Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ranchi Municipal Corporation vs M/S A2Z Waste Management (Ranchi) ...
2025 Latest Caselaw 175 Jhar

Citation : 2025 Latest Caselaw 175 Jhar
Judgement Date : 6 May, 2025

Jharkhand High Court

Ranchi Municipal Corporation vs M/S A2Z Waste Management (Ranchi) ... on 6 May, 2025

Author: Rajesh Shankar
Bench: Rajesh Shankar
                                              2025:JHHC:13549-DB




IN THE HIGH COURT OF JHARKHAND AT RANCHI
                I.A. No. 12521 of 2024
                      In/and
            Commercial Appeal No. 16 of 2024
                      and
            Commercial Appeal No. 16 of 2024

Ranchi Municipal Corporation, having its office at Kutchery Road, P.O.
G.P.O., P.S. Kotwali, District Ranchi, Jharkhand through its
Administrator, Sri Sandeep Singh son of Sri Vijay Pal Singh aged about
40 years resident of Jawahar Nagar, Kanke Road, P.O. Gonda & P.S.
Gonda, District : Ranchi                    ...     ...  Appellant
                          Versus
M/s A2Z Waste Management (Ranchi) Limited, a Company incorporated
under the Companies Act, 1956 having its registered office at O-116,
First Floor, DLF Shopping Mall, Arjun Marg, DLF, Phase-I, Gurgaon,
P.O. & P.S. Gurgaon, District Gurgaon, Haryana, PIN-122002.
                                                ... Respondent
                          with
             Commercial Appeal No. 3 of 2024
M/s A2Z Waste Management (Ranchi) Limited, a Company incorporated
under the Companies Act, 1956 having its registered office at O-116,
First Floor, DLF Shopping Mall, Arjun Marg, DLF, Phase-I, Gurgaon,
P.O. & P.S. Gurgaon, District Gurgaon, PIN-122002, State of Haryana,
through its Authorized Signatory, namely, Vishal G Gussain, aged about
26 years, Son of Chandan Singh Ghurdaura, resident of Flat No. 427, P
And T Flats, R.K. Puram, Sector-6, Postal Sb, P.O. and P.S.-R.K. Puram,
New Delhi, Pin Code-110022.                 ....    ...  Appellant
                          Versus
Ranchi Municipal Corporation, through its Municipal Commissioner,
having its Registered office at Kutchery Road, P.O. G.P.O., P.S. Sukhdeo
Nagar, District Ranchi, Jharkhand, PIN - 834001 ...      Respondent
                          ---------
CORAM: HON'BLE THE CHIEF JUSTICE
             HON'BLE MR. JUSTICE RAJESH SHANKAR
                          ---------
For the Appellant         : Mr. Sachin Kumar, Advocate
                            Mr. Sashank Sekhar, Advocate.
For Respondent            : Mr. Sumeet Gadodia, Advocate.
                            [Commercial Appeal No. 16 of 2024]
For the Appellant         : Mr. Sumeet Gadodia, Advocate.
For Respondent            : Mr. Sachin Kumar, Advocate
                            Mr. Sashank Sekhar, Advocate.
                            [Commercial Appeal No. 3 of 2024]
                          ---------
C.A.V. On: 17.04.2025                  Pronounced On: 6.5.2025




                         -1 of 14-
                                                  2025:JHHC:13549-DB




M.S. Ramachandra Rao, C.J. (Oral)

Commercial Appeal No. 3 of 2024 is filed by M/s A2Z Waste

Management (Ranchi) Limited against the Ranchi Municipal Corporation (for

short the RMC) challenging the judgment dt. 05.01.2024 in Commercial

Arbitration Case No. 11 of 2023 of the Additional Judicial Commissioner-III-

cum-Presiding Officer, Commercial Court, Ranchi under Section 37 of the

Arbitration and Conciliation Act, 1996 (for short 'the Act').

2. The same judgment is also questioned by the RMC in Commercial

Appeal No. 16 of 2024, but the said appeal has been filed under Section 37 of

the Act with a delay of 320 days and I.A. No. 12521 of 2024 is filed by it

under Section 5 of the Limitation Act, 1963 to condone the said period of

delay.

3. Since both appeals arise out of the same judgment, we deem it desirable

to decide these matters together.

The Background facts

4. An agreement dt. 29.01.2011 was entered into by the RMC with M/s. A

to Z Infrastructure Limited for a project dealing with Municipal Solid Waste

Management in Ranchi after a process of tendering in which M/s. A to Z

Infrastructure Limited was the successful bidder.

