Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Karnataka Power Corporation Ltd vs M/S Bangalore Construction Company
2024 Latest Caselaw 5479 Kant

Citation : 2024 Latest Caselaw 5479 Kant
Judgement Date : 22 February, 2024

Karnataka High Court

Karnataka Power Corporation Ltd vs M/S Bangalore Construction Company on 22 February, 2024

                            1
                                        RFA NO. 1188/2010


       IN THE HIGH COURT OF KARNATAKA AT BENGALURU

        DATED THIS THE 22ND DAY OF FEBRUARY, 2024

                         PRESENT

          THE HON'BLE MRS. JUSTICE K.S.MUDAGAL
                          AND
            THE HON'BLE MR. JUSTICE C.M.JOSHI

    REGULAR FIRST APPEAL NO. 1188 OF 2010 (MON)

BETWEEN:

KARNATAKA POWER CORPORATION LTD.,
A GOVERNMENT OF KARNATAKA UNDERTAKING
HAVING ITS OFFICE AT
NO.116/2, TRADE CENTRE BUILDING,
2ND FLOOR, R.C ROAD,
BANGALORE-560 001.
REPRESENTED BY ITS HEAD (LEGAL SERVICES),
MR. CHIDANANDA RAO
                                                ...APPELLANT
(BY SRI MAHESHA A.S, ADVOCATE FOR
    SRI ASHOK N NAYAK, ADVOCATE [PH])

AND:

1 . M/S BANGALORE CONSTRUCTION COMPANY,
    A PARTNERSHIP FIRM
    REGISTERED UNDER THE PARTNERSHIP ACT,
    HAVING ITS OFFICE AT
    NO.104, R V LAYOUT,
    KUMARA PARK EXTENSION,
    BANGALORE-560020.
    REPRESENTED BY ITS 9 PARTNERS.

2 . MR. A S KUPPURAJU,
                                2
                                             RFA NO. 1188/2010


  AGED ABOUT 85 YEARS,
  S/O SRI AKALA RAJU.
  DELETED AS PER ORDER DATED 28.02.2011

3 . SRI K GOPAL RAJU,
    AGED ABOUT 61 YEARS,
    S/O SRI KUPPU RAJU.

4 . SRI KODANDA RAJU,
    AGED ABOUT 38 YEARS,
    S/O SRI A S KUPPU RAJU.

  RESPONDENTS 2 TO 4,
  HAVING ITS OFFICE AT
  NO.104, R V LAYOUT,
  KUMARA PARK EXTENSION,
  BANGALORE-560 020.
                                         ...RESPONDENTS
(BY SRI S.K.V CHALAPATHY, SENIOR COUNSEL A/W
   SMT. ANAGHA JAYAPRAKASH, ADVOCATE FOR R1 & R3 [PH];
   R-4 SERVED;
   R-2 IS DELETED V/O DATED 28.02.2011)

      THIS RFA IS FILED U/S 96 OF CPC, AGAINST THE
JUDGMENT     AND    DECREE    DATED    23.11.2009   PASSED   IN
O.S.NO.1094/1989 ON THE FILE OF THE XLIII ADDL. CITY CIVIL
AND   SESSIONS      JUDGE,    CCH-14,    BANGALORE,      PARTLY
DECREEING     THE    SUIT     FOR     RECOVERY      OF   MONEY.


      THIS REGULAR FIRST APPEAL HAVING BEEN HEARD AND
RESERVED ON 09.01.2024, COMING ON FOR PRONOUNCEMENT
OF JUDGMENT THIS DAY, C.M.JOSHI J., DELIVERED THE
FOLLOWING:
                                3
                                                RFA NO. 1188/2010


                         JUDGMENT

Being aggrieved by the judgment and decree passed

in O.S. No.1094/1989 by the learned XLIII Additional City

Civil and Sessions Judge, Bangalore, (CCH 4), dated

23-11-2009, the plaintiff- The Karnataka Power Corporation

Limited, is before this Court in this appeal.

2. The parties would be referred to as per their ranks

before the trial Court for the sake of convenience.

3. The brief facts of the case are as below:

The plaintiff-Corporation is a Public Undertaking of the

Government of Karnataka registered under the Companies

Act. Defendant No.1- M/s. Bangalore Construction Company

is a registered Partnership Firm engaged in Engineering

Constructional Contracts with the principal place of business

located at Bangalore. Defendants No. 2 to 4 are the

partners of the Firm. The admitted facts are that, the

plaintiff-Corporation had entrusted the construction of its

building at No.82, Race course Road, Bangalore, to the

defendant-Firm under Letter of Intent dated 22-3-1982.

The value of the work was to the extent of Rs.46.13 lakhs

and period of execution was 30 months from 22-3-1982.

The work included in the Contract was construction of a

building with framed structure having seven floors in

addition to cellar and ground floor with all civil works

excluding the electrical work. In pursuance to the Letter of

Intent, the site was handed over to the defendant-Firm on

31-3-1982 and the work commenced on 04-05-1982.

Defendant No.1-Firm gave a detailed programme of

execution by its Letter dated 15-6-1982. Though a detailed

agreement had to be executed by 04-03-1982, it was

actually executed on 09-12-1982 and letter dated

15-06-1982 was part of the agreement.

4. The plaintiff-Corporation averred in the plaint as

follows:

(a) That since the progress of the work was slow

from the beginning and several review meetings were

conducted calling upon the defendants to accelerate

the work, no improvement was shown by the

defendants. A penalty of Rs.50/- per day was imposed

and collected from 01-03-1983.

(b) The defendants issued a letter dated 25-04-1984

to enhance the rates by 30% for the work done from

the inception till 31-03-1984 and 50% of the quoted

rates for the works done from 01-04-1984, though the

contract did not provide for any enhancement.

(c) By letter dated 27-7-1984 defendants requested

for extension of time by eight months, which was

permitted by the plaintiff-Corporation without

acceding to the request for enhancement of the rates.

(d) By 21-09-1984, which was the stipulated date

for completion, defendants executed the work to the

tune of Rs.33.11 lakhs as against the total contract

value of Rs.46.13 lakhs.

(e) On account of certain additions and alterations in

design and additional requirements, the value of the

balance work at the end of 21-09-1984 was Rs.27.87

lakhs including the shortfall of the work was to the

tune of Rs.13.02 lakhs. Even during the extended

period, the defendants could not complete the work as

agreed and the extended period expired on

21-05-1985. The work executed was only to the tune

of Rs.2.56 lakhs as against Rs.27.87 lakhs.

(f) The defendants by their letter dated

14-10-1985 intimated the plaintiff-Corporation that

they are unable to continue the work and requested

the plaintiff to terminate the contract after settling

their claims. Thereafter, the defendants abandoned

the work from 29-12-1985, by which time they had

executed the work to the tune of Rs.3.44 lakhs as

against the balance of Rs.25.31 lakhs. The discussions

between the parties on 06-1-1986, 8-1-1986 and

10-2-1986 went in vain and the defendants had

breached the contract. Therefore, the plaintiff-

Corporation rescinded the contract by letter dated

21-02-1986.

(g) The plaintiff had to get the remaining work

executed by entrusting the work to other Piece

Contractors and get the work finished.

(h) Though the plaintiff had called upon the

defendants to appear at the spot to take accounts

they did not appear but gave an untenable and

evasive reply on 01-03-1986. They also filed a Writ

Petition No.3468/1986 to stay the letter of rescinding

the Contract and ultimately, the petition was

dismissed on 02-04-1986.

(i) The defendants filed OS No.1014/1986 before

the City Civil Court Bangalore, seeking injunction and

a Court Commissioner was appointed to record the

measurements of the work done under the contract

and after the Court Commissioner submitted his

report dated 21-06-1986 and 06-08-1986, the suit

came to be withdrawn.

5. On the above grounds, the plaintiff-Corporation

made following claims:

(A) The plaintiff has sustained loss of Rs.7,21,273.50

ps., due to consequences of breach of contract.

(B) The plaintiff had issued 405.31 MT of steel for

execution of the work and out of it 14.955 MT was

unaccounted and therefore, the defendants are liable

to pay a sum of Rs.1,49,398.06 ps., as value to

unaccounted steel.

(C) The plaintiff had issued 21,411 bags of cement

to the defendants and a quantity of 566 bags

remained unaccounted and as such, sum of

Rs.27,690/- is liable to be paid by the defendants.

(D) The plaintiff has to locate several of its offices in

rented buildings and the rentals per month for such

premises was Rs.53,690.14 ps. If the defendants had

completed the contract within a stipulated time, the

plaintiff could have saved a sum of Rs.13,58,815.10

ps., paid as rentals for its offices, which is liable to be

paid by the defendants.

