Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Highways Authority Of ... vs Intercontinental Consultants & ...
2025 Latest Caselaw 2969 Jhar

Citation : 2025 Latest Caselaw 2969 Jhar
Judgement Date : 28 February, 2025

Jharkhand High Court

The State Highways Authority Of ... vs Intercontinental Consultants & ... on 28 February, 2025

Author: Deepak Roshan
Bench: Deepak Roshan
 IN THE HIGH COURT OF JHARKHAND AT RANCHI
                   Commercial Appeal No. 7 of 2024
The State Highways Authority of Jharkhand through its Chief Executive
Officer, State Highways Authority of Jharkhand (SHAJ), resident of
Deendayal Nagar, Booty Road (Near office of Executive Engineer, N.H.
Ranchi Division), Ranchi-834008 Jharkhand), P.O- Ranchi University,
P.S. Lalpur                                 ...... Appellant/Applicant
                         Versus
Intercontinental Consultants & Technocrats Pvt. Ltd. A-8, Green Park,
New Delhi 110016, India in association with M/s Espana Consultants Pvt.
Ltd. Delhi, Shop No. 17 WZ-23, Jwalaheri, PaschimVihar, Delhi 110063,
India. P.O. Paschimvihar, P.S. Paschimvihar East.
                                   .... Respondent/Respondent
                         ---------
CORAM:             HON'BLE THE CHIEF JUSTICE
             HON'BLE MR. JUSTICE DEEPAK ROSHAN
                         ---------
For the Appellant:       Mr. Rajiv Ranjan, Advocate General
                         Mr. Ashutosh Anand, AAG-III
                         Mr. Sharad Kaushal, A.C. to A.A.G.-III
                         Mr. Shray Mishra, A.C. to A.G.
                         Ms. Bharti Kumari, A.C. to A.G.
For the Respondent:      Mr. Ajit Kumar, Sr. Advocate
                         Mr. Vikalp Gupta, Advocate
                         ---------

Reserved on: 12.02.2025             Pronounced on: 28 . 2 .2025
M.S. Ramachandra Rao, C.J.(Oral)

1. This Commercial Appeal is preferred under Section 13 of the

Commercial Courts Act, 2015 challenging the judgment dt. 16.03.2024 of

Additional Judicial Commissioner-III-cum-Presiding Officer,

Commercial Court, Ranchi (for short 'the Commercial Court') passed in

Commercial Arbitration Case No. 04/2022.

2. By the said judgment the Commercial Court has upheld the Award

dt. 14.12.2021 of the Arbitral Tribunal and dismissed the application

under Section 34 of the Arbitration and Conciliation Act, 1996 (in short

-1 of 7- Commercial Appeal No. 7 of 2024 'the Act') filed before the said Court by the appellant/applicant/State

Highway Authority of Jharkhand.

3. Admittedly, the appellant had entered into an agreement with the

respondent in collaboration with another for providing consultation

services relating to the Second Jharkhand State Road Project (ABD

Funded). This agreement called the 'Time-Based Contract Agreement'

was initiated on 02.11.2016 and the contract stipulated a revised price of

US$ 29,58,300.00 plus Indian Rs.30,60,60,750.00 for the execution,

completion of works, and rectification of defects, inclusive of provisional

sum and contingencies but exclusive of local indirect taxes.

4. Following the issuance of a notice to proceed on 16.11.2016, work

officially commenced on 01.12.2016. The duration of the contract was set

at 50 months including a two month pre-construction period and the

subsequent 12 month defects and liabilities period starting from the

effective date of the contract.

5. The appellant terminated the contract on 05.06.2018 allegedly due

to breach of contract by the respondent.

6. The disputes were referred to an arbitrator. Before the learned

arbitrator, the respondent raised 9 claims while the appellant raised

counter claims.

7. The decision of the Arbitral Tribunal along with 10 claims passed

in the Award is as under:

                        -2 of 7-                 Commercial Appeal No. 7 of 2024
 Claim No.      Contractor's claim Amount     Respondent's   Tribunal Assessment
                                              Assessment
                                              & Counter
                                              claim
               INR            USD                                             INR                    USD
SOC 1          --             --              Claim         Claimant's        --                     --
                                              Rejected      Claim      is
                                                            upheld
SOC 2          6,44,67,031    4,66,205        Claim                           6,44,67,031            4,66,205
                                              Rejected
SOC 3          2,26,49,000                    Claim                           2,26,49,000
                                              Rejected
SOC 4          6,27,41,094    6,39,208        Claim                           6,27,41,094            6,39,208
                                              Rejected

SOC 5                         68,00,000       Claim         Rejected          --                     --
                                              Rejected
SOC 6          1,03,42,664    82,156          Claim                           1,01,35,810            80,500
                                              Rejected
SOC7           27,79,516      9,11,386        Claim                           40,68,680              --
                                              Rejected
SOC8           65,22,000                                                      65,22,000
Sub Total      16,95,01,305   88,98,955                                       17,05,83,615           11,85,913
SOC9           12% interest   12% interest                  Interest for      2,42,04,177            1,68,269
               on the above   on the above                  INR=10 %
               sum            sum 13                        Compounded
                                                            and      for
                                                            USD=8%
                                                            compounded
                                                            per year
Counter                                                     Disallowed
claim of the
respondent
Total                                                                         19,47,87,92            13,54,182


8. The appellant questioned the same before the Commercial Court on

several grounds and the respondent refuted the said grounds.

The judgment of the Commercial Court

9. The Commercial Court first considered the scope of Section 34 of

the Act and referred to the judgments cited by both the parties on the said

aspect. It took the view that an application under Section 34 of the Act is

not an appeal and the evidence cannot be re-appreciated as in an appeal. It

also recognized that there are limited grounds specified in Section 34 of

the Act for setting aside an arbitral Award, and after quoting Section 34

of the Act, framed the question as to "whether the Award given by the

-3 of 7- Commercial Appeal No. 7 of 2024 Arbitrator is against the Public Policy of India with its explanation or it is

hit by the grounds mentioned under Section 34 of the Act?"

10. While dealing with Claim 1 which related to setting aside the

illegal termination of contract by the appellant through a letter dt.

05.06.2018, which the Arbitral Tribunal had accepted, the Commercial

Court gave a finding that the respondent had fulfilled the deliverables on

the work front; in consultancy contracts, not all personnel need to be

deployed at the initial stage and they are mobilized as necessary

according to the work requirements; and the Arbitrator had noted that

intermittent staff were deployed at appropriate intervals and that their

deployment was approved by the respondent.

11. Regarding the allegation of delay in submitting the draft inception

report, it noted that the Arbitrator had observed that submission of the

said report was not mandatory according to the appellant's letter

dt. 24.07.2017; that the appellant had not raised any objection at the time

of its delivery; and that the termination of the contract could have been

under Clause 19 of the General Conditions of Contract.

12. After discussing the terms of the contract and the findings of the

Arbitral Tribunal and also Clause 19 of the General Conditions of

Contract, the Commercial Court held that the Tribunal had succinctly

analysed the issue of termination of the contract and rightly held that such

termination was incorrect, improper and illegal. It also gave a finding

that the appellant failed to show that the findings of the Arbitral Tribunal

on this aspect warrant interference under Section 34 of the Act.

-4 of 7- Commercial Appeal No. 7 of 2024 The consideration by this Court

13. On this point, though the learned Advocate General tried to

contend that the reasoning of the Arbitral Tribunal cannot be sustained in

the light of the grounds mentioned in Section 34 of the Act, and that the

Commercial Court erred in accepting the findings of the Arbitrator as

regards the validity of the termination of the contract by the appellant on

05.06.2018, after perusing the impugned judgment of the Commercial

Court, we are unable to agree with the said submission.

14. On this aspect, the Commercial Court has considered in detail the

pleadings of the parties, the terms of the contract, the correspondence

exchanged between the parties and has given cogent reasons for agreeing

with the Arbitral Tribunal on Claim 1.

15. As regards claim no.1, it rightly held that none of the contentions

raised by the learned Advocate General on behalf of the appellant would

fall within the grounds indicated in Section 34 of the Act for interfering

with the Arbitral Award.

16. The learned Advocate General further contended that the appellant

did not get adequate opportunity before the learned Arbitrator to make

submissions on account of the fact that the arbitration commenced by

submission of the statement of claim by the respondent on 23.10.2020 at

the time when novel corona virus -19 pandemic was in vogue, and that

the Arbitrator was based in Nepal for the most part of the hearing.

This plea does not impress in as much as the statement of defence

was filed by the appellant before the Arbitrator on 21.07.2021 and

rejoinder was filed by the respondent on 11.08.2021 by which time the

-5 of 7- Commercial Appeal No. 7 of 2024 pandemic was on the wane, and there was no impediment for the parties

to participate in the arbitration proceedings which concluded admittedly

on 14.12.2021.

17. The other plea raised by the learned Advocate General on behalf of

the appellant that certain invoices were disputed but the Arbitral Tribunal

held them to be valid without any proper application of mind is also

without merit.

The Arbitral Tribunal had pointed out that it found no ground or

evidence to agree with the appellant, and that there was no evidence or

justification to say that the invoices were manufactured and concocted or

to say that the invoices are not authentic or baseless. A finding was also

recorded by the Arbitral Tribunal that invoices submitted from time to

time do not seem to have been refused by the appellant at any time during

the contract's progress.

18. Therefore we uphold the decision of the Commercial Court in so

far as it confirmed the finding of the arbitral tribunal in the award as

regards claim no.1.

19. However, we find from the judgment of the Commercial Court that

when it considered other claims i.e. Claims 2 to 9, it seems to have simply

referred to the contentions of the appellant, the response of the respondent

and the findings of the Tribunal on such claims and had abruptly

concluded without any discussion/reasoning that no case is made out for

setting aside the Award.

20. The cryptic manner in which it dealt with these claims made by the

respondent before the Arbitrator leaves much to be desired. As the first

-6 of 7- Commercial Appeal No. 7 of 2024 Court considering the application under Section 34 of the Act, the

Commercial Court is expected to deal a little more in detail and give

adequate reasons for it's conclusion on these claims within the scope of

Section 34 of the Act.

21. Therefore, we deem it appropriate to set aside judgment dt.

16.03.2024 of the Additional Judicial Commissioner-III-cum-Presiding

Officer, Commercial Court, Ranchi passed in Commercial Arbitration

Case No. 04/2022, only with regard to findings made by it on Claims 2 to

9 made by the respondent which had been allowed by the Arbitral

Tribunal in favour of the respondent.

22. For the aforesaid reasons and to the extent of it's findings on

claims 2-9, the judgment dt. 16.3.2024 of the Commercial Court in

Commercial Arbitration case no.04/2022 is set aside; the matter is

remitted back to the Commercial Court to hear both sides and pass a fresh

judgment only as regards Claims 2 to 9 made by the respondent before

the Arbitral Tribunal. The Commercial Court shall pass a fresh order after

hearing both sides within three months from the date of receipt of a copy

of this order.

23. It is made clear that this Court has not expressed any opinion on

the findings of the Arbitral Tribunal as regards Claim 2 to 9. No costs.

24. Pending Interlocutory Application, if any, stands disposed of

(M. S. Ramachandra Rao, C.J.)

(Deepak Roshan, J.)

N.A.F.R. VK

-7 of 7- Commercial Appeal No. 7 of 2024

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter