Citation : 2022 Latest Caselaw 5545 Kant
Judgement Date : 28 March, 2022
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 28TH DAY OF MARCH, 2022
PRESENT
THE HON'BLE MRS.JUSTICE S.SUJATHA
AND
THE HON'BLE MR. JUSTICE SHIVASHANKAR AMARANNAVAR
W.A.No.3845/2019 (GM - RES)
BETWEEN :
SHANTHAPPA BHANDARY
S/O NARAYANA BHANDARY
AGED ABOUT 64 YEARS,
R/AT MUGERU PADU HOUSE,
SANGABETTU VILLAGE,
SIDDAKATTE POST
BANTWAL TALUK,
D.K.DISTRICT - 574 144. ...APPELLANT
(BY SRI S.RAJASHEKAR, ADV.)
AND :
1. SOHAM PHALGUNI RENEWABLE
ENERGY PVT. LTD.,
IRUVAIL, MULIBETTU, IRUVAIL POST
PUCHEMOGARU VILLAGE
MANGALORE TALUK
D.K. DISTRICT - 574 237
REP BY ITS CHAIRMAN
K.SADANANDA SHETTY
2. STATE OF KARNATAKA
REP BY ITS CHIEF SECRETARY,
VIDHANA SOUDHA,
Dr. B.R.AMBEDKAR VEEDHI,
BENGALURU - 560 001.
-2-
3. DEPUTY COMMISSIONER
D.K.DISTRICT, MANGALORE - 01.
4. ASSISTANT COMMISSIONER
MANGALORE TALUK,
D.K. DISTRICT - 01.
5. TAHASILDAR
BANTWAL TALUK
D.K. DISTRICT- 16.
6. THE DEPUTY DIRECTOR
HORTICULTURE DEPARTMENT
DAKSHINA KANNADA DISTRICT
MANGALORE - 575 002. ...RESPONDENTS
(BY SRI AJAY J.N., ADV. FOR R-1;
SRI JEEVAN J. NEERALGI, AGA FOR R-2 TO R-6.)
THIS W.A. IS FILED UNDER SECTION 4 OF THE
KARNATAKA HIGH COURT ACT, PRAYING TO SET ASIDE THE
ORDER DATED 18.09.2019 PASSED BY THE LEARNED SINGLE
JUDGE OF THIS HON'BLE HIGH COURT IN W.P.NO.7874/2019
(GM-RES) AND ALLOW THE WRIT PETITION WITH COSTS AS
PRAYED FOR UNDER THE FACTS AND CIRCUMSTANCES OF
THE CASE.
THIS APPEAL COMING ON FOR HEARING, THIS DAY,
S. SUJATHA, J., DELIVERED THE FOLLOWING:
JUDGMENT
This intra Court appeal is filed against the order
dated 18.09.2019 passed in W.P.No.7874/2019
whereby the Writ Petition filed by the respondent No.1
herein - Soham Phalguni Renewable Energy Pvt. Ltd.,
has been disposed of, with a direction to the respondent
No.1 to disburse the sum of Rs.26,00,000/- to the
appellant deducting the amount which has already been
disbursed within a period of one week from the date of
receipt of certified copy of the order.
2. This case has a checkered history. This is
the third round of litigation before this Court.
3. The appellant claims to be the absolute
owner in possession and enjoyment of the property
bearing Sy.No.66/1, measuring 2.90 acres, Sy.No.66/2,
measuring 0.58 acres and Sy.No.66/2, measuring 0.39
acres of Sangabettu village, Bantwal Taluk. The
appellant claims that a house and hatti kottige were
constructed in the said property in addition to effecting
improvement in the said property by planting arecanut,
coconut and other plantation and digging a borewell
with the pumpset installed therein. The appellant
states that the hard earned money was invested for
improving the properties besides availing loan from the
nationalized bank.
4. It transpires that in the year 2004-2005, the
respondent No.1 was allotted the work of construction
of mini hidel project for power generation across
Phalguni river in Dakshina Kannada District. The
appellant and some of the neighbouring land owners
filed a suit for permanent prohibitory injunction in
OS.No.28/2005 on the file of the Civil Judge (Jr.Dn),
Bantwal. Subsequently, during the pendency of the
said suit, the parties to the suit entered into an
agreement dated 10.4.2007 which was registered on
11.4.2007, wherein in terms of clause 2 of the said
agreement, it was agreed that in the event of any
damage or loss of crop, the amount of compensation of
Rs.12.00 lakhs for coconut and arecanut plantation and
Rs.7.00 lakhs per acre for wet land and Rs.3.00 lakhs
per acre for dry land would be paid by the Respondent
No.1. In view of the said agreement entered into between
the parties, the suit filed by the appellant and other
neighbouring land owners in OS.No.28/2005 was
withdrawn on 27.5.2008.
5. Subsequently, W.P.No.5379/2016 was filed
by the appellant before this Court seeking for a direction
to pay the compensation amount pursuant to the letter
dated 30.9.2015 addressed by the Tahsildar, Bantwal
Taluk, Dakshina Kannada District and considering the
report dated 28.12.2015 addressed by the appellant to
the Deputy Commissioner, Dakshina Kannada District,
Mangaluru. The said writ petition came to be disposed
of on 22.2.2017 reserving liberty to the appellant to
make a representation along with all supporting
documents with respondent Nos.1, 3 and 5 herein and
directing the said respondents to hold a joint inspection
in terms as indicated in W.P.No.55938/2015 and allied
matters, decided on 1.3.2016 and take a decision in the
matter in an expedite manner, but not later than three
months from the date on which a fresh representation
submitted by the appellant. Pursuant to the
representation submitted by the appellant on
16.3.2017, an inspection was held on 20.7.2017. The
assessment report dated 28.7.2017 was prepared fixing
the compensation and an award dated 21.8.2017 was
passed.
6. Being aggrieved by the said determination of
compensation and award made by the Deputy
Commissioner, W.P.No.56199/2017 was filed by the
respondent No.1 herein, which came to be disposed of
on 26.2.2018 observing that the Deputy Commissioner
ought to have taken into account the registered
agreement entered into between the parties dated
10.4.2007 (registered on 11.4.2007) while determining
the amount of compensation payable to the appellant,
the exact measurements of land adversely affected by
the submergence with the construction raised by
respondent No.1 company and also the crops adversely
affected of the appellant. But the same having not been
done, directed the Deputy Commissioner to decide the
case afresh by the end of October, 2018, after holding a
joint survey in the presence of both sides - parties, in
the month of September/October 2018 setting aside the
order of the Deputy Commissioner determining the
compensation - award at Rs.36,78,213/-. Pursuant to
the said order, the Deputy Commissioner has passed
the order dated 18.1.2019 reiterating the decision taken
earlier and determining the compensation at
Rs.36,78,213/-. Being aggrieved by the same, the
respondent No.1 had preferred W.P.No.7874/2019,
which came to be disposed of, as stated hereinabove.
Hence, this writ appeal by the appellant/claimant.
7. Learned counsel appearing for the appellant
inviting the attention of the Court to paragraph 5 of
W.P.No.5379/2016 submitted that the factum of
OS.No.28/2005 filed by the appellant and the
neighbouring land owners before the learned Civil Judge
(Jr.Dn), Bantwala, the agreement entered into between
the parties during the pendency of the said suit and
withdrawal of the said suit by the appellant and other
land owners indeed was narrated in the memorandum
of writ petition. It was the grievance of the appellant
that even after the disposal of the said suit, the
respondent No.1 has not paid any amount as
compensation. That being the position, the learned
Single Judge giving a finding that this factual aspect of
having entered into the registered agreement with the
respondent No.1 on 11.4.2007 was suppressed and an
order was obtained by playing fraud, is wholly
unjustifiable. The learned Single Judge considering the
identical matters disposed of in W.P.No.55938/2015
and allied matters, disposed of W.P.No.5379/2016. As
such, it cannot be held that fraud was played by the
appellant.
8. Nextly, the learned counsel submitted that
the damage caused to the appellant has been rightly
assessed by the Deputy Commissioner having
considered the ground realities and conducting the joint
survey as directed by this Court in W.P.No.56199/2017
and determined the compensation at Rs.36,78,213/-,
the same ought not to have been reduced by the learned
Single Judge to Rs.26.00 lakhs. Learned counsel
further submitted that though the agreement was
entered into between the parties, the same was not
acted upon by the respondent No.1 inspite of lapse of
more than ten years. The compensation awarded is on
the lower side and the same is to be enhanced by this
Court pursuant to the spot inspection conducted along
with the Joint Director of Agriculture Department,
- 10 -
Deputy Director of Horticulture Department and other
officials.
9. Learned Counsel appearing for the
respondent No.1 supporting the impugned order
submitted that the learned Single Judge has critically
analyzed the material aspects with respect to the
registered agreement entered into between the appellant
and the neighbouring land owners with respondent No.1
as well as the suppression of material facts made by the
appellant in W.P.No.5379/2016 resulted in the direction
being issued by the writ court (W.P.No.5379/2016)
permitting the appellant to file a fresh representation.
This suppression of material facts was noticed in the
subsequent W.P.No.56199/2017 filed by the respondent
No.1 against the compensation determined and award
dated 21.8.2017 and a categorical direction was issued
to the Deputy Commissioner to redo the joint survey in
the presence of both the parties in the month of
- 11 -
September/October 2018 keeping in mind the registered
agreement dated 11.4.2007. Despite the specific
direction issued by the writ court in
W.P.No.56199/2017, the Deputy Commissioner has not
complied the same and has reiterated the earlier
determination of compensation made at Rs.36,78,213/-.
10. The learned Single Judge in the present
proceedings has observed breach of the order made by
the Deputy Commissioner in not strictly adhering to the
directions issued insofar as the registered agreement
dated 11.4.2007. Though the Deputy Commissioner
was directed to decide the case after holding a joint
survey, the joint survey was conducted by the Joint
Director of Agriculture, the Deputy Director of
Horticulture, the Assistant Commissioner, Mangaluru
District and the Tahsildar, Bantwal, interpreting the
order of the writ court in W.P.No.56199/2017 in a
different manner. These violations have been considered
- 12 -
and reproduced in a tabular form by the learned single
Judge in paragraph 7. In this regard, though the
respondent No.1 was liable to pay a sum of Rs.25.25
lakhs by way of compensation, has agreed to pay a sum
of Rs.26.00 lakhs to the appellant towards full and final
settlement of his claim. There was no application of
mind by the Deputy Commissioner to the directions
issued by this Court. The determined compensation of
Rs.36,78,213/- not being in conformity with the
directions issued by the writ court, the learned Single
Judge has rightly directed the respondent No.1 to pay a
sum of Rs.26.00 lakhs agreed by the appellant. The
same being reasonable, requires to be confirmed by this
Court dismissing the writ petition.
11. We have carefully considered the rival
submissions of the learned counsel appearing for the
parties and perused the material on record.
- 13 -
12. The factual aspects narrated hereinabove are
not in dispute. In order to verify whether any
contention was taken by the appellant in
W.P.No.5379/2016 as contended we have secured the
said file i.e., W.P.No.5379/2016 from the registry and
perused paragraph 5 therein which reads thus;
"5. The petitioner further submits that since, the project was made behind the back of the villagers the neighbouring land owners filed a suit for permanent prohibitory injunction in OS No.28 of 2005 on the file of Civil Judge (JD) at Bantwal. Subsequently, during the pendency of the said suit the parties entered into an agreement and petitioner and other land owners had not persuaded the said suit. Even after the disposal of the suit the respondent No.3 has not paid the any amount as compensation. Thereafter, the petitioner was persuading the matter with the respondents and requested them to take action in the matter. The petitioner sent repeated notices to the respondent No.3 to take action in the matter. Subsequently, petitioner issued a legal notice. The petitioner also made representation to respondents No.2 to 5 to take
- 14 -
action in the matter. True copy of the notice dated 10.7.2015 is produced herewith and marked as ANNEXURE-F. In addition to that the petitioner has addressed yet another notice on 11.8.2015 to the 3rd respondent, which is produced herewith and marked as ANNEXURE-G. Likewise, since there was no action taken by the respondent No.3, the petitioner made representations to the respondents No.2, 4 and 5. It appears that the respondent No.4 directed the 5th respondent to conduct spot inspection and submit a report. True copy of letter dated 25.8.2015 addressed by Assistant Commissioner to Tahasildar is produced herewith and marked as ANNEXURE- H. Subsequent to the said letter the 5th respondent sent a report dated 30.9.2015 to the 3rd respondent vide Annexure-A and sent a copy of the same to the petitioner and 2nd respondent."