5. M/s. A to Z Infrastructure Limited established a special purpose vehicle

namely M/s. A to Z Waste Management, Ranchi Limited (for short

'Contractor') and a Concessionaire agreement was formalized on 03.06.2011

with retrospective effect from 01.04.2011.

6. In the course of execution of the contract, disputes arose between the

parties and the Contractor terminated the contract on 27.12.2013 citing clause

-2 of 14- 2025:JHHC:13549-DB

9.2 (C) and invoked the arbitration clause Article 11.2 (a) of the

Concessionaire agreement dt. 03.06.2011 on 07.04.2014.

7. The Contractor appointed its nominee arbitrator and requested the RMC

to appoint their arbitrator.

8. As RMC failed to appoint its nominee arbitrator the Contractor

approached the High Court of Jharkhand by filing Arbitration Application No.

3 of 2015. The High Court appointed Shri S. K. Murari as a nominee

arbitrator on behalf of RMC.

9. Subsequently, both arbitrators appointed Justice S.B. Sinha, Former

Judge of the Supreme Court of India as Presiding Arbitrator.

10. The parties submitted their claims, objections and counter claims and

presented oral and documentary evidence to support their respective positions.

The Arbitral Award

11. On 11.05.2018, arbitral award was passed in favour of the Contractor

directing RMC to pay Rs.6,41,24,500/-. The summary of the arbitral Award is

as under: -

Claims and order of the learned Arbitral Tribunal-


Sl.        Claim Brief Description Amount of        Whether    If Allowed       Remarks If
           No. of Claims           Claim (In Rs.)   Claim       for What        any
No                                                  Allowed    amount
                                                    or
                                                    Rejected
                                                    or
                                                    modified
 1         Claim Failure to make   Rs.1,71,95,156   Allowed    Rs.1,71,95,156
           No. 1 payments for the
                 monthly bills
                 submitted towards
                 tipping fees for
                 collection and
                 transportation of
                 MSW for the
                 period for the
                 period for


                                   -3 of 14-
                                                    2025:JHHC:13549-DB




           01.04.2011 to
           31.12.2013
2.   Claim Failure to make                   Rejected
     No. 2 payments towards
           investment over
           Capital Grant for
           the vehicles,
           equipment and
           assets engaged in
           C&T operations.
3.   Claim Failure to make                   Rejected
     No. 3 payments towards
           investment over
           Capital Grant for
           development of T
           &
           D facility
4.   Claim Illegal encashment                Rejected            Encashment
     No. 4 of Performance                    (appropriat         not illegal.
           Security Bank                     ed towards          Respondent
           Guarantee of the                  general             was entitled
           Contractor by the                 damages)            to invoke
           Respondent                                            Bank
                                                                 Guarantee.
5.   Claim Claim for                         Rejected
     No. 5 reimbursement of
           additional cost
           incurred by the
           Contractor on
           account of Force
           Majeure, change in
           law and
           Government
           policies resulting
           in material adverse
           effect on the
           operating cost of
           the Contractor
6.   Claim Termination                       Rejected
     No. 6 charges due to
           RMC Event of
           Default as per
           Article 9.2 (f) (i)
7.   Claim Accrued losses due                Rejected            Contractor
     No. 7 to non-production                                     itself is
           of compost & RDF                                      guilty of
           during the                                            breach of
           Operational Period                                    guilty of
           (April 11 to Dec.                                     contract.
           13) due to delay in
           handing over of
           land for MSW
           Waste Processing
           Project.
8.   Claim For opportunity                   Rejected
     No. 8 losses due to
           cancellation of the


                                 -4 of 14-
                                                       2025:JHHC:13549-DB




          contract during the
          remaining
          concession period
          (Jan 14 to Mar 14)
9. Claim Loss of Goodwill                    Rejected
    No. 9 & Reputation of
          the company
10. Claim Interest on the                    Allowed                         Contract
    No. above sums from                                                      envisages
    10    the date the same                                                  15 %
          became due till the                                                interest.
          date of payment.
11. Claim On account of       Rs.25,00,000/-
    No. costs of
    11    Arbitration
          Arbitral Fee not    Rs.30,00,000/-
          paid by
          Respondent
          Nominal Damages INR 2,00,00,000/



Counter-Claims and order of the learned Arbitral Tribunal-

Counter-Claim No. Particulars Amount Award

Counter Claim No. A Loss/damage/injury to Rejected.

Respondent's image in the eyes of Government and public.

Counter Claim No. B Refund of Rs.18,00,96,225 Rejected.

paid towards C &T and P &D operations alongwith SBI Prima Lending Rate the amount of loss incurred upon Capital expenditure.

Counter Claim No. C Refund of Rs.17,65,166/- on Counter claim for account of expenditure Rs.17,65,166/- Allowed. towards initiation of Special drive for Zone I, II and III due to lockout in the Contractor Company Counter Claim No. D Legal expenses likely to be Rejected.

incurred on account of the Respondent being impleaded Held-the matter is still as a party in MSW pending pending in a proceeding Labour Court Ranchi wherein before Labour Court, labour employed by the Ranchi. The counter Contractor are claiming Contractor is to show that it unpaid wages to the extent of is not a necessary party nor it Rs.1 Crore. is liable to pay. Counter Claim No. E Refund of Rs.37,00,000/- on Rejected.

account of direction given to the Respondent to pay the said sum pursuant to n Audit carried out by the CAG.

-5 of 14- 2025:JHHC:13549-DB

Counter Claim No. F Sum of Rs.125 Crore for Rejected.

preparation of DPR.

Counter Claim No. G Refund of sum of Rs.100 Rejected.

crore incurred by the Respondent on account of preparation of fresh tender and DPR for the new incumbent, considering after the closure of JuNURM Scheme, all the grants under the said Scheme have been withdrawn.

Counter Claim No. H Refund of Rs.24,85,73,552/- Rejected.

paid to the Contractor towards tipping fee under the JuNURM Scheme.

Counter Claim No. I Refund of Rs.100 Crores on Rejected account of loss due to cancellation of the remaining period of Concession period (January 2014 to March 2014).

Counter Claim No. J A sum of Rs.10,00,00,000/- Rejected.

on account of loss of goodwill and reputation along with 15 % interest.

Counter Claim No. K A sum of Rs.50,00,000/- for Rejected.

frivolous litigation.

Counter Claim No. L Pre Arbitration, Pendent elite Rejected.

and Future Interest of 25 % General Damages INR 3,50,00,000/-

The Section 34 Application of RMC

12. The RMC filed an application under Section 34 of the Arbitration and

Conciliation Act, 1996 before the Additional Judicial Commissioner-III-cum-

Presiding Officer, Commercial Court, Ranchi which was initially numbered as

Commercial Suit Case No. 04 of 2018 and later re-numbered as Commercial

Arbitration Case No. 11 of 2023.

13. As many as 61 grounds were raised by the RMC before the Commercial

Court.

14. The Contractor refuted the said contentions of RMC in Commercial

Court contending that grounds raised by the RMC in the Section 34

-6 of 14- 2025:JHHC:13549-DB

application are outside the scope of Section 34 of the Act; some of the

grounds require re-appreciation of facts/evidence which cannot be done in the

Section 34 application and the arbitral tribunal has dealt with these aspects in

detail.

15. It was also contended that the arbitral tribunal is a sole judge of the

quantity and quality of evidence before it and factual conclusions arrived at by

the arbitral tribunal cannot be questioned.

16. According to the Contractor, contractual interpretation is the

prerogative of the arbitral tribunal and ought not to be interfered with unless,

it is shown to be of such a nature that it shocks the conscience of the Court

and that the arbitral tribunal has found that there is a breach by both the RMC

and the Contractor. The Contractor therefore prayed for the dismissal of the

application under Section 34 filed by the RMC with cost.

The decision of the Commercial Court

17. The Commercial Court noted the 44 decisions cited by both sides

before it.

18. It rejected the plea of limitation raised by the Contractor who contended

that the application under Section 34 is time-barred.

19. The Commercial Court considered the said decisions and concluded

that under Section 34 of the Act scope of challenge to an arbitral award is very

narrow and no party should be permitted to re-argue or re-agitate the

submissions raised before the arbitrator; and a possible view by the arbitrator

on facts has necessarily to pass Muster as the arbitrator is the sole judge of the

quantity and quality of evidence.

-7 of 14- 2025:JHHC:13549-DB

20. It also held that every error of law committed by the arbitral tribunal

would not fall within the expression patent illegality and a patent illegality

should be such as to go to the root of the matter.

21. According to it, no re-appreciation of evidence is permitted, since the

Court does not sit in appeal against the arbitral award; contractual

interpretation is the sole prerogative of the arbitral tribunal; and determination

of damages need not necessarily be done and the guest estimates (honest guess

work) is permitted, where damages are awarded.

22. While applying the above principles to the arbitral award challenged

before it by the RMC, in Para V at page 59 of its order, the Commercial Court

noted that of all the grounds mentioned in Section 34, no ground has been

advanced except the argument that it is against public policy of India with its

explanation and that the term public policy of India covers a wide

connotation.

