Friday, 15, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Maruthi Power-Gen(India) ... vs Karnataka Power Transmission ...
2022 Latest Caselaw 5404 Kant

Citation : 2022 Latest Caselaw 5404 Kant
Judgement Date : 25 March, 2022

Karnataka High Court
Maruthi Power-Gen(India) ... vs Karnataka Power Transmission ... on 25 March, 2022
Bench: S.R.Krishna Kumar
                            1



     IN THE HIGH COURT OF KARNATAKA, BENGALURU

        DATED THIS THE 25th DAY OF MARCH 2022

                         BEFORE

     THE HON'BLE MR.JUSTICE S.R.KRISHNA KUMAR

         WRIT PETITION No.11894/2021 (GM-KEB)

BETWEEN:

MARUTHI POWER-GEN(INDIA) PRIVATE LIMITED
A COMPANY REGISTERED UNDER THE
COMPANIES ACT 1956,
NO.22/4, RACE COURSE ROAD,
BENGALURU
REPRESENTED BY ITS MANAGING DIRECTOR
MR. K.SHYAMA RAJU
S/O LATE K. RAMA RAJU
AGED ABOUT 73 YEARS
                                            ...PETITIONER

(BY SRI SHASHIKIRAN SHETTY, SENIOR COUNSEL FOR
   SRI KIRAN J., ADVOCATE)

AND:

1.      KARNATAKA POWER TRANSMISSION
        CORPORATION LIMITED
        CAUVERI BHAVAN
        BENGALURU - 560 001
        REPRESENTED BY ITS
        MANAGING DIRECTOR

2.      M/S PASCHIM HYDRO ENERGY PVT. LTD.,
        A COMPANY REGISTERED UNDER
        PROVISIONS OF THE COMPANIES ACT, 1956
        HAVING ITS OFFICE AT NO.23/8
        1ST FLOOR, CHRISTHA KRUPA
        1ST CROSS, CSI COMPOUND
        LALBAGH ROAD, BENGALURU-560 027
        REPRESENTED BY ITS DIRECTOR-TECHNICAL
        MR B.R.VASANTHA KUMAR

3.      M/S. NAGARJUNA HYDRO ENERGY PVT. LTD.,
        A COMPANY REGISTERED UNDER
        PROVISIONS OF THE COMPANIES ACT, 1956
                                 2



        HAVING ITS OFFICE AT NO.23/8, 1ST FLOOR
        CHRISTHA KRUPA, 1ST CROSS, CSI COMPOUND
        LALBAGH ROAD, BENGALURU-560 027
        REPRESENTED BY ITS
        DEPUTY GENERAL MANAGER
        OPERATIONS AND CORPORATE AFFAIRS
        MR.SOMESWARA PRASAD K.M.,

4.      M/S. MYSORE MERCANTILE CORPORATION LTD.,
        201 AND 202, 2ND FLOOR, SHRESHTA BUMI
        NO.87, K.R.ROAD, BASAVANAGUDI
        BENGALURU-560 004
        REPRESENTED BY ITS AUTHORIZED SIGNATORY
        MR.RAKESH SHETTY

                                            ...RESPONDENTS

(BY SRI S. SRIRANGA, SENIOR COUNSEL FOR
    SMT. SUMANA NAGANAND, ADVOCATE FOR R-1;
    SRI. DHYAN CHINNAPPA, SENIOR COUNSEL FOR
    SRI. AJAY J.N., ADVOCATE FOR R-2 & 3;
    SRI. ADITYA NARAYAN, ADVOCATE FOR R-4)


        THIS W.P. IS FILED UNDER ARTICLES 226 AND 227 OF

THE CONSTITUTION OF INDIA PRAYING TO ISSUE A WRIT IN

THE NATURE OF MANDAMUS OR ANY OTHER APPROPRIATE

WRIT,    ORDER    OR   DIRECTION    DECLARING    THAT   THE

RESPONDENTS IMPOSING CONDITION NO.S 1, 4 AND 5 IN THE

REVISED PROVISIONAL INTERCONNECTION APPROVAL DATED

30.06.2021 BEARING NO. CEE(P &C)/SEE(PLG)/EE(PSS)/KCO-

94/30542/F-8891/10/21-22   IS   HIGHLY   ARBITRARY   ILLEGAL

(ANNEXURE-A) AND ETC.


        THIS W.P. COMING ON FOR 'DICTATING ORDERS' THIS

DAY, THE COURT MADE THE FOLLOWING:-
                               3



                          ORDER

This petition takes an exception to the impugned

revised Provisional Interconnection Approval (for short 'the

PIA') at Annexure-A dated 30.06.2021 issued in favour of

the petitioner by the 1st respondent - KPTCL.

2. Initially, the grievance of the petitioner was not in

respect of the entire PIA dated 30.06.2021, but only in

relation to conditions No.1, 4 and 5 of the PIA;

subsequently, petitioner has restricted its challenge only to

condition No.1 of the PIA; in this context, it is relevant to

state that the petitioner has filed a Memo restricting its

claim / challenge only to condition No.1 and giving up its

claim / challenge to condition Nos.4 and 5.

3. Learned Senior counsel for the KPTCL as well as

the learned Senior counsel for respondents 2 and 3 and

learned counsel for respondent No.4 jointly submitted that

the respondents do not have any objection for the petitioner

to give up its claim / challenge in respect of condition Nos.4

and 5 of the PIA and to restrict its claim / challenge only to

condition No.1.

4. The memo filed on behalf of the petitioner /

joint submissions by both sides are placed on record and

accordingly, I have heard the parties only in relation to

impugned condition No.1 of the PIA dated 30.06.2021.

5. Briefly stated, the various contentions urged in

the petition are as follows:-

a) The petitioner is an independent power producer, in

whose favour, the State Government, vide order dated

19.10.2010 allotted a Hydro project, pursuant to which,

the KPTCL issued a regular re-revised Evacuation

Scheme dated 22.06.2017 for the proposed 24 MW

Hongadahalla Mini Hydel Scheme in Sakaleshpura

Taluk, Hassan District, subject to various conditions. As

per the aforesaid scheme, petitioner was granted one

year's time i.e., time up to 21.06.2018 to carryout the

Evacuation Scheme work.

b) It is contended that subsequently, vide Communication

dated 20.07.2018, the KPTCL granted extension of time

up to 21.12.2019 in favour of the petitioner; accordingly,

a Meeting dated 01.02.2019 was called by KPTCL in the

presence of other independent power producers viz.,

respondents 2 to 4, wherein it was resolved that the

petitioner would complete the Evacuation Scheme work

with the cooperation of others at the earliest.

c) Petitioner contends that thereafter it took necessary

steps to complete the work and sought for

interconnection approval from KPTCL. By order dated

27.04.2019, the KPTCL granted PIA in favour of the

petitioner, subject to certain conditions and based on

CEIG approval letter dated 16.04.2019 to take LILO

from the existing 66 KV Sakaleshpura MHS of PHEPL

(respondent No.2). Under the said order, at the request

of the petitioner, further extension was granted on

27.04.2019 for a period of three months which was

extended once again for a further period of three months

on 07.06.2019 and for an additional further period up to

30.09.2019 vide communication dated 11.07.2019.

d) Meanwhile, the respondents 2 to 4 approached this

Court ventilating their grievances in W.P.No.21126/2019

which was disposed of on 08.05.2019 directing the

KERC to consider the rival claims and pass appropriate

orders. Accordingly, vide order dated 30.05.2019

passed in O.P.No.28/2019, the KERC directed that the

PIA dated 27.04.2019 (supra), shall be construed as

having been limited to injection of 4 MW power from the

petitioner herein to the LILO line of PHEPL; in addition

thereto, certain other directions were also issued by the

KERC. Aggrieved by the same, the respondents 2 to 4

approached this Court in W.P.No.23179/2019, which

was rejected vide order dated 06.06.2019.

e) On 07.06.2019, the KPTCL issued a revised PIA in

terms of the aforesaid orders passed by the KERC

dated 30.05.2019. Thereafter, at the instance of the

petitioner, the revised PIA was extended for a further

period up to 30.09.2019 vide letter dated 11.07.2019.

So also, at the request of the petitioner, the KPTCL

issued letters dated 13.08.2019 and 06.11.2019

extending the revised PIA for 4 MW up to 31.12.2019

and 30.06.2020 respectively. Subsequently, as

requested by the petitioner, vide letter dated

02.07.2020, the revised PIA was further extended up to

30.06.2021. It is contended that due to various reasons

including the Covid-19 pandemic and the lock down on

account of the same, the petitioner could not complete

the Evacuation work within time and that accordingly,

the time period for the PIA was required to be extended.

f) Petitioner submits that since he could not complete the

work, petitioner submitted a representation dated

05.05.2021 requesting further extension of time up to

30.06.2022 and also for directions to the KPTCL officers

to permit LILO to 2nd 66 KVA circuit of IPCL -

Sakaleshpura line. On 29.05.2021, one more

representation was submitted by the petitioner.

   Meanwhile,         respondents           2        to      4       preferred

   W.P.No.9821/2021            before   this      Court           which    was

disposed of on 07.06.2021 directing the KPTCL to

consider the representation of the petitioner as well as

respondents 2 to 4 and pass appropriate orders in

accordance with law on or before 30.06.2021. Pursuant

thereto, petitioner gave a representation dated

11.06.2021 as well as an Affidavit dated 29.06.2021 to

the KPTCL. As directed by this Court in

W.P.No.9821/2021 referred to supra, the KPTCL

proceeded to issue the impugned order dated

30.06.2021, in which, condition No.1 has been assailed

by the petitioner as stated supra.

6. The 1st respondent - KPTCL has filed

statement of objections inter alia contending that in view of

the availability of equally efficacious and alternative

remedies under the Electricity Act, 2003, the present

petition was not maintainable and liable to be rejected. It is

contended that on 27.04.2019, PIA was granted in favour of

the petitioner which was challenged by respondents 2 to 4

in W.P.Nos.21126-28/2019 which was disposed of by this

Court vide order dated 08.05.2019 directing the parties to

approach the KERC. Pursuant to the said order passed by

this Court, the respondents 2 to 4 approached the KERC in

O.P.No.28/2019 which was disposed of by issuing certain

directions. Aggrieved by the same, respondents 2 to 4

approached this Court in W.P.Nos.23179-180/2019 which

was rejected by this Court on 06.06.2019 by issuing certain

clarifications and also directing the KPTCL to re-examine

the terms and conditions of the PIA in accordance with law.

Pursuant to the same, the KPTCL issued a revised PIA

restricting the total injection of the petitioner to 4 MW for a

period up to 26.07.2019.

6.1. It is contended that at the request / instance of

the petitioner, the aforesaid revised PIA dated 07.06.2019

was subsequently extended on 11.07.2019 for a period up

to 30.09.2019 and thereafter on 13.08.2019 for a period up

to 31.12.2019 and subsequently, on 06.11.2019 for a

period up to 30.06.2020. Subsequent thereto, at the

request / instance of the petitioner, the revised PIA was

once again extended on 02.07.2020 for a period up to

30.06.2021.

6.2. Meanwhile, respondents 2 to 4 preferred

W.P.No.9128/2021 before this Court assailing the aforesaid

extension granted in favour of the petitioner. By final order

dated 07.06.2021, this Court disposed of the said petition

directing the KPTCL to consider the representations of the

petitioner as well as respondents 2 to 4 and pass

appropriate orders on or before 30.06.2021. Accordingly,

the KPTCL has proceeded to pass the impugned revised

PIA dated 30.06.2021 extending time in favour of the

petitioner for the period up to 30.06.2022, thereby

permitting the petitioner to evacuate 4 MW to Circuit - 1

(exclusive line used for evacuation by IPCL), subject to

certain terms and conditions, amongst which, condition

No.1 is assailed in the present petition.

6.3. The KPTCL, in addition to denying the various

contentions / claims urged by the petitioner has stated that

the LILO arrangement to the petitioner through the LILO of

PHEPL (respondent No.2) was on a temporary basis only

and the petitioner having delayed completion of work in

terms of the Evacuation Scheme has been directed to

disconnect its existing LILO line of Circuit - 2 of LILO of

PHEPL and connect to Circuit - 1 which is the exclusive

line used by IPCL of 66 KV IPCL - Sakaleshpura line.

6.4. At paragraph-11(a) of its statement of

objections, the KPTCL has opposed the challenge / claim

of the petitioner in respect of condition No.1. In this context,

the KPTCL has stated in its representation dated

11.06.2021 that the petitioner itself sought for permission to

connect to LILO of Circuit-1 which is the exclusive line used

by IPCL of 66 KV IPCL - Sakaleshpura line, which was

examined and permitted by the KPTCL, since the same

was in conformity with the re-revised Evacuation Scheme

dated 22.06.2017. It is contended that for the purpose of

allowing the petitioner to connect to the aforesaid 1st Circuit

exclusive line of IPCL, the existing LILO connectivity of the

petitioner to the LILO of PHEPL in Circuit - 2 has to be

disconnected. It is also contended that the petitioner cannot

be allowed to connect to both Circuit -1 and Circuit -2 since

the same will lead to tapping of the circuits resulting in

difficulties in identifying the exact fault location in the lines,

delay in restoration and fault at any point of the line causes

problems to all parties who are connected to the line. It is

therefore contended that the KPTCL was fully justified in

imposing the impugned condition No.1 in the revised PIA

dated 30.06.2001, which was issued by taking into account

and considering the representations of the petitioner as well

as respondents 2 to 4 and that the same does not suffer

from any illegality or infirmity warranting interference by this

Court in the present petition.

6.5. At paragraphs 14 to 26 of its statement of

objections, the KPTCL has denied the various contentions

urged by the petitioner and has stated that connection to

both Circuit-1 and Circuit-2 is technically unfeasible and

accordingly, the KPTCL has sought for dismissal of the

petition.

7. The respondents 2 and 3 have filed their

statement of objections disputing and denying the various

allegations and claims put forth in the petition. It is

contended that the petitioner has not approached this Court

with clean hands and is not entitled to any relief as sought

for by it before this Court. It is also contended that the

conditions in the impugned PIA is purely a technical matter

which is beyond the scope of judicial review in the present

petition, particularly when neither valid nor sufficient

grounds have been made out by the petitioner in support of

its claim.

7.1 The respondents 2 and 3 have also put forth

various other contentions as to how the petitioner who has

continuously delayed the work under the re-revised

evacuation scheme dated 22.06.2017 and cannot assert

that he has better rights than the respondents 2 to 4 who

have invested huge amounts and have been using the line

for several years. After narrating the facts in relation to the

earlier round of litigations and referring to the documents

and other material on record, respondents 2 and 4 have

contended that the petitioner is guilty of misrepresentation

not only to this Court but also to the KPTCL. It is contended

that the repeated extensions granted in favour of the

petitioner has resulted in irreparable injury and hardship to

the respondents 2 to 4 including tripping of the line and

accordingly, pursuant to the order passed by this Court in

W.P.No.9821/2021 dated 07.06.2021, the respondents 2 to

4 have submitted representations which have been

considered by the KPTCL which has taken into account all

technical and non technical aspects in relation to the PIA

and has imposed proper and legal conditions which cannot

be found fault with by the petitioner.

7.2. The respondents 2 and 3 have also urged

several other contentions and have specifically denied and

disputed the various allegations and claims made by the

petitioner and have sought for dismissal of the petition.

8. Similarly, the 4th respondent has also filed its

statement of objections putting forth identical contentions

as that of respondents 2 and 3 and having disputed and

denied the various allegations and claims put forth by the

petitioner, the 4th respondent has also sought for dismissal

of the petition.

9. I have heard Sri.Shashi Kiran Shetty, learned

Senior counsel appearing for the petitioner and

Sri.S.Sriranga, learned Senior counsel for the KPTCL,

Sri.Dhyan Chinnappa, learned Senior counsel appearing

for respondents 2 and 3 as well as Sri.Aditya Narayan,

learned counsel for respondent No.4.

10. As stated supra, though initially the petitioner

had challenged conditions No.1, 4 and 5 in the revised PIA

dated 30.06.2021, during the course of hearing, it was

submitted on behalf of the petitioner that the petitioner was

restricting its claim / challenge only to condition No.1 and

had given up its claim in relation to condition Nos.4 and 5; a

memo in this regard dated 24.03.2022 was also filed by the

petitioner. Accordingly, the only question that arises for

consideration in the present petition is with regard to the

legality and validity of condition No.1 in the revised PIA

dated 30.06.2021.

11. In addition to reiterating the various

contentions urged in the petition and referring to the

material on record, learned Senior counsel for the petitioner

submitted that condition No.1 was not the subject matter of

the proceedings before the KPTCL which was restricted

only to extension of time sought for by the petitioner. It was

submitted that the KPTCL was entitled to only impose fair

and reasonable conditions which were not prejudicial to any

of the parties and under these circumstances, condition

No.1 would prevent the petitioner from completing the

remaining work within the extended period as per the

revised PIA dated 30.06.2021 which is to expire on

30.06.2022. It was also submitted that condition No.1 was

not part and parcel of either the re-revised Evacuation

scheme dated 22.06.2017 or the order extending the same

nor was condition No.1 imposed in the original PIA dated

27.04.2019 nor the subsequent orders extending it and that

the impugned condition which was imposed for the first

time under the revised PIA was illegal, irrational, arbitrary,

unjust, unreasonable and unfair and contrary to the other

conditions contained in the PIA.

Learned Senior counsel submits that in its

representations, petitioner had been requesting for

additional LILO in Circuit No.1 of IPCL in addition to the

existing LILO to the LILO of PHEPL as provided in the

earlier PIAs and revised PIAs and the KPTCL has not

considered the requests made by the petitioner resulting in

great hardship and prejudice to the petitioner. It is also

submitted that if condition No.1 was not imposed, no

prejudice would be caused to the respondents 2 to 4. It is

therefore submitted that the impugned condition No.1 in the

revised PIA dated 30.06.2021 deserves to be quashed.

12. Per contra, learned Senior counsel for KPTCL

as well as learned Senior counsel for respondent Nos. 2

and 3 as well as learned counsel for respondent No.4

submitted that despite repeated extension of time granted

at the instance of the petitioner from 2017 onwards, the

petitioner was not diligent enough to complete the

Evacuation Scheme work by taking sufficient steps in this

regard. It was submitted that the petitioner was guilty of

suppression of material facts and abuse of process of court

/ law and having not come to the Court with clean hands,

the petitioner was not entitled to any relief in the present

petition. It was also submitted that condition No.1 imposed

in the revised PIA dated 30.06.2021 was based on

technical opinion / expertise, the legality or validity of which

cannot be the subject matter of judicial review before this

Court. In the original PIA dated 27.04.2019, the petitioner

was granted approval to the LILO of PHEPL subject to

various conditions including ensuring that no prejudice,

hardship or loss would be caused to respondents 2 to 4

who were all connected to Circuit No.2. The repeated

extension of time granted in favour of the petitioner and the

long and inordinate delay on the part of the petitioner in

completing the evacuation work, had resulted in grave

hardship and injury to the respondents 2 to 4 who had not

only submitted several representations to the KPTCL but

also approached this Court, which directed the KPTCL to

address the grievances of the respondents 2 to 4 before

passing any orders as regards the PIA or its extension in

favour of the petitioner. It was further submitted that in its

representations dated 29.05.2021 and 11.06.2021,

petitioner had sought for a LILO only to Circuit-1 of the 66

KVA IPCL - Sakaleshpura line and not by way of an

additional LILO; under these circumstances, the KPTCL

having granted a LILO in favour of the petitioner to Circuit-1

of the 66 KVA IPCL - Sakaleshpura line, the KPTCL was

fully justified in imposing impugned condition No.1, thereby

directing the petitioner to disconnect the existing LILO by

which the petitioner had connected to the LILO of PHEPL.

12.1 It was therefore submitted that having regard

to the prejudice and hardship is caused to the respondents

2 and 4 as urged by them before the KPTCL as well as

before this Court, the KPTCL was fully justified in taking

into account the hardship to be caused to the petitioner as

well as the respondents 2 to 4 and issuing the PIA dated

30.06.2021 granting extension of time in favour of the

petitioner up to 30.06.2022 and by imposing various

conditions including the impugned condition No.1 which is

perfectly legal, valid, proper, just, fair, rational and

reasonable and the same does not warrant interference by

this Court in the present petition.