(E) Due to the delay in execution of the work by the

defendants, plaintiff had to continue the services of

supervisory staff till the completion of the building by

piece work contractors and as such, a sum of

Rs.4,28,750/- is to be paid by the defendants for the

period of 01-06-1985 to 30-06-1987.

(F) The plaintiff is entitled to adjust the sum of

Rs.3,65,503.31 ps., towards the amount due to the

defendants under the contract and a sum of

Rs.12,364/- towards extra items/works done by the

defendants. Therefore, the defendants are liable to

pay the sum of Rs.26,85,926.66 ps., and after

deducting the dues from the plaintiff to the

defendants, the liability of the defendants is

Rs.23,08.059/-. Thus, the plaintiff claimed

Rs.23,08,059/- along with interest at 12% p.a.

6. After service of summons, defendants have

appeared before the trial Court through their counsel and

filed their written statement. The contentions of the

defendants are as below:

(a) As per the allegations of the plaintiff-Corporation

there was breach of agreement on 29-12-1985 and

the present suit is filed on 20-2-1989 and therefore,

the suit is barred by limitation.

(b) The site was handed over to the defendants on

31-3-1982 and commenced the work in April 1982,

but not on 4-5-1982 as claimed by the plaintiff. It was

denied that the progress of the work was slow and

there were several letters to speed up the work.

(c) Even at the time of signing the agreement the

plaintiff had not supplied the entire drawings and

designs in respect of each and every item of work to

be carried out, so that the defendants could have

chalked out the programme of the work and complete

the same within stipulated time.

(d) Even after the delayed supply of designs and

drawings, on several times they were changed which

resulted in rescheduling of the work by the

defendants, dismantling the fabricated structures and

re-designing such structures. Therefore, the delay in

progress of the work was completely attributable to

the acts, omissions and commissions of the plaintiff.

There was no justification for penalty of Rs.50/- per

day from 1-3-1983.

(e) It is admitted that the defendants claimed

enhancement of the rates for the work done and to be

done and also that the time stipulated for the work

was extended for eight months. There were valid

reasons and the written statement narrates those

reasons in detail.

(f) The time and rates stipulated under the

agreement was relevant only if both the parties

discharged their duties in accordance with the terms

and conditions of the agreement. Since there was

delay on the part of the plaintiff and violations of the

terms of the agreement, the plaintiff had failed to

perform its part of the agreement.

(g) The rates of the material as well as cost of

labour had increased nearly 3/4 and it was impossible

for the defendants to carryout the works at the rates

stipulated in the contract. Despite request by the

defendants, the plaintiff-Corporation did not take any

decision. But the Corporation went on to levy penalty

since it was in dominating position.

(h) The defendants deny the allegations that they

had completed works of the value of Rs.33.11 lakhs

and if any work remained unexecuted as on

21-09-1984, it was mainly due to the failure of the

plaintiff-Corporation in not making available the

drawings and designs, in not taking decisions

regarding height of floors, not communicating its

decision regarding fabrication of the works, etc.

(i) Defendants denied that during the extended

period of contract work only to the extent of 2.56

lakhs was carried out. Therefore, the defendants by

their letter dated 14-10-1985 intimated the plaintiff

that if its demands are not considered and grievance

remedied, they are not interested in continuing the

work. Even then the plaintiff-Corporation terminated

the contract by its letter dated 21-02-1986. The

defendants denied that they had committed any

breach of contract.

(j) The defendants also denied the several of the

claims made by the plaintiffs specifically and

meticulously.

(k) It was alleged that since the defendants had filed

OS No.3423/1986 against the plaintiff-Corporation,

the present suit was filed as a counter blast. On these

grounds, the defendants sought for dismissal of the

suit.

7. On the basis of the above pleadings, the trial

Court framed the following issues for its consideration:

"1. Whether the plaintiff proves the defendants have committed breach of terms of contract, agreement entered into between the parties?

2. Whether the plaintiff proves by 21.9.84 the date originally stipulated for the completion of the contract, the defendants had executed the work of the value of Rs.33.11 lakhs as against the stipulated work of the value of Rs.46.13 lakhs?

3. Whether the plaintiff further proves the defendant has abandoned the work from 29.12.1985 and during the period from 21.5.1985 up to the date of stoppage of the work the defendants had executed work of the value Rs.3.44 lakhs as against the value of Rs.25.31 lakhs?

4. Whether the plaintiff proves that the contract of the defendants was properly rescinded on 21.2.1986 by letter No.CD/C3-T9C?

5. Whether the plaintiff proves they have sustained loss to the extend of Rs.7,21,273=50 ps.?

6. Whether the plaintiff proves the damages sustained by them amounting to Rs.31,58,815=10 ps. as stated in para 16 (d) of the plaint?

7. Whether the plaintiff proves owing to delay in execution work under the contract the plaintiff had incurred loss of Rs.4,28,750/-?

8. Whether the plaintiff further proves that on account of the negligence of the defendants, the defendants are liable to pay Rs.23,08,059/-?

9. Whether the plaintiff proves the defendants are liable to pay interest at 12% per annum?

10. Whether the suit is barred by Limitation?

11. Whether the plaint has been signed and verified by competent persons?

12. Does the defendant prove the site was not handed over to the defendant as contended by the plaintiff and the plan has been supplied to the defendants at a very late stage and also there were modifications to the original plan to that of the work to be carried out by the defendant?

13.Whether the defendants prove the delay in completion of the work only on account of the faults of the plaintiff's and not on the part of the defendants?

14. To what relief the plaintiff is entitled to?"

8. In order to prove its case, the Executive

Engineers of plaintiff-Corporation were examined as PWs 1

and 2 and Exhibits P1 to P41 were marked in evidence.

Defendants have not led any oral evidence, but got marked

Exhibits D1 to D82 through PW2 on their behalf.

9. The trial Court after hearing both the parties,

has answered issue Nos. 1 to 4, 11 in the affirmative, issue

No.5,8 and 12 in partly affirmative and in partly negative

and issue Nos. 6,7,9,10 and 13 in the negative and

ultimately, partly decreed the suit with costs.

10. Being aggrieved by the said judgment and

decree, the plaintiff-Corporation is before this Court in

appeal.

11. On issuance of notice, respondents Nos. 1 and 3

have appeared through their counsel. Respondent No.2 is

deleted and respondent No.4 served and unrepresented.

12. The trial Court records were secured on

admitting the appeal and heard the arguments by

learned counsel appearing for appellant and learned Senior

Counsel appearing on behalf of the counsel on record for

respondent Nos. 1 and 3.

Arguments by appellant/plaintiff:

13. The learned counsel for the appellant- plaintiff

Corporation submits that though the trial Court comes to

the conclusion that there was breach of contract by the

defendants, while considering Issue No.5, it has not

awarded the claims made by the appellant-Corporation in

its entirety. He submits that though the claim made by the

plaintiff was to the extent of Rs.7.21 lakhs in respect of the

extra work which was entrusted to the piece contractors,

the same was not considered by the trial Court and it has

awarded a sum of Rs.53,126.05 ps. It is submitted that

had the plaintiff proceeded with the defendants as the

Contractor, he would have spent a sum of Rs.15.19 lakhs

but on the other hand, they have to spend Rs.22,40,126.05

ps., for which the defendants are liable. He submits that

the trial Court failed to consider the evidence of PW.2 in a

proper perspective.

14. So far as Issue No.6 is concerned, he submits

that the plaintiff-Corporation had to work from rented

premises as the building was under construction. Due to

the breach committed by the defendants, the offices of the

plaintiff-Corporation had to continue to work from the

rented premises for a longer period. Therefore, the rent of

such premises towards longer period of occupation is also

liable to be paid by the defendants as damages. It is

submitted that the Company Secretary had issued a

certificate about the money spent towards the rents and the

same should have been accepted by the trial Court. It is

submitted that the unliquidated damages should have been

considered by the trail Court though there was no such

clause in the Contract.

15. Regarding issue No.7, it is submitted that the

plaintiff-Corporation had to continue the services of the

Supervisory staff for completion of the balance work beyond

the time fixed under the agreement. The trial Court in para

54 of the judgment rejected the claim on the ground that

there was no such clause in the contract and therefore, the

defendants are not liable to pay towards the salary of the

supervisory staff. It is submitted that when there is breach

of contract, all incidental expenses incurred by the plaintiff

should have been compensated by the defendants.

Therefore, the rejection of claim of Rs.4,28,750/- as per the

Certificate at Ex.P37 issued by the Company Secretary

should have been allowed by the trial Court.

