Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Respondent/ vs Jamshedpur Waste Processing Company ...
2025 Latest Caselaw 3502 Jhar

Citation : 2025 Latest Caselaw 3502 Jhar
Judgement Date : 26 March, 2025

Jharkhand High Court

Respondent/ vs Jamshedpur Waste Processing Company ... on 26 March, 2025

Author: Deepak Roshan
Bench: Deepak Roshan
 IN THE HIGH COURT OF JHARKHAND AT RANCHI
           Commercial Appeal No. 16 of 2020
Special Officer, Jamshedpur Notified Area Committee-cum-Nodal
Officer, Jamshedpur Urban Agglomeration (JUA) having registered Office
at Kalimati Road, At, P.O. and P.S.-Sakchi, Jamshedpur
                                      ...  Respondent/Applicant/Appellant
                           Versus
Jamshedpur Waste Processing Company Pvt. Ltd., now known as SMPL
Infrastructure Ltd., through Deepak Sethi, son of Anil Kumar Sethi,
resident of B-9, Epsilon Ventures, Yamlur Main Road, P.O.-Merathauli
Fort, P.S.-Hal, District-Banglore, having registered office at No-8 Floor,
80 H Main Road, P.O.-Indranagar, P.S.-Jeevan Bima Nigam, Indranagar,
Hal 3rd Stage, Banglore and Corporate Office at F-27/2, Okhla Industrial
Area, P.O.-Kaluaji, P.O.-Okhla Industrial Area, District-New Delhi.
                                    ...   Claimant/Respondent/Respondent
                           ---------
CORAM:              HON'BLE THE CHIEF JUSTICE
              HON'BLE MR. JUSTICE DEEPAK ROSHAN
                           ---------
For the Appellant:         Mr. Krishna Kumar, Advocate
                           Mr. Vijay Kumar Roy, Advocate
For the Respondent:        Mr. Arpan Mishra, Advocate
                           ---------
Reserved on: 25.02.2025                      Pronounced on: 26/03/2025
Per M.S. Ramachandra Rao, C.J.

1. This appeal has been filed under Section 13(1A) of the Commercial

Courts Act, 2015 challenging the judgment dt. 24.01.2020 of the District

Judge-I-cum-Commercial Court, East Singhbhum at Jamshedpur in

Revocation (Arbitration) Case No.10 of 2019.

Background facts

2. After a competitive bid process, a Letter of Acceptance was issued

on 02.07.2012 to the respondent and M/s. SPML Infra Ltd for setting up

an Integrated Solid Waste Management Facility under jurisdiction of

Jamshedpur Urban Agglomeration.

3. Thereafter a Concession Agreement dt. 08.08.2012 was entered

into by the appellant with the respondent M/s SPML Infra Limited.

4. Clause 3.1 of the said Agreement required the appellant to hand

over to the respondent and other members of the consortium within 30

days from the appointed date, vacant and peaceful physical possession of

the identified Project Site for the purpose of construction, operation and

maintenance of Transfer Stations, Workshop Facility for Vehicle

Maintenance, Integrated Solid Waste Management Facility site for

Development of Compost Plant, Brick Making Plant, RDF Plant and

Sanitary Landfill Facility and also Secondary Storage depots for all areas

under jurisdiction of Jamshedpur Urban Agglomeration.

5. As per sub clause (b) of Article 3.1, the total land identified at

Mouza Khairbani for development of Integrated Solid Waste Management

Facility is about 36 acres and the said clause also stated that additional

land, if required, would be provided by the appellant from time to time.

6. Sub clause (c) of Article 3.1 stated that upon the Project Site being

handed over pursuant to sub clause (a) of Article 3.1 of the Concession

Agreement, the Concessionaire shall, subject to provisions of Article 5,

have the right to enter upon, occupy and use the same and to make at its

own cost, charges and expenses such investigation, clearance of existing

waste, remediation, development and improvements in the Project Site as

may be necessary or appropriate to implement a project in accordance

with the provisions of the Agreement.

7. Sub clause (d) of Article 3.1 of the Agreement stated that in case of

any delay by the appellant in handing over the Project Sites to the

Concessionaire, the time period for COD-T&D will be adjusted

accordingly with mutual agreement between the parties.

8. Article 11.2 of the Concession Agreement contained the arbitration

clause.