13. I have given my anxious consideration to the

rival submissions and perused the material on record.

14. The material on record discloses that on

22.06.2017, the KPTCL approved regular re-revised

evacuation scheme in favour of the petitioner. The approval

which was valid for a period of 12 months was extended at

the request of the petitioner up to 21.12.2019 vide

communication dated 20.07.2018.

15. Meanwhile, petitioner requested provisional

interconnection approval for 24 MW for its Mini Hydel

scheme. As per the said request, the provisional

interconnection approval had to be granted in favour of the

petitioner by taking a LILO through the existing LILOs of the

respondents 2 to 4. Respondents 2 to 4 objected to the

same on the ground that the same would disrupt and

hamper the transmission of electricity from their power

plants. On 16.04.2019, the State Government (Electrical

Inspectorate) granted approval for PIA in favour of the

petitioner by according LILO from the existing LILO of

PHEPL (respondent No.2). In pursuance of the same, the

KPTCL issued a communication dated 27.04.2019 in favour

of the petitioner granting approval of PIA for 24 MW Mini

Hydel scheme by taking a LILO through the existing LILO

of PHEPL.

16. In this context, it is relevant to state that the

KPTCL specifically noticed that the petitioner had not

completed the evacuation scheme work and granted PIA

based on the request of the petitioner subject to the

condition that if any objections / legal issues / complications

arose from anybody, the PIA shall stand withdrawn without

any notice. The said PIA dated 27.04.2019 also stated that

the petitioner shall complete the revised evacuation

scheme before the commencement of this year (2019)

monsoon, so that other generators on the same line are not

affected and that if the petitioner fails to complete the

revised evacuation scheme within that period, KPTCL

would not be responsible towards the undue consequences

that may arise.

17. A perusal of the aforesaid PIA dated

27.04.2019, would clearly indicate that no vested / accrued

right for obtaining a provisional interconnection approval

had been created or granted in favour of the petitioner by

the KPTCL; the PIA was in the nature of an interim

arrangement so as to enable the petitioner to complete the

evacuation scheme work within the extended period that

was to expire on 21.12.2019; the PIA was not traceable to

any statutory provisions of law, rule or regulation and the

PIA was in consonance with the evacuation scheme.

18. It is also relevant to state that the PIA only

granted a LILO in favour of the petitioner to the already

existing LILO of PHEPL and no separate / independent /

exclusive LILO had been granted in favour of the petitioner;

further, the PIA took into account the difficulties / protests /

objections of respondents 2 to 4 if approval was granted in

favour of the petitioner and accordingly, the PIA was

granted only for a period of three months from 27.04.2019

or till commencement of monsoon period, whichever was

earlier; significantly, the prejudice and hardship as

contended by the respondents 2 to 4 were also considered

by the KPTCL and specific conditions were imposed upon

the petitioner that if any objections / legal issues /

complications arose from anybody (including respondents 2

to 4), the PIA would stand withdrawn and that if the

petitioner did not complete the evacuation scheme within

the stipulated period, KPTCL would not be responsible for

the consequences that would arise on non-completion of

the evacuation scheme by the petitioner. Under these

circumstances, it is clear that since no legal / vested right

had accrued or had been granted in favour of the petitioner

under the PIA, the petitioner was not entitled to complain or

make a grievance against any of the conditions imposed in

the PIA, particularly when the petitioner had not acquired

any vested / accrued right in the already existing LILOs of

respondents 2 to 4.

19. The undisputed material on record also

discloses that the petitioner did not complete the revised

evacuation scheme work even subsequent to 27.04.2019

within the stipulated period; meanwhile, respondents 2 to 4

approached this Court in W.P.No.21126/2019 challenging

the aforesaid PIA dated 27.04.2019 on the ground that the

said PIA dated 27.04.2019 which permits the petitioner to

take a LILO in the already existing LILO of PHEPL was

working great hardship to the respondents 2 to 4; by order

dated 08.05.2019, this Court disposed of

W.P.No.21126/2019 by directing the parties herein to

approach the KERC; pursuant thereto, the KERC disposed

of O.P.No.28/2019 vide order dated 30.05.2019 by

modifying the PIA dated 27.04.2019 to only 4 MW instead

of 24 MW and by directing the KPTCL to re-examine the

terms and conditions to be imposed in the PIA dated

27.04.2019.

20. The aforesaid order dated 30.05.2019, having

been challenged by the respondents 2 to 4 before this

Court in W.P.No.23179/2019, this Court vide order dated

06.06.2019 rejected the said petitions confirming the

directions of the KERC and by making certain clarifications;

pursuant thereto, the KPTCL issued a revised PIA dated

07.06.2019 by reiterating the conditions prescribed in the

PIA dated 27.04.2019 and by imposing certain additional

conditions for exporting 4 MW; needless to state that even

under this revised PIA, petitioner was entitled to take a

LILO only in the existing LILO of PHEPL (respondent No.2);

the revised PIA dated 07.06.2019 was valid for a period up

to 26.07.2019 or completion of line strengthening work by

the petitioner, whichever was earlier.

21. The material on record also reveals that the

petitioner could not complete the work even by 26.07.2019

in terms of the revised PIA and at the requests of the

petitioner, the KPTCL granted further extensions on

11.07.2019 up to 26.07.2019, 13.08.2019 up to 31.12.2019

and on 06.11.2019 up to 30.06.2020; as stated supra, the

said extensions were granted at the request of the

petitioner, who did not complete the evacuation scheme

work despite repeated extensions. It is significant to note

that though the respondents 2 to 4 did not challenge the

revised PIA dated 07.06.2019, they addressed several

letters during the period August 2019 up to October 2020 to

the KPTCL opposing, protesting and objecting to extension

of time being granted in favour of the petitioner.

22. On 16.04.2020, petitioner sought for extension

of time up to June 2021 by citing its inability to complete the

work on or before 30.06.2020 on account of the Covid-19

pandemic; accordingly, vide communication dated

02.07.2020, the time period extension was granted in

favour of the petitioner up to 30.06.2021 by making it clear

to the petitioner and subject to the condition that the

petitioner shall complete the entire revised evacuation

scheme within the said period without seeking any further

extension; in terms of the said extension dated 02.07.2020,

an Undertaking was also furnished by the petitioner that it

would not seek any further extension beyond 30.06.2021.

