Citation : 2021 Latest Caselaw 6426 Kant
Judgement Date : 18 December, 2021
-1-
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 18TH DAY OF DECEMBER, 2021
PRESENT
THE HON'BLE MR. RITU RAJ AWASTHI, CHIEF JUSTICE
AND
THE HON'BLE MR.JUSTICE SACHIN SHANKAR MAGADUM
WRIT PETITION NO.9540 OF 2020 (GM-MMS)
BETWEEN:
1. SRI ASHOK JOGI
AGED ABOUT 52 YEARS
S/O LATE JAGANNATHA JOGI
R/O "SHANTHA NILAYA" , PUTTHIGE
HIRIYADKA, BOMMARABETTU
UDUPI - 576 113
2. M/S.YOJAKA (INDIA) PVT. LTD.
REG. OFFICE:D.NO.3-28/43, 2ND FLOOR
ABCO TRADE CENTRE, N.H.66
KOTTARA CHOWKI
MANGALORE - 575 006
REP. BY ITS MANAGING DIRECTOR
... PETITIONERS
(BY SRI NATARAJA BALLAL A, ADVOCATE)
AND:
1. STATE OF KARNATAKA
DEPARTMENT OF MINES & GEOLOGY
1ST FLOOR, RAJATADRI, MANIPAL
UDUPI - 576 104
2. DEPUTY COMMISSIONER
UDUPI DISTRICT
RAJATADRI, MANIPAL
UDUPI - 576 104
3. COMMISSIONER
UDUPI CITY MUNICIPAL COUNCIL
UDUPI - 576 101
-2-
4. SRI KARTHIK NAYAK
MAJOR
CHIKKANSAL ROAD
GANDHI MAIDAN
KUNDAPURA - 576 201
5. SRI ARJUN MANO SHETTY
PROPRIETOR
M/S. NEMMADI CONSTRUCTIONS
KALLIANPUR, 2-4F, JAYANAGAR
SANTHEKATTE ROAD
UDUPI TQ. & DIST. - 576 114
... RESPONDENTS
(SRI S.S.MAHENDRA, AGA FOR RESPONDENT NOS.1 AND 2
SRI T.I.ABDULLA, ADVOCATE FOR RESPONDENT NO.3
RESPONDENT NO.5 - SERVED)
---
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND
227 OF THE CONSTITUTION OF INDIA PRAYING TO ISSUE A
WRIT OF CERTIORARI TO QUASH THE E-AUCTION DATED
06.08.2020 BEARING NO.DMG/SGUDUPI/NOTIFICATION/E-
AUCTION/2020-21 (ANNEXURE-A) ISSUED BY THE RESPONDENT
NO.1 OR IN THE ALTERNATIVE NOT TO REMOVE THE DESILTED/
DREDGED MATERIALS UNTIL THE COMPLETION OF THE
CRIMINAL CASE NO.PCR 295/2020 PENDING ON THE FILE
PRINCIPAL CIVIL JUDGE & JMFC, UDUPI AND ETC.
THIS PETITION COMING ON FOR ORDERS THIS DAY,
CHIEF JUSTICE MADE THE FOLLOWING:
ORDER
Heard learned counsel for the petitioners, learned
Additional Government Advocate appearing for respondent
Nos.1 and 2 and learned counsel appearing for respondent
No.3.
2. The writ petition has been filed seeking the following
reliefs:
"(a) Issue a writ of CERTIORARI to quash the e-auction dated 06/08/2020 bearing no.DMG/SGUdupi/Notification/e-auction/ 2020-21 (Annexure-A) issued by the Respondent no.1 or in the alternative not to remove the desilted/dredged materials until the completion of the criminal case no.PCR 295/2020 pending on the file Principal Civil Judge & JMFC, Udupi;
(aa) Issue a writ of CERTIORARI to quash the e-auction dated DMG/SGUdupi/ Notification/e-auction/2020-21 dated 26/08/2020 (Annexure-D) issued by the Respondent no.1 or in the alternative not to remove the desilted/dredged materials until the completion of the criminal case no.PCR 295/2020 pending on the file Principal Civil Judge & JMFC, Udupi;
(b) Issue a writ of MANDAMUS to release the amounts payable to the Petitioners for the work done vide tender no.DMA/2019- 20/OW/WORK_INDENT87330/CALL-2 dated 25/06/2019 (Annexure-B);
(c) Award costs of this proceedings;
(d) Pass such other order or orders as this Hon'ble Court deems fit in the fact and circumstances of the case in the interest of justice and equity."
3. Learned counsel appearing for respondent No.3 points
out that the Court, vide order dated 26.05.2021, had
restricted consideration of only the third prayer that is, with
regard to release of the amounts allegedly payable to the
petitioners for the work done vide Tender No.DMA/2019-
20/OW/WORK_INDENT87330/CALL-2. For convenience, the
order dated 26.05.2021 is reproduced below:
"1. The learned counsel appearing for the petitioners states that now he is not challenging the notices of e-auction which are the subject matter of challenge in prayers (a) and (aa). He states that he is seeking two prayers. The first prayer is directing the first respondent not to remove the desilted/dredged materials until the completion of trial of criminal case No.PCR/295/2020 pending in the Court of Principal Civil Judge and JMFC at Udupi. He states that the second prayer is confined to a direction to the third respondent to make payment of the amount payable to the petitioners as per the work order.
2. As far as first prayer is concerned, admittedly the petitioners are not the owners of the desilted/dredged materials. Therefore, the prayer made in the petition directing the respondents not to remove the said materials till disposal of the said criminal case cannot be granted. It is ultimately for the parties to lead evidence in the pending criminal case.
3. As regards the second prayer for the release of amount, we issue notice to the third respondent returnable on 30th June 2021. In addition to the notice through the Court, the advocate for the petitioners will serve a soft copy of the amended petition along with annexures and a soft copy of this order at email-id of Udupi City Municipal Council. On receiving the soft copy of this order along with a soft copy of this petition with annexures by email, the third respondent will be under an obligation to appear before the Court on the next date."
4. An objection has been raised by learned counsel
appearing for respondent No.3 regarding grant of a writ of
mandamus to the respondents regarding payment/release
of the amounts allegedly due to the petitioners. It is
submitted by him that in the statement of objections, it is
the specific case of respondent No.3 that the amounts
claimed by the petitioners are disputed amounts.
Moreover, as per the contract, there is an arbitration clause
and in case the petitioners are aggrieved due to
non-payment of any amount, they can invoke the
arbitration clause under the contract. It is also submitted
that a criminal case is pending in this regard on the basis of
a complaint made to Lokayuktha. Lokayuktha has enquired
into the complaint and the police has submitted the report.
His submission is that in the given facts, no payment can
be made to the petitioners at this stage.
5. Learned counsel for the petitioners, on the other
hand, submits that it is only after filing of the writ petition
that the respondents have disputed the payment/release of
the due amounts. As per the terms of the contract, the
time period provided for payment is 60 days. It is also
submitted that the respondents have not disputed the
quantum of amounts to be paid, but only on the basis of
some enquiry pending with the Lokayuktha that they are
denying payment which cannot be done. In support of his
submissions, he has relied on the following judgments:
(i) UTTAR PRADESH POWER TRANSMISSION
CORPORATION LTD. AND ANOTHER vs. CG POWER AND
INDUSTRIAL SOLUTIONS LIMITED AND ANOTHER reported
in 2021 SCC ONLINE SC 383
(ii) M/S.CHAITHANYA GEO SURVEYS vs. STATE OF
KARNATAKA [Writ Petition No.10392/2020 (GM-
MMS)]
6. We have considered the submissions made by learned
counsel for the petitioners as well as learned counsel
appearing for the respondents and gone through the
record.
7. The sole question involved in the writ petition for
consideration is whether a writ Court can issue a writ of
mandamus for payment of the claimed amounts.
8. It is not in dispute that the petitioners had performed
certain work on the basis of the contract which was entered
into between petitioner No.2 and respondent No.3. It is
also not in dispute that as per the said contract, there is an
arbitration clause and in case of any dispute, the aggrieved
party can invoke the arbitration clause. The statement of
objections filed by respondent No.3 clearly indicates that in
the payment of any amount to the petitioners, several
departments are involved with respect to measurement of
work, approval and payment of the amount due.
Respondent No.3 has seriously disputed the amounts
claimed by the petitioners.
9. In this view of the matter, we are of the considered
view that the amounts claimed by the petitioners are
disputed by respondent No.3 and as such, the amount due
to the petitioners, if any, cannot be determined in a writ
Court. In case any amount is due on the basis of certain
work performed pursuant to the contract and the said
amount is 'Admitted Amount', a direction can be issued by
the writ Court for payment of the admitted amount.
However, no direction can be issued in writ jurisdiction for
payment of amount which is not admitted and rather
disputed.
10. In the case of M/S.CHAITHANYA GEO SURVEYS
(supra), the Co-ordinate Bench of this Court has considered
the issue of release of amount due to the petitioner of that
writ petition. The Court, considering the facts of the case,
has opined that in view of the order dated 06.09.2019
according approval for release of certain amount in favour
of the petitioner of that writ petition, the act of the
Competent Authority of withholding the amount which is
admittedly due to the petitioner was unfair. In paragraph
14 of the judgment, the Court has held that if the admitted
amount is not paid within the time fixed to the person
concerned, it will carry interest at the rate of 6% per
annum from the date of the order till the date of payment.
The relevant paragraphs 13 and 14 are reproduced
below:
"13. If there is a right, there should be a remedy. A writ of mandamus is issued against a person who has a legal duty to perform, but has failed or neglected to do so. In the case on hand, respondent No.2 has passed the order dated 6th September 2019 according approval for release of Rs.42,12,600/- in favour of the petitioner and a copy of the said order is forwarded to the competent authority for information and further action. It is not in dispute that the said order subsists even on this date. Inspite of the same, the payment covered under the said order has been not released in favour of the petitioner. This omission on the part of the competent authority who was obliged to comply the order dated 6th September 2019 passed by respondent No.2 to release the amount smacks of arbitrariness and unfairness. The act of the Competent Authority
of withholding the amount which is admittedly due to the petitioner as per the order dated 6th September 2019 is unfair. Similarly, the invoices raised by the petitioner for payment of Rs.6,60,800/- and Rs.1,42,910/- has been forwarded by respondent No.3 to respondent No.2 with a request to take appropriate action for release of the amounts covered under the said invoices. The petitioner, thereafter, has made representations as per Annexures-H & H1 both dated 17th April 2020 requesting respondent No.2 to take appropriate action for release of the payments. The respondent No.2 is duty bound to consider the said representations made by the petitioner. Under the circumstances, we are of the considered view that the petitioner has made out a case for issuing appropriate directions to the concerned respondents/competent authority.
14. If the admitted amount is not paid within the time fixed under this order, it will carry interest at the rate of 6% per annum from the date of this order till the date of payment. Accordingly, we pass the following:
ORDER
(i) The writ petition is allowed in part;
(ii) A writ of mandamus is issued to the competent authority of respondent No.1 to release the payment covered under the office order dated 6th September 2019 vide Annexure-G issued by respondent No.2 in favour of the petitioner in respect of conducting drone survey in 18 'C' Category mines;
(iii) The respondent No.2 is directed to consider the representations at th Annexures-H & H1 dated 17 April 2020 submitted by the petitioner in the background of the communications issued by respondent No.3 at Annexures-E & F
- 10 -
dated 4th September 2019 and 13th September 2019, respectively, for release of payments in respect of other two invoices;
(iv) The aforesaid directions shall be complied within a period of two months from the date of receipt of a copy of this order;
(v) On the failure to release the amount as mentioned in clause (ii) within the stipulated time, the same shall be paid with interest at the rate of 6% per annum from the date of this order till the date of payment."
11. In the present case, the amounts in question which
are claimed by the petitioners are disputed by respondent
No.3 and there is no order for release/approval of the
amounts and as such, the said judgment cited by the
petitioners is of no help to them.
12. In the case of UTTAR PRADESH POWER
TRANSMISSION CORPORATION LTD. (supra), the Apex
Court has held that even though there is an arbitration
clause, the Corporation has not opposed the writ petition on
the ground of existence of an arbitration clause. There is no
whisper of any arbitration agreement in the counter
affidavit filed by UPPTCL to the writ petition in the High
Court. In any case, the existence of an arbitration clause
does not debar the Court from entertaining a writ petition.
- 11 -
Paragraph 67 of the judgment is relevant which is
reproduced below:
"67. Even though there is an arbitration clause, the Petitioner herein has not opposed the writ petition on the ground of existence of an arbitration clause. There is no whisper of any arbitration agreement in the Counter Affidavit filed by UPPTCL to the writ petition in the High Court. In any case, the existence of an arbitration clause does not debar the court from entertaining a writ petition."
13. There is no dispute to the legal proposition laid down
by the Apex Court that even in case of existence of an
arbitration clause, a writ petition can be entertained.
However, it will depend on the facts and circumstances of
the case as to whether a writ petition can be entertained or
not.
14. In view of the above, we are of the considered view
that in the given facts and circumstances of the case, no
writ of mandamus can be issued to the respondents to
make payment of the amounts claimed by the petitioners
on the basis of certain work done by them vide tender
No.DMA/2019-20/OW/WORK_INDENT87330/CALL-2 dated
25.06.2019. The writ petition as such is dismissed.
- 12 -
15. The pending interlocutory application does not
survive for consideration and stands disposed of.
Sd/-
CHIEF JUSTICE
Sd/-
JUDGE
AHB
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!