Citation : 2021 Latest Caselaw 7097 Kant
Judgement Date : 23 December, 2021
IN THE HIGH COURT OF KARNATAKA
DHARWAD BENCH
DATED THIS THE 23RDDAY OF DECEMBER 2021
BEFORE
THE HON'BLE MR.JUSTICE N.S.SANJAY GOWDA
C.M.P.100019/2019
BETWEEN:
DAYANAND MASUR S/O SHRI BASAVARAJ MASUR,
AGE: 48 YEARS,
OCC: ENGINEER AND PWD CLASS-I CONTRACTOR,
C.B. GUTTAL COMPLEX, UB HILLS,
DHARWAD TALUK,DIST: DHARWAD,
DHARWAD-580007.
...PETITIONER
(BY SRI NARAYAN G.RASALKAR, ADVOCATE)
AND :
1. THE GENERAL MANAGER
SOUTH WESTERN RAILWAYS,
RAIL SOUDHA,GADAG ROAD,
HUBBALLI-580020,
HUBBALLI TALUK,DIST: DHARWAD.
2. THE CHIEF ADMINISTRATIVE OFFICER
CONSTRUCTION,18, MILLERS ROAD,
BENGALURU-560046,
BENGALURU URBAN DISTRICT.
3. THE CHIEF ENGINEER(CONSTRUCTIONS II),
SOUTH WESTERN RAILWAY,
RAIL SOUDHA,GADAG ROA,
HUBBALLI-580020,HUBBALLI TALUK,
DIST: DHARWAD.
:2:
4. THE DEPUTY CHIEF ENGINEER,
CONSTRUCTION- III,
SOUTH WESTERN RAILWAY,
RAIL SOUDHA,GADAG ROAD,
KESHWAPUR, HUBBALLI-580020,
HUBBALLI TALUKA,DIST: DHARWAD.
5. THE DEPUTY CHIEF ENGINEER
CONSTRUCTION/II,
SOUTH WESTERN RAILWAY,
RAIL SOUDHA,GADAG ROAD,
KESHWAPUR, HUBBALLI-580020,
HUBBALLI TALUK,DIST: DHARWAD.
..RESPONDENTS
(BY SRI AJAY U.PATIL, ADVOCATE)
THIS CMP IS FILED UNDER SECTION 11(6) OF THE
ARBITRATION AND CONCILIATION ACT, 1996 PRAYING TO
APPOINT SRI. S.H.MITTALKOD, RETIRED DISTRICT JUDGE AS THE
SOLE ARBITRATOR APPOINT TO RESOLVE THE DISPUTES RAISED
BY THE PETITIONER IN HIS REQUISITION DATED 12.09.2018 AS
PER DOCUMENT 27 AND AS PER CONDITIONS MENTIONED IN THE
AGREEMENT OF WORK DATED 19.02.2014 VIDE DOCUMENT
NOS.2 AND 3 AND RESPONDENTS IN ACCORDANCE WITH LAW, IN
THE INTEREST OF JUSTICE.
THIS PETITION WAS HEARD ON 01.12.2021 AND
REASERVED FOR ORDERS, THIS DAY THE COURT PRONOUNCED
THE FOLLOWING:
:3:
ORDER
In this petition a request is made to appoint Sri
S.H.Mittalkod, Retired District Judge, as sole arbitrator to
resolve a dispute said to have arisen from the execution of
the work executed under the contract dated 12.08.2014.
2. It is the case of the petitioner that he had entered
into contract with the Railways on 19.02.2014 and under the
terms of the contract, the work was to be completed
by 18.02.2015 and the value of the work was
Rs.19,90,30,639/-. It is the case of the petitioner that he
completed the work on 04.09.2017 and this was also
acknowledged by the Deputy General Engineer. It is his
further case that he had raised certain disputes by notice
dated 12.09.2018 and sought the intervention of the General
Manager in settling the 13 claims.
3. The petitioner has stated that as the claim sought by
him was not settled by the General Manager, he sought for
the reference of the disputes to should an arbitral tribunal
and made a demand for arbitration. In the said demand, it
was clearly stated by the petitioner that he was not waiving
the applicability of Section 12(5) of the Arbitration and
Conciliation Act.