16. It is submitted that the suit is filed within three

years from the date of Ex.P12, the letter under which the

Contract was terminated. It is also submitted that even

after the alleged abandonment of the work on 29-12-1985,

the defendants had continued the work and therefore, it

was the date as per Ex.P12 which is relevant for Limitation.

Therefore, in the absence of any cross- objection or appeal

by the defendants, the claim of the plaintiff has to be

allowed.

Arguments by respondents/defendants:

17. The learned Senior counsel appearing for the

defendants/respondents No.1 and 3 herein, in his elaborate

and meticulous arguments has contended that even though

the defendants have not filed any cross- objection, by

virtue of Order 41 Rule 33 of CPC he is entitled to lay a

challenge to the findings rendered against the defendants.

In this regard, he relies on the judgments in the case of

Pannalal Vs. State of Bombay and others1 and in the case

of Saurav Jain and others Vs. A.B.P Design and others2 .

18. The first contention of the learned counsel for

the defendants is regarding the limitation. He submits that

the plaintiff clearly admits that the breach of contract was

on 29-12-1985 and PW.2 also states in his cross-

examination that the breach of contract occurred on

AIR 1963 SC 1516

Manu/SC/0509/2021

29-12-1985. The trial Court also holds that the breach

occurred on 29-12-1985. Article 55 of the Limitation Act,

prescribes a period of 3 years from the date of breach of

contract to claim damages. The plaint was filed on

20-2-1989 and therefore, the suit is obviously time barred.

He submits that the trial Court wrongly held that the

termination of the contract vide Ex.P12 dated 21-2-1986 is

the starting point of limitation.

19. He submits that Article 55 employs the words

'Breach' and 'Broken' and they connote the same meaning

in reference to commencement of the limitation under the

said Article. The word 'Broken' does not refer to termination

of the contract, but it is breach of the contract. It is

submitted that the termination of the contract is

subsequent to the breach and the limitation has to be

reckoned from the date of breach, but not

termination/rescission. In this regard, he relies on the

judgments in the case of Food Corporation of India and

others Vs. Babulal Agrawal,3 State of Gujarat Vs. Kothari

and Associates4, The Senior Regional Manager, Food

Corporation of India Vs. G.V.V.N. Hanumantha Rao and

others5 and Rajgopal Naidu Vs. Aiyyaswamy Chettiar and

others6. Relying on the judgments in the case of K.

Ramkumar Vs. Marappa and others7 and in the case of

Kamalesh Babu and others Vs. Lajapat Rai Sharma and

others8, he further submitted that the question of Limitation

being a question of law may be raised by the defendants in

appeal also.

20. Regarding 'Breach of Contract', he submitted

that to ascertain as to who has committed the breach of

contract, the nature of the Contract is to be appreciated.

The Contract between the plaintiff and the defendants being

the reciprocal in nature, it required both the parties to

discharge their obligations. In this regard, he relied on

Sections 52 and 54 of the Contract Act.

(2004) 2 SCC 712

(2016) 14 SCC 761

1993 (2) ALT. 524

1965(2) MLJ 135

21. He submitted that in the case on hand, the

defendants have clearly contended that work could not be

completed due to; (a) non supply of drawings and designs;

(b) repeated revision of the drawings even after the

fabrication works commenced and completed as per the

original drawings; (c) non payment of the running bills in

time; (d) not enhancing the rates regarding the altered

quantities which exceeded 25%; and (e) non supply of

material on time. When these breaches were shown to have

been committed by the plaintiff, the Breach of the Contract

could not have been attributed to the defendants.

22. In this regard, he has taken us through the

evidence on record and has pointed out that each of the

above elements of the breach are borne out of the records.

He further submitted that when considering the question as

to who has committed the breach? and as to whether the

plaintiff is entitled to damages?, the principle of mitigation

2021 (4) AKR 371

of damages as contained in Section 73 of the Indian

Contract Act, has to be considered. While calculating the

loss or damages, the means which existed of remedying the

inconvenience caused by non performance of the contract

must be taken into account. The plaintiff had not taken

steps to mitigate the loss consequent upon the breach and

therefore, the plaintiff is not entitled to any damages. In

this regard, he has pointed out to the testimony of PW.2 in

the cross-examination.

23. He submits that the Contract was entrusted to

piece work contractors with much delay and an early action

by the plaintiff could have resulted in the damages being

lessened. In this regard, he has relied on the judgments in

the case of M/s. Muralidhar Chiranjilal Vs. M/s.

Harishchandra Dwarakadas and another9 and in the case

of M. Nanjappa Vs. Muthuswamy10.

(2008) 12 SCC 577

AIR 1962 SCC 366

AIR 1975 KAR 146

24. Regarding claim for cost of cement and steel, he

submitted that Exs.P31 and P32 relied by the plaintiff do

not show that the defendants had received the cement and

steel and there is no acknowledgement in that regard. He

has pointed out some inconsistency in para 16 (f) of the

plaint to contend that the claim cannot be calculated twice.

25. Regarding rental expenses he submitted that

there is no clause in the contract which entitles the plaintiff

to seek rental expenses. He points out that there was no

difficulty for the plaintiff to occupy the first and the second

floors after completing the pending work within a week and

this aspect having been admitted by PW.2, the principle of

mitigating damages comes in play. Moreover, no material

is placed to substantiate that such rentals were paid by the

plaintiff. The certificate produced is self serving certificate

of the Company Secretary of the plaintiff-Corporation.

26. Regarding salaries of the supervisory staff, the

claim is bereft of any support from the clauses in the

contract. Moreover, since the piece work contractors were

entrusted with the work with much delay, there was no

necessity for the plaintiff to continue the supervisory staff.

Therefore, he submitted that the suit filed by the plaintiff

should have been dismissed by the trial Court.

Analysis and Conclusions:

27. Having heard the learned counsels appearing for

both the sides and having perused the records, the points

that arise are as below:

     (i)     Whether the suit is barred by time?

     (ii)    Whether there was breach of contract by the
             defendant?

     (iii)   Whether the     calculation of the claims of the

plaintiff under different heads is proper and correct?

28. The first contention of the learned counsel for

the respondents that the Appellate Court has the power to

grant relief to the respondents sans the filing of the cross

objections or cross appeal is no more res-integra. The

judgment in the case of Pannalal Vs. State of Bombay

(supra) as early as in the year 1963 had the occasion to

deal with the powers of the Appellate Court under Order 41

Rules 22 and 33 of CPC. In para 12 of the judgment, it was

stated as below:

" Even a bare reading of O.41 R.33 is sufficient to convince any one that the wide wording, was intended to empower the appellate court to make whatever order it thinks fit, not only as between the appellant and the respondent but also as between a respondent and a respondent. It empowers the appellate court not only to give or refuse relief to the appellant by allowing or dismissing the appeal but also to give such other relief to any of the respondents as "the case may require". In the present case, if there was no impediment in law the High Court could, therefore, though allowing the appeal of the State by dismissing the plaintiff's suits against it, give the plaintiff a decree against any or all the other defendants who were parties to the appeal as respondents. While the very words of the rule make this position abundantly clear the Illustration puts the position beyond argument."

(Emphasis supplied)

29. Such view of the Apex Court was again

reiterated in the case of Ravinder Kumar Sharma Vs. State

of Assam and others . It is settled principle of law that a

party who suffered an issue being answered against him

but not assailing the result of the suit can very well

challenge such a finding on the issue in the appeal filed by

the other party. Therefore, the defendant who suffered an

issue being answered against him need not file cross

objection or cross appeal to assail the issue provided the

resultant effect of the suit was in his favour. However, he

can assail the issue in the appeal filed by the other party.

30. Similar view was taken in several other

judgments of the Apex Court. Moreover, the powers of the

Appellate Court are wide enough to grant relief in favour of

the respondent. In the case of Koksingh vs. Deokabai12,

the Apex Court has held that, if an appellate Court is of the

view that any decree which ought in law to have been

passed was in fact was not passed by the court below it

(1999) 7 SCC 435

may pass or make such further other decree or order as the

justice of the case may require. Such view was reiterated in

the case of Mahant Dhangir and another vs. Shri Madan

Mohan and others13; Manasa Housing Co-operative

Society Limited Vs. Marikellaiah and others 14; Babusab

and others Vs. Maniksab and others15. The recent

judgment in the case of Saurav Jain Vs. ABP design and

others (supra) has again reiterated this view in para 25 of

the judgment, which reads as below:

"25. It is apparent from the amended provisions of Order XLI Rule 22 Code of Civil Procedure and the above authorities that there are two changes that were brought by the 1976 amendment. First, the scope of filing of a cross- objection was enhanced substantively to include objections against 'findings' of the lower court; second, different forms of raising cross-objections were recognized. The amendment sought to introduce different forms of cross-objection for assailing the findings and decrees since the

AIR 1976 SC 634;

AIR 1988 SC 54;

AIR 2006 Kar.273;

2013 (2) KCCE 1309

amendment separates the phrase "but may also state that the finding against him in the Court below in respect of any issue ought to have been in his favour" from "may also take any cross-objection to the decree" with a semi colon. Therefore, the two parts of the sentence must be read disjunctively. Only when a part of the decree has been assailed by the Respondent, should a memorandum of cross- objection be filed. Otherwise, it is sufficient to raise a challenge to an adverse finding of the court of first instance before the appellate court without a cross objection."

(Emphasis supplied)

31. Keeping in mind the above judgments on the

scope and powers of the Appellate Court under order 41

Rule 22, 33 of CPC, we proceed to consider the points

framed by us:

Re.Point No.1- Limitation

32. The question of limitation raised by learned

counsel for the respondents being a question of law can be

raised in appeal also. This Court in the case of K.

Ramkumar Vs. Marappa and others (supra) by relying on

the judgment in the case of Ravinder Kumar Sharma Vs.

State of Assam and others (supra), has held that the

question of limitation can also be considered by the

Appellate Court. Moreover, Section 3(1) of the Limitation

Act casts a duty upon the Court to consider the question of

limitation even though the bar of limitation has not been set

up as a defence.

33. The learned counsel for the respondents contend

that in para-18 of the plaint the plaintiff has clearly averred

that the defendant committed breach of contract on

29-12-1985. So also PW.2 in the cross-examination states

that the breach of contract had occurred on 29-12-1985.

He submits that the trial Court also holds that the

defendants committed the breach of contract on

29-12-1985 by abandoning the work. Therefore, the suit

should have been filed by the plaintiff within three years

from the date when the contract was broken, i.e., on or

before 28-12-1988. Evidently, the suit has been filed on

20-02-1989, which is beyond the period of three years.

34. Per contra, the learned counsel for the

plaintiff/appellant contend that the contract was terminated

on 21-02-1986 by a letter of the plaintiff at Ex.P12.

Therefore, it is the date of rescission of the contract which

is material. In the background of this contention, it is

necessary to consider whether the breach of contract would

be a relevant date or the date of termination of contract/

rescission of the contract which would be material to

calculate the period of limitation.

35. The provisions of Article 55 of the Limitation

Act, read as below:

Description of suit Period of Time from which period Limitation begins to run

55.For compensation Three years When the contract is for the breach of broken or (where there any contract, express are successive breaches) or implied not herein when the breach in specially provided for respect of which the suit is, instituted occurs or (where the breach is continuing) when it ceases.

36. Thus, it is evident that the time from which the

period of limitation begins to run is, when the contract is

broken or where there are successive breaches, when the

breach in respect of suit is instituted occurs or where the

breach is continuing, when it ceases.

37. In Food Corporation of India and others Vs.

Babu Lal Agarwal (supra), the Apex Court has observed

as below:

"In the case in hand, as indicated above, the notice terminating the contract is dated 26.9.1988 saying that "we are going to vacate your above plinths by October 10, 1988". The plaintiff replied to the notice saying that the defendant could not vacate the premises before 23.1.1990. However, the defendant vacated the premises on 10.10.1988. This is the date when the contract was broken and cause of action also accrued. The suit had been filed on 4.10.1991 i.e., within three years of vacating the premises. In view of the position indicated above, we do not find any merit in the argument raised on behalf of the appellant that the suit of the plaintiff was barred by time. In the result, we find no substance In the appeal preferred by the Food Corporation of India".

38. In the case of State of Gujarat Vs. Kothari

and Associates (supra), where again, it was observed as

below:

"3. The period of limitation would be computed under either Article 55 or Article 113. The facts at hand are dissimilar to those in Gannon Dunkerley and Co. Ltd. v. Union of India in that the damages sought by the present Respondent are for work covered by the contract, and the change in circumstances was directly caused by breaches ascribable to the Appellant State in not handing-over the site on time. Facially, the suit claims are damages incurred due to the extension of the contract period and the resultant damages are incurred by the Respondent. The suit would therefore fall within the ambit of article 55. Article 113, which is a residuary provision, cannot be resorted to.

4. It also appeared to the Court that the contract was clearly not broken as the Respondents chose to keep it alive despite its repeated breaches by the Appellant State. The factual matrix presents a situation of successive or multiple breaches, rather than of a continuous breach, as each delay in handing over the canal/site by the Appellant State constitute to a breach that was distinct and complete

in itself and gave rise to a separate cause of action for which the Respondent could have rescinded the contract or possibly claimed compensation due to prolongation of time and resultant escalation of costs. Of course the Respondent is enabled to combine all these causes of action in one plaint, as postulated in the Code of Civil Procedure provided each claim is itself justiciable. Even the Respondent has argued before the High Court that the suit was based on successive breaches committed by the Appellant State. In Court's opinion, the suit was required to be filed within three years of the happening of each breach, which would constitute a distinct cause of action."

(Emphasis supplied)

39. In the case of the Senior Regional Manager,

Food Corporation of India Vs. G.V.V.N. Hanumanth

Rao, (supra) while distinguishing "Breach of Contract" and

"Termination of Contract", in para 14, it was observed as

below:

"14. It may be pointed out here that there is difference between breach of a contract and termination of a contract; every breach of a contract by one party to it does not result in termination of

the contract though it may furnish ground to the other party to terminate the contract and every termination of a contract does not necessarily result in breach of the contract. The question here is not as to when the contract as such was terminated or came to an end; the short question which is to be considered for purposes of application of Article 55 is when did the breach of the contract, in respect of which compensation is claimed, occur? On 28-9-1972 the contractor has expressed his inability to execute the work. That letter reached the Food Corporation of India on 3-10-1972. Therefore on that date the contract was broken, whether or not the Food Corporation of India has accepted the breach. Subsequent termination of contract by the Food Corporation of India on 8-12- 1972, is immaterial for the purposes of Article 55. The suit was filed by the Food Corporation of India on 18-10-1975 which was beyond three years from the date of breach of the contract on 28-9-1972 when the contractor declined to take up the work by Ex.C-5 which was received by the Food Corporation of India on 3-10-1972. It follows that the arbitrator was right incoming to the conclusion that the suit itself was barred by limitation and consequently the claim put forth in I.A No.137 of 1976 which was filed on 27-3-1976 was barred within the meaning of Sub- section (3) of Section 37 of the Arbitration Act".

(Emphasis supplied)

40. In the case on hand, it is evident that the

plaintiff-Corporation, in para 18 of the plaint states that the

cause of action arose on 29-12-1985 when the defendants

committed the breach of the Contract by abandoning the

execution of the contracted work, and also on or about

21-02-1986 when the plaintiff rescinded the contract of

which the defendants committed breach and also on

30-6-1987 when the building was got completed by the

Corporation. It is evident that the intimation of termination

of contract was sent to the defendants on 21-02-1986 as

per Ex.P12. Much prior to that, the defendants had

indicated that the contract be terminated as per Ex.P11

dated 14-10-1985. In Ex.P11, the defendants had informed

the plaintiff to terminate the contract in view of the financial

stringency. There was no reply to the letter at Ex.P11 by

the plaintiff till 29-12-1985. It was also indicated in Ex.P11

that the successive requests for enhancement of the rates

was not considered for long period and ultimately, the

defendants abandoned the work on 29-12-1985. This

abandoning of the work by the defendants on 29-12-1985

is not in dispute.

41. PW2 in the cross-examination (Page 138 of PB)

has stated as below:

"It is true that there was delay in payment of 4th R.A. Bill as seen in Exhibit D.18. Witness Volunteers: That he does not know the reason. It is true that there was delay in payment of 5th R.A. Bill as seen in Exhibit D55. I agree that as per the original contract the entire work had to be completed by 21st September 1984. By letter dated 27th September 1984 by Exhibit D58, the Defendant was intimated to alter the height of the 6th Floor from 3.10 Metres to 3.80 Metres. It is not true that the height of the 7th Floor also was altered. It is true that even by date of Exhibit D61 the details regarding 7th Floor were not furnished. It is true that as per Exhibit D69 there was a delay of 2 Months in the payment of 8th R.A. Bill."

