Monday, 01, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Nischal Constructions vs The Vice Chancellor
2024 Latest Caselaw 18719 Kant

Citation : 2024 Latest Caselaw 18719 Kant
Judgement Date : 26 July, 2024

Karnataka High Court

M/S Nischal Constructions vs The Vice Chancellor on 26 July, 2024

                          -1-




 IN THE HIGH COURT OF KARNATAKA AT BENGALURU

        DATED THIS THE 26TH DAY OF JULY, 2024

                      PRESENT
       THE HON'BLE MR JUSTICE V KAMESWAR RAO
                         AND
           THE HON'BLE MR JUSTICE C M JOSHI
              RFA NO. 108 OF 2019(MON)
BETWEEN:

M/S. NISCHAL CONSTUCTIONS,
A PROPRIETARY CONCERN,
REPRESENTED BY ITS PROPRIETOR,
SRI.G.C.RAMACHANDRA,
S/O. SRI.CHENNIGARAYAPPA,
R/O. NO.111, 16TH CROSS ROAD,
11TH MAIN ROAD,
NEAR LAKSHMIKANTHA KALYANA MANTAPA,
PADMANABHANAGAR,
BANGALORE - 560 070.

                                         ...APPELLANT
(BY SRI. AMITH L.M, ADVOCATE FOR
    SRI. L.M. CHIDANANDAYYA, ADVOCATE)

AND:

1.     THE VICE CHANCELLOR,
       TUMKUR UNIVERSITY,
       VISHWAVIDAYALAKARYALAYA,
       B.H.ROAD,
       TUMAKURU.

2.     TUMKUR UNIVERSITY,
       REPRESENTED BY ITS
       REGISTRAR,
       VISHWAVIDAYALAKARYALAYA,
       B.H.ROAD,
       TUMAKURU.
                                  -2-




3.   THE REGISTRAR,
     TUMKUR UNIVERSITY,
     VISHWAVIDAYALAKARYALAYA,
     B.H.ROAD,
     TUMAKURU.

4.   EXECUTIVE ENGINEER,
     TUMKUR UNIVERSITY,
     VISHWAVIDAYALAKARYALAYA,
     B.H.ROAD,
     TUMAKURU.

5.   FINANCE OFFICER,
     TUMKUR UNIVERSITY,
     VISHWAVIDAYALAKARYALAYA,
     B.H.ROAD,
     TUMAKURU.

                                                ...RESPONDENTS

(BY SRI. PALLAVA R., ADVOCATE FOR R1 TO R3,
     R4 AND R5 SERVED, BUT UNREPRESENTED)


     THIS APPEAL IS FILED UNDER SECTION 96 OF THE
CODE OF CIVIL PROCEDURE AGAINST THE JUDGMENT AND
DECREE DATED 27.08.2018 PASSED IN OS 81/2016 ON THE
FILE OF THE III ADDITTIONAL SENIOR CIVIL JUDGE AND
JMFC.,   TUMKUR      PARTLY      DECREEING     THE   SUIT   FOR
RECOVERY OF MONEY.

     THIS APPEAL HAVING BEEN HEARD AND RESERVED ON
14.06.2024,    COMING       ON    FOR    PRONOUNCEMENT       OF
JUDGMENT      THIS   DAY,     THE      COURT   DELIVERED    THE
FOLLOWING:
                              -3-




CORAM:    THE HON'BLE MR JUSTICE V KAMESWAR RAO
          AND
          THE HON'BLE MR JUSTICE C M JOSHI


                      CAV JUDGMENT

(PER: THE HON'BLE MR JUSTICE V KAMESWAR RAO)

This Regular First Appeal ('RFA' in short) has been

filed by the appellant herein assailing the judgment of the

Court of III Additional Senior Civil Judge and JMFC,

Tumakuru in OS No.81/2016, whereby the learned Trial

Court had decreed the suit partially with cost.

2. The appeal has been filed to the extent of

Judgment & Decree denying the interest on Rs.2,67,217/-

at 18% p.a. and also interest of Rs.20,09,275/- being 18%

on the paid amount and the loss of profit and the legal

expenses claimed by the appellant in the aforesaid suit.

3. Some of the facts to be noted in this judgment

are, Respondent No.1 is the University established by the

Government of Karnataka under the Karnataka State

Universities Act. The other respondents are the

functionaries of Respondent No.1. The respondents invited

E-Bids in order to undertake the repair works of

underground drainage, water supply and electricity

connection to the Faculty Guest House at Tumakuru

University.