4. This demand for arbitration was followed by
reminders dated 10.12.2018 and 04.03.2019, once again
calling upon the Railways to General Manager to appoint the
arbitral tribunal. The Railways, according to the petitioner,
responded by letter dated 29.04.2019 stating that as per
Clause-63 of the General Conditions of the contract which had
been issued in November-2018, the settlement of disputes
and differences was required to be reconciled and should be
referred to by the contractor to the Chief Engineer or
Divisional Railway Manager through a notice of dispute and
thereafter if the conciliation proceedings were not successful,
the matter would be processed for arbitration.
5. This was responded to by the petitioner saying that
the amendment made to Clause-63 in November-2018 was
not applicable since the contract was much prior to
November-2018, the petitioner therefore once again called
upon the Railways to refer the matter for arbitration.
6. It is also stated that the petitioner had approached
Sri S.H.Mittalkod and sought his consent for being appointed
as an Arbitrator and Sri S.H.Mittalkod had indicated his
willingness to appoint the Sole Arbitrator.
7. In this context, the present petition has been filed
seeking for appointment of Sri S.H.Mittalkod as the
Arbitrator.
8. On notices of the petition being served, the Railways
entered appearance and contended that a no claim certificate
had been signed by the petitioner and therefore the petitioner
was the barred from demanding arbitration. It was also
stated that since a no claim certificate had been given, the
claims raised by the petitioner fell within the purview of
accepted matter and was not referable to arbitration.
9. The contention advanced by the petitioner in this
petition is that the General Manager by virtue of being the
employee of the Railways was himself ineligible to be an
arbitrator and therefore he could not inturn appoint another
person as the Arbitrator. The case of the petitioner is that
despite an agreement which enabled an employee to appoint
an arbitrator, the General Manager did not possess the power
of appoint the Arbitrator since it amounted to an unilateral
act on the part of the one of the contracting parties.
10. He relied upon the decision rendered by the three
Judges Bench of the Hon'ble Supreme Court in the case ofTRF
Ltd. v. Energo Engineering Projects Limited, reported in(2017) 8
SCC 377, which has been followed by the Hon'ble Supreme
Court in the case of Perkins Eastman Architects DPC and
Another vs. HSCC (India) Ltd., reported in 2019 SCC OnLine SC
1517 and also in Bharat Broadband Network Limited v. United
Telecoms Limited, reported in (2019) 5 SCC 755 and in Haryana
Space Application Centre (HARS AC) and Another v. PAN India
Consultants Private Limited, reported in (2021) 3 SCC 103.
11. Sri Ajay U.Patil, learned counsel for the Railways, on
the other hand contended that the petitioner having entered
into an agreement in which power of appointment of an
Arbitrator was conferred on the General Manager could not
thereafter resile from the contractual terms. He contended
that the Courts are required to give effect to the contractual
clause and they could not rewrite the contract. He submitted
that the decisions relied upon by the learned counsel were
inapplicable and were clearly distinguished by a decision of
three Judges Bench of the Hon'ble Supreme Court in the case
of Central Organization for Railway Electrification vs. ECI-SPIC-
SMO-MCML (JC) A Joint Ventur Company, reported in2019 SCC
OnLine SC 1835.
12. He submitted that while considering Clause-64 of
the GCC, the Hon'ble Supreme Court had stated that the
petitioner was bound to abide by the contractual term in the
manner of appointment of an arbitrator, the appointment
could be made only in accordance with Clause-64 and the
prayer for appointment of independent Arbitrator could not be
granted.
13. It is not in dispute that the General conditions of the
contract govern the rights and obligations of the parties in
respect of Railway Contracts. In respect of settlement of
disputes, the GCC contemplates that the matters should be
first considered in the following manner.
"Clause No.63 of GCC : Matters finally determined by the Railway.
All disputes and differences of any kind whatsoever arising out of or in connection with the contract, whether during the progress of the work or after its completion and whether before or after the determination of the contract, shall be referred by contractor to the General Manager and the General Manager shall within 120 days after receipt of the Contractor's representation make and notify decisions on all matters referred to by the Contractor in writing provided that matters for which provision has been made in Clauses 8, 18, 22(5), 39, 43(2), 45(a), 55, 55-A(5), 57, 57-A, 61(1), 61(2) and 62(1) to (xiii)B of the General Conditions of Contract or in any clause of the special conditions of contract shall be deemed as 'excepted matters' (matters not arbitrable) and decisions of the Railway authority, thereon shall be final and binding on the Contractor provided further that "excepted matters" shall stand specifically excluded from the purview of the arbitration clause."
14. In respect of demand for arbitration, the clause
reads as under :
"(Clause 64(1) of GCC) Demand for Arbitration:
In the event of any dispute or different between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute ; or difference on any account, or
as to the withholding by the Railway of any certificate to which the Contractor may claim to be entitled to, or if the Railway fails to make a decision within 120 days, then and in any such case, but except in any of the "excepted matters" referred to in Clause 63 of these conditions, the Contractor, after 120 days but within 10 days of his presenting his final claim on disputed matters, shall demand in writing that the dispute or difference be referred to arbitration."
15. Clause 64(3) of GCC provides for appointment of an
Arbitrator and this reads as follows :
"(i) In cases where the total value of all claims in question added together does not exceed Rs.10,00,000/- (rupees Ten lakh only), the Arbitral Tribunal shall consist of a sole arbitrator who shall be a gazetted officer of Railway not below JA grade nominated by the General Manager in that behalf. The sole arbitrator shall be appointed within 60 days from the day when a written and valid demand for arbitration is received by the General Manager.
(ii) In case not covered by Clause 63(3)(a)(i), the Arbitral Tribunal shall consist of panel of three Gazetted Railway Officers not below, JA grade or two Railway gazetted officers not below JA grade and a retired Railway Officer, retired not below the rank of SAG
Officer, as the arbitrators. For this purpose, the Railway will send a penal of more than 3 names of Gazetted Railway officers of one or more departments, of the railway, which may also include the name(s) of retired Railway Officer (s) empanelled to work as Railway Arbitrator to the Contractor within 60 days from the day when a written and valid demand for arbitration is received by the General Manager. Contractor will be asked to suggest to the General manager at least 2 names out of the panel for appointment as the Contractor's nominee within 30 days from the date of dispatch of the request by Railway. The General Manager shall appoint atleast one out of them as the Contractor's nominee and will, also simultaneously appoint the balance number of arbitrators either from the panel or from outside the panel, duly indicating the "Presiding Arbitrator" from amongst the 3 Arbitrators so appointed. General Manager shall complete the exercise of appointing the Arbitral Tribunal within 30 days from the receipt of the names of contractor's nominees. While nominating the arbitrators it will be necessary to ensure that one of them is from Accounts Department. An Officer of Selection Grade of the accounts department shall be considered of equal status to the officers in SA grade of other Departments of the railways for the purpose of appointment of arbitrators."
16. It is thus clear that the parties have agreed on
procedure for appointing the Arbitrator and the Railways have
admittedly not acted in terms of the agreed procedure and
appointed an Arbitral Tribunal.
17. It is the specific case of the petitioner that by virtue
of Section 12(5) of the Arbitration and Conciliation Act, the
General Manager being ineligible to be Arbitrator would not
possess the power to appoint another person or persons as
Arbitrators. In this regard he strongly relies on the decision
rendered by the Apex Court in TRF Ltd.,'s case and more
specifically on paragraph No.54, which reads as follows :
"54. In such a context, the fulcrum of the controversy would be, can an ineligible arbitrator, like the Managing Director, nominate an arbitrator, who may be otherwise eligible and a respectable person. As stated earlier, we are neither concerned with the objectivity nor the individual respectability. We are only concerned with the authority or the power of the Managing Director. By our analysis, we are obligated to arrive at the conclusion that once the arbitrator has become ineligible by operation of law, he cannot nominate another as an arbitrator. The arbitrator becomes ineligible as per prescription contained in Section 12(5) of the Act. It is inconceivable in law
that person who is statutorily ineligible can nominate a person. Needless to say, once the infrastructure collapses, the superstructure is bound to collapse. One cannot have a building without the plinth. Or to put it differently, once the identity of the Managing Director as the sole arbitrator is lost, the power to nominate someone else as an arbitrator is obliterated. Therefore, the view expressed by the High Court is not sustainable and we say so."
18. In order to reinforce his argument, he also relied
upon the Judgment of the Hon'ble Supreme Court rendered in
the Perkins's case, which reads as under :
"20.We thus have two categories of cases. The first, similar to the one dealt with in TRF Limited where the Managing Director himself is named as an arbitrator with an additional power to appoint any other person as an arbitrator. In the second category, the Managing Director is not to act as an arbitrator himself but is empowered or authorised to appoint any other person of his choice or discretion as an arbitrator. If, in the first category of cases, the Managing Director was found incompetent, it was because of the interest that he would be said to be having in the outcome or result of the dispute. The element of invalidity would thus be directly relatable to and arise from the interest that he would be having in such outcome or decision. If that be the test, similar invalidity would always arise and spring
even in the second category of cases. If the interest that he has in the outcome of the dispute, is taken to be the basis for the possibility of bias, it will always be present irrespective of whether the matter stands under the first or second category of cases. We are conscious that if such deduction is drawn from the decision of this Court in TRF Limited, all cases having clauses similar to that with which we are presently concerned,a party to the agreement would be disentitled to make any appointment of an Arbitrator on its own and it would always be available to argue that a party or an official or an authority having interest in the dispute would be disentitled to make appointment of an Arbitrator."
19. A reading of the said paragraph would makes it clear
that even, if, the General Manager was not the Arbitrator
himself, by virtue of being an employee of the Railways he
would become ineligible to appoint another Arbitrator also.
20. However, the Hon'ble Supreme Court in a
subsequent decision which is also rendered by the three
Judges Bench in the case of Central Organisation For Railway
Electrification v. ECI-SPIC-SMO-MCML (JC) A Joint Venture
Company, reported in(2020) 14 SCC 712, has considered both
TRF Ltd.,'s case and Perkins's case and has held as follows :
34. Considering the decision in TRF Limited, in Perkins Eastman Architects DPC and another v. HSCC (India) Limited, the Supreme Court observed that there are two categories of cases. The first, similar to the one dealt with in TRF Limited where the Managing Director himself is named as an arbitrator with an additional power to appoint any other person as an arbitrator. In the second category, the Managing Director is not to act as an arbitrator himself; but is authorized to appoint any other person of his choice or discretion as an arbitrator. Observing that if in the first category, the Managing Director was found incompetent similar invalidity will always arise even in the second category of cases, in para 20 in Perkins Eastman, the Supreme Court held as under:-
"20. ....If, in the first category of cases, the Managing Director was found incompetent, it was because of the interest that he would be said to be having in the outcome or result of the dispute. The element of invalidity would thus be directly relatable to and arise from the interest that he would be having in such outcome or decision. If that be the test, similar invalidity would always arise and spring even in the second category of cases. If the interest that he has in the outcome of the dispute, is taken to be the basis for the possibility of bias, it will always be present irrespective of whether the matter stands under the first or second category of cases. We are conscious that if such deduction is drawn from the decision of this Court in TRF Limited, all cases having clauses similar to that with which we are presently concerned, a party to the agreement would be disentitled to make
any appointment of an Arbitrator on its own and it would always be available to argue that a party or an official or an authority having interest in the dispute would be disentitled to make appointment of an Arbitrator."
35. After referring to para 50 of the decision in TRF Limited, in Perkins Eastman, the Supreme Court referred to a different situation where both parties have the advantage of nominating an arbitrator of their choice and observed that the advantage of one party in appointing an arbitrator would get counter-balanced by equal power with the other party. In para 21, it was held as under:-
"21. ....The next sentences in the paragraph, further show that cases where both the parties could nominate respective arbitrators of their choice were found to be completely a different situation. The reason is clear that whatever advantage a party may derive by nominating an arbitrator of its choice would get counter balanced by equal power with the other party"
36. As discussed earlier, after Arbitration and Conciliation (Amendment) Act, 2015, the Railway Board vide notification dated 16.11.2016 has amended and notified Clause 64 of the General Conditions of Contract. As per Clause 64(3)(a)(ii) [where applicability of Section 12(5) of the Act has been waived off], in a case not covered by Clause 64(3)(a)(i), the Arbitral Tribunal shall consist of a panel of three Gazetted Railway Officers not below the rank of Junior Administrative Grade or two Railway Gazetted Officers not below the rank of Junior Administrative Grade and a
retired Railway Officer retired not below the rank of Senior Administrative Grade Officer, as the arbitrators. For this purpose, the General Manager, Railway will send a panel of at least four names of Gazetted Railway Officers of one or more departments of the Railway within sixty days from the date when a written and valid demand for arbitration is received by the General Manager. The contractor will be asked to suggest to General Manager at least two names out of the panel for appointment as contractor's nominees within thirty days from the date of dispatch of the request from the Railway. The General Manager shall appoint at least one out of them as the contractor's nominee and will also simultaneously appoint balance number of arbitrators from the panel or from outside the panel duly indicating the "Presiding Officer" from amongst the three arbitrators so appointed. The General Manager shall complete the exercise of appointing the Arbitral Tribunal within thirty days from the date of the receipt of the names of contractor's nominees.
37. Clause 64(3)(b) of GCC deals with appointment of arbitrator where applicability of Section 12(5) of the Act has not been waived off. In terms of Clause 64(3)(b) of GCC, the Arbitral Tribunal shall consist of a panel of three retired Railway Officers retired not below the rank of Senior Administrative Grade Officers as the arbitrators. For this purpose, the Railway will send a panel of at least four names of
retired Railway Officers empanelled to work as arbitrators indicating their retirement date to the contractor within sixty days from the date when a written and valid demand for arbitration is received by the General Manager. The contractor will be asked to suggest the General Manger at least two names out of the panel for appointment of contractor's nominees within thirty days from the date of dispatch of the request of the Railway. The General Manager shall appoint at least one out of them as the contractor's nominee and will simultaneously appoint the remaining arbitrators from the panel or from outside the panel, duly indicating the "Presiding Officer" from amongst the three arbitrators. The exercise of appointing Arbitral Tribunal shall be completed within thirty days from the receipt of names of contractor's nominees. Thus, the right of the General Manager in formation of Arbitral Tribunal is counter- balanced by respondent's power to choose any two from out of the four names and the General Manager shall appoint at least one out of them as the contractor's nominee.
38. In the present matter, after the respondent had sent the letter dated 27.07.2018 calling upon the appellant to constitute Arbitral Tribunal, the appellant sent the communication dated 24.09.2018 nominating the panel of serving officers of Junior Administrative Grade to act as arbitrators and asked the respondent to select any two from the list and communicate to the
office of the General Manager. By the letter dated 26.09.2018, the respondent conveyed their disagreement in waiving the applicability of Section 12(5) of the Amendment Act, 2015. In response to the respondent's letter dated 26.09.2018, the appellant has sent a panel of four retired Railway Officers to act as arbitrators giving the details of those retired officers and requesting the respondent to select any two from the list and communicate to the office of the General Manager. Since the respondent has been given the power to select two names from out of the four names of the panel, the power of the appellant nominating its arbitrator gets counter-balanced by the power of choice given to the respondent. Thus, the power of the General Manager to nominate the arbitrator is counter-balanced by the power of the respondent to select any of the two nominees from out of the four names suggested from the panel of the retired officers.In view of the modified Clauses 64(3)(a)(ii) and 64(3)(b) of GCC, it cannot therefore be said that the General Manager has become ineligible to act as the arbitrator. We do not find any merit in the contrary contention of the respondent. The decision in TRF Limited is not applicable to the present case.
39. There is an express provision in the modified clauses of General Conditions of Contract, as per Clauses 64(3)(a)(ii) and 64(3)(b), the Arbitral Tribunal shall consist of a panel of three Gazetted Railway
Officers [Clause 64(3)(a)(ii)] and three retired Railway Officers retired not below the rank of Senior Administrative Grade Officers [Clause 64(3)(b)]. When the agreement specifically provides for appointment of Arbitral Tribunal consisting of three arbitrators from out of the panel serving or retired Railway Officers, the appointment of the arbitrators should be in terms of the agreement as agreed by the parties. That being the conditions in the agreement between the parties and the General Conditions of the Contract, the High Court was not justified in appointing an independent sole arbitrator ignoring Clauses 64(3)(a)(ii) and 64(3)(b) of the General Conditions of Contract and the impugned orders cannot be sustained."
21. As noticed by the Hon'ble Supreme Court in the
above case, the General conditions of contract of the Railways
was amended by the Railway Board on 16.11.2016 and the
amended Clause 64 provided for a situation where a party
could waive the applicability of Section 12(5) of the Arbitration
and Conciliation Act, in which the case serving Officer could be
appointed and at the same time the amended Clause also
provided for a situation where the applicability of Section
12(5) of the Arbitration and Conciliation Act had not been
waved off by the contractor.
22. The Hon'ble Supreme Court has noticed that in cases
where the applicability of Section 12(5) of the Arbitration and
Conciliation Act was not waived the arbitral Tribunal would
consist of a panel of three retired Railway Officers not below
the rank of Senior Administrator Grade Officers as the
Arbitrator. The Apex Court has noticed that for this purpose
the Railway would send a panel of at least four names of
retired Railway Officers empanelled to work as arbitrators
indicating their retirement dates to the contractor and the
contractor would be asked to suggest to the General Manager
at least two names out of the panel for appointment of
arbitrators as contractors nominee and the General Manager
was thereafter required to appoint atleast one of them as the
contractors nominee and simultaneously appoint remaining
arbitrators from the panel, duly indicating the Presiding Officer
amongst the three arbitrators. The Apex Court has concluded
that the right of the General Manager in formation of the
Arbitral Tribunal stood counter balanced by the contractors
power to chose any two from out of the four names and the
General Manager was required to appoint at least one out of
them as such Contractor nominee.
23. The Hon'ble Supreme Court has held that in view of
the modified Clause-64.3 of the GCC it could not be said that
the General Manager had become ineligible to act as the
Arbitrator and the decision in TRF Ltd.,'s case and Perkins
case was not applicable to a case concerning Clause 63 (3) of
the GCC pertaining to the Railways.
24. In the instant case, admittedly, the parties are
governed by the General conditions of contract and thus in the
light of the Judgment rendered by the Hon'ble Supreme Court
in COFRE's case, wherein judgment rendered in TRF Ltd.,'s
case and Perkins's case has been distinguished, the agreed
procedure under Clause 64 (3) of the GCC would have to be
adhered to.
25. It cannot be in dispute that the amended Clause 64
(3) would also apply to all contracts governing Railways from
16.11.2016 and thus the ratio laid down in COFRE's case will
hold the field when it comes to Railway Contracts.
26. Since in this case, the General Manager has not
acted upon the request of the petitioner, it would be necessary
to direct the General Manager to act in accordance with the
amended clause of GCC and send a panel of retired Officers in
terms of Clause 64.3(B) of the GCC within a period of 30 days
from the date of receipt of a copy of this order.
27. The contractor shall thereafter select two names
from the four suggested nominees and communicate the same
to the General Manager within 30 days from the date of
receipt of the nominees from the General Manager. There
upon the General Manager shall constitute a Arbitral Tribunal
in terms of the clause 64.3B of the GCC within a period of 30
days.
28. As regards the contention of the Railways that the
disputes have become non-arbitrable by reason of the fact
that the petitioner has given a No claim certificate is
concerned, the ratio laid down by the Apex Court in the case
of Union of India vs Parmar Constructions Company, reported
in (2019) 15 SCC 682, would apply. In para 36 it has been
stated as follows:
"36. The respondents are the contractors and attached with the railway establishment in the instant batch of appeals are claiming either refund of security deposits/bank guarantee, which has been forfeited or the escalation cost has been reduced from final invoices unilaterally without tendering any justification. It is manifest from the pleadings on record that the respondent contractors who entered into contract for construction works with the railway establishment cannot afford to take any displeasure from the employer, the amount under the bills for various reasons which may include discharge of his liability towards the bank, financial institutions and other persons, indeed the railway establishment has a upper hand. A rebutable presumption could be drawn that when a no claim has been furnished in the prescribed format at the time of final bills being raised with unilateral deductions made even that acceptable amount will not be released, unless no claim certificate is being attached to the final bills. On the stated facts, para 52(iii) referred to by this Court in National Insurance Company Limited Vs. Boghara Polyfab Private Limited (supra) indeed covers the cases of the present contractors with whom no option has been left and being in financial duress to accept the amount tendered in reference to the final bills furnished and from the discharge voucher which has been taken to be a defence by the appellants prima
facie cannot be said to be voluntary and has resulted in the discharge of the contract by accord and satisfaction as claimed by the appellants. In our considered view, the arbitral dispute subsists and the contract has not been discharged as being claimed by the appellants employer(s) and all the contentions in this regard are open to be examined in the arbitral proceedings."
29. In the light of this decision and also the decision of
the three Judges Bench in the case of Vidya Drolia and Others
v. Durga Trading Corporation, reported in (2021) 2 SCC, the
question of the contract being discharged will have to be
examined by the Arbitral Tribunal.
The petition is accordingly disposed off.
Sd/-
JUDGE CKK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!