42. From the above facts and circumstances, it is

clear that the termination of the contract by letter dated

21-02-1986 is not the breach of the contract, but it was

when the defendants expressed their inability to go on with

the contract. Evidently, it was on 14-10-1985 when the

defendants asked the plaintiff to terminate the contract. A

perusal of Ex.P11 shows that it runs to 4 pages and after

narrating the various reasons indicating the breach of the

contractual obligations by the plaintiff, the defendants

states as below:

"Under the above circumstances, we are not prepared to continue the work further and our Agency may please be terminated after settling all our claims in full."

(emphasis by us)

43. This averment in Ex.P11 clearly indicates that

the defendants would no longer wished continue to perform

the contractual obligations. Even then the plaintiff has not

responded to the same. The response is only on

21-02-1986 in the form of Ex.P12, whereby, termination

was informed. Therefore, it is evident that the defendants

had expressed their withdrawal from the contract by its

letter dated 14-10-1985. In other words, the cause of

action arose on 14-10-1985 when the breach of contract

was brought to the notice of the plaintiff in unequivocal

terms.

44. Now let us see whether there is any successive

breach which has occurred and whether the breach was

continuing?

45. As noted supra, PW.2 in his testimony has stated

that the plaintiff had permitted the defendants to continue

with work even after 21-5-1985 which is the date after

extension of 08 months period from 21-09-1984 to

complete the project. He also states that to the best of his

knowledge the defendants continued with the work even

after 29-12-1985 and subsequently, abandoned the work.

This testimony of PW2 is not supported by the pleadings.

The plaint avers in para 8 that the balance of the works till

the end of 21-09-1984 was Rs.27.87 lakhs. Thereafter, an

extension of 08 months was permitted and during such

period, i.e., till 21-05-1985, the work turned out was

Rs.2.56 lakhs. Even thereafter, i.e. from 21-05-1985 till

the stoppage of work on 29-12-1985, the work turned out

by the defendants was Rs.3.44 lakhs. In other words, there

was absolutely no work turned out after 29-12-1985 when

the defendants abandoned the work. The termination of the

contract was informed by the defendants under letter at

Ex.P11 dated 14-10-1985. Therefore, it is evident that

there was no such continuing breach after 29-12-1985. No

work was turned out after 29-12-1985 as per the pleadings.

There is no evidence on record to show that the defendants

had continued the work after 29-12-1985. Under such

circumstances, we are unable to accept the contentions of

the plaintiff that the limitation started from 21-02-1986.

Plaintiff knew that the termination was informed by the

defendants on 14-10-1985, but they kept mum till

21-02-1986.

46. It is also evident that the defendants filed

W.P.No.3468/1986 on 21-02-1986 which came to be

withdrawn later. O.S.No.1014/1986 was filed for injunctive

relief on 12-3-1986 where a Court Commissioner was

appointed for measurements of the works done. After the

Court Commissioner submitted the report on 21-6-1986

and 6-8-1986, the said suit came to be withdrawn.

Thereafter, the defendants filed OS No.3423/1986 seeking

certain claims. Therefore, it is evident that there was no

such continuing breach of contract by the defendants after

29-12-1985 when they abandoned the work.

47. Under these circumstances, it is clear that after

the cause of action arose on 29-12-1985, there was no

such continuing breach of the contract and the breach or

breaking was final and conclusive when the defendants

abandoned the work. It is evident that the plaintiff knew

the abandonment of the work in pursuance to Ex.P11 by

the defendants. Therefore, it was incumbent upon the

plaintiff to file the suit within three years from 14-10-1985

or from 29-12-1985. Certainly, Ex.P12 dated 21-2-1986

cannot be the starting point of the limitation.

48. The trial Court in the impugned judgment

observes that the time starts to run from the date of

rescinding of the contract and holds 21-2-1986 as per

Ex.P12 to be the starting point of the limitation. Article 55

of the Limitation Act, does not speak rescinding of contract,

but it speaks of the breach of the contract or when the

contract is broken. Evidently, the contract was broken by

the defendants addressing a letter as per Ex.P11.

Therefore, the trial Court erred in holding that Ex.P12 is the

starting point for the limitation.

49. In that view of the matter, we are of the view

that the suit filed by the plaintiff is barred by limitation. The

right to terminate the contract is on account of the contract

terms being broken by a party to the contract. In the case

on hand, the plaintiff alleged that the defendants had

breached the contract by abandoning the work on

29-12-1985 and to give effect to such breach, the contract

was terminated by letter dated 21-2-1986. Plaintiff knew

that the defendants had in unequivocal terms had broken

the contract by letter dated 14-10-1985. Consequently the

point No. 1 is answered in the affirmative.

Re.Point No.2: Breach of Contract

50. The second question that arises for our

consideration is, who has committed the breach of the

contract. The plaintiff alleged that though the letter of

intent was issued on 22-03-1982 stipulating the period of

completion of contract as 30 months i.e., till 21-09-1984,

the defendants did not commence the work and had to

remind them by letter dated 04-05-1982 as per Ex.P4.

Thereafter, the defendants furnished the bar chart showing

the program of the project to be executed by them as on

15-05-1982 as per Ex.P5. The agreement was entered into

between the parties on 09-12-1982. Thereafter, the

progress of the work had been slowed down and therefore,

the plaintiffs issued letter dated 03-03-1983 as per Ex.P6

indicating imposition of the penalty of Rs.50/- per day as

per Clause-3 of the agreement.

51. Thereafter, the defendants wrote a letter as per

Ex.P7 dated 25-04-1984 seeking enhancement of the rate

for the work already done at 30% and balance work at 50%

even though there was no provision in the agreement to

enhance the rate. Then on 25-07-1984 as per Ex.P8, the

defendants wrote a letter to the plaintiff seeking extension

of eight months time to complete the work beyond the

stipulated date of 21-09-1984. By that time, work executed

was to the extent of Rs.33.11 Lakhs out of Rs.46.13 Lakhs.

52. The plaintiff wrote a letter as per Ex.P9 on

25-05-1985 extending the time to complete the project by

8 months, however, the escalation of the prices claimed by

the defendants was not acceded to. On 14-10-1985,

defendants wrote to the plaintiff as per Ex.P11 seeking

termination of the contract and requesting to settle their

claims. Thereafter, on 21-02-1986, the plaintiff terminated

the contract as per letter at Ex.P12.

53. The defendants contend that the terms and

conditions of the contract show that it was a reciprocal

contract. They contend that non-supply of the drawings and

designs, repeated revision of the drawings, non-payment of

the running bills, non-enhancement of the rates regarding

altered quantities exceeding 25% and non-supply of the

material on time has seriously affected the timelines fixed

for completion of the project. In this regard, they rely on

several correspondences between the plaintiffs and

defendants.

54. The fact that the contract was of reciprocal in

nature and several of the acts of the defendants depended

upon supply of the designs, drawings and material is not

seriously disputed. The Clause 12 of Ex.P3 agreement reads

as below:

"Clause 12: The contractor shall execute the whole and every part of the work in the most sound and

substantial and workman like manner and in strict accordance with the specifications both as regards materials and workmanship. The contractor shall also conform exactly, fully and faithfully to the designs, drawings and instructions in writing relating to the work signed by the Divisional Engineer or other competent authority and lodged in his office and to which the contractor shall be entitled to have access at such office, or on the site of the Work, for the purpose of inspection during office hours and the contractor, shall if he so requires, be entitled to his own expense to make or cause to be made copies of the specifications and of all such designs, drawings, and instructions as aforesaid. The contractor shall also be responsible for the delivery of structure in sound condition and the execution of work strictly in accordance with the specifications for the work."

(emphasis by us)

As per above clause, the defendant was ordained to

conform exactly and fully to the drawings and designs

supplied by the plaintiff in writing. It is clear that the

defendants were not responsible for preparation of the

working drawings/designs of the construction of the

building. Therefore, the defendants were dependant upon

the plaintiff for working designs and drawings. This

obligation of the plaintiff is admitted by PW.2 in his cross-

examination. However, the extensive correspondence

between the parties is available before the Court.

55. We have carefully gone through these letters

exchanged between the plaintiff and the defendants. The

correspondences between the plaintiff and defendants as

per Exs.D1 to D82 are admitted by PW2 in the cross-

examination. Though an objection was raised by the

learned counsel for the appellant/plaintiff that the original

letters were not produced, but only photo copies were

produced, the Court Commissioner who recorded the

evidence of PW2 has clearly stated that these letters were

admitted by PW2 and therefore, they were marked. Section

58 of Evidence Act, states that facts admitted need not be

proved. Therefore, despite the defendants not entering the

witness box to prove those letters, in view of the admission

of PW.2 that the correspondence was there between

plaintiff and defendants as per Ex.D1 to D82, it is not

necessary for us to say that the defendants had to prove

those correspondences. It is also clear that the progress of

the project depended on the timely supply of working

designs and drawings as well as supply of material like steel

and cement.

56. Here it is necessary to mention the provisions of

Sections 52 and 54 of the Contract Act, which read as

below:

"52. Order of performance of reciprocal promises.--

Where the order in which reciprocal promises are to be performed is expressly fixed by the contract, they shall be performed in that order; and where the order is not expressly fixed by the contract, they shall be performed in that order which the nature of the transaction requires.

54. Effect of default as to that promise which should be performed, in contract consisting of reciprocal promises.--

When a contract consists of reciprocal promises, such that one of them cannot be performed, or that its performance cannot be claimed till the other has been performed, and the promisor of the promise

last mentioned fails to perform it, such promisor cannot claim the performance of the reciprocal promise, and must make compensation to the other party to the contract for any loss which such other party may sustain by the non-performance of the contract".

57. The judgment of the Apex Court in the case of K

C Skaria Vs Govt of State of Kerala and another16 also

recognizes the principle of reciprocal promises and the

delay on the part of the employer to supply the materials to

the contractor.

58. We, therefore, come to the conclusion that the

contract between the plaintiff and the defendants was

reciprocal in nature. Our reasons in the below mentioned

paragraphs regarding the breach alleged by the parties also

augment this conclusion.

Non-supply of drawings and designs:

59. Exs.D1, 12, 13, 16, 20, 23, 26, 28, 30, 32, 35,

49, 61 and 62 are the letters between June-1982 to

I(2006) SLT 332

07.02.1985. Under these letters, the plaintiff had supplied

the drawings to the defendants. The Ex.D4, 6 to 8, 14, 19,

29, 38, 45, 58, 62, 65, 66, 71 are the letters between

02.08.1982 to 08.06.1985, under which, the plaintiff

furnished the revised drawings to the defendants. These

letters show that the drawings supplied earlier were revised

subsequently and fresh drawings were supplied to the

defendants.

60. We find from a perusal of Ex.P3, the contract

between the parties that, the dates on which the drawings

have to be supplied to the defendants are not stated.

However, in the cross-examination, PW.2 states that the

drawings and designs have to be furnished to the

defendants at least a week prior to the commencement of

the work as per the Bar Chart produced at Ex.P5. Ex.P5

happens to be a promise made by the defendants to

commence the work and to complete the different stages of

the work during the contract period. It is pertinent to note

that the comparison of Ex.P5 with reference to the letters

referred supra, shows that there was delay in supply of the

designs and drawings. There is no evidence on behalf of

PW.2 that the supply of drawings and designs at different

stages of the execution of the work depended upon the

completion of the previous stage as per Ex.P5. Therefore, if

the supply of the drawings and designs did not depend

upon the completion of the previous stages, there was no

impediment for the plaintiff to supply the drawings and

designs in one go.

61. In the cross- examination of PW2, he admits that

the defendants sought drawings and designs from the

plaintiff on different dates and there were minor changes in

the design. In the cross-examination, PW.2 has admitted

several of these aspects and that there was a need for the

revision of the drawings and the designs. Further, the

completion of each stage of the constructions of the

building as per Ex.P5 was not fully visualized when Ex.P5

was prepared. Evidently, in reply to Ex.P5, the plaintiff has

not stated as to when the final designs and drawings would

be supplied to the defendants. There is no material on

record to show that the defendants had demanded the

working drawings and designs atleast a week prior to the

commencement of each stage of the work as per Ex.P5.

Under these circumstances, we are of the view that though

the delay in supply of the working drawings and designs is

also the cause for the delay of the execution of work, there

is no sufficient material that the supply of drawings and

designs was the sole cause for delayed execution of the

work since there is no mention in the contract as to when

and at what time the drawings and designs have to be

supplied. It would suffice to say that there was delay on

the part of the plaintiff in supplying the working drawings

and the designs and revised drawings to the defendants.

Delayed payment of running bills:

62. The next aspect to be considered is non-

payment of the Running Bills. Again, PW2 in the cross-

examination has admitted that there was delay in payment

of the running bills. The payment of running bills to the

Contractor as agreed between the parties is one of the

reason for continuity in the work. When, such delay in

payment of bills was put to PW2 in his cross-examination,

he states that as and when the Contractor was preparing

the running bills, they were scrutinized and they were paid

to the defendants. However, he admits that there is a

delay in payment of 4th running bill which is as per Ex.D48.

He states that he does not know the reason as to why there

was a delay in payment of 4th and 5th running bills as per

Exs.D48 and D55. From the perusal of these documents, it

appears that there was delay of about two months in

payment of the RA bills.

63. It is also pertinent to note that, the entire

contract period was 30 months and due to the increased

quantity of the work, the period was extended by eight

months. In other words, a total of 38 months was allotted

for the Contractor to complete the work. Considering this

total period of the work, the delay in payment of the RA

bills by about a month or two cannot be said to be a

substantial breach on the part of the plaintiff.

Increase in quantity of work:

64. The third component of the breach is the

increase in quantities of the work. There cannot be any

doubt that there was increase in the quantity of the work.

Evidently, the quantity of the work is not specified in any of

the documents produced by the plaintiff. However the value

of such increased quantity of the work can be found in

para- 8 of the plaint.

65. It is relevant to note that, initially, the value of

Contract was Rs.46.13 lakhs. Later, the total quantity of the

work that was to be executed by the defendants is Rs.60.98

lakhs. In other words, there was increase of the value of

the work by Rs.14.85 lakhs. Therefore, obviously, such

increase in the quantity of the work was more than 25% of

the work which was stipulated under the contract. 25% of

Rs.46.13 lakhs would come to Rs.11.53 lakhs. Therefore,

any quantity which is in excess of Rs.11.53 lakhs was

obviously beyond the scope of the contract between the

parties as per Ex.P3. Such increase in the quantity of the

work should have been on the basis of the rates that could

be mutually accepted by both the parties. Such quantity of

work could not be on the same rates which existed as per

the contract entered into between the parties.

Delay in commencement and completion of work:

66. We have already held that the contract between

the parties was a reciprocal contract in view of Clause 12 of

the agreement. We have also noticed that the execution of

the contract was dependent upon the timely supply of the

working design and drawings, supply of steel and cement

etc. If the supply of steel and cement was delayed, then

definitely, it would have the bearing on the timely

completion of the work under the contract. Therefore, it is

necessary to ascertain whether the parties have understood

that the time was essence of the contract or not. In doing

so, it is relevant to note that in the case of M/s Hind

Construction Contractors By Its Sole Proprietor

Bhikamchand Mulchand Jain (Dead) By LRs Vs State

of Maharashtra17 it was held as below:

"(1)(a) The question whether or not time was of the essence of the contract would essentially be a question of the intention of the parties to be gathered from the terms of the contract. Even where the parties have expressly provided that time is of the essence of the contract such a stipulation will have to be read along with other provisions of the contract and such other provisions may, on construction of the contract, exclude the inference that the completion of the work by a particular date was intended to be fundamental; for instance, if the contract were to include clauses providing for extension of time in certain contingencies or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clauses would be construed as rendering ineffective the express provision relating to the time being of the essence of contract."

67. The contract at Ex.P3 stipulated 30 months for

construction of the building and such construction shall be

(1979) 2 SCC 70

as per the designs, drawings and specifications suggested

and supplied by the plaintiff. Initially, both the parties

agreed for time bound execution and understood that the

time was the essence of the contract. Later, the increase in

quantity of the work beyond 25% was accepted and

therefore, as per Ex.P11(a) and Ex.P9, the period of

contract was extended by eight months. So also, the

contract envisaged imposition of the penalty for delayed

execution of the work at different stages. As noted supra,

there was delay on the part of the plaintiff also for supply of

the designs and drawings. There was delay in payment of

RA Bills by the plaintiffs. These aspects are admitted by

PW.2 in his cross-examination. Therefore, the parties

understood and acted in a way that the time was not the

essence of the contract. They had foregone the essentiality

of time as a fundamental requirement of the contract. The

delay in execution of the work could not have been a

substantial ground to rescind the contract, in view of the

conduct of the plaintiff and the defendants.

68. Thereafter, the plaintiff in pursuance to the letter

at Ex.P9 dated 25-07-1984, extended the dead line for

completion of the work by eight months i.e., till

21-05-1985. It was communicated through letter dated

25-5-1985. Obviously, it was after 04 days of the expiry of

the extended period of eight months. Clause 5 of the

contract at Ex.P3 contemplates extension of time for

completion of the work. It reads as below:

"Clause.5: If the contractor shall desire an extension of the time for completion of the work on the ground of his having been unavoidably hindered in its execution or any other ground such as increase in quantities over 25% (vide clause no.14), he shall apply I writing to the Divisional Engineer before the expiration of the period stipulated in the tender or before the expiration of 30 days from the date on which he was hindered as aforesaid or on which the cause for asking for extension occurred, which ever is earlier and the Divisional Engineer or other competent authority may, if in his opinion there are reasonable grounds for granting an extension, grant such extensions as he thinks necessary or proper."

Further, Clause 14 of the contract also deals with

extension of time in case there is increase in the cost

occasioned by additions. It reads as below:

"Clause.14: The time limit for completion of the work shall be extended commensurate with the increase in its cost occasioned by additions, and the certificate of the Divisional Engineer or competent authority to such proportion shall be conclusive.

XXXX"

69. It is to be noted that in case there is increase in

the quantity of work by more than 25%, the contract does

not mention anything about the rates at which the

additional and extra work is to be carried out. It does not

provide for enhancement of the rates agreed.

70. Thus, it is evident that when the parties had

foregone the condition that time was essence of the

contract and even the extended period of eight months was

communicated by plaintiffs to the defendants after expiry of

eight months, it is evident that there is no reason to believe

that the parties had again, agreed upon the time lines and

revived the contract regarding its essentiality of time.

Therefore, the conduct of the plaintiff does not show that it

had kept up its promise regarding the time lines and

accepted the time to be the essence of the contract.

71. Coming to the delay in commencement of the

work, it is an admitted fact that the site was handed over to

the defendants on 31-03-1982 and thereafter, as per Ex.P4

dated 20-04-1982, the plaintiff states that the defendants

had agreed to commence the excavation work from

15-4-1982, but even till 20-04-1982 such work has not

commenced. In other words, there was delay of about 20

days in commencement of the work. When we compare

this delay of 20 days with reference to the total period of

contract which is 30 months, it is not possible to hold that

there was substantial delay in commencement of the work.

72. We have already noticed that there was delay in

supply of designs and drawings and payments of the

running account bills.

73. So also, a careful perusal of the correspondences

between the parties discloses that when the work was in

progress, there were several impediments which surfaced.

The height of the retaining wall, non- availability of the

space for the storage of the building materials like, steel

and cement and the excavated muck, were also the cause

for the delay. There was no effort by the plaintiff to resolve

these issues which surfaced, though he was in dominant

position. However, the defendants were in the knowledge of

the fact that there was no such space for storage and the

defendants had not flagged these aspects at the time of

entering into the contract between the parties. In that view

of the matter, the defendants had accepted that there were

difficulties for the storage of the building material, etc., and

even then, they had agreed to complete the work as per

the timelines mentioned in Ex.P5. Once the defendants had

agreed that they would execute the work as per the

timelines mentioned in Ex.P5, it was their duty to see that

the work gets completed subject to the plaintiff adhering to

the terms of the contract by supplying the working designs

and drawings and payment of the running bills in time.

Enhanced rates:

74. Apart from the delay, the plaintiff has contended

that though there was no such clause in the agreement, the

defendant demanded the enhanced rates at 30% and 50%.

There was no justification for the defendant to demand the

enhanced rates since the defendant had entered into

agreement as per Ex.P3 and the timelines agreed was 30

months. Therefore, such demand by the defendant for

enhanced rate so far as th work envisaged under the

contract was beyond the scope of the contract and on that

ground, the defendant could not have sought for

termination of the contract and abandonment of the work.

Conclusions reg. breach:

75. From the conspectus of the above documentary

evidence which is available and also evidence of PW.2

available on record in the cross- examination, we are of the

view that though the initial breach of contract was on the

part of the defendants in commencement of work as per

schedule, the subsequent conduct of both the parties show

that there were breaches by both the sides. The substantial

breach was on the part of the plaintiff on account of the

delay in resolving the issues like dearth for space for

storage of steel and cement, clearing and dumping of the

muck from the excavation, supply of working designs and

drawings well in time, considering the request by the

defendants for extension of time lines in time and payment

of the running bills in time. However, the increase in

quantity of the work by more than 25% is also an indicator

which show that the plaintiff had not planned the building

very well. Plaintiff went on increasing the quantity of the

work which is beyond 25% of the total quantity under

contract. This itself shows that the plaintiff was not prompt

in supplying the designs and drawings and also that it

increased the quantity of the work.

76. Thus, the substantial breach of the contract was

on the part of plaintiff and the breaches on the part of the

defendants were minor. The delay in commencement of the

work was only about 20 days as compared to total period of

30 months for completion of project. Even though the

defendants had demanded the higher rates at 30% till

the request was made and 50% for future work, that was

not permissible under the contract. It is evident that the

defendants had not stopped the work until 29-12-1985

even though there was no communication that the request

was not heeded to. All that was informed under Ex.P9 while

granting extension of time was that the other requests

were under consideration.

77. Hence, we hold that the substantial breach of

the contract was on the part of the plaintiff. The

admissions of PW.2 clearly establish that the reciprocal

promises were not adhered to by the plaintiff and the

essentiality of the time was also not adhered by the

plaintiff.

Reg: Point No. 3 - The damages

78. We now proceed to consider each of the claims

made by the plaintiff. The plaintiff has claimed the damages

under the following heads:

  Plaint                                                                  Amount
                           Description of the claim
   para                                                                   (In Rs.)
   16(a)     Money spent by plaintiff to complete the work through       7,21,273.50
             peace work contractors
   16(b)     Unaccounted steel                                           1,49,398.06
   16(c)     Unaccounted cement                                              27,690
   16(d)     Rentals for housing the offices of plaintiff-Corporation   13,58,815.10
             till completion of construction
   16(e)     Salary of Supervisory Staff                                   4,28,750
   16(f)     Reversal of EMD, Security Deposit and work turned            -69,112.13
             out by defendant after 9th RA bill
   16(g)     Extra items done regarding ramp and teak wood door             -12,364
                                                                          26,04,450


                                  Total Claim                             23,08,059



79. The plaintiff contends that as on 21-09-1984,

the date originally stipulated for the completion of the

construction, the defendants had not executed the work of

the value of Rs.32.02 lakhs. It is admitted that there were

additions and alterations in the design and there was

requirement of additional quantities of certain items.

Including the unexecuted portion of the work to the extent

of Rs.13.02 lakhs, the balance of the work was Rs.27.87

lakhs as on 21-09-1984. Thus, it is evident that there was

increase in the quantity of the work by Rs.14.85 lakhs

which was beyond the 25% that was permissible as per the

agreement Ex.P3. In other words, the total value of the

contract had increased to Rs.60.98 lakhs. It is an admitted

fact by the plaintiff that till 21-09-1984, the work of the

value of Rs.33.11 lakhs was completed. Thereafter, from

21-09-1984 to 21-05-1985, work of the value Rs.2.56 lakhs

was completed. Thereafter, from 21-5-1985 to 29-12-1985

when the defendants abandoned the work, the value of the

work completed was Rs.3.44 lakhs. Thus, totally, the work

completed by the defendants was to the tune of Rs.39.11

lakhs. The balance of the work including the increased

quantity was to the tune of Rs.21.87 lakhs. Curiously, the

plaintiff nowhere mentions as to what was the total quantity

of the extra work entrusted to the defendants.

80. It is pertinent to note that the plaintiff claims

that the plaintiff had to spend a sum of Rs.22.40 lakhs by

entrusting the work to the Piece Work Contractors. It is

stated that such contract entrusted to the Piece Work

Contractors was to the tune of Rs.22.40 lakhs. The plaint

schedule shows that the total expenditure incurred by the

Corporation due to non completion of the work by the

defendants was Rs.22,40,126.05 ps. It states that if the

work had been entrusted to the defendants as per the

terms of the contract, it would have valued Rs.15,18,852/-.

It is not known how the sum of Rs.15,18,852/- was arrived

at. Evidently, the balance of the work as mentioned in para

8 of the plaint shows that it was to the extent of (27.87-

(2.44+3.56)) Rs.21.87 lakhs including the extra work

entrusted to the defendants. It is not known as how the

plaintiff arrived at the figure of Rs.15,18,852.55 ps., as per

the plaint schedule. The plaint never explains as to how this

figure was arrived at.

81. Thus, it is evident that the total balance of the

work which was not executed by the defendants, including

the additional or extra work was to the tune of Rs.21.87

lakhs. The plaintiff claimed Rs.22.40 lakhs for the same

and therefore, the difference or the excess amount claimed

by the plaintiff was only to the extent of Rs.53,126.05 ps.

Though the trial Court has rightly arrived at this figure in

the impugned judgment, the analogy for having arrived at

the said figure was not properly explained by it. Therefore,

we do not find any reason to find fault with the trial Court

so far as the claim under this head is concerned.

82. The next claim by the plaintiff is in respect of

unaccounted steel and the cement as claimed in para 16(b)

and 16(c) of the plaint. The plaintiff has claimed that it had

issued 405.31 MT of steel and out of it, 14.955 MT of steel

has remained unaccounted and the value of the same is

Rs.1,49,398/-. It also claimed that 21,411 bags of cement

were supplied to the defendants, out of them 566 bags

remained unaccounted, the value of which was Rs.27,690/-.

83. In para 16(f) of the plaint, it is stated that,

EMD, Security Deposit and the amount towards the extra

work done by the defendants is due from the plaintiff to the

defendants. There cannot be any doubt on this aspect since

the plaintiff admits the same. However, the learned counsel

for defendants submits that the quantity of cement and

steel has also been deducted in the said amount and that is

not justifiable. It is pertinent to note that para 16(f) of the

plaint pertains to the payments which are due from the

plaintiff to the defendants. It is not the sum of Rs.69,112/-

alone which is stated to be payable by the plaintiff to the

defendants, but in addition to it, EMD amount of

Rs.46,125/- and security deposit of Rs.2,56,066/- is also

payable by the plaintiff to defendants. Totally, a sum of

Rs.3,77,867/- is payable to the defendants. Therefore, we

find no reason to find any fault in this regard, as it is an

admitted figure stated by the plaintiff. However, so far as

the loss of the unaccounted quantity of the steel and the

cement is concerned, the learned counsel for the

defendants states that Exs.P31 and P32 are the relevant

documents and there is no acknowledgement by the

defendants regarding this claim. If the defendants have not

rebutted this evidence of the plaintiff in any way, it cannot

be said that the said claim by the plaintiff is inadmissible.

The manner in which the quantity of the cement and steel

was consumed and whether it was in stock was the subject

matter of of RA Bill No.9. It is relevant to note that though

the defendants had got appointed the Court Commissioner

and he had visited the spot and had measured the quantum

of the work executed under the Contract, such a report was

not placed before the trial Court. Even, such report was not

relied by the defendants. Therefore, we find no reason to

accept the argument of the learned counsel for the

defendants in respect of the unaccounted quantity of the

steel and the cement.

84. Similarly, the plaintiff has stated in para 16(g)

that extra-work regarding the teak wood doors in the first

floor was to the extent of Rs.12,364/- and the plaintiff has

to pay the same to the defendant.

85. In para 16(d) the plaintiff has made claim in

respect of the damages occurring on account of the rent

paid by the plaintiff towards the premises occupied by the

Corporation till the completion of the construction of the

building. The said amount is assessed at Rs.13,58,815/-.

The learned counsel appearing for the defendants submits

that the provisions contained in Section 73 of the Indian

Contract Act, stipulate that in calculating the loss or

damage arising out of the breach of contract, the means

which existed for remedying the inconvenience caused by

non performance of the contract must be taken into

account. In this regard, he has drawn the attention of this

Court to the fact that there was delay in entrusting the

unfinished work to the Piece Work Contractors after the

defendants abandoned the work on 29-12-1985. He points

out to the cross-examination of PW.2 where he had stated

that he does not know why there was a delay in entrusting

the work to Piece Work Contractors after abandoning the

contract by the defendants on 29-12-1985 or after

rescission of the Contract by the plaintiff as per letter

Ex.P12. Therefore, he contends that the plaintiff had not

tried to mitigate the damages by expeditiously entrusting

the work to the Piece Work Contractor.

86. The trial Court in the impugned judgment has

elaborately discussed this aspect and has referred to the

judgment in the case of Muralidhar Chiranjilal Vs M/s

Harishchandra Dwarakadas and another (AIR 1962

SC 366) and Nanjappa Vs M P Muthuswamy (AIR

1975 Karnataka 146). Ultimately, it has come to the

conclusion that the person who is claiming damages is

under the duty to take all reasonable steps to mitigate the

loss consequent on the breach and he would be debarred

from claiming any part of the damages due to its neglect to

take such steps. It also noted that the plaintiff had not

entrusted the balance of the work expeditiously, had not

occupied the two floors which were completed. Thus, trial

Court did not award any damages in respect of the rentals

paid by the plaintiff in occupying the other premises.

87. We have another reason to concur with the

conclusions reached by the trial Court. Evidently, the

plaintiff has not produced any substantial evidence to show

that after the rescission of the contract and till the

completion of the work by the Piece Work Contractors, the

plaintiff had paid the rent of Rs.13,58,815/-. Except the self

serving certificate issued by the Company Secretary of the

plaintiff, there is nothing on record to show that such a rent

was paid. Obviously, the plaintiff was in possession of the

best evidence in this regard in the form of the receipts, the

agreement in respect of the tenancy, etc., and also the

receipts for having paid the rent during the said period.

The extract of the certificate or the ledger kept by the

plaintiff and certified by the company Secretary of the

plaintiff-Corporation would not be sufficient evidence within

the meaning of the provisions of the Evidence Act.

88. It is relevant to note that the author of Ex-P33-

Company Secretary, and author of Ex.P37 Senior Executive

(Finance)I, who prepared such documents were not

examined before the Court. The plaintiff relies on Exs.P33

and 37 the statement and certificate issued by the

Company Secretary and the Senior Executive Officer

(Finance) I showing the extra expenditure incurred by the

plaintiff towards the rent and expenses of the staff. It is

worth to note that Exs.P34 to P36 are the ledgers of the

plaintiff-Corporation, but there is no such presumption of

correctness for such statement of the account book kept by

it. It is not a banking company and therefore, it was

necessary for the plaintiff to prove such certificate and the

statement and subject the persons who authored these

documents to the cross-examination by the defendants.

Therefore, the best evidence that could have been produced

by the plaintiff is not available before the Court.

89. In para 16(e), the plaintiff has claimed a sum of

Rs.4,28,750/-, that was spent towards the salaries of Group

Engineers, Engineers, Work Assistants, 3 helpers and other

officers in-charge for the period 01.06.1985 to 30.06.1985.

The analogy applied for the claim in respect of rents for

buildings also applies to the claim in respect of the

expenses made by the plaintiff towards the supervisory

staff. It is relevant to note that neither the clauses in the

Contract nor any correspondence between the parties show

that the plaintiff was supposed to maintain a supervisory

staff over the defendants while executing the contract. It is

the case of the plaintiff that, it had maintained the

supervisory staff for the purpose of completion of the

building and such costs towards the salaries of the

supervisory staff has to be borne by the defendants. The

trial Court observes that there is no such agreement

between the parties. Even if we accept that such liability is

to be fastened on the defendants, the proof regarding the

salaries paid to such supervisory staff is not available on

record. The best evidence was to produce the details of the

salaries paid and examine the persons who were working as

a Supervisory Staff. A Certificate issued by the Company

Secretary cannot be sufficient evidence in this regard. Such

Company Secretary who issued the Certificate is not

examined before the Court. Under the circumstances, we

concur with the conclusions reached by the trial Court in

this regard that the plaintiff is not entitled for these claims.

90. For the foregoing reasons, we have come to the

conclusion that the finding of the trial Court that the

plaintiff is entitled for a sum of Rs.53,126.05 ps., for extra

expenditure, a sum of Rs.1,49,398.06 ps., towards

unaccounted steel and a sum of Rs.27,690/- towards the

unaccounted cement was proper and correct. The trial

Court has also awarded a damages of Rs.10,000/- to the

plaintiff. We have come to the conclusion that the plaint is

barred by time and the trial Court had erred in holding that

the breach of the contract was not on 29-12-1985 but it

was on 20-03-1986. Such conclusion of the trial Court

regarding limitation is not based on the material available

on record, especially, Ex.P11 which we have noted above.

Consequently, the suit has to be dismissed as barred by

time. Hence, the following:

ORDER

(i) The appeal is dismissed.

(ii) The impugned judgment and decree passed by

the trial court in OS No.1094/1989 on 23-11-2009 is set

aside.

(iii) The suit of the plaintiff against the defendants

stands dismissed as barred by time.

(iv) The amount paid by the defendants, if any,

pursuant to decree, be refunded to them.

Sd/-

JUDGE

Sd/-

JUDGE tsn*/NR

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter