Citation : 2022 Latest Caselaw 9129 Kant
Judgement Date : 20 June, 2022
IN THE HIGH COURT OF KARNATAKA AT
BENGALURU
DATED THIS THE 20TH DAY OF JUNE 2022
BEFORE
THE HON'BLE MR. JUSTICE B. M. SHYAM PRASAD
CIVIL MISCELLANEOUS PETITION NO.43/2018
BETWEEN :
M/S VISHAL INFRASTRUCTURE LTD.,
A COMPANY INCORPORATED UNDER
THE COMPANIES ACT, 1956
HAVING ITS HEAD OFFICE AT NO.52
R V ROAD, BASAVANAGUDI
BENGALURU - 560 004.
REP. BY ITS SPA HOLDER
MAYIL VAGANAN A
MANAGER
... PETITIONER
(By SRI. RAMACHANDRA H., ADVOCATE)
AND :
M/S SANZ CONSTRUCTIONS PVT LTD
A COMPANY INCORPORATED UNDER THE
COMPANIES ACT 1956
HAVING ITS HEAD OFFICE AT NO.54,
1ST FLOOR, NEW DIAGONAL ROAD
3RD BLOCK, JAYANAGAR
BENGALURU - 560 011
REP. BY ITS MANAGING DIRECTOR.
... RESPONDENT
(SERVICE HELD SUFFICIENT
VIDE COURT ORDER DATED 8.11.2021)
2
THIS CIVIL MISCELLANEOUS PETITION IS FILED
UNDER SEC.11 OF THE ARBITRATION AND CONCILIATION
ACT 1996, PRAYING FOR A JUDGMENT OR
ORDER/DIRECTION ETC, DIRECTING THE PETITIONER
COMPANY AND RESPONDENT COMPANY TO APPOINT AN
ARBITRATOR FROM THEIR SIDE AND BOTH THESE
ARBITRATORS TO APPOINT SUITABLE ARBITRATOR TO
ADJUDICATE THE DISPUTE BETWEEN THE PARTIES;
THIS PETITION COMING ON FOR ADMISSION, THIS
DAY, THE COURT MADE THE FOLLOWING:
ORDER
The petitioner, who relies upon a purported
agreement dated 06.08.2007 with the respondent, has
filed this petition for constitution of an Arbitral Tribunal
comprising of three Arbitrators. The petitioner's prayer
reads as follows:
"[a] Judgment or order/direction etc., directing the petitioner company and respondent company to appoint an Arbitrator from their side and both these arbitrators to appoint suitable arbitrator to adjudicate the dispute between the parties.
[b] To pass a judgment to appoint an arbitrator who is acceptable to both the parties with a direction to adjudicate the dispute following the
procedural law including the procedure laid down in the CPC."
The arbitration clause in this Agreement dated
06.08.2007 reads as under:
"29. In case of any disputes between the parties about this agreement, the disputes shall be referred to Arbitration in terms of Indian Arbitration Act 1940 as repelled by Ordinance of 1996."
2. The petitioner's case is that the Kerala
Tourism Development Corporation [KSTDC] hired the
services of another State undertaking, M/s. KITCO
Limited. This Consultant caused publication of a tender
for executing certain civil works and the petitioner was
successful in its bid. The petitioner could engage the
services of the respondent as a 'Sub-Contractor' and the
respondent has executed the tender work. One of the
former Executive Directors of the petitioner was
responsible for the contract with the respondent. The
petitioner, who had to suffer an Arbitral Award because
of certain deficiencies in the construction, has paid
certain amounts, and the petitioner would be entitled to
recover such amounts along with damages from the
respondent. The petitioner relying upon the terms of
the Agreement dated 06.08.2007 and contending that it
has issued legal Notices for commencement of arbitral
proceedings, has filed this petition. In the
correspondence relied upon by the petitioner to assert
that Notice has been issued for commencement of
arbitral proceedings, the petitioner has stated that it
has appointed a certain Mr.T.V. Prabhakaran as one of
the Arbitrators.
3. Sri. H. Ramachandra, the learned counsel
for the petitioner, taking this Court through the terms of
the Agreement dated 06.08.2007 and the Award dated
12.11.2015 in O.P. [Arb] No.850/2014 as also the
exchange of correspondence as referred to above,
submits that this Court must allow the petition and
appoint a sole Arbitrator. Admittedly, the agreement
does not bear the respondent's company seal and
nothing is placed on record to establish that the
petitioner's letters dated 17.02.2017 [addressed to the
respondent and certain other addressees] are actually
sent to the respondent/other addressees or is served on
the respondent/the other addressees.
4. Sri. H. Ramachandra was extended an
opportunity to substantiate that these letters dated
17.02.2017 are sent to the respondent or the
addressees. In response, Sri. H. Ramachandra, without
filing any additional document, submits that he could
state on instructions that the letters dated 17.02.2017
are sent to the respondent/and the other addressees by
e-mail. As regards the agreement not containing the seal
of the respondent, the learned counsel seeks to rely
upon the decision of the Hon'ble Supreme Court in 'N.N.
Global Mercantile Pvt. Ltd., v. Indo Unique Flame Ltd and
Others'1 to bolster his submissions that even if there is
any doubt about the due execution of the agreement,
which incorporates the arbitration clause, questions in
this regard must be decided in the arbitral proceedings
and this Court cannot reject the petition only because
there could be some deficiency in the document.
5. It is settled law that the designated Courts
under Section 11 of the Arbitration and Conciliation
Act, 1996 [for short, 'the Arbitration Act'] exercise
judicial power to ascertain the existence of an
arbitration agreement and that the dispute is not a
deadwood. Further, the designated Courts would
exercise jurisdiction under Section 11 of the Arbitration
Act only if notice is issued for commencement of arbitral
1 [2021] 4 SCC 379
proceedings as contemplated under Section 21 of the
Arbitration Act and if there is failure in these regards,
the petitioner under section 11 of the Arbitration Act,
would fail.
6. This Court must opine that the petitioner
has failed to establish even prima facie the existence of
a contract with the respondent because of the following
reasons. As observed earlier, the Agreement dated
06.08.2007 does not bear the respondent's company
seal and there is nothing on record to indicate that
there is any communication with the respondent based
on the same. The petitioner relies on correspondences
dated 17.02.2017. Crucially, there is nothing on record
to even establish that the correspondences are sent to
the addresses. Therefore, this Court is of the
considered view that the petitioner has failed to
establish the requirements for exercise of jurisdiction
under Section 11 of the Arbitration Act and hence, the
petition is dismissed.
Sd/-
JUDGE
AN/-
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!