Citation : 2022 Latest Caselaw 12924 Kant
Judgement Date : 9 November, 2022
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 09TH DAY OF NOVEMBER, 2022
BEFORE
THE HON'BLE MR. JUSTICE M. NAGAPRASANNA
WRIT PETITION No.20761 OF 2022 (GM - TEN)
C/W
WRIT PETITION No.20762 OF 2022 (GM - TEN)
BETWEEN:
SREE GAJANANA POWER CONTROLS PVT. LTD.,
A COMPANY INCORPORATED UNDER THE
COMPANIES REGISTRATION ACT, 1956
NO.1, 2ND FLOOR, SWWC, 407,
MAIN ROAD, 4TH PHASE,
YELAHANKA NEW TOWN
BENGALURU - 560 106
REPRESENTED BY ITS DIRECTOR
SRI. ANIL. N.,
... COMMON PETITIONER
(BY SRI RAJENDRA.M.S., ADVOCATE FOR
M/S HOLLA AND HOLLA ASSOCIATES )
AND:
1. THE DEPUTY GENERAL MANAGER (ELE)
OPERATIONS-I
BANGALORE ELECTRICITY SUPPLY
COMPANY LIMITED
4TH FLOOR, CORPORATE OFFICE
2
BESCOM, K.R. CIRCLE
BENGALURU - 560 001.
2. THE ADDITIONAL CHIEF SECRETARY
ENERGY DEPARTMENT
GOVERNMENT OF KARNATAKA
VIKASA SOUDHA
BENGALURU - 560 001.
... COMMON RESPONDENTS
(BY SRI S.SRIRANGA, SR.ADVOCATE FOR
SMT.SUMANA NAGANAND, ADVOCATE FOR R1;
SRI M.VINOD KUMAR, AGA FOR R2)
WRIT PETITION No.20761 OF 2022 IS FILED UNDER
ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING
TO QUASH THE ORDER REJECTING THE TECHNICAL BID
SUBMITTED BY THE PETITIONER IN RESPECT OF THE TENDER
NOTIFICATION BEARING NO.COM/CGM(OP)/DGM(OP-1)21-22/54
DTD 28.03.2022 ANNEXURE-F; DECLARE THAT THE BID
SUBMITTED BY THE PETITIONER UNDER THE TENDER
NOTIFICATION BEARING NO.COM/CGM(OP)/DGM(OP-1)21-22/54
DTD 28.03.2022 IS TECHNICALLY RESPONSIVE ANNEXURE-F.
WRIT PETITION No.20762 OF 2022 IS FILED UNDER
ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING
TO QUASH THE ORDER REJECTING THE TECHNICAL BID
SUBMITTED BY THE PETITIONER IN RESPECT OF THE TENDER
NOTIFICATION BEARING NO.COM/CGM(OP)/DGM/(OP-1)21-22/76
DTD.28.3.2022 ANNEXURE-E; DECLARE THAT THE BID SUBMITTED
BY THE PETITIONER UNDER THE TENDER NOTIFICATION BEARING
NO.COM/CGM(OP)/DGM/(OP-1)21-22/76/28.3.2022/CALL-2
DTD.28.3.2022 IS TECHNICALLY RESPONSIVE ANNEXURE-E.
THESE WRIT PETITIONS HAVING BEEN HEARD AND
RESERVED FOR ORDERS ON 07.11.2022, COMING ON FOR
PRONOUNCEMENT THIS DAY, THE COURT MADE THE FOLLOWING:-
3
ORDER
The petitioner common in both these petitions calls in
question the rejection of his technical bids submitted pursuant to
notice inviting tenders dated 28-03-2022 and consequently seeks a
declaration that his bids are responsive.
2. Heard Sri.Rajendra.M.S., learned counsel for M/s Holla and
Holla Associates appearing for petitioner, Sri.S.Sriranga, learned
senior counsel appearing for respondent No.1 and Sri.M.Vinod
Kumar, learned Additional Government Advocate appearing for
respondent No.2.
3.Brief facts that lead the petitioner to this Court in the
subject petitions, as borne out from the pleadings, are as follows:-
The petitioner claims to be in the business of repair and
distribution of transformers for close to 25 years and further claims
that he has a recognized name in the reconditioning and
distribution of transformers. The 1st respondent/Bangalore
Electricity Supply Company Limited ('BESCOM' for short) issued a
notice inviting tenders on 28-03-2022 for the work of repair and re-
conditioning 11 KV class single coil/multi coil conventional and 3, 4,
5 star rated failed distribution transformers of various capacities
from 25 to 100 KVA and other allied works of lumpsum percentage
on rate contract basis. The petitioner in both these cases submits
his bids for Doddaballapura Taluk, Nelamangala Division of
BESCOM. The tender was to be a two cover tender - first part
would be the technical bid and the second the price bid. The last
date for submission of technical bid was 26-04-2022. As observed
hereinabove, the petitioner participates in the competitive bidding
process finding himself eligible in terms of the notice inviting
tenders, as according to him, he was qualified in all the terms and
conditions and submits all necessary documents within the time
stipulated. EMD of Rs.1,50,995/- was also deposited as required in
terms of NIT. The technical bids of the petitioner come to be
rejected on 01-10-2022, the same was displayed in the e-
procurement portal of BESCOM. The petitioner, on the ground that
he was the lowest bidder, submitted a representation seeking
BESCOM to furnish the reason for rejection. No reply was received
on the said representation of the petitioner. He appears to have
come to understand that infrastructure facilities depicted by him in
the tender documents were not countersigned by the competent
authority i.e., the Executive Engineer of BESCOM. On the ground
that they did not bear the signature endorsing the infrastructure,
the petitioner's bid had come to be rejected. It is this rejection that
drives the petitioner to this Court in the subject petitions.
4. The learned counsel appearing for the petitioner would
contend that the bids of the petitioner could not have been rejected
as signature part of the document was a curable defect and is only
ancillary to the terms and conditions; it is not the primary term or
condition that would entail rejection of technical bids altogether. He
would submit that only thing that is not found in the documents is
attestation of infrastructure by the Executive Engineer.
5. On the other hand, the learned senior counsel Sri S.
Sriranga appearing for the 1st respondent/BESCOM would refute the
submissions to contend that the petitioner though had submitted
everything did not get the infrastructure available with him
endorsed by the competent authority. This was the necessity in the
tender and without this, technical bid could not have been
accepted. The learned senior counsel would submit that most of the
tenderers bids who did not have this endorsement have been
rejected at the technical bid stage itself, as the lacunae is uniformly
applied to deny acceptance of technical bids. He would submit that
the petition lacking in merit be dismissed.
6. I have given my anxious consideration to the submissions
made by the respective learned counsel and have perused the
material on record.
7. Notice inviting tenders is for short term. The conditions
stipulated in the bid are depicted in Clause 15 which deals with
Technical requirement and in column 'Transformer Repair' clauses
(c) and (d) which are germane read as follows:
"(c) The bidder shall upload all the transformers repaired during the year for the same year uploaded in QR-I
(b). For example if Bidder has repaired 1250 nos. of transformers during 2018-19 and has uploaded 400 nos. for meeting technical requirement as in QR 1(b), in such case the bidder should upload performance certificate for total 1250 nos. of repairs carried out in that particular year i.e.,2018-19.
The Bidder shall upload the Performance Certificate for the above (ex.1250 nos.) along with percentage failure rate of repaired distribution transformers within guarantee period is less than 6% issued by the concerned jurisdiction al officer not below the rank of Executive Engineer (Ele.) of C, O&M Divisionis of BESCOM/ESCOMs of Karnataka as per Revised Abstract-2 (enclosed) to be uploaded.
(d) Bidder should have necessary infrastructure for repairing at least 150 Nos. of Distribution Transformers per month. The Bidder should upload necessary self-declaration and Annexure-D."
(Emphasis added)
Clause (c) directs that the tenderer shall upload all the transformers
repaired during the year for the same year uploaded and clause (d)
mandates that bidders should have necessary infrastructure for
repairing at least 150 Nos. of distribution transformers per month
and the bidder should upload self-declaration to that effect which is
styled as Annexure-D. This is the technical requirement of any
tender.
8. The petitioner uploads all the documents and with regard
to details of T & P materials and testing equipments available with
the bidder at the bottom of the list it had to be endorsed by the
competent authority i.e., the Executive Engineer in terms of sub-
clause (d) of Clause 15.1 supra. What the petitioner does is gives a
declaration that he has submitted all the documents and has
complied with all the conditions and stipulations and has not done
any deviation whatsoever. This is declared by the petitioner as
being the Director of the Company. What the petitioner would do is
put his signature in place of signature of the Executive Engineer.
What is found in the document is the signature of the petitioner
alone with the seal of the company in place of Executive Engineer
(Ele.). Therefore, the petitioner has not got his list of infrastructure
endorsed at the hands of the competent authority i.e., the
Executive Engineer as is required in the tender conditions of the
notice inviting tender. The petitioner if had stopped at that would
have been a circumstance altogether different. But, the petitioner
puts his signature at the place of the signature of the Executive
Engineer only to show that the document is complete in all respects
and further declares that he has submitted all the documents in
tune with the terms and conditions stipulated. Therefore, the act of
the petitioner in not getting it signed by the competent authority is
the first flaw and his act of signing the document in place of the
Executive Engineer to make it complete is the next flaw, which
would deny the relief to the petitioner.
9. The contention of the learned counsel for the petitioner is
with reference to Clause 12.11 of the tender conditions which reads
as follows:
"12.11 The bidder shall establish the infrastructure required for carrying out transformer repairs at repair center within 15 days from the date of issue of DWA."
Clause 12.11 permits the Bidder to establish the infrastructure to
carry out transformer repairs, at the repair center within 15 days
from the date of issuance of work order. This is relied on to contend
that 15 days time is available to the petitioner to demonstrate that
he had the infrastructure to submit his technical bid is
unacceptable. What is to be furnished by the tenderer is found in
Clause 15 to be the Technical requirement. What is found in Clause
12.11 is he should establish the infrastructure within 15 days of
awarding of contract at the place where he is awarded the contract.
This clause would not mean, even after the award of contract he
can display his infrastructure. Displaying of infrastructure is a pre-
requisite for submitting the technical bid. It cannot be a post award
of contract act on the part of the tenderer. Therefore, the
submission that he has 15 days time even to submit that he has
infrastructure is misplaced on a reading of clause 12.11, as the
Clause itself clearly depicts within 15 days of issuance of DWA.
10. Therefore, there is no ground that would warrant any
interference in favour of the petitioner for the reason that the
petitioner has misled the Tendering Inviting Authority by affixing his
signature in place of the signature of the Executive Engineer only to
make it complete which is a tender condition. That condition is
ancillary to the main condition or not need not be gone into,
because of the act of the petitioner in misleading the Tender
Inviting Authority. He has not submitted the documents with clean
hands and the condition in the tender clearly indicated that it has to
be endorsed by the Executive Engineer. Being in violation of the
tender condition, no fault can be found with the 1st
respondent/BESCOM in declining to accept the tender of the
petitioner at the technical bid stage itself.
11. The submission of the learned senior counsel for the
respondent/BESCOM that this rule has been uniformly applied to all
the tenderers who have submitted their infrastructure without
getting it countersigned by the Executive Engineer and rejected
would also be another circumstance apart from what is narrated
hereinabove, to decline any interference at the hands of this Court.
12. The judgments relied by the learned counsel for the
petitioner in the case of GUJARAT LIQUI PHARMACAPS
PRIVATE LIMITED, VADODARA v. THE SECRETARY,
DEPARTMENT OF HEALTH AND FAMILY WELFARE SERVICES,
BANGALORE - 2008 SCC OnLine Kar 506 and in the case of
BMM ISPAT LIMITED v. STATE OF KARANTAKA AND
ANOTHER - 2016 SCC OnLine Kar 4549 to contend that such a
condition being ancillary to the tender conditions cannot overpower
the tender conditions to reject the tender are also unacceptable, as
the issue in those cases was entirely different and the issue in the
case at hand is violation of tender condition coupled with the act of
the petitioner to have mislead the Tender Inviting Authority.
Therefore, the judgments would not become applicable to the facts
of the case at hand. Even otherwise, as held by the Apex Court in
the case of N.G. PROJECTS LIMITED v. VINOD KUMAR JAIN
AND OTHERS - (2022) 6 SCC 127 the Apex Court holds that
constitutional Courts, in exercise of their judicial review, cannot
substitute their opinion in respect of any condition of tender. The
case before the Apex Court was concerning a particular format of a
bank guarantee which the bidder was required to stick to, and that
particular format alone had to be submitted. Both the learned
single Judge and the Division Bench had held that, that was not a
condition that could have led rejection of the tender. The Apex
Court upturns the said finding by observing as follows:
"13. This Court sounded a word of caution in another judgment reported as Silppi Constructions Contractors v. Union of India [Silppi Constructions Contractors v. Union of India, (2020) 16 SCC 489] , wherein it was held that the courts must realise their limitations and the havoc which needless interference in commercial matters could cause. In contracts involving technical issues, the courts should be even more reluctant because most of us in Judges' robes do not have the necessary expertise to adjudicate upon technical issues beyond our domain. As laid down in the judgments cited above, the courts should not use a magnifying glass while scanning the tenders and make every small mistake appear like a big blunder. In fact, the courts must give "fair play in the joints" to the government and public sector undertakings in matters of contract. The courts must also not interfere where such interference would cause unnecessary loss to the public exchequer. It was held as under: (SCC p. 501, paras 19-
20)
"19. This Court being the guardian of fundamental rights is duty-bound to interfere when there is arbitrariness, irrationality, mala fides and bias. However, this Court in all the aforesaid decisions has cautioned time and again that courts should exercise a lot of restraint while exercising their powers of judicial review in contractual or commercial matters. This Court is normally loathe to interfere in
contractual matters unless a clear-cut case of arbitrariness or mala fides or bias or irrationality is made out. One must remember that today many public sector undertakings compete with the private industry. The contracts entered into between private parties are not subject to scrutiny under writ jurisdiction. No doubt, the bodies which are State within the meaning of Article 12 of the Constitution are bound to act fairly and are amenable to the writ jurisdiction of superior courts, but this discretionary power must be exercised with a great deal of restraint and caution. The courts must realise their limitations and the havoc which needless interference in commercial matters can cause. In contracts involving technical issues the courts should be even more reluctant because most of us in Judges' robes do not have the necessary expertise to adjudicate upon technical issues beyond our domain. As laid down in the judgments cited above the courts should not use a magnifying glass while scanning the tenders and make every small mistake appear like a big blunder. In fact, the courts must give "fair play in the joints" to the government and public sector undertakings in matters of contract. Courts must also not interfere where such interference will cause unnecessary loss to the public exchequer.
20. The essence of the law laid down in the judgments referred to above is the exercise of restraint and caution; the need for overwhelming public interest to justify judicial intervention in matters of contract involving the State instrumentalities; the courts should give way to the opinion of the experts unless the decision is totally arbitrary or unreasonable; the court does not sit like a court of appeal over the appropriate authority; the court must realise that the authority floating the tender is the best judge of its requirements and, therefore, the court's interference should be minimal. The authority which floats the contract or tender, and has authored the tender documents is the best judge as to how the documents have to be interpreted. If two interpretations are possible then the interpretation of the author must be accepted. The courts will only interfere to prevent arbitrariness, irrationality, bias, mala fides or perversity. With this approach in mind, we shall deal with the present case."
(emphasis supplied)
14. In National High Speed Rail Corpn. Ltd. v. Montecarlo Ltd. [National High Speed Rail Corpn. Ltd. v. Montecarlo Ltd., (2022) 6 SCC 401] , this Court sounded a word of caution while entertaining the writ petition and/or granting stay which ultimately may delay the execution of the mega projects. It was held as under : (SCC para 48)
"48. Even while entertaining the writ petition and/or granting the stay which ultimately may delay the execution of the Mega projects, it must be remembered that it may seriously impede the execution of the projects of public importance and disables the State and/or its agencies/instrumentalities from discharging the constitutional and legal obligation towards the citizens. Therefore, the High Courts should be extremely careful and circumspect in exercise of its discretion while entertaining such petitions and/or while granting stay in such matters. Even in a case where the High Court is of the prima facie opinion that the decision is as such perverse and/or arbitrary and/or suffers from mala fides and/or favouritism, while entertaining such writ petition and/or pass any appropriate interim order, High Court may put to the writ petitioner's notice that in case the petitioner loses and there is a delay in execution of the project due to such proceedings initiated by him/it, he/they may be saddled with the damages caused for delay in execution of such projects, which may be due to such frivolous litigations initiated by him/it. With these words of caution and advise, we rest the matter there and leave it to the wisdom of the Court(s) concerned, which ultimately may look to the larger public interest and the national interest involved."
13. In view of the preceding analysis, finding no merit to
entertain the petitions, the petitions would necessarily meet its
dismissal and are accordingly dismissed.
Consequently, pending applications also stand disposed.
Sd/-
JUDGE
bkp CT:MJ
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!