Citation : 2021 Latest Caselaw 1745 Kant
Judgement Date : 16 March, 2021
1
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 16TH DAY OF MARCH, 2021
PRESENT
THE HON'BLE MR.JUSTICE ALOK ARADHE
AND
THE HON'BLE MR.JUSTICE NATARAJ RANGASWAMY
WRIT APPEAL NO.373 OF 2012 (GM-KEB)
C/W
WRIT APPEAL NO.550 OF 2012 (GM-KEB)
W.A. NO.373/2012:
BETWEEN:
1. SRI. D. SURESH KUMAR
S/O DHANRAJ,
AGED ABOUT 39 YEARS
2. SRI. PRAKASH D JAIN
S/O DHANRAJ
AGED ABOUT 37 YEARS
BOTH RESIDENTS OF
SUBHASHCHANDRA BOSE EXTENSION,
HULIYAR ROAD, HIRIYUR,
CHITRADURGA DISTRICT-572143.
...APPELLANTS
(BY DR. NANDA KISHORE, ADVOCATE FOR SRI. A.C. BALARAJ,
ADVOCATE)
2
AND:
KARNATAKA POWER TRANSMISSION
CORPORATION LIMITED,
MAJOR WORKS DIVISION,
II FLOOR, R.H. BUILDING,
P.B. ROAD, DAVANGERE,
DAVANGERE DISTRICT-577001
REPRESENTED BY ITS
EXECUTIVE ENGINEER
...RESPONDENT
(BY SRI. H.V.DEVARAJU, ADVOCATE)
THIS WRIT APPEAL IS FILED UNDER SECTION 4 OF THE
KARNATAKA HIGH COURT ACT PRAYING TO SET ASIDE THE
ORDER OF THE LEARNED SINGLE JUDGE PASSED IN
W.P.5578/2010 AND W.P.NO.8078/2010 DATED 11.08.2011 IN
SO FAR AS RESTRICTING THE COMPENSATION TO
RS.1,46,030/- AS AGAINST RS.350/- PER SQ.FT. FOR TOTAL
EXTENT OF THE LANDS BELONGING TO THE APPELLANTS AND
BE PLEASED TO GRANT THE RELIEFS AS PRAYED FOR IN THE
ABOVE WRIT PETITION AND ALLOW THE WRIT APPEALS WITH
COSTS, TO MEET THE ENDS OF JUSTICE AND EQUITY.
W.A. NO.550/2012:
BETWEEN:
KARNATAKA POWER TRANSMISSION
CORPORATION LTD.,
MAJOR WORKS DIVISION,
II FLOOR, R.H. BUILDING,
P.B. ROAD, DAVANGERE,
DAVANGERE DISTRICT-577001
NOW CHITRADURGA DISTRICT-572143
REPRESENTED BY ITS
EXECUTIVE ENGINEER
...APPELLANT
(BY SRI. H.V.DEVARAJU, ADVOCATE)
3
AND:
1. SRI. D. SURESH KUMAR
AGED ABOUT 39 YEARS,
SON OF DHANRAJ,
SUBHASHCHANDRA BOSE EXTENSION,
HULIYAR ROAD, HIRIYUR,
CHITRADURGA DISTRICT-572143.
2. SRI. PRAKASH D. JAIN
AGED ABOUT 37 YEARS,
SON OF DHANRAJ,
SUBHASHCHANDRA BOSE EXTENSION,
HULIYAR ROAD, HIRIYUR,
CHITRADURGA DISTRICT-572143.
...RESPONDENTS
(BY DR. NANDA KISHORE, ADVOCATE FOR SRI. A.C. BALARAJ,
ADVOCATE FOR RESPONDENT NOs.1 AND 2)
THIS WRIT APPEAL IS FILED UNDER SECTION 4 OF THE
KARNATAKA HIGH COURT ACT PRAYING TO SET ASIDE THE
ORDER PASSED IN WRIT PETITION NOs.5578/2010 AND
8078/2010 DATED 11.08.2011.
THESE APPEALS HAVING BEEN HEARD AND RESERVED
FOR JUDGMENT ON 17.02.2021, COMING ON FOR
PRONOUNCEMENT OF JUDGMENT THIS DAY, NATARAJ
RANGASWAMY J., DELIVERED THE FOLLOWING:
JUDGMENT
These intra-court appeals are filed challenging the
order dated 11.08.2011 passed by the learned Single
Judge of this Court in W.P.Nos.5578/2010 and 8078/2010.
2. W.A. No.373/2012 is filed by the land
losers/petitioners challenging the quantum of
compensation determined by the District Judge which was
enhanced by learned Single Judge of this Court, while W.A.
No.550/2012 is filed by the Karnataka Power Transmission
Corporation Limited (henceforth referred to as
'Corporation' in short) challenging the quantum of
compensation determined by the learned Single Judge in
W.P.Nos.5578/2010 and 8078/2010.
3. The facts leading to the filing of
W.P.Nos.5578/2010 and 8078/2010 are that the land
bearing Sy.Nos.202/1A and 202/2A situate at Metikurke
Village, Hiryur Taluk, Chitradurga District were converted
from agricultural to non-agricultural industrial purposes.
The land losers/ petitioners purchased the above land in
terms of a sale deed dated 05.08.1992 to install a
decorticating factory. They got a plan sanctioned for the
building. It is stated that a portion of the land in question
was acquired by the National Highway Authorities for
widening the NH-4 and determined the market value of the
land so acquired at Rs.75/- per sq.ft. and passed an award
on 24.06.2005. Later, the Corporation drew high tension
cables over a portion of the land which divided the
property into two pieces. The land losers/petitioners
claimed compensation which was denied by the
Corporation. The land losers/petitioners therefore filed
W.P.No.23600/2005 to direct the Corporation to remove
the high tension power line and the high tension tower
constructed on their land. The writ petition was disposed of
directing the land losers/petitioners to claim compensation
in accordance with Section 16 of the Indian Telegraph Act,
1885. The land losers/petitioners therefore, sought
compensation at the rate of Rs.350/- per sq.ft. as on the
date of using the land for installation of high tension tower
and the electric line. The land losers/petitioners contended
that after acquisition of 18 guntas of land for the highway,
50% of the remaining land to an extent of 2 acres 29
guntas could not be used for industrial purposes in view of
the overhead high tension line passing through the land.
Therefore, they claimed compensation at the rate of
Rs.350/- per sq.ft. for 50% of the land out of 2 acres 29
guntas along with interest at the rate of 12% p.a. from the
date of installation of the said High Tension Tower and
electric line. When the Corporation failed to pay the
compensation, the land losers/petitioners filed a
Miscellaneous Petition No.16/2006 before the Principal
District Judge at Chitradurga under Section 16(3) of the
Indian Telegraph Act, 1885 seeking compensation at the
rate of Rs.350/- per sq.ft. for 50% of the land out of 2
acres 29 guntas with interest at the rate of 12% p.a. from
the date of installation of high tension tower and electric
line. The District Judge in terms of the Order dated
05.11.2007 allowed the petition and determined the
market value at a sum of Rs.65/- per sq.ft. and held that
the land losers/petitioners were entitled to compensation
of Rs.17,33,550/- with interest at the rate of 6% p.a. from
the date of filing of the petition till payment.
4. The Corporation challenged this order before
this Court in W.P.No.3260/2008 while the land
losers/petitioners also filed W.P.No.10517/2008 for
enhancement of the compensation. The writ petitions were
disposed of in terms of an order dated 09.09.2009 in
terms of which, the claim of the land losers/petitioners
was ordered to be reconsidered.
5. Based on the aforesaid said order, the District
Judge conducted proceedings, passed an order dated
08.12.2009 determining the market value of the property
at a sum of Rs.38,500/- as against the earlier quantified
amount of Rs.17,33,550/-.
6. Being aggrieved by the aforesaid order of the
District Judge, the land losers/petitioners filed
W.P.Nos.5578/2010 and 8078/2010.
7. The learned Single Judge held that the land
losers/petitioners could still utilize the land to raise
agricultural crops in the land under the electric lines and
therefore, held that the land is not totally unfit for
agriculture. The learned Single Judge also held that the
land did not lie in an industrial township to consider
whether it could be used for the purpose of industrial
layout. The learned Single Judge further held that the
height of the structures of the intended factory of the land
losers/petitioners would not be more than 15-20 feet tall
and such structures would not be in conflict with the safety
of the power lines. The learned Single Judge noticed that a
portion of a land was acquired for widening of national
highway No.4 and the compensation was determined at a
sum of Rs.75/- per sq.ft. But, the learned Single Judge
held that the amount could not be considered as a safe
guideline to assess the compensation in the present case
as the land would continue remain with the land
losers/petitioners. Hence, the learned Single Judge felt it
appropriate to award Rs.5/- per sq.ft. for the aerial
encroachment and sum of Rs.75/- per sq.ft. for the area of
the tower measuring 189 sq.ft. and thus, enhanced the
compensation to Rs.1,46,030/-.
8. Being aggrieved by the order passed by the
learned Single Judge, the present appeals are filed. The
learned counsel for the appellants contended that the
power line has now bifurcated the property in to two parts
and that it would be impossible for them to use the land
for the purpose for which they had purchased. They
contended that the utility of the land is now depleted since
no structures can be now put up underneath the power
lines and a set back area is also prescribed which
diminishes the utility of the land. Therefore, he contended
that the compensation awarded by the District Judge as
well as the learned Single Judge is liable to be modified.
He contended that the market value determined by the
National Highway Authorities would be a safe guideline to
determine the market value in the present case. He
contended the land is converted for non agricultural
industrial use and therefore, the appellant cannot
undertake any agricultural activity in the land in question.
Be that as it may, he contended that since the utility of the
entire land is wasted, 50% of the land has to be treated as
the affected portion and compensation has to be
determined at the market value at a sum of Rs.75/- per
sq.ft. The learned counsel brought to our notice a copy of
the sketch of the power line running through the land of
the land losers/petitioners which indicate that the property
is now bifurcated into two portions. The learned counsel
brought to our notice a decision passed by a learned Single
Judge of this court in the case of THE EXECUTIVE
ENGINEER, KARNATAKA POWER TRANSMISSION
CORPORATION LIMITED, CHITRADURGA AND ANOTHER
Vs. DODDAKKA, 2014(6) KARL J 185. He also brought to
our notice the Judgment of Supreme Court of India in
KERALA STATE ELECTRICITY BOARD Vs. LIVISHA AND
OTHERS, 2007(6) SCC 792 and invited our attention to
para No.9 and 10 of the Judgment which is extracted
below:
"9. Both telegraph lines and electrical lines are required to be drawn over the agricultural lands and/or other properties belonging to third parties.
In drawing such lines, the entire land cannot be acquired but the effect thereof would be diminution of value of the property over which such line is drawn. The Telegraph Act, 1885 provides for the manner in which the amount of compensation is to be computed therefor. Section 10 of the Act empowers the authority to place and maintain a telegraph line under, over, along or across, or posts in or upon any immovable property. Section 11 empowers the officers to enter on property in order to repair or remove telegraph lines or posts. Section 12 empowers the authority to grant permission for laying down such lines to a local authority in terms of clauses (c) & (d) of the proviso to Section 10 of the Act subject to reasonable conditions as it may think fit. Section 16 of the said Act reads as under :-
"16. Exercise of powers conferred by section 10, and disputes as to compensation, in case of property other than that of a local authority.- (1) If the exercise of the powers mentioned in section 10 in respect of property referred to in clause (d) of that section is resisted or obstructed, the District Magistrate may, in his discretion, order that the telegraph authority shall be permitted to exercise them.
(2) If, after the making of an order under section (1), any person resists the exercise of those powers, or, having control over the property, does not give all facilities for their being exercised, he shall be deemed to have committed an offence under section 188 of the Indian Penal Code (45 of 1860).
(3) If any dispute arises concerning the sufficiency of the compensation to be paid under section 10, clause (d), it shall, on application for that purpose by either of the disputing parties to the District Judge within whose jurisdiction the property is situate, be determined by him.
(4) If any dispute arises as to the persons entitled to receive compensation, or as to the proportions in which the persons interested are entitled to share in it, the telegraph authority may pay into the court of the District Judge such amount as he deems sufficient or, where all the disputing parties have in writing admitted the amount tendered to be sufficient or the amount has been determined under sub-section (3), that amount; and the District Judge, after giving notice to the parties and hearing such of them as desire to be heard, shall determine
the persons entitled to receive the compensation or, as the case may be, the proportions in which the persons interested are entitled to share in it.
(5) Every determination of a dispute by a District Judge under sub-section (3), or sub- section (4) shall be final:
Provided that nothing in this sub-section shall affect the right of any person to recover by suit the whole or any part of any compensation paid by the telegraph authority, from the person who has received the same."
10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small track of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
9. Per contra, the counsel for the corporation
contended that the market value fixed by the National
Highway Authority cannot be the criteria as in the latter
case, the possession of the land would be taken over while
in the present case, the possession of the land would be
with the petitioners. He contended that the land
losers/petitioners could still utilize the remaining portion of
the land and therefore, they cannot claim that the utility of
the land is diminished.
10. We have given our anxious consideration to
the arguments advanced by the learned counsel for the
parties. As rightly contended by the learned counsel for the
land losers/petitioners the Corporation has to follow the
provisions made in the Indian Electricity Rules, 1956 while
drawing overhead lines. Rule 77 deals with the clearance
to be provided from the ground to lowest conductor. Rule
79 provides for clearance from low and medium voltage
lines and service lines which is extracted below:
"79. Clearance from buildings of low and medium voltage lines and service lines:-
(1) Where a low or medium voltage over-
head lines passes above or adjacent to or terminates on any building, the following minimum clearances from any accessible point, on the basis of maximum sag, shall be observed:-
(a) for any flat roof, open balcony, verandah roof and lean-to-roof--
(i) when the line passes above the building a vertical clearance of 2.5 metres from the highest point, and
(ii) when the line passes adjacent to the building a horizontal clearance of 1.2 metres from the nearest point, and
(b) for pitched roof--
(i) when the line passes above the building a vertical clearance of 2.5 metres immediately under the lines, and
(ii) when the line passes adjacent to the building a horizontal clearance of 1.2 metres.
(2) Any conductor so situated as to have a clearance less than that specified in sub-rule (1) shall be adequately insulated and shall be attached words "by means of metal clips" omitted by GSR 523, dated 28.3.1966 (w.e.f. 9.4.1966) at suitable intervals to a bare earthed bearer wire having a breaking strength of not less than 350 kg.
(3) The horizontal clearance shall be measured when the line is at a maximum deflection from the vertical due to wind pressure."
11. While Rule 80 provides for clearance from
buildings of high and extra high voltage lines.
12. In the present case, the corporation has drawn
transmission lines and have erected a tower in an area
measuring 30ft x 40ft in the land of the land
losers/petitioners. On account of the overhead lines, the
land losers/petitioners are deprived of undertaking any
industrial activity below the overhead lines and therefore
to that extent, they are deprived of the usage and utility of
the land. This deprivation shall continue so long as the
overhead lines exist over the property of the land
losers/petitioners. Having regard to the judgment of the
Apex court in the case of Kerala State Electricity board
(Supra) it cannot be gainsaid that there is diminision of the
value of the property over which the overhead lines are
drawn. In the instant case, the property of the land
losers/petitioners lie adjacent to the NH-4 since a portion
of the land is acquired by the National Highway Authorities
for the purpose of widening the Highway. Thus, the
property in question has a high potential and having
regard to the fact that the overhead line passes through
the middle of the land of the land losers/petitioners and
having regard to the fact that the National Highway
Authority has determined the market value at Rs.75/- per
sq.ft., it is appropriate in the present case too, having
regard to the peculiar facts and circumstances of the case,
the market value is determined at a sum of Rs.75/- per
sq.ft. Since the area covered by the overhead lines is
around 24 guntas of land and having regard to the fact
that the land losers/petitioners are deprived of the usage
of this area forever, they are entitled to compensation at
the rate of Rs.75/- per sq.ft. Since the tower is constructed
within 24 guntas of land, the question of granting any
compensation towards the area occupied by the tower
would not arise. Thus the land losers/petitioners are
entitled to a sum of Rs.19,60,200/- as compensation
towards the deprivation of the use of 24 guntas of land
belonging to them. The land losers/petitioners are entitled
to interest at rate of 12% p.a. from the date of drawing
the overhead lines till the date of payment.
Hence, the appeal filed by the land losers/petitioners
in W.A. No.373/2012 is allowed and the appeal filed by
the corporation in W.A.No.550/2012 is dismissed.
The parties to bear their own costs.
Sd/-
JUDGE
Sd/-
JUDGE
KGR*
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!