13. We are of the considered view that though
this factum was narrated in the pleadings, the same
was not brought to the notice of the Hon'ble Court while
hearing the matter which came to be disposed of placing
reliance on W.P.No.55938/2015. It is significant to note
- 15 -
that respondent No.1 herein was arrayed as respondent
No.2 in the said proceedings. After hearing both the
sides, the order dated 22.2.2017 was passed in
W.P.No.5379/2016. It was obligatory for both sides to
bring to the notice of the Hon'ble Court inasmuch as the
registered agreement dated 11.4.2007 executed between
the appellant and the neighbouring land owners with
respondent No.1. In the circumstances, there being
lapse on the part of both sides, we cannot subscribe to
the view of the learned Single Judge that a fraud was
played by the appellant in obtaining the order in
W.P.No.5379/2016 on 22.2.2017. It is discernable that
pursuant to the direction issued by this Court in
W.P.No.5379/2016 the Deputy Commissioner has
determined the compensation at Rs.36,78,213/- and
passed the award, which was the subject matter of
W.P.No.56199/2017. The subsequent order of the
Deputy Commissioner pursuant to the remand made in
W.P.No.56199/2017 is not in conformity with the
- 16 -
specific directions as noticed by the learned single
Judge in paragraph 7 of the order impugned herein.
The directions issued in W.P.No.56199/2017 and the
flaws found in the order of the Deputy Commissioner
are reproduced in the tabular form by the learned Single
Judge, which reads as under;
Sl. Extracts from the order of Extracts from the Order this Hon'ble Court in passed by R-2 at Annexure- No.
WP56199/2017 A 1 "8 Having heard the learned "16. Point No.1: The counsel for the parties, this Agreement between the Court of the opinion that parties Vide No:BNT-4- the learned Deputy 00002-2007-08 dated Commissioner ought to 11.04.2007 was not even have taken into account the brought to the notice of the Registered Agreement learned single judge who between the parties dated passed the order on 11/04/2017 while 22.02.2017 in Writ Petition determining the No:5379/2016 & 9629- compensation payable by 30/2016. The said the petitioner, the exact agreement was brought to measurements of land the notice of this office after adversely affected by the Deputy Commissioner DK submergence due to wrote to the company to pay construction raised by the compensation to Mr. petitioner company and also Shantappa Bhandary on crops adversely affected of 21.08.2017. There is lapse the Respondent. The said from both the side. As per Agreement has not been the agreement, legal notices apparently considered by had been given to the the learned Deputy petitioner for the payment Commissioner. of the compensation, even though the service of
9. It is now brought to the
- 17 -
notice of the Court by both notices, Petitioner has failed the learned counsels that to make payment and could the fact of the said not act upon the said Registered Agreement dated agreement. Therefore, the 11/04/2017 was not even agreement could not be brought to the notice of the considered at this point learned Single Judge who causing further damage to passed the order on the property of Mr. 22/02/2017. Shantappa Bhandary" (At p.23 of WP)
10. In view of the aforesaid, the present writ petition is Submission: Despite a clear disposed of and the matter direction to consider the is remanded back to the Agreement, R-2 has ignored learned Deputy the Agreement. The Commissioner, Dakshina Agreement fixed the Kannada District, compensation based on Mangalore to decide the extent of land damaged and case again between the not on quantum of crop on parties after giving an the land.
opportunity of hearing afresh"
(at p.159-160 of WP) "13. The learned counsel for "18. Point No.3: As per the the Petitioner further order of the Hon'ble High submitted that the actual Court of Karnataka in WP extent of submergence can 56199/2017, the Joint be determined only during Director Agriculture, the the rainy season, therefore, Deputy Director the period for re- Horticulture, the Assistant determining the Commissioner Mangaluru compensation after and the Tahsildar Bantwal verification of the actual were directed to conduct submerged land and loss of the joint inspection at the crops may be extended up end of September/October to the end of September and once again submit the 2018. report regarding the damage caused due to the
14. The request of the stagned (sic.) water in the learned counsel appears to said land.
be fair and reasonable.
Therefore, the learned Assistant Commissioner
- 18 -
Deputy Commissioner is along with JD Agriculture, directed to decide the case DD Horticulture again upon remand by the Department, Assistant end of October 2018, after Commissioner Mangaluru holding a joint survey in the and Tahsildar Bantwal and presence of both the sides revenue official visits the in the month of spot on 27-09-2017 and September/October 2018". submitted that, at an outward appearance, it Submission: (1) This appears that the damaged Hon'ble Court directed the (sic.) was caused due to Respondent No.2 to stangned (sic.) water in the personally conduct the said land and due to the survey. The Respondent increase in the level of No.2 neither personally water there may the (sic.) in visited the spot nor flaw of the water in the said conducted the survey. The land. There are total 1041 compensation has been arecanut trees, 61 coconut fixed on assumptions and trees, of which 901 surmises and blindly arecanut trees, 56 are accepting the report of his completely damaged and juniors without application 564 trees were partially of mind.
damaged. All remaining (2) No measurement of trees could be completely extent of land submerged as damaged in the near future, was directed by this Hon'ble and there is no difference in Court. Instead only the report submitted earlier. 'outward appearance was The total value of the considered' and that too damaged coconut and only of the trees. arecanut trees is (3) This Hon'ble Court had Rs.36,78,213/-. The directed R-2 to conduct a Detailed joint survey report fresh joint survey. R-2 has submitted earlier was as relied on the earlier joint follows: (Table is not measurement survey to extracted) award compensation. Hence value of damage Therefore, this Hon'ble determined by the Joint Court's directions have Director Agriculture, The been violated. Deputy Director (4) The Agreement Horticulture Department, (Annexure-B to the WP) at the Assistant Commissioner Mangaluru and the
- 19 -
Clause 2 (at p.65 - Tahsildar Bantwal and Translated version and p.32 other revenue officials
- Kannada version) fixed the appears to be reasonable. compensation based on 'per It is sure that the trees have acre' basis. As R-6 land is been damaged due to arecanut/coconut stagnant water. Hence the plantation, the level of water in the river is compensation is Rs.12 not the same. There is the lakhs per acre. The total possibility that, the trees extent of damage is around can be damaged completely 2.1 acres, the Respondent by the roots." No.6 is entitled to only (at p.24 of the WP) around Rs.24 lakhs compensation. However, the Respondents 1 to 5 have not considered the extent of land submerged but have fixed compensation on the total number of trees. The petitioner has specifically disputed the extent of trees.
14. These lapses being ex facie apparent and in
breach of the directions issued in W.P.No.56199/2017,
the learned Single Judge in the present proceedings i.e.,
W.P.No.7874/2019 has rightly rejected the
determination of compensation awarded by the Deputy
Commissioner at Rs.36,78,213/-, which is nothing but
the replica of the earlier decision made ignoring the
remand order.
- 20 -
15. It is not in dispute that under the agreement
the respondent No.1 is entitled to pay a sum of Rs.25.25
lakhs towards the compensation for the actual extent of
submergence of the land of the appellant, wherein
approximately an area of 2.10 acres of land has come
under the submergence area. It appears, on the
submissions made by respondent No.1, on instructions,
wherein the respondent No.1 has agreed to pay a sum of
Rs.26.00 lakhs towards full and final settlement of the
claim of the appellant, the learned Single Judge
proceeded to award the same. It is also not in dispute
that the respondent No.1 has paid a sum of Rs.5.00
lakhs to the appellant on 30.1.2018 and further handed
over a cheque bearing No.843674, dated 22.2.2018,
drawn on State Bank of India, for a sum of
Rs.13,39,000/- in favour of the appellant. Learned
counsel for the respondent No.1 has submitted that the
mini hidel project of power generation was
- 21 -
commissioned in the year 2015 and the land of the
appellant was submerged for the first time in the year
2016. If these dates are considered, then the appellant
being a farmer is entitled to interest at 9% p.a., on the
amount which was liable to be paid as per the registered
agreement at Rs.25.25 lakhs atleast from the date of the
lands getting submerged. If this aspect is considered
even ignoring Rs.6,86,000/- the balance amount which
was liable to be paid as on 26.2.2018, said to have been
paid subsequent to the disposal of W.P.No.7874/2019
decided on 18.9.2019, if we calculate interest at 9% pa.,
for two years, the appellant would be entitled to a sum
of Rs.4,54,500/-, in addition to Rs.26.00 lakhs. Having
regard to the peculiar facts and circumstances, we have
made this order and it is made clear that it will not be
considered as a precedent and shall not apply to the
other agreement holders/claimants.
- 22 -
16. For the reasons aforesaid, we modify the
order of the learned single Judge as under;
ORDER
i) The writ appeal is allowed-in-part.
ii) The order of the learned Single Judge dated
18.9.2019 passed in W.P.No.7874/2019
impugned herein is modified.
iii) The direction issued by the writ Court
directing the respondent No.1 to disburse a
sum of Rs.26,00,000/- to the appellant,
deducting the amount which has already
been disbursed within a period of one week
from the date of receipt of the certified copy
of the order is modified, directing the
respondent No.1 to disburse a sum of
Rs.30,54,500/- to the appellant deducting
the amount which has already been
disbursed, i.e., Rs.4,54,500/- within a period
- 23 -
of four weeks from the date of receipt of
certified copy of this order.
Sd/-
JUDGE
Sd/-
JUDGE
nd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!