4. The case of the appellant-M/s. Nischal

Constructions ('Company' for short) before the Trial Court

was that, it had obtained the Tender Form and submitted

its Tender through Techno-Commercial Bid and the price

bid on 22.03.2013 to the respondents. The appellant was

the sole bidder to the said work of the respondents.

Accordingly, it qualified for the said work for a sum of

Rs.56,40,125/- which was the lowest one. Thereafter, the

respondents have placed the quotation of the appellant

before the Syndicate of the University and passed a

resolution accepting the Bid of the appellant for a sum of

Rs.56,40,125/-. Thereafter, on 29.03.2013, Respondent

No.1 on behalf of University, had issued Letter of

Acceptance and called upon the appellant to sign the

agreement in terms of Para No.24.4 of invitation Bid.

5. It was the case of appellant, as per the terms of

agreement, the period of completion of the project was

fixed as three months from the date of agreement. But,

the respondents instructed the appellant to complete the

work within 30 days due to urgency and accordingly, the

appellant has mobilized the huge resources for the purpose

of executing the project work within 30 days.

6. It was the case of the appellant that, it had

completed the entire work on 28.04.2013 in less than 30

days from the date of entrustment of the project work. It

was also the case of the appellant that, the respondents

issued Work Completion Certificate intimating that, the

appellant has completed the entire work at Rs.56,40,125/-.

7. It was also the case of the appellant that, the

project work was for a higher consideration and there was

no denial of payment to the said work. Therefore, there

was a contractual obligation on the part of the respondents

to pay bill amount without any delay.

8. The stand taken by the appellant was that, as

per the terms and conditions of the contract, the bill shall

be paid within 60 days from the date of submission of the

Bill. It after completing the entire project work, had

submitted the first and final bill on 28.04.2013 to the

Executive Engineer as per the terms and conditions of the

agreement.

9. Thereafter, the Executive Engineer cross-checked

the said bill with reference to the bills of quantity in the

tender and certified the bill for payment of

Rs.56,39,678.81. However, the Vice Chancellor, without

any basis, had on 13.01.2015, placed the Bill before the

Syndicate of University. The Syndicate passed a resolution

for payment of Rs.56,25,322.50 to the appellant.

10. It was the case of the appellant that there was no

authority to the Vice Chancellor to deduct a sum of

Rs.2,67,217/- from the running account bill submitted by

the appellant. It was stated that the Vice Chancellor

without any authority, passed an order on 05.05.2015

directing to deduct Rs.2,67,217/- by falsely stating that the

plaintiff has not executed the work to the tune of

Rs.2,67,217/-. Accordingly, payment of Rs.53,58,107-50

was made on 08.03.2015.

11. The appellant addressed a letter to the

respondents dated 01.06.2015 for payment of the balance

amount together with interest. However, the respondents

had not taken any steps in spite of receiving said letter.

12. It was the case of the appellant that the

respondents have illegally delayed payment of its final bill

amount and illegally withheld the balance amount of

Rs.2,67,217/- without any proper reason.

13. The appellant got issued a legal notice calling the

respondents to make payment of the balance amount of

Rs.2,67,217/- with interest at 18% p.a. Further, the

interest at the rate of 18% p.a., on the delayed payment of

Rs.53,58,107-50 to the tune of Rs.20,09,275/- was

claimed apart from loss of profit on account of blockade of

funds to the tune of Rs.25,00,000/- and legal expenses of

Rs.5,00,000/-.

14. The non-payment of the aforesaid amount has

resulted in filing of the suit, wherein the impugned

judgment and decree has been passed.

15. The case of the respondents before the trial

Court was that the, Tender Notification dated 19.02.2013

was issued. The said tender was allotted to the appellant

for contract price of Rs.56,40,125/-. They have also issued

the Letter of Acceptance to the appellant dated 29.03.2013.

On the aspect of deduction of Rs.2,67,217/- is concerned,

their case was that the appellant has not done the project

work properly and as such, they have held-up the said

amount as per the opinion of the Senior Engineer and paid

the entire amount to the appellant by obtaining permission

from the committee and there was no balance amount due

for payment to the appellant.

16. Based on the pleadings of the parties, the Trial

Court had framed eight issues in the following manner:-

i) Whether plaintiff proves that it has completed the tender work as per the tender contract?

ii) Whether plaintiff proves that it has submitted first and final bill within time?

iii) Whether plaintiff proves that the defendants are due to pay bill amount of Rs.2,67,217/- to him?

iv) Whether plaintiff proves that the defendants are liable to pay interest of 18% p.a. to the plaintiff on dues as claimed?

v) Whether plaintiff proves that the defendants are liable to pay interest on delayed payment, loss of profit on account of blockade of funds and legal expenses as claimed?

vi) Whether defendants prove that the plaintiff has not executed the tender work as per agreed quality and quantity?

vii) Whether the plaintiff is entitled for the reliefs as prayed?

viii) What order or decree?

17. The Issue Nos. 1, 2, 3, 4, 5 & 7 have been

decided partially in the affirmative. Issue No.6 was

decided in the negative. Issue No.8 was decided as per

the final order.

18. Suffice to state, the Trial Court has granted an

amount of Rs.2,67,217/- to the appellant with interest at

the rate of Rs.6% p.a., from the date of suit till realization.

The Trial Court has also granted an amount of

Rs.2,00,000/- towards loss of profit on account of delay in

payment of bill amount, the legal expenses and other

charges to the plaintiff. While granting interest of 6% p.a.,

instead of 18% p.a., as was claimed by the appellant, the

- 10 -

conclusion of the Trial Court was that, there is no

conclusive proof that the respondents have agreed for

payment of the amount with interest at the rate of 18%

pa., in the event of default.

19. In so far as claim for Rs.20,09,275-00 (which is

a claim of interest at the rate of 18% p.a. on Rs.53,58,107-

50) as interest, on the ground that there is delay of 25

months in payment of the said amount is concerned, the

Trial Court has granted an amount of Rs.2,00,000/- under

the head 'Loss of Profit' on account of delay in payment of

bill amount/legal expenses and other charges.

20. The submission of the learned counsel for the

appellant is primarily is that the denial of 18% interest on

the amount of Rs.2,67,217/- and also denial of claim of

Rs.20,09,275/- which claim is on the basis of entitlement of

interest at the rate of 18% p.a., from 28.04.2013 to

08.05.2015 for 25 months is completely illegal and without

authority of law and contrary to the material evidence

produced by the appellant before the Trial Court.

21. He qualifies his submission by stating that, the

Trial Court has failed to consider that it having given a

- 11 -

finding that the deduction of Rs.2,67,217/- is illegal, it

ought to have granted interest at the rate of 18% p.a.,

from the date of submission of the bill till payment.

According to him, the Trial Court failed to consider that,

under Clause (33) of GCC, there is a contractual obligation

on the part of the respondents to make payment of bill

within 60 days from the date of submission of the bill. The

amount of Rs.2,67,217/- was not paid even on the receipt

of the legal notice as on the date of the suit.

22. Therefore, the appellant is entitled to interest at

the rate of 18% p.a.. He submitted that the appellant had

made huge investments for completing the project work.

Therefore, the appellant's entitlement of interest from the

date of submission of bill is genuine and could not have

been denied by the Trial Court. According to him, the

appellant produced the documents to show that the

appellant had suffered on account of breach committed by

the respondents. That apart, there is no justifiable reason

to delay the payment of the final bill for a period of 25

months.

- 12 -

23. In fact, he stated, it is because of the processes

undertaken by the University, (i) by appointing Sri. H.C.

Shivakumar, the Retired Executive Engineer as One Man

Commission, who had verified and found that the appellant

had completed the work and recommended payment of

Rs.56,39,678.81, and (ii) the Vice Chancellor placed the

matter before the Syndicate of University, which also

carried out inspection of the work to assess the quality

though not contemplated in the contract and if such a

process has been undertaken, i.e., at the risk of the

respondents, it could not have caused prejudice to the

appellant resulting in the delay of payment for 25 months.

24. In fact, he heavily relied on the fact that, even

when the Syndicate has recommended the release of the

bill for an amount of Rs.56,39,678-81, the Vice Chancellor

could not have deducted the amount of Rs.2,67,217/-.

25. According to him, the appellant is entitled to the

interest at the rate of 18% p.a. on Rs.2,67,217/- and on

Rs.53,58,107.50 (for 25 months), which has been denied to

the appellant by the Trial Court, by granting 6% interest

and an amount of Rs.2,00,000/- under different heads,

- 13 -

which according to the counsel is a perverse finding over-

looking the stipulation in the GCC, more particularly, which

contemplates release of the bill within 60 days of its

receipt.

26. In support of his submissions, learned counsel has

relied upon two Judgments of the Supreme Court in the

case of State of Haryana and Others Vs. S.L. Arora and

Company reported in (2010) 3 SCC 690 and also in

Executive Engineer Dhenkanal Minor Irrigation

Division, Orissa and others reported in (2001) 2 SCC

721. He also relied upon the judgment in the case of

Secretary, Irrigation Department, Government of

Orissa and others Vs. G.C. Roy and connected appeal,

reported in (1992) 1 SCC 508, in support of his

submissions.

27. On the other hand, learned counsel for the

respondents would contest the appeal filed by the appellant

by stating that, there is no illegality in the judgment and

decree passed by the Trial Court. He stated the plea of the

learned counsel for the appellant on the provision of GCC to

contend that, the time stipulated for payment of final bill

- 14 -

was within 60 days of its presentation is a misconceived

plea as no such stipulation is provided in the agreement.

According to him, the GCC on which reliance has been

placed by the learned counsel for the appellant, has been

issued by CPWD for its own works. The said GCC was not

the part of the contract between the parties.

28. It is his submission that, the grant of interest is a

discretion that lies with the Trial Court, more so when

interest has not been prescribed in the

contract/agreement/statutory provision.

29. He submitted in the background of aforesaid

facts, it has to be seen whether the Trial Court was justified

in granting interest at 6% pa., on the amount of

Rs.2,67,217/-. According to him, the discretion exercised

by the Trial Court is not illegal as there is some basis for

grant of the same.

30. That part, it is his submission that, when there is

no stipulation in the contract, for release of the payment

as per the bill within 60 days, if the respondents after

following the due process ensuring that the appellant has

completed the work as per the tender documents by

- 15 -

appointing One Man Committee and also through the

process of Syndicate of University which concluded that

there was a defective work, resulted in withholding of an

amount of Rs.,2,67,217/-, the action of the respondents

cannot be contested. He do concede to the fact that the

respondents have not filed any appeal against the

judgment and decree. In any case, it is his submission that

the judgment and decree of the Trial Court is justified and

should not be interfered with. In support of his

submissions, he has relied upon the Judgment of the

Supreme Court in the case of Continental India Private

Limited Vs. General Manager, Northern Railway

reported in 2022 SCC OnLine SC 922.

ANALYSIS

31. Having heard the learned counsel for the parties

and perused the record, the question which arises for

consideration is, whether the Trial Court is justified in

awarding interest on Rs.2,67,217/- at the rate of 6% p.a.,

and also awarding Rs.2,00,000/- towards loss of profit on

account of delay in payment of bill amount, legal expenses

and other charges, instead of the claim of the appellant for

- 16 -

interest at the rate of 18% p.a., on Rs.2,67,217/- and also

for interest at the rate of 18% on the delayed payment of

Rs.53,58,107.50 quantified as Rs.20,09,275/- and for loss

of profit on account of blockade of funds of Rs.25,00,000/-

and legal expenses of Rs.5,00,000/-.

32. The plea of the learned counsel for the appellant

is, primarily as the claim of the appellant was on the basis

of a commercial contract and as per Clause 33 of the GCC,

the final bill dated 28.04.2013 having not been paid within

60 days from the date of submission, the Trial Court erred

in not granting interest at the rate of 18% in the manner

claimed.

33. The plea is also that the Trial Court has failed to

consider that, under Clause 33 of the GCC, the

respondent/University had to make payment of bill within

60 days from the date of submission of the bill. So his

submission is that, Rs.2,67,217/- which is with-held

amount having not been paid within 60 days with effect

from 28.04.2013 and also the amount of Rs.53,58,107.50,

having been paid after 60 days, the appellant is entitled to

the interest at the rate of 18% p.a.

- 17 -

34. On the other hand, the learned counsel for the

respondents has disputed the applicability of the GCC to

contend, the same is a part of tender issued by CPWD. In

that sense, clause 33 is not part of the tender documents in

respect of the work in question and hence, it has no

applicability.

35. We agree that the submission of the learned

counsel for the respondents for the reason, it has not been

shown that GCC was made part of the contract. In fact, the

appellant in its written submissions before the Trial Court

has stated that the respondents have not denied Clause-33

in their written statement. Suffice to state an existence of a

clause in contract has to be established from the document

itself and not on the basis of pleadings. It follows the

conclusion of the Trial Court (at Page No.61 of the appeal)

on payment of interest is justified.

36. Having said so, the issue which now has to be

decided is even if interest at the rate of 18% is not an

obligation under the contract, whether the Trial Court has

erred in exercising its discretion to grant interest at the

rate of 6% p.a., and not 18% p.a.?

- 18 -

37. We must state that, the present proceedings

arises from the proceedings initiated before the Civil Court

and not from an award rendered by an Arbitrator. In that

sense, the provisions of Arbitration and Conciliation Act,

1996 in so far as grant of interest by an Arbitrator, are not

applicable.

38. The above has been stated by us because, the

learned counsel for the appellant has heavily relied on the

judgment of the Supreme Court in support of his

submission for grant of interest at the rate of 18% p.a.

The Supreme Court in State of Haryana Vs. S.L. Arora

and Company (supra) has inter alia held that the power of

the Arbitral Tribunal under the old act to award interest was

for post decree. The power of the Trial Court to award

interest is governed by the Interest Act, 1978 and the

Supreme Court in the aforesaid case has held in Paragraph-

22 that the principles relating to award of interest, in

general, are not different for the Courts and the Arbitral

Tribunals, except to the extent indicated in Section 31(7) of

the Act and the Civil Procedure Code.

- 19 -

39. In the case on hand, we are concerned with the

discretion exercised by the Trial Court to award interest at

the rate of 6% p.a. Concedingly, there is no stipulation for

payment of interest in the contract at least nothing has

been shown to us in that regard. In that sense, it has to be

seen whether the discretion exercised by the Trial Court is

justified. The grant of interest at the rate of 18% p.a., as

sought by the appellant is not the normal rate of interest,

nor such an interest rate is prescribed in Section 34 of CPC.

Further, the appellant has not produced any document

showing the respondents have agreed to pay 18% interest

in the event of breach of contract.

40. We note, Courts have on facts granted interest at

6% P.A. In that sense, the grant of 6% of interest is

permissible on facts. In this case the Trial Court, while

granting 6% interest has not given any justification. Be that

as it may, we are of the view, since the respondent No.1 is

a University (educational institute), any grant of interest,

above 6% shall put financial burden on it more so when the

University functions survive on the grant-in-aid provided by

the Government. As such, the grant of 6% interest and

- 20 -

denial of 18% interest by the Trial Court, cannot be faulted.

It follows the grant of interest at 6% p.a., on the amount of

Rs.2,67,217/- is justified. The question would be whether

the grant of Rs.2,00,000/- against loss of profit, on account

of blockade of funds, legal expenses etc., and not in the

manner claimed by the appellant is justified. The claim of

the appellant is also for interest on the amount of

Rs.53,58,107-50/-. Though the same has been claimed at

18% p.a., in view of our above conclusion, even if the

appellant is not entitled to 18%, still the appellant shall be

entitled to interest at 6% p.a., because of delay in making

payment of Rs.53,58,107-50/-. The amount Rs.2,00,000/-

granted by the Trial Court is under different heads. The

same includes loss of Profit because of blockade of funds,

legal expenses etc. We note, there is no justifiable reason

given by the respondents to pay the amount of

Rs.53,58,107-50/- after 25 months. The procedure

evolved by the respondents of constituting a one man

Committee and placing the matter before the Syndicate is

not a stipulated procedure under the agreement and the

same could not have resorted to, which delayed the release

of the payment of Rs.53,58,107-50. So, the delay having

- 21 -

occurred in payment, the issue is whether the Trial Court is

justified in awarding Rs.2,00,000/- as a lump-sum amount

for loss of profit because of blockade of funds, legal

expenses etc. The answer has to be in the negative for the

reason, even if interest for 25 months of delay in releasing

Rs.53,58,107-50/- is calculated at 6% p.a., then also the

amount shall be approximately Rs.6,50,000/- which is

much higher than the amount granted by the Trial Court.

So, the grant of Rs.2,00,000/- for loss of profit, blockade of

funds, legal expenses cannot be countenanced. To that

extent the grant of Rs.2,00,000/- by the Trial Court is

unsustainable. The amount need to be increased to

Rs.6,00,000/- (as a cumulative amount) for loss of profit,

legal expenses etc. We limit the amount to Rs.6,00,000/-

keeping in view the fact that respondent No.1 is an

Educational Institution.

41. So, to that extent, the impugned judgment and

decree is modified. The appellant shall be entitled to an

amount of Rs.6,00,000/- and not Rs.2,00,000/-. The same

shall be paid within twelve weeks of the receipt of Certified

Copy of this order.

- 22 -

42. Decree sheet be prepared accordingly.

43. No costs.

Sd/-

(V KAMESWAR RAO) JUDGE

Sd/-

(C M JOSHI) JUDGE

KGR*

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter