Citation : 2024 Latest Caselaw 18700 Kant
Judgement Date : 26 July, 2024
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 26TH DAY OF JULY, 2024
PRESENT
THE HON'BLE MRS JUSTICE ANU SIVARAMAN
AND
THE HON'BLE MR JUSTICE ANANT RAMANATH HEGDE
COMMERCIAL APPEAL NO. 225 OF 2024
BETWEEN:
M/S SBR INFRA BUILDTECH,
A PARTNERSHIP FIRM,
REGISTERED UNDER THE INDIAN
PARTNERSHIP ACT 1932, HAVING ITS OFFICE AT
SY NO 24/5, SBR HORIZON SEEGEHALLI,
BENGALURU - 560067,
REPRESENTED BY ITS MANAGING PARTNER
MR T VENUGOPAL.
...APPELLANT
(BY SRI SIDDHARTH SUMAN, ADVOCATE)
AND:
M/S. APYA CAPITAL SERVICES PRIVATE LIMITED,
A COMPANY INCORPORATED UNDER THE PROVISION
OF THE COMPANIES ACT 1956
HAVING ITS REGISTERED OFFICE AT FLAT NO.22,
TOWER 6, PEBBLE BAY, RAJ MAHAL VILAS - II,
RAMAKRISHNAPPA LAYOUT,
NAGASHETTY HALLI, BENGALURU - 560094,
REPRESENTED BY ITS AUTHORIZED SIGNATORY
MS DURGA G.
...RESPONDENT
(BY SRI CHINTAN CHINNAPPA, ADV. FOR C/RESPONDENT)
-2-
THIS COMMERCIAL APPEAL IS FILED UNDER
SECTION 13 (1a) OF THE COMMERCIAL COURTS ACT 2015
UNDER SECTION 37 (1) (b) OF THE ARBITRATION AND
CONCILIATION ACT 1996 PRAYING THAT THIS HON'BLE
COURT BE PLEASED:
(i) TO CALL FOR THE RECORDS AND SET ASIDE
THE ORDER DATED 10.06.2024 IN COM. AA. NO.
148/2024 PASSED BY HON'BLE LXXXVII ADDITIONAL CITY
CIVIL AND SESSIONS JUDGE AT BANGALORE,
COMMERCIAL COURT CCH-88 ON THE APPLICATION FILED
BY THE RESPONDENT APPLICANT UNDER SECTION 9 OF
THE ARBITRATION AND CONCILIATION ACT, 1996 AND TO
DISMISS THE APPLICATION FILED UNDER SECTION 9 OF
THE ARBITRATION AND CONCILIATION ACT, 1996 IN THE
COURT BELOW IN COM.A. NO. 148 2024.
(ii) TO AWARD COSTS AND GRANT SUCH OTHER
RELIEFS AS THIS HON'BLE COURT DEEMS FIT AND
EXPEDIENT IN THE CIRCUMSTANCES OF THE CASE, IN
THE INTERESTS OF JUSTICE AND EQUITY.
THIS APPEAL HAVING BEEN HEARD AND RESERVED
FOR JUDGMENT ON 23RD JULY, 2024 AND COMING ON FOR
PRONOUNCEMENT THIS DAY, ANANT RAMANATH
HEGDE J., PRONOUNCED THE FOLLOWING:
CORAM: HON'BLE MRS JUSTICE ANU SIVARAMAN
AND
HON'BLE MR JUSTICE ANANT RAMANATH HEGDE
-3-
CAV JUDGMENT
(PER: HON'BLE MR JUSTICE ANANT RAMANATH HEGDE)
This appeal is directed against the order under Section
9 of the Arbitration and Conciliation Act, 1996 (Hereinafter
referred to as the 'Act of 1996' for short). In terms of the
impugned order, Section 9 Court has allowed the
application filed by the present respondent and restrained
the appellant from selling/alienating/encumbering/creating
third party rights over 'C' schedule property and also
restrained them from collecting any money, receivables,
directly or indirectly till the disposal of the arbitration
proceeding.
2. It is brought to the notice of this Court that a writ
petition No.12181/2024 is pending before this Court
wherein the present appellant has challenged the order
passed by Section 9 Court in a review petition filed by the
respondent seeking review of the order dismissing the
earlier Section 9 application filed by the respondent in
respect of Schedule - A and B properties.
3. The learned counsel appearing for the appellant and
the learned Senior counsel appearing for the respondent
jointly submit that the contention in this appeal and the
writ petition being substantially the same (in so far as
merits or demerits of both Section 9 applications),
requested the Court to pass appropriate orders covering
properties involved in both Section 9 applications.
Accordingly, the present order is passed which shall apply
to properties covered in both Section 9 applications.
4. The appellant before this Court is a developer and
the respondent is a Marketing Service Provider to sell the
properties developed by the appellant. The contractual
relationship between the appellant and the respondent is
governed by the Marketing Services Agreement dated
19.10.2022. Various terms and conditions have been
incorporated in the agreement defining the rights and
responsibilities of the appellant and the respondent.
5. Admittedly, the appellant had hired the services of
the respondent to market the property covered in the
agreement dated 19.10.2022. The respondent claims that
excluding 6% of the total properties developed, it has the
exclusive right to sell the properties. The respondent is
entitled to certain commission agreed upon by the parties
which are specifically enumerated in schedule II of the
agreement dated 19.10.2022.
6. Clause 3.4 of the agreement provides for termination
of the agreement. The fees payable to the respondent are
also set out in Clause F of Schedule I.
7. Clause 3.4 also stipulates that in case, the
agreement is to be terminated, then the developer can
terminate the agreement after giving 30 days' notice in
writing to the respondent.
8. The appellant claims that the agreement is
terminated with immediate effect by issuing an email on
05.04.2023. The appellant further also claims that on
22.05.2023, the agreement is once again terminated with
immediate effect by sending one more email. In both
emails referred to above, the agreement is terminated
with immediate effect without giving 30 days' notice as
contemplated under clause 3.4 of the agreement. On this
premise, the respondent contends that the termination is
invalid and the agreement still subsists. The appellant
would contend that the respondent has agreed to abide by
the conditions mentioned in the termination notice and the
respondent has treated the agreement as terminated. It is
also the contention of the appellant that after the
termination notice dated 05.04.2023, the respondent has
not acted as the service provider in terms of the
agreement.
9. During the course of the hearing, both the parties
admitted that 210 customers out of 235 customers who
approached through the respondent have agreed to
purchase the properties developed by the appellant.
10. The respondent has invoked Section 9 of the Act of
1996 on the premise that the appellant is in arrears of
commission/service charges payable to the respondent to
the tune of Rs.11,73,95,985/- after deducting Rs.1.75
crores. Respondent also claimed that the alleged
termination of the agreement is illegal. Thus, the
respondent claims that it is entitled to provide marketing
services in respect of all other properties covered by the
agreement dated 19.10.2022.
11. The appellant contends that the respondent is
entitled to 5% of the agreed sale consideration amount,
and 60% of the said amount is to be paid only after 20%
of the sale consideration amount is paid by the purchaser
as well as the balance amount released by the financier.
12. The respondent's entitlement to 5% of the
consideration amount on the minimum sale consideration
amount agreed is not in dispute. Additional revenue
sharing @ 5.5% if the property is sold at a higher price
than the benchmark price fixed under the agreement is
also not in dispute. However, what is the disputed breakup
of said 5% or 5.5% amount payable? This question
involves the interpretation of the clause relating to the
payment schedule.
13. It is an admitted position that the respondent has
not yet marketed the flats in the 'C' schedule property.
The respondent submits that the necessary approval from
the competent authority is received recently and the
appellant issued a notice terminating the contract which
though not invalid, came in the way of the respondent
going ahead with the marketing of the properties in the 'C'
schedule.
14. Whether the agreement is validly terminated or not
requires consideration. Whether the respondent has
waived 30 days notice of termination of the agreement by
its conduct also requires consideration.
15. The right of the appellant to terminate the contract
is very much recognised and the respondent does not
have any right over the properties in question. This being
the position, even if the termination of the contract is
illegal, a claim for specific performance, at the instance of
the respondent, to compel the appellant to enter into a
sale deed in favour of the purchaser identified by the
respondent, prima facie may not be maintainable. Thus,
the remedy for the respondent in case of breach of the
agreement is to recover the service charges and damages
if any.
16. During the course of the hearing, it is submitted by
the learned counsel for the appellant that in case, all the
agreements for sale in respect of 210 units result in
absolute sale deeds, then the respondent approximately
would be entitled to Rs.8.5 crores towards commission. It
is further submitted that on deducting Rs.1.75 crores
already paid, and Rs.86,08,276.00 paid to the channel
partners of the respondent, the appellant at the most
would be liable to pay Rs.5.88 crores.
17. After hearing both parties, this Court indicated that
there has to be some interim measure to secure the
interest of the respondent.
18. In the above-said background, the appellant has
offered, as an interim measure, to provide some security
to the respondent's claim that it has provided 210
customers to purchase the flats developed by the
appellant.
19. The respondent has claimed that the security is to
be offered not only in respect of the service charges
payable to the respondent in respect of 210 customers
- 10 -
provided by the appellant but also to be paid in respect of
the claim arising from the illegal termination of the
agreement.
20. Interpreting the clause relating to the payment,
respondent claims that it has already provided service
worth approximately Rs.16.40 crores and the respondent
is prevented from providing service in respect of unsold
units and the respondent is losing the profits which it
would have made by further sales.
21. It is also required to be noticed that the respondent
is claiming his right to market the units in the 'C' schedule
and damages for not allowing it to market the same. It is
not possible at this juncture to assess the damages as it
cannot be predicted that the respondent would have
managed to sell the remaining units. Admittedly, no sale
agreements have been entered into in respect of the
properties in the 'C' schedule. Thus, there is no question of
unpaid service charges or commission in respect of 'C'
schedule property.
- 11 -
22. It is an admitted position that Rs.1.75 crores is
already paid to the respondent. Respondent in his
application has claimed that Rs.11,73,95,985/- is due
(deducting Rs.1.75 crores) towards the services rendered.
The said figure of Rs.11,73,95,985/- is on the assumption
that all the 235 sale agreements will translate into the sale
deeds. Admittedly, the respondent can claim full payment
of 5% or 5.5% commission as the case may be, only after
execution of the sale deed. Before completion of the sale
deeds, respondent is only entitled to a certain percentage
of 5% or 5.5% fees agreed upon.
23. In the backdrop of the above-mentioned facts, the
impugned order is not sustainable. In the first place, the
restraint order could not have been passed with respect of
6% of the total properties since the developer has the
exclusive right to sell the same, even under the agreement
dated 19.10.2022. The absolute restraint order against the
appellant from selling the units is also not justified as the
respondent does not have a right over the properties.
- 12 -
Thus, this Court is of the view that the interim order needs
modification.
24. Considering the above-mentioned factors, as an
interim measure, to balance the equity, till the application
under Section 17 is heard by the Arbitral Tribunal, this
Court deems it appropriate to direct the appellant to
furnish security to the tune of Rs.10.00 crores, keeping
open all the questions relating to the interim measure to
be adjudicated under Section 17 of the Act of 1996. This
order is made also taking into account that both parties
have agreed and requested this Court to appoint an
arbitrator to resolve the dispute.
25. Hence, the following interim measures are passed:
(i) The appellant shall furnish security to the tune of
Rs.10.00 crores (Rupees Ten Crores only) to the
satisfaction of the Commercial Court. Any security offered
shall be free from all or any encumbrance and the
respondent shall have first charge over the same.
- 13 -
(ii) Till furnishing of security as ordered, the appellant
shall not alienate, or create any third party charge over
the properties, excluding 6% of the properties over which
appellant has exclusive right to sell.
(iii) On acceptance of security the appellant is permitted
to sell or otherwise deal with the properties, and on sale or
receipt of the installment amount from 210 purchasers
brought by the respondent, the amount/commission due
to the respondent under the agreement dated 19.10.2022,
shall be paid within 15 days from such receipt of the sale
consideration and on such payment, the value of the
security offered by the appellant shall stand reduced
proportionately.
(iv) Even in case, the appellant fails to offer security as
mentioned above, the appellant is entitled to sell 6% of
the properties without any restrictions, as such right is
recognised under the agreement dated 19.10.2022.
(v) As suggested by both parties Sri Justice Ajit Gunjal
(subject to his consent and availability) is appointed as the
- 14 -
sole arbitrator to adjudicate the dispute between the
parties.
(vi) The interim measure shall be in force till 30 days from
the date of receipt of the notice by the Arbitral Tribunal or
till any interim order is passed by the Arbitral Tribunal
whichever is earlier.
(vii) The parties are at liberty to move the Arbitral
Tribunal for appropriate interim measures under Section
17 of the Act of 1996.
(viii) If any application is filed before the Arbitral Tribunal
for appropriate interim measures, the same shall be
considered by the Arbitral Tribunal without being
influenced by any of the observations made in this order
as all observations made in this order are only confined to
the application under Section 9 of the Act of 1996.
Appeal is allowed-in-part.
Sd/-
(ANU SIVARAMAN) JUDGE Sd/-
(ANANT RAMANATH HEGDE) JUDGE brn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!