Citation : 2023 Latest Caselaw 10380 Kant
Judgement Date : 13 December, 2023
-1-
NC: 2023:KHC:45245
WP No. 13629 of 2021
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 13TH DAY OF DECEMBER, 2023
BEFORE
THE HON'BLE MR JUSTICE M.NAGAPRASANNA
WRIT PETITION NO. 13629 OF 2021 (GM-RES)
BETWEEN:
M/S SRI PATHY ASSOCEATES
REPRESENTED BY ITS MANAGING PARTNER,
THIRU. S.SEAKAR,
S/O SUBRAMANIAM
CIVIL ENGINEERING CONTRACTORS,
62, THANGAPERUMAL STREET,
ERODE-638001.
...PETITIONER
(BY SRI. BASAVARAJ SABARAD, SENIOR ADV.
ALONG WITH SRI.H.L.PRADEEP KUMAR, ADV.)
AND:
Digitally signed by 1. THE DIRECTOR
PADMAVATHI B K DIRECTORATE OF FISHERIES,
Location: HIGH 3RD FLOOR, PODIUM BLOCK,
COURT OF VV.TOPWER,
KARNATAKA
DR AMBEDKAR ROAD,
BANGALORE-560001.
2. THE CHIEF ENGINEER
PUBLIC WORKS,
PORT AND INLAND WATER
TRANSPORT DEPARTMENT
COMMUNICATION AND BUILDING (NORTH)
SIR M.VISHWESHRAYA ROAD,
DARWAD-585 101.
-2-
NC: 2023:KHC:45245
WP No. 13629 of 2021
3. THE SUPERINTENDING ENGINEER
DIRECTORATE OF PORTS
PORT AND INLAND WATER TRANSPORT
DEPARTMENT,
BAITHKOL,
KARWAR-581301.
4. THE EXECUTIVE ENGINEER
DEPARTMENT OF PORT AND INLAND WATER
TRANSPORT,
PORT AND FISHERIES SUB DIVISION,
UDUPI - 576101
5. THE ASSISTANT EXECUTIVE ENGINEER
DEPARTMENT OF PORT AND INLAND WATER
TRANSPORT,
PORT AND FISHERIES SUB-DIVISION,
UDUPI- 576101.
6. THE JUNIOR ENGINEER
DEPARTMENT OF PORT AND INLAND WATER
TRANSPORT,
PORT AND FISHERIES SUB-DIVISION,
UDUPI - 575 101
7. THE PRINCIPAL SECRETARY TO GOVERNMENT
PUBLIC WORKS, PORTS AND INLAND WATER
TRANSPORT DEPARTMENT,
VIKASA SOUDHA,
BENGALURU - 560042
8. THE PRINCIPAL SECRETARY TO GOVERNMENT
ANIMAL HUSBANDRY AND FISHERIES DEPARTMENT,
IV FLOOR, VIKAS SOUDHA,
BENGALURU - 560 001
9. THE SECRETARY
ANIMAL HUSBANDRY AND FISHERIES DEPARTMENT,
4TH FLOOR, VIKASA SOUDHA,
BENGALURU - 560001
...RESPONDENTS
(BY SRI.KIRAN KUMAR, HCGP)
-3-
NC: 2023:KHC:45245
WP No. 13629 of 2021
THIS W.P. IS FILED UNDER ARTICLE 226 OF THE
CONSTITUTION OF INDIA PRAYING TO DIRECT THE
RESPONDENTS TO RELEASE THE GST PAYMENTS ALONG WITH
INTEREST AND PENALTY.
THIS PETITION, COMING ON FOR PRELIMINARY
HEARING - 'B' GROUP, THIS DAY, THE COURT MADE THE
FOLLOWING:
ORDER
The petitioner is before this Court seeking the following
prayer:
" MAIN PRAYER
The Petitioner, therefore, most respectfully prays that this Hon'ble Court may be pleased to
i. Issue a WRIT OF MANDAMUS directing the Respondents to release the GST payments along with interest and
ii. pass such further or other orders as this Hon'ble court may deem fit in the interest of justice."
2. Heard the learned Senior counsel Sri. Basavaraj
Sabarad, along with the learned counsel Sri.H.L.Pradeep
Kumar, appearing for the petitioner and the learned HCGP, Sri.
Kiran Kumar, appearing for the respondents.
NC: 2023:KHC:45245
3. Learned Senior counsel Sri.Basavaraj Sabarad
representing the petitioner would submit that the prayer that is
sought in the petition or the issue involved need not detain this
Court for long or delve deep into the matter, as two co-ordinate
Benches of this Court have held in favour of identically placed
petitioners.
4. Learned HCGP though would admit that the issue in
the lis stands answered by the aforesaid co-ordinate Benches,
he would submit that the State is intending to prefer a writ
appeal against those orders and therefore, this Court should
hold its hands in passing any order following the earlier
judgments of the co-ordinate Benches.
5. The submission of the learned HCGP is noted only
to be rejected, as if there is a binding precedent, which is
neither stayed or upturned by the Division Bench or the Apex
Court, it would become binding upon the co-ordinate Benches
of the Court. The dispute is not with regard to its binding
nature, but is on the submission of the learned HCGP that the
NC: 2023:KHC:45245
State is intending to file a writ appeal against the orders. The
writ appeal is yet to be filed.
6. Therefore, I deem it appropriate to follow the order passed by the co-ordinate Bench in W.P.No.9721/2019 and connected cases, which is followed by another co-ordinate Bench in W.P.No.2130/2022 and connected cases. The co-ordinate Bench in W.P.No.9721/2019 has held as follows:
" 18. I find considerable force in the submission made by the learned Senior counsel for the petitioners that the tax component is an independent component which the petitioners do not retain as a profit and is a statutory payment to be made; that looking into the nature of such payment of GST, the respondents/employers are required to honour the same after determining the differential tax burden, especially for the Petitioners who are before this court where "works contract"
were entered prior to 01.07.2017 during KVAT regime and works are completed pre-GST but payments are made post-GST or Contracts entered prior to 01.07.2017 but partly executed pre-GST and balance work executed post-GST or Contracts for which tenders were invited during KVAT regime and finalised after 01.07.2017 under GST regime or contracts which were invited during KVAT regime
NC: 2023:KHC:45245
under old schedule of rates (SR) but finalised under GST regime and that a certain procedure is required to be followed to determine the amount payable by or to the works contractors/Petitioners.
19. In view of the aforesaid facts and circumstances and the Circulars dated 03.01.2020 and 14.12.2020, which have been followed by this Court in MAS constructions's case supra, and also the judgments of other High Courts referred to supra rendered under identical / similar circumstances, in order to do substantial justice, I deem it just and appropriate to dispose of the present petitions by issuing appropriate directions in this regard.
20. In the result, I pass the following:-
ORDER
(i) Petitions are hereby disposed of.
(ii) The Respondents-State and other Govt agencies / Respondents who have entered into works contract with the Petitioners are issued the following directions / guidelines:-
(a) Calculate the works executed pre-GST (prior to 01.07.2017) under KVAT regime and payments received by the Petitioners.
NC: 2023:KHC:45245
(b) The payments received by the Petitioners pre-GST for such of the works executed before 01.07.2017 are to be assessed under KVAT tax regime - either under COT or VAT scheme as applicable.
(c) Calculate the balance works to be completed or completed after 01.07.2017, in the original contract.
(d) Derive the rate of materials, KVAT items required or used to complete the balance works.
(e) Deduct the "KVAT" amount from those materials and the service tax, if applicable.
(f) Add the applicable "GST" on those items.
(g) Input Credit on the materials is to be arrived at and be set off as against the output GST, for those assessed under regular VAT.
(h) Further, the "tax difference" should be calculated on such balance works executed or to be executed after 01.07.2017 separately.
(i) Based on the result obtained on calculation of the tax difference on the contract value, concerned department/authority has to decide whether agreement needs to be changed or not.
(j) A supplementary agreement may be signed with the Petitioners for the revised GST-
NC: 2023:KHC:45245
inclusive work value for the Balance Work completed or to be completed as determined above and in case the revised GST-inclusive work value for the Balance Work, completed or to be completed after 01.07.2017, is more than the original agreement work value, the Petitioners are to be paid /reimbursed, as the case may be, the differential tax amount by the concerned employer; so also, in case payments for works completed pre-GST are made post-GST, the concerned employer has to pay or reimburse, as the case may be, the differential tax amount, to the Petitioners.
(iii) Petitioners are directed to submit comprehensive representations to the respective employers/Respondents within a period of 4 weeks from the date of receipt of a copy of this order, irrespective of whether they have completed the works pre-GST or post-GST or payments were received or yet to be received post-GST.
(iv) If such representations are submitted, the respective employers/Respondents are directed to consider and dispose of the same in the light of the aforesaid directions / guidelines as expeditiously as possible and at any rate within a period of 8 weeks from the date of submission of the representations.
NC: 2023:KHC:45245
(v) In view of the interim orders passed by this Court in the present petitions, such of the petitioners who had not filed their GST returns during the period after 01.07.2017 are permitted to file their returns / amended returns, pursuant to the calculation of the differential tax as per procedure above under GST regime, without insisting on interest or penalty or limitation.
(vi) The GST authorities are also directed not to take precipitative action against the Petitioners for a period of 6 months from the date of receipt of a copy of this order.
(vii) Liberty is reserved in favour of the petitioners to challenge any order / decision passed / taken by the respondents or the authorities, subsequent to this order and also take recourse to such remedies as available in law."
7. The conclusions arrived at by the said learned
single judge is followed by another co-ordinate Bench in
W.P.No.2130/2022, observing as follows:
"20. In the result, I pass the following:-
ORDER
(i) Petitions are hereby disposed of.
- 10 -
NC: 2023:KHC:45245
(ii) The Respondents-State and other Govt agencies /Respondents who have entered into works contract with the Petitioners are issued the following directions / guidelines:-
(a) Calculate the works executed pre-GST (prior to 01.07.2017) under KVAT regime and payments received by the Petitioners.
(b) The payments received by the Petitioners pre-GST for such of the works executed before 01.07.2017 are to be assessed under KVAT tax regime - either under COT or VAT scheme as applicable.
(c) Calculate the balance works to be completed or completed after 01.07.2017, in the original contract.
(d) Derive the rate of materials, KVAT items required or used to complete the balance works.
(e) Deduct the "KVAT" amount from those materials and the service tax, if applicable.
(f) Add the applicable "GST" on those items.
- 11 -
NC: 2023:KHC:45245
(g) Input Credit on the materials is to be arrived at and be set off as against the output GST, for those assessed under regular VAT.
(h) Further, the "tax difference" should be calculated on such balance works executed or to be executed after 01.07.2017 separately.
(i) Based on the result obtained on calculation of the tax difference on the contract value, concerned department/authority has to decide whether agreement needs to be changed or not.
(j) A supplementary agreement may be signed with the Petitioners for the revised GST-inclusive work value for the Balance Work completed or to be completed as determined above and in case the revised GST-inclusive work value for the Balance Work, completed or to be completed after 01.07.2017, is more than the original agreement work value, the Petitioners are to be paid /reimbursed, as the case may be, the differential tax amount by the concerned employer; so also, in case payments for works completed pre-GST are made post-GST, the concerned employer has to pay or reimburse, as the case may be, the differential tax amount, to the Petitioners.
- 12 -
NC: 2023:KHC:45245
(iii) Petitioners are directed to submit comprehensive representations to the respective employers/Respondents within a period of 4 weeks from the date of receipt of a copy of this order, irrespective of whether they have completed the works pre-GST or post-GST or payments were received or yet to be received post-GST.
(iv) If such representations are submitted, the respective employers/Respondents are directed to consider and dispose of the same in the light of the aforesaid directions / guidelines as expeditiously as possible and at any rate within a period of 8 weeks from the date of submission of the representations.
(v) In view of the interim orders passed by this Court in the present petitions, such of the petitioners who had not filed their GST returns during the period after 01.07.2017 are permitted to file their returns /amended returns, pursuant to the calculation of the differential tax as per procedure above under GST regime, without insisting on interest or penalty or limitation.
(vi) The GST authorities are also directed not to take precipitative action against the Petitioners for
- 13 -
NC: 2023:KHC:45245
a period of 6 months from the date of receipt of a copy of this order.
(vii) Liberty is reserved in favour of the petitioners to challenge any order / decision passed / taken by the respondents or the authorities, subsequent to this order and also take recourse to such remedies as available in law."
3. Accordingly, these Writ Petitions are disposed off in terms of the conclusion in W.P.No.9721/2019 and connected petitions, the operative portion of which is extracted hereinabove."
8. In the light of the co-ordinate Bench in
W.P.No.2130/2022 following the earlier order, I deem it
appropriate to dispose the present petition by the following
order:
ORDER
(i) Petition is hereby disposed of.
(ii) The Respondents-State and other Govt agencies/Respondents who have entered into
- 14 -
NC: 2023:KHC:45245
works contract with the Petitioner are issued the following directions / guidelines:-
(a) Calculate the works executed pre-GST (prior to 01.07.2017) under KVAT regime and payments received by the Petitioners.
(b) The payments received by the Petitioner pre-GST for such of the works executed before 01.07.2017 are to be assessed under KVAT tax regime - either under COT or VAT scheme as applicable.
(c) Calculate the balance works to be completed or completed after 01.07.2017, in the original contract.
(d) Derive the rate of materials, KVAT items required or used to complete the balance works.
(e) Deduct the "KVAT" amount from those materials and the service tax, if applicable.
(f) Add the applicable "GST" on those items.
(g) Input Credit on the materials is to be arrived at and be set off as against the output GST, for those assessed under regular VAT.
- 15 -
NC: 2023:KHC:45245
(h) Further, the "tax difference" should be calculated on such balance works executed or to be executed after 01.07.2017 separately.
(i) Based on the result obtained on calculation of the tax difference on the contract value, concerned department/authority has to decide whether agreement needs to be changed or not.
(j) A supplementary agreement may be signed with the Petitioner for the revised GST-inclusive work value for the Balance Work completed or to be completed as determined above and in case the revised GST-inclusive work value for the Balance Work, completed or to be completed after 01.07.2017, is more than the original agreement work value, the Petitioner is to be paid /reimbursed, as the case may be, the differential tax amount by the concerned employer; so also, in case payments for works completed pre-GST are made post-GST, the concerned employer has to pay or reimburse, as the case may be, the differential tax amount, to the Petitioner.
(iii) Petitioner is directed to submit comprehensive representations to the respective
- 16 -
NC: 2023:KHC:45245
employers/Respondents within a period of 4 weeks from the date of receipt of a copy of this order, irrespective of whether they have completed the works pre-GST or post-GST or payments were received or yet to be received post-GST.
(iv) If such representations are submitted, the respective employers/Respondents are directed to consider and dispose of the same in the light of the aforesaid directions / guidelines as expeditiously as possible and at any rate within a period of 8 weeks from the date of submission of the representations.
(v) In view of the interim orders passed by this Court in the present petitions, such of the petitioner who had not filed their GST returns during the period after 01.07.2017 are permitted to file their returns /amended returns, pursuant to the calculation of the differential tax as per procedure above under GST regime, without insisting on interest or penalty or limitation.
(vi) The GST authorities are also directed not to take precipitative action against the Petitioner for a period of 6 months from the date of receipt of a copy of this order.
- 17 -
NC: 2023:KHC:45245
(vii) Liberty is reserved in favour of the petitioner to challenge any order / decision passed / taken by the respondents or the authorities, subsequent to this order and also take recourse to such remedies as available in law."
Sd/-
JUDGE
KG
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!