23. The material on record also discloses that the

petitioner did not complete the evacuation scheme work

within the stipulated period expiring on 30.06.2021; instead,

petitioner submitted a representation dated 05.05.2021 to

the KPTCL requesting further extension of time up to

30.06.2022; interestingly, in the said representation,

petitioner also sought for modification of the evacuation

scheme and requested for grant of LILO to both Line -1 and

Line - 2 by contending that the said arrangement will not

affect the respondents 2 to 4. However, subsequently,

petitioner submitted one more representation dated

29.05.2021 and intimated the KPTCL that M/s.IPCL's 2nd

Line has the capacity of 31 MW out of which, IPCL was

pumping only 18 MW and since the balance 13 MW is

available, the IPCL had come forward to help the petitioner

and given consent for the arrangement by which the

petitioner was requesting LILO of 2nd 66 KV circuit of IPCL

- Sakaleshpura line; the said representation dated

29.05.2021 clearly indicates that the petitioner had not

asked for retention / continuation of the LILO to the LILO of

PHEPL which had been granted in favour of the petitioner

earlier under the PIAs referred to supra; instead, the

petitioner had specifically stated that since IPCL was ready

and willing to help and cooperate with the petitioner,

petitioner was requesting permission to LILO 2nd 66 KV

circuit of IPCL - Sakaleshpura line.

24. On 02.06.2021, respondents 2 to 4 herein

preferred W.P.No.9821/2021 for a direction to the KPTCL

not to issue or extend any revised PIA to the petitioner

herein without hearing the respondents 2 to 4 and other

affected power producers; by final order dated 07.06.2021,

this Court disposed of the said petition directing the KPTCL

to consider the representations / grievances of the

petitioner as well as respondents 2 to 4 herein and pass

appropriate orders on or before 30.06.2021. Pursuant

thereto, petitioner submitted one more representation dated

11.06.2021; in this representation also, intimated the

KPTCL that M/s. IPCL's 2nd Line has the capacity of 31

MW out of which, IPCL was pumping only 18 MW and

since the balance 13 MW is available, the IPCL had come

forward to help the petitioner and given consent for the

arrangement by which the petitioner was requesting LILO

of 2nd 66 KV circuit of IPCL - Sakaleshpura line and that

the petitioner had not asked for retention / continuation of

the LILO to the LILO of PHEPL which had been granted in

favour of the petitioner earlier under the PIAs referred to

supra and that since IPCL was ready and willing to help

and cooperate with the petitioner, petitioner was requesting

permission to LILO 2nd 66 KV circuit of IPCL -

Sakaleshpura line; respondents 2 to 4 also submitted their

respective representations.

25. After considering the representations of the

petitioner and respondents 2 to 4, the KPTCL proceeded to

pass the revised PIA dated 30.06.2021 extending time up

to 30.06.2022 and by imposing several conditions upon the

petitioner, amongst which, the impugned condition No.1

directing the petitioner to disconnect the existing LILO

connectivity to the LILO of PHEPL (respondent No.2) has

been assailed in the present petition,.

26. In order to appreciate the rival contentions, it is

necessary to extract the various terms and conditions of the

PIA dated 30.06.2021 including the impugned condition

No.1, which reads as under:

1. You shall disconnect your existing LILO connectivity i.e., from your MHS plant to the LILO line of M/s PHEPL.

2. You are permitted to LILO the 1st Circuit of 66kv IPCL-Sakaleshpura line from your MHS plant which is in line with the re-revised evacuation scheme cited in ref (8).

3. The time period extension for the revised provisional interconnection approval for the period from 01.07.2021 to 30.06.2022 is subject to connectivity of your MHS plant to the 1st Circuit of 66kv IPCL Sakaleshpura line and delinking of your existing connectivity from LILO lien of M/s PHEPL.

4. The generation from your MHS plant is limited to 04MW as per KERC orders in OP no.28/2019 dated: 30.05.2019 and at any point of time, the generation from your MHS plant shall not exceed 4 MW till approval of regular interconnection is granted. Your shall retain the SPS installed at your MHS plant end to limit overall export from your plant to 04MW.

5. Within the extended period for revised provisional interconnection approval you shall complete all the balance work in accordance with re-revised evacuation scheme cited in ref(8 & 9) failing which KPTCL is at the liberty to disconnect the existing arrangement. Your shall abide by your affirmation furnished in the Affidavit dated: 29.06.2021.

CEE/TZ/Hassan shall ensure that, till the completion of the entire re-revised evacuation scheme work, the generation of M/s Maruthi Power Gen (India) Pvt Ltd shall not exceed 4MW and the loading of the existing 66kV DC line between IPCL to Sakaleshpura substation shall be maintained within the safe loading limits. Further, CEE/TZ/Hassan shall note that, before interconnecting the MHS plant to the 1st Circuit of 66kV IPCL-Sakaleshpura line, the CEIG approval for having disconnected the plant from the LILO line of M/s PHEPL and having connected to the 1st Circuit of 66kV IPCL-

Sakaleshpura line shall be obtained.

You shall note that you shall furnish CEIG approval for having disconnected your plant from the LILO line of M/s PHEPL and having connected to the 1st Circuit of 66kV IPCL-

Sakaleshpura line to CEE/TZ/Hassan before interconnecting your plant with KPTCL grid. If you fail to do so, your will not be allowed to interconnect with KPTCL grid.

27. A perusal of the PIA dated 30.06.2021 will

indicate that the KPTCL has taken into account the entire

material on record including the past conduct of the

petitioner, inability and omission on the part of the petitioner

to complete the revised evacuation scheme within the

stipulated period, repeated extensions sought for and

granted in favour of the petitioner to complete the work, the

various terms and conditions of the evacuation scheme

dated 22.06.2017 and the earlier PIAs granted in favour of

the petitioner, the several undertakings submitted by the

petitioner that it would complete the evacuation scheme

work within the stipulated period, the repeated objections

and protests of respondents 2 to 4 including the respondent

No.2 - PHEPL from whose LILO, the petitioner had

obtained a LILO as per the 1st PIA dated 27.04.2019, the

prejudice, loss and hardship that was being caused to

respondents 2 to 4 on account of the delay and latches of

the petitioner in completing the evacuation scheme work,

the earlier rounds of litigation between the petitioner and

respondents 2 to 4 in which they had continuously

ventilated their grievances in granting / extending PIA in

favour of the petitioner, the specific assertion on the part of

the petitioner that since IPCL had addressed a

communication dated 12.04.2021 to the KPTCL, wherein it

was stated that IPCL did not have any objection for the

petitioner to connect to its 2nd 66 KV circuit of IPCL -

Sakaleshpura line by way of LILO as an alternative to the

existing LILO of PHEPL and the submission of IPCL that

they will abide by a balanced decision to be taken by the

KPTCL and also the request made by the petitioner in its

representations dated 29.05.2021 and 14.06.2021

requesting for permission for grant of LILO to 2nd 66 KV

circuit of IPCL - Sakaleshpura line and other attendant

circumstances for the purpose of coming to the conclusion

that all necessary terms and conditions for the purpose of

protecting the interest of the petitioner, IPCL as well as the

respondents 2 to 4 were required to be imposed while

issuing the revised PIA in favour of the petitioner. Under

these circumstances, in the backdrop of the aforesaid

sequence of events and earlier rounds of litigation between

the parties, it cannot be said that impugned condition No.1

is illegal, invalid, unfair, irrational or unreasonable

warranting interference by this Court in the present petition.

28. A perusal of the aforesaid various terms and

conditions incorporated in the POA dated 30.06.2021 will

also indicate that the same are interlinked and intimately

connected to each other and are not separable from one

another; neither the impugned condition No.1 nor the other

conditions are independent or stand alone conditions for

the purpose of giving effect to and making the interim

arrangement under the PIA workable; to put it differently,

having regard to the undisputed fact that the subject matter

of the PIA dated 30.06.2021 was with regard to grant of

extension of provisional interconnection approval in favour

of the petitioner up to 30.06.2022, in the light of the

representations of the parties and in the light / backdrop of

the earlier events / litigations between the parties, in the

facts of the case on hand, the question of deletion of only

condition No.1 while retaining the other conditions does not

arise, since deletion of condition No.1 will not only have an

impact and bearing on the remaining conditions but will

also render the same unworkable and on this ground also,

the impugned condition No.1 does not warrant interference

by this Court in the present petition.

29. As stated supra, neither the original PIA dated

27.04.2019 nor in the extension orders including the PIA

dated 30.06.2021 were not traceable to any statutory

provisions, rule or regulation and as such, no legal / vested

/ statutory right had accrued in favour of the petitioner

under the same, so as to entitle him to challenge the

conditions imposed in the revised PIA dated 30.06.2021

where under he had asked for extension of time for

completion of the evacuation scheme work; in other words,

in the absence of any vested / legal / statutory right that

had accrued in favour of the petitioner under the temporary

provisional interconnection approval dated 27.04.2019

which had been extended at the instance of the petitioner,

subsequently on account of the evacuation scheme work

not having been completed by him within the stipulated

period, it is clearly impermissible for the petitioner to

demand that only the terms and conditions which are

convenient and suitable to him can be imposed and all

other terms and conditions which are inconvenient to him

ought to be struck down by this Court in the exercise of its

jurisdiction under Article 226 of the Constitution of India; in

this regard, it is well settled that merely because condition

No.1 may cause inconvenience to the petitioner, the said

circumstance cannot be made the basis to come to the

conclusion that condition No.1 was liable to be quashed

and as such, the contention of the petitioner in this regard

cannot be accepted.

30. Insofar as the contention of the petitioner that

the impugned condition No.1 is contrary to the other

conditions and cannot be imposed is concerned, a perusal

of the PIA dated 30.06.2021 which contains the impugned

condition No.1 as well as other conditions clearly indicates

that the KPTCL has taken into account and considered the

previous events and all relevant facts and circumstances

and has issued the said PIA by imposing several terms and

conditions including condition No.1 which cannot be said to

be contrary to the other conditions; needless to say that it is

not open for this Court to dissect the terms and conditions

of the PIA issued by the KPTCL which is clearly

impermissible in law and consequently, even this

contention of the petitioner cannot be accepted.

31. It is well settled that the scope of interference

by this Court under Article 226 of the Constitution of India in

relation to technical issues/policy decisions or matters is

extremely limited and restricted; in the case of Jal Mahal

Resorts Private Limited vs K.P.SHarma and others -

(2014)8 SCC 804, the Apex Court held as under:

"137. From this, it is clear that although the courts are expected very often to enter into the technical and administrative aspects of the matter, it has its own limitations and in consonance with the theory and principle of separation of powers, reliance at least to some extent to the decisions of the State authorities, specially if it is based on the opinion of the experts reflected from the project report prepared by the technocrats, accepted by the entire hierarchy of the State administration, acknowledged, accepted and approved by one Government after the other, will have to be given due credence and weightage.....

140. At this juncture, we take note of two overriding considerations which combined, narrow the scope of review. The first is that of deference to the views of administrative experts and the other we take assistance from the words of Chief Justice Neely who expressed as follows:

"I have very few illusions about my own limitations as a judge and from those limitations I generalise to the inherent limitations of all appellate courts reviewing rare cases."

The learned Chief Justice further observed as follows:

"I am not an accountant, electrical engineer, financier, banker, stock broker, or systems management analyst. It is the height of folly

to expect judges intelligently to review a 5000 page record addressing the intricacies of public utility operation.

It is not the function of a judge to act as a super board, or with the zeal of a pedantic schoolmaster substituting its judgment for that of the administrator. The result is a theory of review that limits the extent to which the discretion of the expert may be scrutinised by the non-expert judge. It was suggested that the alternative for the court is to desist itself from interference on technical matters, where all the advantages of expertise lie with the agencies. If the court were to review fully the decision of an expert body such as State Board of Medical Examiners, 'it would find itself wandering amid the maze of therapeutics or boggling at the mysteries of the pharmacopoeia'."

32. Similarly, in N.D.Jayal and others vs. Union

of India and others - (2004) 9 SCC 362, it was held as

under:-

"20. This Court cannot sit in judgment over the cutting edge of scientific analysis relating to the safety of any project. Experts in science may themselves differ in their opinions while taking decisions on matters related to safety and allied aspects. The opposing viewpoints of the experts will

also have to be given due consideration after full application of mind. When the Government or the authorities concerned after due consideration of all viewpoints and full application of mind took a decision, then it is not appropriate for the court to interfere. Such matters must be left to the mature wisdom of the Government or the implementing agency. It is their forte. In such cases, if the situation demands, the courts should take only a detached decision based on the pattern of the well-settled principles of administrative law. If any such decision is based on irrelevant consideration or non- consideration of material or is thoroughly arbitrary, then the court will get in the way. Here the only point to consider is whether the decision-making agency took a well-informed decision or not. If the answer is "yes", then there is no need to interfere. The consideration in such cases is in the process of decision and not in its merits."

33. Subsequently, in the case of Centre for

Public Interest Litigation vs. Union of India and others -

(2016) 6 SCC 408, it was held as under:

" 21. In this context, reliance is sought to be placed on the decision of this Court in A.P. Pollution Control Board v. Prof. M.V. Nayudu [(1999) 2 SCC 718] . In that decision, this Court viewed that in scientific matters of complex nature resulting in uncertainty,

reference has to be made to a specialised technical/expert body and not merely decide the matter on well-known principles of administrative law of court not re-examining the matter if all relevant considerations have been taken note of. "

34. In the case of Peerless General Finance and

Investment Company and others vs. Reserve Bank of

India - AIR 1992 SC 1033, in relation to the scope of

interference with policy matters/decisions, it was held:

" It is not the concern of this Court to find out as to whether actuarial method of accounting or any other method would be feasible or possible to adopt by the companies while carrying out the conditions contained in paragraphs (6) and (12) of the directions of 1987. The companies are free to adopt any mode of accounting permissible under the law but it is certain that they will have to follow the entire terms and conditions contained in the impugned directions of 1987 including those contained in paragraphs (6) and (12). It is not the function of the Court to amend and lay down some other directions and the High Court was totally wrong in doing so.

The function of the Court is not to advise in matters relating to financial and economic policies for which bodies like Reserve Bank are fully competent. The Court can only strike down some or entire directions issued by the Reserve Bank in case the Court is

satisfied that the directions were wholly unreasonable or violative of any provisions of the Constitution or any statute. It would be hazardous and risky for the courts to tread an unknown path and should leave such task to the expert bodies. This Court has repeatedly said that matters of economic policy ought to be left to the government. While dealing with the validity of an order passed on September 30, 1977 fixing a retail price of mustard oil not exceeding Rs 10 per kilogram in exercise of powers conferred by Section 3 of the Essential Commodities Act, a bench of Seven Judges of this Court in Prag Ice & Oil Mills v. Union of India and Nav Bharat Oil Mills v. Union of India [(1978) 3 SCC 459 : AIR 1978 SC 1296 : 1978 Cri LJ 1281] observed as under: (SCC p. 478, para 24)

"We have listened to long arguments directed at showing us that producers and sellers of oil in various parts of the country will suffer so that they would give up producing or dealing in mustard oil. It was urged that this would, quite naturally, have its repercussions on consumers for whom mustard oil will become even more scarce than ever ultimately. We do not think that it is the function of this Court or of any court to sit in judgment over such matters of economic policy as must necessarily be left to the government of the day to decide. Many of them, as a measure of price fixation must necessarily be, are matters of prediction of ultimate results on which even experts can seriously err and doubtlessly

differ. Courts can certainly not be expected to decide them without even the aid of experts."

35. In the case of Bharat Jhunjhunwala vs

Union of India - 2019(1) ADJ 837, it was held as under:

"47. The ambit of judicial review of the decision making process of the Government again came up before the Supreme Court in a matter pertaining to the safety and environmental aspects of the Tehri Dam, in N.D. Jayal & Anr. Vs. Union of India & Ors.11 wherein the decision of the Government on a particular safety aspect of the dam, which was based upon a report submitted by group of experts, was sought to be questioned, and the Apex Court by its majority judgment held that the Court cannot sit in judgment over the cutting edge of scientific analysis and where the Government or the authorities concerned after due consideration of all view points and full application of mind had taken a decision it would not be appropriate for the Court to interfere and such matters must be left to the wisdom of the Government or the implementing agency, and only, if such decision is based on irrelevant consideration or non-consideration of material or is thoroughly arbitrary, then the Court would get in the way........

22. Minimal interference is called for by the courts, in exercise of judicial review of a Government policy when the said policy is the outcome of

deliberations of the technical experts in the fields inasmuch as courts are not well-equipped to fathom into such domain which is left to the discretion of the execution. It was beautifully explained by the Court in Narmada Bachao Andolan v. Union of India (2000) 10 SCC 664 and reiterated in Federation of Railway Officers Assn. v. Union of India (2003) 4 SCC 289 in the following words:

"12. In examining a question of this nature where a policy is evolved by the Government judicial review thereof is limited. When policy according to which or the purpose for which discretion is to be exercised is clearly expressed in the statute, it cannot be said to be an unrestricted discretion. On matters affecting policy and requiring technical expertise the court would leave the matter for decision of those who are qualified to address the issues. Unless the policy or action is inconsistent with the Constitution and the laws or arbitrary or irrational or abuse of power, the court will not interfere with such matters."

36. In the case of Reliance Infrastructure

Limited vs State of Maharashrta and others reported in

AIR 2019 SC 567, it is held as under:

30. The National Tariff Policy has multi-faceted objectives. Significant among them is the need to ensure to consumers the availability of electricity at reasonable and competitive rates. The policy also seeks to ensure the financial viability of the sector and underlines the need to attract investments. A financially sustainable electricity sector is an important facet of the overall regulatory framework. The objectives of the policy emphasis the need to promote transparency, consistency and predictability in regulatory approaches across jurisdictions. The policy emphasis the need to minimise perceptions of regulatory risk. Finally, the policy recognises the need to promote competition, efficiency in operations and improvements in the quality of supply. In designing and formulating the regulatory framework for tariffs, the delegate of the legislature has to bring about a balance between the competing goals which the Tariff Policy incorporates.

37. As can be seen from the aforesaid decisions,

the scope of judicial review in technical issues/policy

decisions or matters has limited scope of interference and

this Court cannot sit in judgment over technical related

issues/policy decisions or matters as held by the Apex

Court in the aforesaid decisions. In the instant case, the

KPTCL has considered the entire material on record

including the technical / non-technical aspects involved in

the matter and has issued the PIA dated 30.06.2021 and

consequently, the judicial review of the legality or validity of

the terms and conditions of the PIA, in the peculiar facts

and circumstances of the instant case are incapable of

being interfered with by this Court in the present petition.

38. Insofar as the hardship pleaded by the

petitioner by imposition of the impugned condition No.1 is

concerned, it is necessary to state that both petitioner on

one hand and respondents 2 to 4 on the other have

pleaded their respective hardships; comparative hardship

of both the petitioner and respondents 2 to 4 based on their

respective contentions which give rise to disputed and

complicated questions of fact is also beyond the scope of

judicial review warranting interference in the present

petition, especially when it is the specific contention of the

petitioner that condition No.1 is causing hardship to the

petitioner, it is contended by the respondents 2 to 4 that if

condition No.1 is set aside, they would be put to great

hardship and prejudice. Under these circumstances, the

question of examining condition No.1 in the light of

comparative hardship that would be caused to the parties

would also not arise for consideration in the present

petition.

39. To reiterate, the various contentions/claims put

forth by the petitioner in order to challenge the impugned

condition No.1 in the PIA dated 30.06.2021 cannot be

accepted for the following reasons:

a) The PIA dated 27.04.2019 granted in favour of the

petitioner, subsequent extensions granted up to

30.06.2021 as well as the PIA dated 30.06.2021

granting extension up to 30.06.2022 are not traceable to

any statutory provision/rule/regulation, so as to enable

the petitioner to demand/claim any

vested/accrued/statutory right of approval or extension

or challenge the terms and conditions incorporated in

the PIAs/extension orders which are in the nature of

interim arrangements for the purpose of enabling the

petitioner to complete the evacuation scheme work and

consequently, it is not open for the petitioner to

challenge the impugned condition No.1 in the PIA dated

30.06.2021.

b) A perusal of the material on record obtaining in the

instant case clearly establishes that the terms and

conditions of the PIA dated 30.06.2021 including the

impugned condition No.1 are in the realm of technical

issues and matters relating to the policy of the KPTCL

which are not capable of judicial review by this Court in

the present petition as held by the Apex Court in the

aforesaid decisions.

c) The comparitive hardship pleaded by both sides as

regards condition No.1 being inserted/deleted also gives

rise to several contentious issues and complicated and

disputed questions of fact which are also not capable of

adjudication by this Court in the exercise of its

jurisdiction under Article 226 of the Constitution of India

in the facts of the instant case.

d) The issues that arise for consideration in this petition in

relation to the evacuation scheme, provisional

interconnection approval, extensions of the same sought

for by petitioner and protests/objections by respondents

2 to 4, rival contentions in this regard etc., are in the

nature of contractual disputes and viewed from this

angle also, in the facts of the case on hand, the

impugned condition No.1 does not warrant interference

by this Court.

e) The material on record including the past conduct of the

petitioner, inability and omission on the part of the

petitioner to complete the revised evacuation scheme

within the stipulated period, repeated extensions sought

for and granted in favour of the petitioner to complete

the work, the various terms and conditions of the

evacuation scheme dated 22.06.2017 and the earlier

PIAs granted in favour of the petitioner, the several

undertakings submitted by the petitioner that it would

complete the evacuation scheme work within the

stipulated period, all of which are a clear pointer to the

fact that despite sufficient time having been granted in

favour of the petitioner, the evacuation scheme work

has not been completed by the petitioner and

consequently, petitioner is not entitled to any relief on

this ground also.

f) The material on record also indicates that the repeated

objections and protests of respondents 2 to 4 including

the respondent No.2 - PHEPL from whose LILO, the

petitioner had obtained a LILO as per the 1st PIA dated

27.04.2019, the prejudice, loss and hardship that was

being caused to respondents 2 to 4 on account of the

delay and latches of the petitioner in completing the

evacuation scheme work, the earlier rounds of litigation

between the petitioner and respondents 2 to 4 in which

they had continuously ventilated their grievances in

granting / extending PIA in favour of the petitioner also

indicate that the KPTCL was fully justified in imposing

several terms and conditions in the PIA dated

30.06.2021 by balancing the rival interests, claims and

contentions of both the petitioner as well as respondent

Nos.2 to 4 and viewed from this angle also, the

challenge to condition No.1 on the ground that it is

causing inconvenience and hardship to the petitioner

alone cannot be countenanced and the same is liable to

be rejected.

g) The material on record indicates that it was the specific

assertion on the part of the petitioner that since IPCL

had addressed a communication dated 12.04.2021 to

the KPTCL, wherein it was stated that IPCL did not have

any objection for the petitioner to connect to its 2nd 66

KV circuit of IPCL - Sakaleshpura line by way of LILO

as an alternative to the existing LILO of PHEPL and the

submission of IPCL that they will abide by a balanced

decision to be taken by the KPTCL and also the request

made by the petitioner in its representations dated

29.05.2021 and 14.06.2021 requesting for permission

for grant of LILO to 2nd 66 KV circuit of IPCL -

Sakaleshpura line; in this context, it is relevant to state

that it is an undisputed fact that in the original PIA dated

27.04.2019, the petitioner had been granted a LILO to

the existing LILO of PHEPL (respondent No.2) and the

same LILO in favour of the petitioner was subsequently

extended up to 30.06.2021; though in its representation

dated 05.05.2021, petitioner asked for an additional

LILO to 2nd 66 KV circuit of IPCL - Sakaleshpura line in

addition to the existing LILO to the LILO of PHEPL as

per the previous PIAs, in the subsequent representation

dated 29.05.2021 and 14.06.2021, petitioner did not

insist on continuation of the existing LILO of the PHEPL

and instead, the petitioner merely sought for a LILO to

2nd 66 KV circuit of IPCL - Sakaleshpura line in view of

the NOC given by IPCL; this aspect is clarified by the

KPTCL in its Statement of Objections as well as the

other material on record. Under these circumstances, in

the backdrop of the events that have transpired prior to

30.06.2021 and the specific request made by the

petitioner that it intends to LILO to 2nd 66 KV circuit of

IPCL - Sakaleshpura line of IPCL, the KPTCL was fully

justified in imposing suitable terms and conditions in the

PIA dated 30.06.2021 including condition No.1 directing

disconnection of the existing LILO of the petitioner to the

LILO of PHEPL for the purpose of obtaining LILO and

extension of time for provisional interconnection

approval up to 30.06.2022 by taking a LILO to 2nd 66 KV

circuit of IPCL - Sakaleshpura line and as such, the

challenge to condition No.1 to the PIA dated 30.06.2021

must fail on this ground also.

h) The material on record also reveals that the claim of the

petitioner that taking a LILO to 2nd 66 KV circuit of IPCL

- Sakaleshpura line would consume a lot of time,

thereby resulting in great hardship and prejudice to the

petitioner if it is asked to disconnect the existing LILO to

the LILO of PHEPL also stands falsified by the conduct

of the petitioner in not taking necessary steps from July,

2021 onwards till date despite obtaining an interim order

dated 06.07.2021 in the present petition, which

continued to subsist and remain in force till disposal of

the petition; in other words despite specifically stating

that disconnection of the existing LILO to the LILO of

PHEPL would result in hardship, petitioner did not take

suitable steps from July, 2021 onwards to shift to the

LILO granted in 2nd 66 KV circuit of IPCL -

Sakaleshpura line and consequently, the said conduct of

the petitioner also disentitles him from any relief in the

present petition.

i) The material on record also discloses that the KPTCL

was fully justified in coming to the conclusion that all

necessary terms and conditions for the purpose of

protecting the interest of the petitioner, IPCL as well as

the respondents 2 to 4 were required to be imposed

while issuing the revised PIA in favour of the petitioner.

Under these circumstances, in the backdrop of the

aforesaid sequence of events and earlier rounds of

litigation between the parties, it cannot be said that

impugned condition No.1 is illegal, invalid, unfair,

irrational or unreasonable warranting interference by this

Court in the present petition.

j) The PIA dated 30.06.2021 issued by the KPTCL will

indicate that it has taken into account all relevant

considerations and factors for the purpose of granting

extension of the interconnection approval in favour of

the petitioner; while considering the representations put

forth by the petitioner on one hand and respondents 2 to

4 on the other, the KPTCL had come to the unequivocal,

clear, definite and certain conclusion that it was not

possible to grant extension of the PIA in favour of the

petitioner in the LILO to the LILO of PHEPL; however, in

view of the specific no objection / consent given by IPCL

that it was ready and willing for the petitioner to permit

LILO of 1st circuit of 66 KV IPCL - Sakaleshpura Line,

KPTCL agreed to grant the said approval for LILO

subject to the condition that the petitioner disconnects

the existing LILO to the LILO of PHEPL; a careful

reading of the entire PIA dated 30.06.2021 will clearly

indicate that the terms and conditions contained therein

are supplementary and complementary to each other

and the same has taken into account the grievances of

all concerned parties including the petitioner and

consequently, on this ground also, the challenge to

condition No.1 must fail.

40. In the result, I do not find any merit in the

present petition and the same is hereby dismissed.

Consequently, the interim order that was in force stands

dissolved.

SD/-

JUDGE

Srl.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter