Citation : 2022 Latest Caselaw 3482 Kant
Judgement Date : 2 March, 2022
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 2ND DAY OF MARCH, 2022
BEFORE
THE HON'BLE Dr. JUSTICE H.B.PRABHAKARA SASTRY
WRIT PETITION No.46998 OF 2014 (GM-KEB)
BETWEEN:
1. The Executive Engineer,
KPTCL, Major Works Division,
Chitradurga - 577501.
2. Assistant Executive Engineer,
Major Works Sub-Division,
Chitradurga 578501.
3. The Managing Director,
KPTCL, Kaveri Bhavan,
Bangalore.
.. Petitioners
(By Smt. M.C. Nagashree, Advocate)
AND:
1. Jayanna,
S/o. Hattappa,
Aged about 32 years,
Occ: Agriculture,
R/o. Gollanakatte village,
Kasaba Hobli,
Chitradurga Taluk
and District 577501.
2. Sannaeramma,
W/o. Hattappa,
Aged about 63 years,
W.P.No.46998/2014
2
Occ: Agriculture,
R/o. Gollanakatte village,
Kasaba Hobli,
Chitradurga Taluk
and District 577501.
.. Respondents
(By Sri. R. Shashidhara, Advocate for R-1 & R-2)
****
This Writ Petition is filed under Articles 226 and 227 of the
Constitution of India, praying to issue a writ of certiorari
quashing the order dated 15-02-2014 passed in Misc.309/2011
(Annexure A) of the learned Additional District and Sessions
Judge, Chitradurga and pass any other order as this Court deems
fit in the facts and circumstances of the case including an order
as to costs in the interest of justice and equity.
This Writ Petition coming on for Hearing, through Physical
Hearing/Video Conferencing Hearing, this day, the Court made
the following:
ORDER
The petitioners in the present writ petition have
challenged the quantum of compensation awarded by the
Court of the Additional District and Sessions Judge,
Chitradurga (hereinafter for brevity referred to as "the
District Court") in Misc.No.309/2011 vide its judgment
dated 15-02-2014.
W.P.No.46998/2014
2. The admitted fact remains that the present
petitioners have erected electricity supply tower and drawn
high tension electricity supply lines in the agricultural land
bearing R.S.78/1p2 belonging to the respondents herein
and situated in J.N. Kote Village, Kasaba Hobli, Chitradurga
Taluk and Chitradurga District. Out of the total extent of 27
acres 13 guntas in the said survey number, an extent of
131.06 guntas is said to have been used for the said
purpose. The District Court, based upon the Miscellaneous
case filed by the present respondents under Section 16 (3)
of Indian Telegraphic Act, 1885 (hereinafter for brevity
referred to as "the Act") has awarded a total compensation
of a sum of `3,33,650/- with interest at `6% per annum from
the date of petition till payment, payable by the petitioners
herein (respondents therein) to the respondents herein
(petitioners therein). Challenging the same, the petitioners
have come up through this writ petition.
3. The argument advanced by the learned counsel
for the petitioners is that, the District Court, taking the W.P.No.46998/2014
market value of the land at `2,00,000/- per acre was
exorbitant and was without any basis and also taking the
diminution value at 50% was also less and it also ought to
have been 30% by virtue of the judgment of the Co-
ordinate Bench of this Court in the case of The Executive
Engineer, KPTCL, Chitradurga and another Vs. Doddakka
reported in ILR 2015 KAR 677:2014 (6) Kar.L.J.185.
4. Learned counsel for the respondents herein
(petitioners therein) submitted that, Ex.P-2 which is the
RTC extract for the relevant year shows that, the
claimants/respondents herein were growing arecanut, as
such, as per Ex.P-3, the market value of the land per acre
ought to have been taken at `3,00,000/- per acre.
However, the District Court has not considered the same.
He further submitted that the compensation awarded in
respect of installation of the Tower is only a sum of
`6,000/- which is a small amount. He also submits that the
rate of interest awarded at the rate of `6% per annum is
also very less which requires reconsideration.
W.P.No.46998/2014
5. In her reply, the learned counsel for the petitioners
herein submitted that, the respondents/claimants, without
challenging the impugned judgment cannot seek for
enhancement of the compensation, that too, without any
grounds or basis for seeking such an enhancement.
6. With respect to the alleged fixation of market value
is concerned, the District Court has taken the market value
at `2,00,000/- per acre. According to respondents/
claimants, they were growing Arecanut, as such, the market
value ought to have been taken at `3,00,000/- per acre.
Though the respondent No.1 (claimant No.1), who got
himself examined as PW-1, in his examination-in-chief has
stated that, his land was very fertile, red soil and had
market value at `10,00,000/- per acre, but himself has
produced the Market Valuation Certificate and got it marked
at Ex.P-3, wherein the market value is shown as between a
sum of `90,000/- to a sum of `3,00,000/- per acre, depending
upon the nature of the soil and the crop grown. While for dry W.P.No.46998/2014
land, it is fixed at `90,000/- per acre, for garden land, it is
fixed at `2,00,000/- per acre. If the said garden land is
being cultivated with Arecanut, then, the market value is
fixed at `3,00,000/- per acre. To show the type of crops
the claimants were growing including Arecanut, they have
produced copies of the RTC extracts which are at Exs.P-1
and P-2.
7. A perusal of the RTC extracts (Exs.P-1 & P-2)
would go to show that, at the relevant point of time, the
respondents herein (claimants) were growing plantain,
ground nut and Arecanut. However, the learned District
Court, without there being any basis, treating the land in
question as dry land, has arrived at a market value at
`2,00,000/- per acre. As such, the market value per acre
was required to be taken at `3,00,000/- (`7,500/- per
gunta).
8. In so far as the calculation of the compensation is
concerned, the District Court has taken 50% of the total
market value as diminution. No doubt, though earlier some W.P.No.46998/2014
of the Courts were taking 50% as the diminution value,
however in Doddakka's case (supra), it has been held that
the said diminution value has to be taken at 30%. Since
the said value of diminution is being uniformly applied in all
the matters, the diminution value is now required to be
taken even in the instant case also at 30% and the
compensation is to be calculated accordingly.
Thus, at the rate of `3,00,000/- per acre, per gunta,
the market value would be at `7,500/-. For 131.06 guntas,
the diminution value would be `7,500X131.06 guntas X
30% = `2,94,885/-.
9. Admittedly, a single tower has been installed in the
land of the respondents/claimants. Towards one tower
installation, the compensation of `6,000/- is awarded.
Though the learned counsel for the respondents submitted
that for single tower installation, the compensation is
required to be `1,00,000/-, but the said submission bears
no support either by oral and documentary evidence. A
uniform compensation is awarded for the relevant period of W.P.No.46998/2014
time for the said utilisation of the land for drawing of
electricity supply lines at `6,000/- for single tower.
Therefore, I do not find any discrepancy in the quantum of
compensation awarded towards the installation of the
tower.
10. Thus, when calculated, the total compensation for
which the respondents/claimants would be entitled would
come as follows:
(i) 131.06x7,500/-x30% = `2,94,885/-
(ii) Towards Tower installation = 6,000/-
Total = `3,00,885/-
11. The interest at the rate of `6% awarded by the
District Court also being reasonable, does not warrant any
interference at the hands of this Court.
12. Considering the circumstances of the case and
also the evidence led by PW-1, I do not find that the
claimants are entitled for any other enhancement, on the
other hand, the petitioners could able to show that, the W.P.No.46998/2014
diminution of valuation calculated by the District Court was
slightly on the higher side.
Accordingly, since the total compensation awarded by
the District Court in the impugned judgment is slightly on
the higher side, the same warrants interference by this
Court and to that extent only, the writ petition requires to
be allowed.
Accordingly, the Writ Petition is allowed in part.
The judgment dated 15-02-2014 passed in Misc. No.
309/2011 (Annexure-A) by the Court of the learned
Additional District and Sessions Judge, Chitradurga, is
modified to the extent that the entitlement of the
respondents/claimants for compensation is reduced from
`3,33,650/- to `3,00,885/-.
`
The rest of the order including awarding of interest at
the rate of `6% per annum from the date of petition till
payment remains unaltered.
Draw modified Award accordingly.
W.P.No.46998/2014
Registry to transmit a copy of this order to the
concerned District Court, without delay.
Sd/-
JUDGE
BMV*
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!