The Commercial Court then contradicted itself in Para VI by saying

that the counsel for the RMC had not stated much in explicit terms about the

award being against the public policy.

23. It also stated that much of the argument advanced by the RMC was

devoid of merit and cannot be considered in isolation.

24. It then referred to Para 230 of the arbitral award where the arbitral

tribunal was considering the claims made by the Contractor regarding "Failure

to make payments towards investment over Capital grant for the vehicles,

equipment and assets engaged in C & T Operations" i.e. the Contractor had

contended that it had procured a large number of vehicles and incurred to

expenditure of Rs.1.68 crores.

-8 of 14- 2025:JHHC:13549-DB

The arbitral tribunal rejected the said claim and observed at Para 230

that the registration numbers of the vehicles provided by the Contractor to

RMC on verification showed that some of the registration numbers were of

two wheelers and others were found to be non-existent.

The arbitral tribunal held that the Contractor was guilty of

committing fraud and fraud would vitiate all solemn acts and so the

Contractor is not entitled to any amount regarding this claim.

The Commercial Court applied this finding on that particular claim

No.2 regarding supply of vehicles to the entire award and set aside the entire

arbitral award even on other claims awarded in it's favor by the arbitral

tribunal such as 'tipping fee for collection and transportation of MSW',

nominal damages and costs, which is entirely different and which are covered

by other claims.

Also the Commercial Court set aside even that portion of the award of

the arbitral tribunal awarding certain counter claims in favor of the RMC.

The Contractor's Appeal under Section 37 of the Act

25. Challenging the arbitral award, the Contractor has filed Commercial

Appeal No. 3 of 2024.

RMC's Appeal under Section 37 of the Act with application under

Section 5 of the Limitation Act

26. To the extent the Commercial Court set aside the entire award including

the award of counter claims by the arbitral tribunal to the RMC, the RMC

filed Commercial Appeal No. 16 of 2024 but with a delay of 320 days and had

filed I.A. No. 12521 of 2024 for condonation of the said delay under section 5

of the Limitation Act,1963.

-9 of 14- 2025:JHHC:13549-DB

Consideration by the Court

27. We may point out that claim 1 dealt with 'delay in payment of tipping

fee' which is governed by Article 7.3 of the concessionaire agreement.

The arbitral tribunal held that non-payment of the tipping fee for

December, 2013 and delay in payment of the tipping fee from April, 2011 to

August, 2011 is established and in this regard there was a breach of contract

on the part of the RMC.

28. The claim regarding 'supply of vehicles' has nothing to do with claim

for 'non-payment of the tipping fee' made by the Contractor before the

arbitral tribunal and the former had admittedly not been granted by the arbitral

tribunal to the Contractor on the ground of fraud.

29. When the claims are unrelated to each other, on the basis of a fraud

with regard to the claim regarding procurement of vehicles, the Commercial

Court could not have interfered with the arbitral award with regard to the

award of the claim to the Contractor regarding tipping fee.

30. In our opinion, this is a perverse approach.

31. Also, the arbitral tribunal had granted Rs.2 crores by way of nominal

damages to the Contractor instead of Rs.9,62,04,313/- towards another claim

for C&T operations and also costs of Rs.55 lacs.

32. The counsel for the Contractor contended that this aspect has been dealt

with in Para 475 and is not linked in any way with the 'supply of vehicles

aspect' and the Commercial Court erred in interfering with the award of

damages of Rs.2 crores on this count. We agree with the said submission.

33. The award of costs of Rs.55 lacs was made in favor of the Contractor

on the ground that the RMC, despite the mandate of the arbitral tribunal,

-10 of 14- 2025:JHHC:13549-DB

refused to pay the arbitral fee of Rs.30 lacs to each of the members of the

arbitral tribunal, which the Contractor had to pay, and it was therefore held

entitled to the said amount by the arbitral tribunal.

Cost of Rs. 25 lacs was also awarded to the Contractor against the

RMC.

34. This aspect of award of costs of Rs.55 lacs has also no relation to the

findings of the arbitral tribunal about fraud being made by the Contractor with

regard to claim of 'procurement of vehicles'.

35. We are therefore satisfied that the award of the arbitral tribunal, in so

far as the Contractor is concerned, was erroneously interfered with by the

Commercial Court in a perverse manner.

36. Therefore to the extent the Commercial Court interfered with the award

of the arbitral tribunal in favour of the Contractor, its judgment is set aside.

Commercial Appeal No.3 of 2024 is allowed.

I.A. No. 12521 of 2024 In/and Commercial Appeal No. 16 of 2024

37. Coming to the appeal filed by the RMC as per Section 13 (1-A) of the

Commercial Court's Act, 2015, an appeal can be preferred from a judgment of

a Commercial Court at the level of District Judge exercising original civil

jurisdiction to the Commercial Appellate Division of the High Court within 60

days from the date of judgment or order.

38. This aspect came to be considered in the judgment of the Supreme

Court in the State of Maharashtra-Vs.-Bose Brothers Engineers &

Contractors Private Limited1.

(2021) 6 SCC 460

-11 of 14- 2025:JHHC:13549-DB

In the said judgment the Supreme Court considered the provisions

of Commercial Court's Act as well as the Arbitration & Conciliation Act,

1996 and concluded that the object and context of the said statute is speedy

disposal of appeals filed under Section 37 of the Arbitration and Conciliation

Act, 1996; the delay beyond 90 days, 30 days or 60 days, respectively, is to be

condoned by way of exception and not by way of Rule; in a fit case in which a

party has otherwise acted bona fide and not in a negligent manner, a short

delay beyond such period can, in the discretion of the court, be condoned.

In Para 15 of the said judgment, the Supreme Court held that the

expression 'sufficient cause' in section 5 of the Limitation Act, 1963 is not

elastic enough to cover long delays beyond the period provided by the appeal

provision itself; and that the expression sufficient cause is not itself a loose

panacea for the ill of pressing negligent and stale claims.

39. In other words, the Supreme Court indicated that in exercise of power

under Section 5 of the Limitation Act, 1963, a delay beyond the period of 60

days from the date on which the appeal could have been filed, can be

condoned i.e. delay below 120 days from the date of pronouncement of the

judgment by invoking Section 5 of the Limitation Act, 1963.

40. But where there is negligence, inaction or lack of bona fides, such

power ought not to be exercised. It also held that merely because the

Government is involved, a different yardstick for condonation of delay cannot

be laid down.

41. In Jharkhand Urja Utpadan Nigam Limited and Another-Vs. M/s.

Bharat Heavy Electricals Limited, Commercial Appeal No. 1 of 2025 a

Division Bench of this Court has also taken the same view by following the

-12 of 14- 2025:JHHC:13549-DB

judgment of the Supreme Court and held that the rule laid down by the

Supreme Court equally apples to instrumentalities of Government like the

applicant in the Commercial Appeal No. 16 of 2024 i.e. the RMC.

42. In I.A. No. 12521 of 2024 filed under section 5 of the Limitation

Act,1963 for condonation of delay of 320 days in filing the Commercial

Appeal, the stand of the RMC is that the judgment dt. 05.01.2024 of the

Commercial Court was challenged by the Contractor in Commercial Appeal

No. 3 of 2024 which was taken up on 16.10.2024; and at that time, the

applicant in the delay application revisited the judgment of the Commercial

Court and discovered that the entire award including counter claims granted in

its favour had been set aside, though there was no discussion in the entire

judgment of the Commercial Court as far as counter claims are concerned.

43. It is also contended that the delay in filing the appeal is not intentional

but bona fide, and the applicant was prevented by sufficient cause from filing

the appeal within time, that it was pursuing the matter diligently and so the

delay in filing the appeal of 320 days is to be condoned.

44. The explanation offered by the applicant, RMC for filing the appeal

with a delay of 320 days is not bona fide because no valid reason is found

therein.

45. When the judgment of the Commercial Court was received by its

counsel in the said court and forwarded to it, then itself, the applicant or its

counsel should have detected the error in the judgment of the Commercial

Court, and taken steps to file the appeal within 60 days or within 120 days

from 05.01.2024.

-13 of 14- 2025:JHHC:13549-DB

46. However, the appeal was filed on 21.11.2024, more than six months

later than the last date for filing the appeal.

47. We therefore hold that the applicant, RMC did not provide any

sufficient cause for condoning the said period of delay of 320 days in filing

the Commercial Appeal No. 16 of 2024 against the judgment of the

Commercial Court dt. 05.01.2024 in Commercial Arbitration Case No. 11 of

2023.

48. Therefore, I.A. No. 12521 of 2024 in Commercial Appeal No. 16 of

2024 is dismissed. Consequently, Commercial Appeal No. 16 of 2024 is

dismissed.

49. However, Commercial Appeal No. 3 of 2024 filed by the Contractor is

allowed for the reasons indicated above. No costs.

(M. S. Ramachandra Rao, C.J.)

(Rajesh Shankar, J.) APK

-14 of 14-

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter