Citation : 2023 Latest Caselaw 1025 Kant
Judgement Date : 18 January, 2023
1
IN THE HIGH COURT OF KARNATAKA
KALABURAGI BENCH
DATED THIS THE 18TH DAY OF JANUARY, 2023
BEFORE
THE HON'BLE MR.JUSTICE C.M.POONACHA
RSA No.7050/2009 (REC/MON)
BETWEEN
SANGARAJ SARNAD GOUDAR
S/O KALLANNA GOUDA SARNAD
AGE: 56 YEARS, OCC: LECTURER
R/O DATTANAGAR, JEWARGI COLONY
GULBARGA
...APPELLANT
(BY SRI M. M. PATIL, ADVOCATE)
AND
NIRANJAN S/O KAMALAKAR RAO
AGE:45 YEARS, OCC: CONTRACTOR
R/O BRAHMAPUR, GULBARGA
...RESPONDENT
(BY SRI YASHAS S. DIKSHIT, ADVOCATE FOR
SRI GANESH S. KALBURGI AND
SMT. JYOTI KULKARNI, ADVOCATES)
THIS RSA IS FILED UNDER SECTION 100 OF CPC
AGAINST THE JUDGEMENT AND DECREE DTD. 01.01.2009
PASSED IN R.A.NO.30/2005 ON THE FILE OF THE PRINCIPAL
DISTRICT JUDGE AT GULBARGA PARTLY ALLOWING THE APPEAL
AND SETTING ASIDE THE JUDGEMENT AND DECREE DTD.
22.03.2005 PASSED IN O.S.NO.211/1996 ON THE FILE OF THE
II ADDL. CIVIL JUDGE (SR.DN.) GULBARGA.
2
THIS APPEAL HAVING BEEN HEARD AND RESERVED ON
10.01.2023, COMING ON FOR 'PRONOUNCEMENT OF
JUDGMENT' THIS DAY, THE COURT DELIVERED THE
FOLLOWING:
JUDGMENT
This Second Appeal is filed by the Defendant seeking
to set aside the Judgment and Decree dated 01.01.2009
passed in Regular Appeal No.30/2005 by the Principal
District Judge at Gulbarga.
2. The parties are referred to as per their
rankings before the Trial Court for the purpose of
convenience.
3. The Plaintiff filed a suit in O.S. No.211/1996
for recovery of a sum of `98,272/- together with interest
and costs from the Defendant. It is the case of the Plaintiff
that he is a Contractor and the Defendant had entrusted
him the work of construction of a house in his plot bearing
No.56 at Sy. No.89/1/A at Datta Nagar, Jewargi Colony,
Gulbarga measuring 40x60; that the Plaintiff and the
Defendant executed an agreement dated 27.4.1994 in this
regard and the plan as per which the construction was
required to be made was annexed to the Agreement; that
it was specifically agreed between the plaintiff and
defendant that if any extra construction or any deviation
from the original agreement was made then the cost of the
deviation would be paid by the defendant.
4. It is the further case of the Plaintiff that he
started the construction work as per the agreement in the
first week of May 1994 and in the course of construction,
he carried out certain extra works and that the extra
construction carried out was as per the instructions of the
Defendant; that the Plaintiff completed the construction
work in the month of March 1995 and the last payment
made by the Defendant was `20,000/- on 06.03.1995;
that the Plaintiff had carried out extra construction of a
sum of `80,272/- and that the Defendant had promised to
pay the amount of extra work within a short period.
However, since he did not pay the same, the Plaintiff got
issued a legal notice and it was served on the Defendant.
Thereafter, the Plaintiff filed a Suit claiming a sum of
`80,272/- towards extra work carried out and a sum of
`18,000/- towards interest. Hence, the Suit was filed for a
recovery of total sum of `98,272/- together with further
interest.
5. The Defendant entered appearance and
contested the suit of the Plaintiff and filed written
statement inter alia contending that no extra
work/construction was carried out by the Plaintiff as
averred in the plaint and that the Plaintiff had issued
certificates on various dates detailing the works carried
out. Further that, based on the said certificate, the HDFC
released the loan amount to him; The Defendant further
averred that the Plaintiff had used substandard material
for construction of work, due to which cracks have been
developed in the roof and walls and as such, denied his
liability to pay any further amount to the Plaintiff and
sought for dismissal of the suit.
6. The Trial Court, pursuant to the pleadings filed
by the parties, framed five issues. The Plaintiff examined
himself as PW.1 and got marked three documents i.e.
Exs.P1 to P3. The Defendant examined himself as DW.1.
However, no documents were marked in evidence. The
Trial Court vide its judgment and decree dated
22.03.2005, dismissed the suit filed by the Plaintiff.
7. Being aggrieved, the Plaintiff filed R.A.
No.30/2005. The Defendant who was arrayed as
Respondent before the First Appellate Court entered
appearance in the said Appeal and contested the same.
The First Appellate Court vide its judgment dated
01.01.2009, allowed the Appeal filed by the Plaintiff, set
aside the Judgment and Decree passed by the Trial Court
and decreed the suit of the Plaintiff in part and held that
the Plaintiff was entitled from the Defendant in a sum of
`43,281/- together with proportionate cost. Being
aggrieved, the present Second Appeal is filed.
8. This Court vide order dated 21.08.2009,
admitted the above Second Appeal and framed the
following substantial question of law for consideration in
this second appeal:
Whether in the facts and circumstances of the case, the Appellate Court was justified in reversing the findings of the Trial Court and decreeing the suit?
9. The learned counsel for the
appellant/defendant contends that there is no pleading
regarding extra work in the plaint; that the plaintiff had
completed the construction work and had received the
entire payments and after one year of the same, the
demand for extra payment has been made; that the extra
work carried out has not been proved; that despite the
defendant filing objections to the Commissioner's Report,
the Commissioner has not been examined by the plaintiff
and hence, the first appellate Court ought not to have
relied on the Commissioner's Report. Hence, he seeks for
answering of the substantial question of law in the
negative and for allowing the appeal and granting of the
reliefs sought for therein.
10. Per contra, learned counsel for the
respondent/plaintiff submits that the averments made in
paragraph No.5 of the plaint regarding extra construction
has not been denied by the defendant in his written
statement; no ground has been taken in the above appeal
regarding consideration of the Commissioner's evidence by
the first appellate Court and hence, the appellant cannot
be permitted to urge the said contention; that the
agreement executed between the parties being undisputed
and the said agreement contains clause for payment
towards any extra work done by the plaintiff and the
defendant in his cross-examination admitting to the same,
he is liable to pay for the extra work done by the plaintiff;
that the Commissioner's Report clearly discloses carrying
out of the extra work by the plaintiff and the extra work
having been carried out by the plaintiff, he is liable to be
paid having regard to Section 70 of the Indian Contract
Act. In reliance of his contention that in the absence of
the Commissioner being examined also, the report filed
can be considered, the learned counsel relies on a
judgment rendered by a Coordinate Bench of this Court in
the case of Parappa and Another vs. Bhimappa and
Another1.
11. I have considered the submissions made by
both the learned counsel and perused the material
available on record.
12. The undisputed facts are that the defendant
and the plaintiff entered into an agreement dated
27.04.1994 for construction of a residential house in the
property of the defendant and that the said construction
work was completed by the plaintiff. The dispute is only
with regard to the extra work allegedly done by the
plaintiff, which the defendant has denied. The Trial Court,
after both the parties filed their respective pleadings has
framed the following five issues:
ILR 2008 KAR 1840
1) Whether the plaintiff proves that the defendant has consented for the extra construction work cost shown in Annexure-A of the defendant's house?
2) Whether the plaintiff is entitled to recover `80,272/- as the cost of extra construction work mentioned in Annexure-A and interest of `18,000/- as per agreement from the defendant?
3) Whether the defendant proves that the plaintiff has constructed house as per agreement between the parties, hence, he is not liable to pay the suit amount towards cost of extra construction work?
4) Whether the plaintiff is entitled for the decree prayed in the plaint?
5) What decree or order?
13. The Trial Court while considering issue Nos.1
to 3 has recorded the following findings:
i. The material on record substantially prove that
the defendant having agreed to pay the extra
charges for any construction or deviation from the
approved plan.
ii. That as per the agreement, the earthwork for
foundation was to be dug up to 3' average, but,
the plaintiff contends has done the work of
foundation to a depth of 5½' all over because
there was no hard soil till that depth. However,
the Commissioner in his report has noticed that
the depth of foundation on all the four corners of
the building is 1.40 metres or 4.59'.
iii. As per the agreement, the parties are required to
do earthwork to a depth of 3' only. Hence, the
plaintiff was not entitled to extra charges towards
the earthwork for foundation done beyond the
said 3'.
iv. The plaintiff was not entitled for extra charges
towards soiling for floorings.
v. That the Court is not in a position to appreciate
whether the plaintiff has fixed extra windows in
the said house more than what is specified in the
approved plan.
vi. That the plaintiff has done extra work by fixing
five more doors in the house.
vii. That the plaintiff has failed to prove any extra
work done towards Rex and Shelves.
viii. That the plaintiff has done extra work in respect
of projection of roofing.
ix. There is no material to demonstrate that the
plaintiff has done extra work of roof, plaster,
sevara finish in hall and dining, sundry works and
parapet wall.
x. The plaintiff was not entitled to extra amounts
towards plumbing/sanitary work.
xi. The plaintiff has not proved any extra work of
plastering and finishing.
xii. That the agreement between the parties did not
specify the rates at which the plaintiff is entitled
to for extra work.
xiii. The material on record indicates that the plaintiff
has done extra work in respect of the doors and
roofing projection.
xiv. That there is no agreement to pay the interest.
The Trial Court held that the plaintiff has failed to prove
issue Nos.1 to 4 and dismissed the suit.
14. It view of the aforementioned, it is clear that
even the Trial Court has considered the Commissioner's
Report and has noticed that the plaintiff has done extra
work. However, merely because there was no agreed rate
fixed in the agreement with regard to the extra work, the
Trial Court has dismissed the suit of the plaintiff.
15. The first appellate Court has re-appreciated the
entire material on record including the Commissioner's
Report and has held that the Commissioner's Report is the
part of the record and the same can be looked into. The
first appellate Court has held that the plaintiff has carried
out the following extra work and the amounts to which the
plaintiff is entitled to:
i. With regard to extra work done by the plaintiff
regarding the foundation which has been done for
1.59' at the rate of 54.26 per cubic metre, and the
rubble filling, the plaintiff is entitled to `374/- and
`13,289/- and regarding soling of the flooring
`5,542/-
ii. That the plaintiff has fixed five extra doors and
is entitled to `15,993/- and `772/-.
iii. The plaintiff has done projection of roof on all
sides of the wall to the extent of 3' and the plaintiff
is entitled to `2,788/- and `523/- for plastering of
the extra projection.
iv. The plaintiff is entitled to a sum of `4,000/-
towards landing room to the staircase.
Hence, the plaintiff is entitled to extra work in a sum
of `43,281/- together with proportionate cost.
16. The first appellate Court has also relied on the
Commissioner's Report and has also noticed other material
on record for the purpose of re-appreciating the fact that
the plaintiff has done extra work and for the purpose of
ascertaining the amount to be awarded towards extra work
done by the plaintiff. The first appellate Court has noticed
that the rates stated by the plaintiff has not been
challenged in cross-examination. That the defendant,
except contending that he is not liable to pay the extra
work done by the plaintiff, has not stated about the rate
which has been stated by the plaintiff regarding the extra
work done by him. Hence, it is clear that there is a
concurrent finding of fact that the plaintiff has done extra
work and the appellant/defendant has failed to
demonstrate as to how the said concurrent finding of fact
is erroneous and liable to be interfered with in this second
appeal.
17. The first appellate Court has further noticed
that there is a specific clause in the agreement dated
27.04.1994 that contemplates carrying out of extra work
which is to be paid by the defendant. The same has also
been admitted in the cross-examination of DW.1.
18. Further, both the Trial Court and the first
appellate Court have relied on the Commissioner's Report.
The first appellate Court has recorded a finding that the
Commissioner's Report can be looked into as it found part
of the record irrespective as to whether the Commissioner
is examined or not. A Coordinate Bench of this Court in
the case of Parappa (supra), has held as follows:
"22. xxx It is thereafter when the commissioner/expert submits his report to the Court which appointed him, the report of the Commissioner shall become evidence in the suit and shall form part of the record.
Therefore, the report of the commissioner/expert prepared and submitted on the orders of the Courts stands on a totally different footing in the matter of admissibility than the report of an expert prepared at the instance of either of the parties of the suit or
at the instance of the prosecution in a criminal case xxx.
23. Therefore, the expert becomes a Commissioner only when court appoints him under order XXVI of the CPC. The expert is only a witness for the prosecution in a criminal case, and a witness for the party who appointed him in civil cases. It is only the report of the Commissioner, who is appointed by the Court, shall be evidence in the suit and shall form part of the record and it is not necessary to examine him and get it marked through him to make it evidence."
(Emphasis supplied)
19. Having regard to the judgment of this Court in
the case of Parappa (supra), it is clear that the
Commissioner's Report can be relied upon and shall
become evidence in the suit and shall form part of the
record, even in the absence of Commissioner being
examined and the said report being marked and exhibited
in the case.
20. The appellant/defendant in this second appeal
has not pointed out any specific rate of any specific extra
work that has been assessed by the first appellate Court
being either contrary to the material on record or the
assessment being made without any material on record for
the same to be erroneous.
21. The first appellate Court has noticed all the
materials on record and re-appreciated the entire matter.
As noticed above, even the Trial Court had recorded that
the plaintiff had carried out extra work. However, only on
the ground that the rate at which the plaintiff is sought to
be paid for the extra work was not agreed upon between
the parties, the Trial Court has dismissed the suit of the
plaintiff. The first appellate Court having noticed each of
the items of the extra work and the rate payable for the
same, has reversed the judgment and decree of the Trial
Court and partly decreed the suit in favour of the plaintiff
only to the extent of `43,821/- together with proportionate
cost. In the absence of any evidence regarding interest,
the first appellate Court has rightly not awarded any
interest.
22. The first appellate Court has noticed the
material on record and set out adequate reasons while
partly decreeing the suit filed by the plaintiff. Hence, it
cannot be said that there was no material basis or
justification for the first appellate Court to reverse the
findings of the Trial Court and decreeing the suit of the
plaintiff in part. In view of the same, substantial question
of law framed for consideration by this Court is answered
in the affirmative and against the appellant.
23. Hence, the above appeal is dismissed. The
judgment and decree dated 01.01.2009 passed in
R.A.No.30/2005 by the Principal District Judge at Gulbarga
decreeing the suit of the plaintiff in part holding that the
plaintiff is entitled to `43,281/- from the defendant with
proportionate cost is upheld.
Sd/-
JUDGE
BS/Srt
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!