9. After the disputes arose between the parties, it appears that one of

them filed an Arbitration Application No. 21 of 2014 before this High

Court under sections 11 (5) and (6) of the Act for appointment of an

Arbitrator and Justice Amareshwar Sahay (Retd. Judge) was appointed as

Sole Arbitrator to adjudicate the disputes between the appellant and the

respondent.

The stand of the respondent/claimant before the arbitrator

10. Before the Arbitrator, the main point of issue, according to the

respondent, was that out of six major land passages, that were required to

be handed over to the respondent, the appellant had failed to hand over 5

sites required for the establishment of the Transfer Stations; the land,

which was handed over for establishment of the Project of the Integrated

Solid Waste Management Facility, was also insufficient since out of total

36 acres of land, possession of which was required to be handed over, only

30.39 acres were provided; and even the said 30.39 acres of land was not

free from encumbrances as there were several encroachments and

structures standing thereon over an area of 5.00 acres.

11. The respondent also contended that there was a village road

passing through the Project Site, which was dividing the land into two

parts.

12. According to the respondent, it had attempted to start the

construction of boundary walls over the 25 acres of available land, but

even that work was forcibly stopped several times due to protest,

agitations and obstructions from the local villagers and even the police

support that was provided by the appellant on few occasions did not yield

any result.

13. The respondent contended that as per the Agreement, it was the

fundamental obligation of the appellant to provide peaceful physical

possession of the Project Site free from all hindrances, but since the

appellant had failed to hand over the sites as required, it was in serious

breach of the terms of the Agreement which forced the respondent to

terminate the said Agreement.

14. The respondent also contended that repeated correspondences

made by it for handing over of the Project Site, release of the termination

payments, performance and bank guarantee etc. and for appointment of

Arbitrator did not yield any result and so, they filed the application under

Section 11 of the Act. The respondent made the following claims before

the learned arbitrator :-

Claim                       Amount                    Interest Amount
                                                       @ 15%
Claim for payment of Rs.1,16,57,989/-                 Rs.31,50,960/-
Termination Payment (Rupees One Crore                 (Rupees Thirty One
                     Sixteen Lac Fifty Seven          Lac Fifty Thousand
                     Thousand           Nine          Nine     Hundred &
                     Hundred & Eighty                 Sixty)
                     Nine)
Claim for Loss of Rs.15,00,00,000/-                   NIL
Profit               (Rupees Fifteen Crore)
Refund    of    Bank Rs.1,66,00,000/-                 Rs.14,66,201/-
Guarantee            (Rupees One Crore                (Rupees Fourteen Lac
                     Sixty Six Lac)                   Sixty Six Thousand
                                                      Two Hundred & One)





 Claim                 for Rs.14,93,633/- (Rupees      Rs.49,911/- (Rupees
Compensation          for Fourteen Lac Ninety         Forty Nine Thousand
bank charges              Three Thousand Six          Nine    Hundred  &
                          Hundred    &     Thirty     Eleven)
                          Three)

Balance       payments Rs.2,83,077/- (Rupees          Rs.5,40,666/- (Rupees
towards capital grant  Two Lac Eighty Three           Five     Lac    Forty
                       Thousand      Seventy          Thousand Six Hundred
                       Seven)                         & Sixty Six)
Future Interest

Cost of Arbitration       Rs.4,50,000/- (Rupees
                          Four      Lac    Fifty
                          Thousand)

The stand of the appellant before the arbitrator

15. Before the arbitrator, the appellant refuted the said contentions in

statement of defence.

16. It contended that the accusations made by the respondent with

regard to failure to provide total land or for the land being full of

encroachment etc., are things which are inevitable in the case of huge

projects; and if the respondent would have implemented the said project

work under the said agreement with strong will and intention to serve the

society apart from only attaining monetary benefits, then the project would

have been a great success.

17. The appellant in the statement of defence filed before the Arbitrator

had even admitted that they were in breach of the agreement, as they could

not hand over the land within 30 days from the appointed date as

envisaged in the agreement. They had contended that since vast

Government land was vacant for a long period of time, it was encroached

upon and the same was known to the respondent during the two years'

period of the agreement. The appellant admitted that out of 36 acres of

identified land for landfill site, 30.39 acres were handed over to the

respondent and that it was sufficient to set up plant for landfill site.

18. The appellant also contended that the land for Transfer Station and

Workshop Facility was also under process of acquisition and the same

would have been required by the respondent only in the event when they

would have started door-to-door collection activity and, therefore, the

issues made under such a head were baseless.

19. The appellant also blamed the respondent for not commencing

boundary work and contended that boundary work could not be completed

due to inefficiency of the respondent in handling any practical situation

every time as and when required.

20. The appellant also contended that as regards the issue of village

road through the Project Site, a meeting with the Deputy Commissioner

was held, and it was decided that the road would be diverted outside the

Project Site. It contended that the decision on the part of the respondent to

terminate the agreement was one-sided and the respondent did not follow

the rules regarding the same and so the termination was not accepted by

the appellant.

21. The appellant also contended by filing a counter claim that for the

purpose of initiating the project, yet again, it has become necessary to

revise the DPR; as per the revised DPR, there was an inflation in the entire

project cost leading to huge losses to the appellant amounting to

Rs.5,83,24,100/- approximately; and the appellant was also entitled for

hire charges of vehicles which had not been returned by the respondent,

amounting to Rs.37,57,224/-. It therefore, made a counter claim of

Rs.4,54,81,324/- after adjusting the bank guarantee of Rs.1,66,00,000/-.

Award of the Arbitrator

22. After noting the contentions of the parties, the learned Arbitrator

referred to Article 3 and Article 6 of the Concession Agreement and stated

that these Articles indicate the important and crucial responsibilities of the

appellant which can be said to be the backbone of the entire project

involved. He then held that the appellant had three basic and fundamental

obligations to perform:-

(i) Handing over the entire land required for different purposes

for the said project within 30 days from the date of the said

Agreement;

(ii) Should hand over the vacant and peaceful physical

possession of the said required lands for the said project; and

(iii) Removal of all the encroachments over the land required for

the said Project.

23. The Arbitrator held that it was an admitted fact that the appellant

had failed to provide the required land to the respondent within the time

stipulated in the agreement and it had delivered only Ac. 30.39 instead of

Ac.36 and even the said land was having encumbrances.

24. He also held that so far as the site for four Transfer Stations is

concerned, the appellant had admitted that the acquisition of land for these

sites were under process and the said acquisition was not even finalised

and in such a situation, the appellant cannot hand over physical possession

of the said land for setting up the four Transfer Stations.

25. He therefore, concluded that the appellant committed breach of

Article 3.1, Article 6.1(a) and Article 6.1(b) of the Agreement.

26. He thereafter concluded that the respondent was willing to execute

his part of the contract but due to non-performance of the fundamental

obligations on the part of the appellant, it was simply impossible for the

respondent to proceed any further with the work.

27. The Arbitrator also held that the termination initiated by the

respondent was in accordance with the terms and conditions of the

agreement between the parties and such termination was valid.

28. He then discussed the claims made by the respondent. The

Arbitrator held that the respondent was entitled for compensation equal to

the money spent by him for construction/upgradation of the project facility

which was not paid by the appellant as per the project milestones

estimated by the TA Cum PMC (Transaction Advisor Cum Project

Management Consultant).

29. He, therefore, awarded Rs.1,16,57,989/- along with interest upon

the same @ 15% per annum to be calculated from 25.09.2014, i.e., the

date of termination of the agreement till the date of the Award.

30. The Arbitrator declined to award any amount to the respondent

towards loss or profit because he found the said claim to be uncertain and

hypothetical. He also awarded to the respondent the amount covered by

the bank guarantee amount of Rs.1,66,00,000/-, but without interest. He

rejected the claim made by the respondent for balance payment towards

capital grants of Rs.2,83,077/-. The Arbitrator then awarded a cost of

Rs.4,50,000/- to the respondent but without any interest.

31. In para 59 of the Award, the Arbitrator rejected the separate claim

raised by the respondent regarding pendente lite and future interest on the

ground that interest upon awarded amount was already decided and that

the said issue did not require separate adjudication.

32. The counter claim made by the appellant towards increase in

project cost was rejected.

33. He also rejected the claim of the appellant for hire charges of

vehicles, which were not returned by the respondent but he granted cost of

the vehicle of Rs.20,25,000/- with interest @ 15% per annum upon it to be

calculated from the date of termination of the Agreement till the date of

the Award.

The Section 33 application filed by the respondent after passing of

award

34. After the award was pronounced by the Arbitrator, an application

under Section 33 of the Arbitration and Conciliation Act, 1996 was filed

by the respondent/Claimant contending that the Arbitrator has to pass an

additional award with regard to future interest on the already awarded

amount in exercise of power conferred under Section 33(4) of the Act.

35. It contended that in the award passed by the Arbitral Tribunal on

08.11.2017, issue regarding No.(v) for future and pendente lite interest

was not adjudicated and was omitted from consideration. It contended that

as per the award, the appellant had been directed to pay the awarded

amount within two months from the date of award, but the award does not

speak of the consequences if the appellant fails to comply with the

directions contained in the Award dt. 08.11.2017. It was further contended

that in the event of non-compliance of the directions of the Arbitral

Tribunal, the appellant should be held responsible for payment of interest

as per Section 31(7)(b) of the Act of 1996.

36. The appellant opposed the said application filed by the

respondent/Claimant contending that once the Award is declared after a

full-fledged hearing, there is no scope for passing additional award, since

the Arbitral Tribunal had not omitted to entertain the claim of the

respondent; and if the respondent was aggrieved in any manner, it should

challenge the award under Section 34 of the Act. It was also contended

that the appellant was not liable to pay any interest towards future interest.

37. The Arbitrator then passed an additional award on 27.01.2018

holding that under Section 33(4) of the Act, there is a power given to the

Arbitral Tribunal to pass an additional arbitral award; and the condition

precedent for passing such award was that when the claim was made in the

Statement of Claim during the arbitral proceeding but the Arbitral

Tribunal had omitted to pass an award in that regard.

38. The Arbitrator then observed that the consequences of non-payment

of the awarded amount by the appellant to the respondent after the

completion of two months' period from the date of award has not been

stated and appears to have been left out.

39. He, therefore, directed the appellant to pay the awarded amount as

stated in the Arbitral Award on 08.11.2017 within two months from the

date of the additional arbitral award, failing which the appellant would be

liable to pay interest @15% p.a. till the payment is made or the same is

realized in accordance with law.

The Judgment of the Commercial Court

40. Challenging both the original award dt. 08.11.2017 and the

additional award dt. 27.01.2018, the appellant filed an application under

Section 34 of the Arbitration and Conciliation Act, 1996 before the

District Judge-1-cum-Commercial Court, East Singhbhum at Jamshedpur.

It was number as Revocation (Arbitration) Case No.10 of 2019.

41. By judgment dt. 24.01.2020, the said application filed by the

appellant was dismissed by the Commercial Court.

42. The Commercial Court noted the contentions of the parties and the

findings of the Arbitrator and also the scope of Section 34 of the

Arbitration and Conciliation Act, 1996.

43. It held that the appellant failed to bring the case within the ambit of

34 of the Act and that only a bald statement has been made that the arbitral

award is against the public policy of India but no effort was made to show

as to how the award was against the public policy of India.

44. The Commercial Court also held that there is no allegation made by

the appellant that the award was induced by fraud and corruption; that the

arbitral award as well as the additional arbitral award was not in any way

contrary to substantial provisions of law or the provisions of Act.

45. It observed that in the entire pleadings, there was not a single

pleading alleging therein that the arbitral award is patently illegal or

prejudicial to the rights of the parties.

46. It held that the arbitral award and the additional arbitral award were

both reasoned orders and there was no need to interfere with the said

awards.

47. It also held that there was no cogent reason or material available on

record to set aside the original or the additional arbitral award; that there

was no error apparent on the face of the record and it also cannot be said

that the Arbitrator had not followed the statutory legal position. The

Commercial Court further held that there is no material available to prove

that the Arbitrator had mis-conducted himself or the proceedings or the

award had been improperly procured or is otherwise invalid.

Argument on behalf of the appellant

48. Challenging the said decision of the Commercial Court, the instant

appeal has been preferred by the appellant under Section 13(1A) of the

Commercial Courts Act, 2015.

49. Counsel for the appellant contended that the Arbitrator did not

consider the documents submitted by the appellant in the course of

proceedings in the right perspective; that the Commercial Court failed to

appreciate that the arbitral award and the additional award were contrary

to the facts of the agreement; that the judgment of the Commercial Court

is erroneous; Commercial Court failed to appreciate that a fraudulent act

was made by the respondent after raising false planning for termination of

the agreement; the Arbitrator and the Presiding Officer failed to consider

that 30.36 acres of land was handed over for the purpose of the project in

place of 36 acres and it was sufficient for the purpose; they failed to

consider that the appellant had requested several times by way of letters to

the respondent to continue the work but the respondent was never ready;

that the intention of the respondent from the beginning was to grab money

only; that they both acted in a one-sided manner in favour of the

respondent; and the respondent had not acted fairly as it did not wait for

amicable settlement.

Argument on behalf of the respondent

50. The counsel for the respondent refuted the said contentions and

supported the award as well as additional award of the Arbitrator and also

the judgment of the Commercial Court.

Findings of this Court

51. We shall first consider the plea of the appellant that the Arbitrator

had not waited for amicable settlement of dispute as per the provision of

the agreement before proceeding with the arbitration and pronouncing the

award.

52. Admittedly, the Arbitrator had been appointed by this Court in an

application under Section 11(5) and (6) of the Arbitration and Conciliation

Act, 1996 through an order dt. 07.04.2016 in Arbitration Application

No.21 of 2014.

53. The contention now raised by the appellant should have been raised

in the said Arbitration Application No.21 of 2014 when it was pending

before this Court. Without raising it at that time and having allowed the

appointment of Arbitrator to happen, it is not open to the appellant to raise

the said plea at this stage.

54. We have already noticed Article 3.1 of the Concession Agreement

which mandated the appellant to deliver the respondent within 30 days

from the appointed date fully vacant and peaceful physical possession of

the identified project site for implementation of the project and this was

also reiterated in Article 6.1.

55. As noted by the Arbitrator, though the appellant in Article 3 had

promised to handover land of about 36 acres to the respondent, it had

delivered only 30.39 acres of land; and even in that area, there were

encroachments to the extent of 5 acres and there was also a village road

passing through the project site.

56. In addition, there were protests, agitations and obstructions from the

local villagers.

57. The defence of the appellant was that such things are inevitable in

the case of huge projects and where there is vast government land vacant

for a long period of time, it could be encroached upon and this was known

to the respondent during the two years' period of the agreement. It was

also admitted that land for Transfer Station and Workshop Facility was not

even acquired.

58. Thus, it is clearly admitted by the appellant that it could not

handover the entire 36 acres of land within the 30 days' period from the

appointed date and even the land handed over by it was not fully vacant

nor was peaceful physical possession given as mandated in Article 3.1.

Therefore, the learned Arbitrator did not commit any error in giving a

finding that the appellant committed clear breach of Article 3.1, Article

6.1(a) and Article 6.1(b) of the Concession Agreement and this was rightly

upheld by the Commercial Court.

59. The appellant is not correct in contending that the Arbitrator or the

Commercial Court had acted contrary to the Concession agreement, that

there was a fraudulent act on the part of the respondent or that the

respondent was intent to only in making money and they had acted in a

one-sided manner.

60. The awards of the Arbitrator of the claims in the Award dt.

08.11.2017 are based on a proper appreciation of the materials on the

record and do not suffer from infirmity warranting interference by this

Court in exercise of its appellate jurisdiction.

61. But we may point out that in paragraph 59 of the arbitral award

passed on 08.11.2017, the Arbitrator had considered the claim regarding

pendente lite and future interest and specifically rejected the same on the

ground that the interest to be paid on the awarded amount had already

been decided in the earlier paragraphs and therefore did not require afresh

adjudication.

62. Having specifically rejected the same in the original award passed

by him on 08.11.2017, it was therefore not open to the Arbitrator to

entertain the application under Section 33 of the Act for the same relief on

the pretext that he had omitted to deal with this aspect in the original

award. To this extent, the additional arbitral award passed by the

Arbitrator on 27.01.2018 cannot be sustained.

63. For the aforesaid reasons, the appeal is allowed in part to the extent

of setting aside the additional arbitral award dt. 27.01.2018 passed by the

learned Arbitrator only, and the appeal is dismissed as regards challenge

to the final award dt. 08.11.2017 of the Arbitrator as confirmed by the

Commercial Court is concerned. No costs.

64. Pending Interlocutory Applications, if any, stand disposed of.

(M.S. Ramachandra Rao, C.J.)

(Deepak Roshan, J.) N.F.R. Manoj/-

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter