condone the delay.

The co-ordinate bench of this Court, in the case of

Razaqsab M. Kamalsabanavar and Another V/s The

Special Land Acquisition Officer, Malaprapha

Project-3, Dharwad and connected matters decided on

NC: 2024:KHC-D:10797

19.07.2016 has considered the above aspects and

condoned the delay in filing the appeal denying the

interest for the period of delay.

14. Keeping in view of the above, the delay in filing

the appeal filed before the appellate Court stands

condoned by denying the interest for the period of delay.

It is made clear that there shall be no liability on the

respondents to pay interest to the appellant on the

enhanced compensation for the period of delay in filing the

appeal under Section 54(1) of the Act. Point No.1 stands

answered accordingly.

15. Re-point No.2: In respect of similar lands

acquired for same project, the appellate Court has

determined compensation payable at Rs.3,50,000/- per

acre and allowed statutory benefits. The co-ordinate bench

in the case of Razaqsab (supra), in respect of similar

lands acquired for same project following the judgment

and award dated 26.08.2013 passed in MFA

No.24037/2012 and MFA No.21438/2012 and connected

NC: 2024:KHC-D:10797

appeals, the compensation payable was determined at

Rs.5,08,000/- per acre with the statutory benefits. Hence,

the appellant being identically placed and the land being of

similar nature acquired for the same project, the appellant

is entitled to the market value of Rs.5,08,000/- per acre

along with statutory benefits and costs, as was determined

by the Division Bench of this Court in MFA No.21438/2012

and connected appeals disposed of on 13.11.2014.

16. In view of the above, the following:

ORDER

i) Appeal is allowed with cost and the impugned

judgments and awards are set aside.

ii) The market value of acquired property of the

appellant is fixed at Rs.5,08,000/- per acre with all

statutory benefits and costs.

iii) The appellant is not entitled to interest for the

delay period in preferring of the first appeal. The

enhanced award amount shall be deposited in the

reference Court within a period of three months.

- 10 -

NC: 2024:KHC-D:10797

iv) The office is directed to draw award accordingly.

Sd/-

(SHIVASHANKAR AMARANNAVAR) JUDGE

RKM CT:ANB

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter