Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Damodar Ropeways And Infra Limited vs The State Of Jharkhand Through The ...
2024 Latest Caselaw 10346 Jhar

Citation : 2024 Latest Caselaw 10346 Jhar
Judgement Date : 12 November, 2024

Jharkhand High Court

M/S. Damodar Ropeways And Infra Limited vs The State Of Jharkhand Through The ... on 12 November, 2024

Author: S.N. Pathak

Bench: S. N. Pathak, Navneet Kumar

                     IN THE HIGH COURT OF JHARKHAND AT RANCHI
                                          W.P.(C) No. 3858 of 2024
                   M/s. Damodar Ropeways and Infra Limited, its registered office at 1/A,
                   Vansittart Row, P.O. - GPO, Kolkata, P.S. Hare Street, District - Kolkata -
                   700001, represented through its authorized signatory namely Mahesh
                   Mohata, son of Shri Damodar Lal Mohata, Aged about - 50 years, 2/1 B.
                   Dr. Rajesndra Road, L.R. Sarani, Kolkata, P.O. and P.S. - L.R. Sarani,
                   District - Kolkata - 700001.
                                                                                      ... Petitioner
                                                   VERSUS
               1. The State of Jharkhand through the Secretary, Department of Tourism,
                   Officiating from his office at Project Bhawan, P.O. - Jaganjnathpur,
                   P.S. - Jagannathpur, District Ranchi.

               2. Jharkhand Tourism Development Corporation Limited through its
                   Managing Director, officiating from his office at 6th Floor, Premium
                   Suite Building, JUPMI Campus, Plant Plaza Road, P.O. and P.S. -
                   Dhurwa, District - Ranchi.
                                                                            ... ... Respondents.
          CORAM: HON'BLE DR. JUSTICE S. N. PATHAK
                 HON'BLE MR. JUSTICE NAVNEET KUMAR

                 For the Petitioner   :    Mr. Prashant Pallav, Advocate
                                           Mr. Parth Jalan, Advocate
                                           Ms. Shivani Jaluka, Advocate
                                           Mr. Bajrang Kumar, Advocate
                 For the Respondent No. 1: Mr. Piyush Chitresh, AC to AG
                 For the Respondent No. 2: Mr. Sumeet Gadodia, Advocate
                                           Ms. Shilpi Sandil Gadodia, Advocate
                                           Mr. Prakher Harit, Advocate

          C.A.V. on. 11.09.2024                                 Pronounced on 12.11.2024
Dr. S.N. Pathak, J. Heard the parties.
                  PRAYER
            2.         Petitioner, a Limited Company, through its authorized signatory has
                  knocked door of this Court against the order of blacklisting for a period of
                  five years and imposition of penalty of Rs.9,11,63,250/-, issued vide order
                  as contained in Memo No. 614/2024, dated 24.06.2024 (Annexure-21).
          RC                                       1                          W.P.(C) No. 3858 of 2024
            Further prayer has been made for quashing the report dated
      07.04.2023 (Annexure-8), limited to the extent that its finding with respect
      to (i) management of record (ii) greasing (iii) testing of shaft (iv) mobility
      of transitioning devices and (v) training of its personnel, as the findings
      are unscientific and contrary to the records and arrived at in complete
      violation of principles of natural justice.

      FACTS OF THE CASE
 3.        As per the factual matrix, petitioner, a Limited Company registered
      under the Companies Act, is engaged in operation and maintenance of
      Ropeways with experience of more than fifty years in constructing highest
      number of passenger ropeways and is operating highest number of
      ropeways. Petitioner has constructed several Ropeways in India including
      Vaishno Devi, Hirakund, Guwahati, Tawang, Digha, Kolkata, Naina Devi
      - Himachal Pradesh, Chitrakoot, Maihar, Jammu, Nandankanan -
      Bhubaneswar, Udaipur, Namchi, Dewas, Pushkar, Auli and Gangtok.

 4.        A detailed Project Report was prepared by the RITES Limited with
      an estimated cost of Rs.6,14,00,000/-. After approval, budgetary allocation
      was made and an agreement was signed between RITES and the
      respondent no. 2 for construction of Ropeway at 'Trikut Parvat'.
      Thereafter, the work order was issued in favour of the petitioner for the
      construction of Ropeway. The Project was completed on 21.07.2009 and
      was handed over to RITES who then handed it over to the State. the
      Technical Committee conducted detailed inspection of the site and was
      found fit in all aspects and thereafter, the Project was made operational
      vide Resolution bearing number 1976, dated 21.08.2009. The Ropeway
      was operated by the petitioner till 21.01.2010 i.e. for a period of six
      months only and thereafter, a tender was floated by the respondent no. 1
      for operation and management of passenger ropeways. In the said tender,
      petitioner emerged as a successful party and was awarded the contract for
      operation and maintenance of the ropeway. In the year 2014, petitioner
      again qualified in the second tender and entered into a contract dated
      28.05.2014 with the respondent no. 2 to operate and maintain passenger

RC                                       2                          W.P.(C) No. 3858 of 2024
       ropeway which was valid for a period of five years i.e. till 15.05.2019
      with a clause of extension for another two terms of five years each.
      Petitioner continued to deposit royalty and agreement continued, which is
      evident from the letter of the respondent no. 2 bearing number
      DRIL/2021-22/695, dated 28.02.2022. The parties were acting in
      accordance with contract and petitioner was vigilant and continued to
      undertake the required tests as per prevalent norms.

 5.        It is further case of the petitioner that on 10.04.2022, an unfortunate
      incident took place at the ropeway site of 'Trikut Parwat' where the shaft
      of the ropeway broke owing to which ropeway was stuck and one
      passenger car plummeted to the ground. Thereafter, all the steps were
      taken to bring back the stranded passengers to the nearest station. Rescue
      operation was stopped due to unavailability of sunlight and the next day
      morning i.e. on 11.04.2022, the district administration arranged the
      helicopters for safe rescue of left over stranded passengers. One passenger
      was declared dead at the hospital on 11.04.2022 whereas two passengers
      lost their lives during joint rescue operation being performed by the team
      members of Indian Airforce and NDRF.

 6.        After the incident, petitioner released a sum of Rs.25,00,000/- to the
      family members of each of the three deceased persons, total being
      Rs.75,00,000/-. However, pursuant to the letter number 286/2022, dated
      13.04.2022, order of 'status quo' was issued and as such no repair,
      maintenance or construction was allowed to be done. An inquiry
      committee was constituted for finding out the reasons behind the fatal
      incident. According to the team from Central Mechanical Engineering
      Research Institute, acting at the behest of Technical Committee, the main
      cause of the incident was 'entrapment of hydrogen' in the shaft.

 7.        It is further case of the petitioner that a suo motu Public Interest
      Litigation was heard by Hon'ble Court in W.P. (PIL) No. 1663 of 2022
      wherein petitioner was not a party but the respondents have portrayed that
      main cause of accident was attributable to the petitioner. Thereafter, a
      show-cause notice being 426/2023, dated 04.05.2023 was issued to the
RC                                     3                          W.P.(C) No. 3858 of 2024
        petitioner which was duly replied vide letter dated 22.05.2023 clearly
       stating therein that the inquiry team itself has found that the shaft did not
       suffer any damage at the time of procurement. The fracture analysis
       revealed that the fracture occurred due to high concentration of hydrogen,
       which had developed at the time of manufacturing itself. The defect was
       of the rarest category and the accident was beyond control of operation
       and maintenance person. The annual testing of the shafts was done by
       NABL accredited labs and no anomaly was detected during the tests
       conducted in the year 2016, 2018, 2019 and 2021.
 8.         It is further case of the petitioner that a pre-meditated notice being
       102/2024, dated 31.01.2024 was sent to the petitioner wherein it was
       stated that a sum of Rs.9,11,63,250/- was payable on account of damages.
       The respondent no. 2 sought a sum of Rs.3,29,40,000/- on account of lease
       rent (royalty) payable from 16.05.2021 to 15.05.2024; sum of
       Rs.82,33,250/- on account of charges of rescue by Air Force; a sum of
       Rs.5,00,00,000/- on account of cost towards repair without any working of
       cost estimation. The said notice was also replied by the petitioner-
       Company vide its letter dated 09.02.2024 stating therein that the accident
       was not attributable to the petitioner-Company and further the imposition
       of charges were not proper.
 9.         Another notice dated 31.01.2024 was issued to the petitioner
       questioning therein regarding (i) greasing (ii) tensioning arrangements (iii)
       non-compliance of PMP (Preventive Maintenance Plan) format as per
       code and (iv) training of manpower. This notice was also duly replied vide
       letter dated 09.02.2024 denying the allegations levelled against them.
 10.        Petitioner was shocked and surprised to come to know from the
       newspaper report wherein it was mentioned that respondent no. 2 had
       taken a decision to blacklist the Company and further penalty to the tune
       of Rs.9,11,63,250/- was imposed without any notice or opportunity of
       being heard. Thereafter, petitioner approached before the respondents vide
       letter dated 18.06.2024 requesting therein to provide an opportunity of
       being heard. An order issued vide memo no. 614/2024, dated 24.06.2024
       was communicated on the email of the petitioner on 26.06.2024 informing
RC                                       4                          W.P.(C) No. 3858 of 2024
        that petitioner had been blacklisted for a period of five years and a penalty
       of Rs.9,11,63,250/- had been imposed. Being aggrieved, petitioner has
       knocked door of this Court.
       ARGUMENTS ON BEHALF OF THE PETITIONER-COMPANY

 11.        Mr. Prashant Pallav assisted by Mr. Parth Jalan, Ms. Shivani Jhaluka
       and Mr. Bajrang Kumar, learned counsels argues that petitioner is a
       Limited Company registered under the Companies Act, 2013 and is a
       leader in the field of operation and maintenance of Ropeways since last 50
       (fifty) years. Learned counsel further argues that the basic mandate of law
       has not been followed by the Respondents at the stage of Enquiry as well
       as the decision-making process. Action of the respondents is an example
       of gross illegalities at the stage of the decision-making process which led
       to the petitioner being blacklisted for a period of 5 (five) years.

 12.        Mr. Prashant Pallav, learned counsel argues that the respondent has
       proceeded on the basis that in case if an accident has occurred, then some
       person has to be held responsible. The easiest way is to blame the O&M
       operator. The Respondent has conveniently chosen to ignore that an
       accident can take place inevitably without the fault being attributed to
       anyone. The 'doctrine of inevitable accident' is recognized by the Hon'ble
       Apex Court and in the case of State of Uttar Pradesh v. M/s Mcdowell
       and Company Limited reported in (2022) 6 SCC 223 at page 274.
       Quoting para 80 and 81, learned counsel submits that petitioner has
       unnecessarily been punished. The para-80 and 81 of the said Judgment
       reads as under:

        "80. The submissions before this Court on behalf of the respondent
        Company had been that the company had taken all precautions which
        was expected of it and yet if the fire incident took place, it was something
        beyond human control for which the respondent Company cannot be held
        liable. This line of submission, at best, could be taken into another
        exception to the rules governing liability, where inevitable accident is
        generally recognised as a ground of exception. This line of submission,
        at best, could be taken into another exception to the rules governing
        liability, where inevitable accident is generally recognised as a ground of
        exception. Again, we may refer to the principles stated by Salmond [12th
        Edn., p. 399.] thus:

RC                                        5                           W.P.(C) No. 3858 of 2024
             "Accident, like mistake, is either culpable or inevitable. It is
            culpable when due to negligence, but inevitable when the
            avoidance of it would have required a degree of care exceeding
            the standard demanded by the law. Culpable accident is no
            defence, save in those exceptional cases in which wrongful intent
            is the exclusive and necessary ground of liability. Inevitable
            accident is commonly a good defence, both in the civil and in the
            criminal law.
        81. To accept the case of the respondent Company about it being an
        "inevitable accident", it is to be seen if preventing of the fire in question
        would have required a degree of care from the respondent Company
        beyond or exceeding the standard demanded by law. ... ... ...

 13.        Learned counsel argues that the petitioner-Company is engaged in
       operation and maintenance of Ropeways and has experience of more than
       fifty years with experience of constructing highest number of passenger
       ropeways and is operating highest number of ropeways. Petitioner had
       taken all care and precaution and had gone beyond the requirement of the
       Code and the agreement to ensure safety of the passengers. It is an
       admitted fact that the reason behind the accident i.e. failure of the shaft
       occurred due to the hydrogen entrapment at the stage of manufacturing of
       the steel. This is a rarest defect, which was beyond the control of the
       petitioner-Company. The detection of the same could not be done despite
       repeated tests by NABL accredited labs which is recognized by the
       Government. The remaining ancillary reasons have not led to the accident
       and the finding returned are also contrary to the records of the case. The
       entire purpose and the action of blacklisting was to justify themselves
       before the Court of Justice and, therefore, the petitioner-Company has
       been made a scapegoat. It is also the reason that the most basic principles
       of natural justice, fairness, reasonableness and equality, which are required
       to be followed so diligently in cases of blacklisting have been ignored.
 14.        The main cause of the incident was 'entrapment of hydrogen' in the
       shaft at the stage of manufacturing itself. This defect had occurred during
       the time of manufacturing of raw material i.e. steel itself and despite
       regular and repeated tests, the same could not be detected. Learned
       counsel further argues that such defect is of rarest category and arose at
       the stage of manufacturing of the raw material itself and as such
RC                                       6                          W.P.(C) No. 3858 of 2024
        petitioner-Company could not be held responsible for the same. There was
       regular annual testing done by NABL accredited labs and no anomaly was
       ever detected during such tests. Learned counsel further argues that after
       COVID-19, the petitioner-Company promptly arranged for the shaft to be
       tested before it resumed operation after COVID-19.
 15.        Relying upon the Judgment rendered in the case of Gorkha Security
       Services V. Government (NCT of Delhi) & others reported in (2014) 9
       SCC 105, learned counsel argues that action of the respondents is in teeth
       of the Judgment as it has clearly been held that no order of blacklisting
       can be passed without adhering to the principles of natural justice.
 16.        Mr. Prashant Pallav, learned counsel further argues that the basic
       mandate of law has not been followed by the respondents at the stage of
       the Enquiry and the Decision-making process. There are improprieties at
       the stage of enquiry and the gross illegalities at the stage of the decision-
       making process which lead to the petitioner-Company being blacklisted
       for a period of 5 (five) years. Pointing out the improprieties, learned
       counsel submits that action of the JTDC based on the Enquiry Report,
       submitted by the Enquiry Committee constituted by the State, suffers from
       vice of arbitrariness, illegality and procedural impropriety as the said
       report was never submitted by the State authorities nor it was approved by
       the State authorities. The said report was never accepted by the State,
       however, was accepted by JTDC which is a separate juristic entity and as
       such the entire enquiry suffers from procedural impropriety, no order of
       blacklisting could have been passed on the basis of the same. This shows
       the apparent biasness, haste and pre-meditated mindset of the Respondent.

 17.        Learned counsel further argues that the Enquiry Committee cannot
       defer from the finding of the expert committee which was constituted by
       the Enquiry Committee considering the technical issue involve in the case.
       The 5 (five) members committee appointed an independent expert body
       i.e. CSIR-CMERI to find the cause behind the accident. The CSIR-
       CMERI, on the basis of a detailed study, returned a finding that the reason
       behind the accident was hydrogen entrapment which took place at the

RC                                       7                          W.P.(C) No. 3858 of 2024
        stage of manufacturing of steel (i.e. the raw material for the manufacturing
       of the shaft) and was beyond the control of the operation and maintenance
       personnel. It was also stated that the accident was of the rarest category.
       However, the Enquiry Committee, went beyond the report of CSIR-
       CMERI and assigned vague reasons such as issues of greasing, tensioning
       arrange and non-compliance with the format of the Preventive
       Maintenance Plan and Preventive Maintenance Schedule. Once the
       Enquiry Committee found conclusively on basis of reports of independent
       experts, that the accident was beyond the control of the O&M operator (i.e
       the Petitioner-Company), they indulged in the exercise of finding ancillary
       and vague reasons to make the Petitioner-Company a scapegoat. This
       amounts to witch hunting on part of the Respondent No. 2. Such deference
       from the finding of the expert committee, without any cogent reasons and
       holding the petitioner accountable, shows arbitrariness on part of the
       Respondent. The petitioner was not provided the opportunity of being
       heard, during the stage of Enquiry. The Enquiry Committee in its report
       has gone beyond its mandate and attributed reasons to the petitioner-
       Company. In doing so, the Petitioner-Company was not afforded any
       opportunity of being heard. No notices were issued to the Petitioner by the
       Committee which has been admitted by the Respondent in Para-26 of their
       counter-affidavit, relevant portion thereof reads as under:

            "In this context, it is stated that there is no requirement under law
            to involve the Petitioner an/or to grant opportunity of hearing to the
            Petitioner by the said fact finding committee".

 18.        Learned counsel further argues that petitioner has been running and
       operating the ropeway since 2009. It was well aware about the technical
       aspects of the ropeway and accordingly should have been given an
       opportunity of being heard, where such technicalities are involved.
       Moreso, the Enquiry Committee, in the garb of finding out the reasons of
       the accident has essentially attributed reasons adverse to the Petitioner-
       Company and as such the Respondent ought to have adhered to the
       principles of audi alterum partum, before returning any adverse finding as
       against the Petitioner.
RC                                       8                           W.P.(C) No. 3858 of 2024
  19.        Referring to different clauses at Pages-213 and 214 of the report,
       learned counsel submits that the Managing Director has not given any
       independent finding rather he has relied upon the enquiry report which
       was prepared without considering reply of the petitioner-Company and
       without hearing them, the impugned order has been passed which is not
       tenable and fit to be quashed and set aside. From perusal of impugned
       order itself it would be apparent that the same has been passed without
       application of mind. Several irregularities have been pointed out in the
       report and it has been submitted that the deadlock of the show-cause was
       the enquiry report and no show-cause was issued during the course of
       enquiry while coming to the finding against the petitioner. The three
       show-cause notices were issued without considering the reply.
 20.        The Petitioner-Company was not able to clarify the same to the
       enquiry committee as no opportunity was given to it. Owing to the failure
       of adhering to the principles of natural justice, the findings so returned by
       it caused serious prejudice to the Petitioner-Company. The opportunity of
       being heard was mandatory requirement owing to the ground that enquiry
       committee not only returned findings on fact but also attributed the cause
       behind them to the Petitioner. Moreover, the report was the basis on which
       the entire reply of the Petitioner was negated by the decision-making
       authority. The above facts show the finding of the Enquiry Committee
       with respect to (i) greasing, (ii) tensioning arrangement and (iii)
       manpower is not only contrary to the records (and therefore perverse) but
       also violates the principle of natural justice and as such is fit to be set
       aside. Consequently, the order of backlisting, which is based solely on the
       Enquiry Report is also liable to be quashed.
 21.        Learned counsel argues that the enquiry committee dated 07.04.2023
       is liable to be set aside as the same suffers from violation of principles of
       natural justice as petitioner was not given any opportunity at the stage of
       enquiry by the expert committee. Learned counsel further argues that the
       impugned order of blacklisting for a period of five years and imposition of
       penalty of Rs.9,11,63,250/- contained in Memo NO. 614/2024 dated
       24.06.2024, has been passed in a mechanical manner without due
RC                                       9                          W.P.(C) No. 3858 of 2024
        application of mind and without giving sufficient opportunity of being
       heard to the petitioner. Learned counsel further argues that the report of
       the expert committee dated 07.04.2023 is incorrect and suffers from vice
       of perversity with respect to its findings on (i) management of record (ii)
       greasing (iii) testing of shaft (iv) mobility of transitioning devices and (v)
       training of its personnel.
 22.           To buttress his arguments, learned counsel has placed reliance upon
       the Judgments, which are as follows:

       (i)      Rail Engineering Works Vs. The Chairman-cum-Managing Director,
                Tamil Nadu Generati9on and Distribution Corporation Limited and
                Others reported in MANU/TN/2639/2022;
       (ii)     Kulja Industries Limited Vs. Chief General Manager W.T. Proj
                BSNL and others reported in (2014) 14 SCC 731;
       (iii)    Daffodills Pharmaceuticals Ltd. & Others Vs. State of U.P. &
                Others reported in (2020) 18 SCC 550;
       (iv)     UMC Technologies Private Limited Vs. Food Corporation of India
                & others reported in (2021) 2 SCC 552.

       ARGUMENTS ON BEHALF OF RESPONDENT NO. 2
 23.           Mr. Sumeet Gadodia, learned counsel representing Jharkhand
       Tourism Development Corporation Limited argues that in terms of
       Clauses of the Agreement, petitioner was required to carry out operation
       and maintenance of all constituent parts of the ropeway and it is an
       admitted fact as per para-7(q)(2) of the writ petition filed by the petitioner
       that a new shaft was replaced with the old one by the petitioner-Company
       in the year 2016. The said shaft was manufactured by M/s. NMW India
       (P) Limited. As per clause 7(n) of the agreement, petitioner was required
       to carry out Ultrasonic Testing (NDT) for all critical components annually
       of the ropeway. Learned counsel submits that the incident took place on
       10.04.2022 due to failure/breaking of return shaft during operation. The
       failure/breaking of shaft caused the bull wheel to shift from its position
       and impacted the existing front structure. It resulted into dislocation of the
       rope from the return bull wheel. As the disk was dislocated, at the same
       time a cabin leaving the return station was unable to grip/catch at the UTP
       Station's end point, which resulted in fall of the cabin to ground due to
RC                                        10                         W.P.(C) No. 3858 of 2024
        which one person died and another was seriously injured. The rescue
       operation was performed by the help of District Administration, Indian Air
       Force, National Disaster Rescue Force, Indian Tibet Border Police, Indian
       Army and the local people. The admitted position is that the accident took
       place due to breakage of shaft and the reason for breakage of shaft was
       entrapment of hydrogen at the stage of manufacturing of shaft.
 24.        Learned counsel further argues that after the accident, the Expert
       Committee was constituted by the Department of Tourism, Art, Culture,
       Sports and Youth Affairs, Government of Jharkhand, vide Notification No.
       25, dated 19.04.2022 to determine cause of accident with the help of
       experts/specialized institutions across the country. The CSIR in its report
       has opined that during manufacturing of shaft, hydrogen got entrapped in
       the steel of shaft. Hydrogen has a tendency to get entrapped during
       manufacturing stage of the shaft and is generally removed by vaccum
       degassing. Such entrapment of hydrogen at the manufacturing stage of
       shaft being a flaw in the component should have been detected using more
       sensitive NDT Equipment i.e. Ultrasonic Testing Equipment. Learned
       counsel further argues that on the basis of report of CSIR and other
       agencies, the Expert Committee came to the conclusion that cause of
       accident was failure/breaking of return shaft during operation. Learned
       counsel gives emphasis towards the various reports and submits that there
       is total laches on part of the petitioner-Company and as such the impugned
       order needs no interference.
 25.        Learned counsel argues that there is no requirement in law to give
       any opportunity of hearing at the stage of enquiry being conducted by the
       expert committee. The expert committee was constituted for enquiring
       into the cause which led to the accident. The said enquiry committee was
       an independent enquiry committee and was not directed against the
       petitioner-Company rather it was constituted to enquire into the cause of
       accident. The experts of the committee reported that there was
       manufacturing defect in the shaft which was replaced by the petitioner-
       Company in the year 2016, in terms of the Agreement, as a part of
       operation and maintenance activity. After the investigation committee
RC                                      11                        W.P.(C) No. 3858 of 2024
        report, petitioner-Company was specifically confronted with the report of
       the Committee and was directed to give its comments/written explanation
       to the findings of the investigating report. There was no violation of
       principles of natural justice and there is no requirement in law to give any
       opportunity of hearing to the petitioner at the stage of independent
       investigation of the cause of accident.
 26.        Learned counsel further argues that after report of the Committee,
       show-cause notice vide letter no. 426/2023, dated 04.05.2023 was issued
       to the petitioner-Company to show-cause as to why it be not
       penalized/blacklisted and as to why the agreement be not terminated,
       which was replied vide letter dated 22.05.2023. Petitioner-Company,
       according to its own convenience, has tried to make out a case that the
       entrapment of hydrogen content in the steel from which shaft was
       manufactured, was beyond its purview as it was concerned with the
       operation and maintenance of the ropeway only. Another notice vide letter
       no. 103/2024, dated 31.01.2024 was issued to the petitioner-Company
       wherein it was informed that the reply filed by the Company was not
       found satisfactory and as such it was directed to explain as to why it
       should not be blacklisted on account of receipt of unsatisfactory
       clarification. The same was replied by the petitioner-Company vide letter
       dated 09.02.2024 primarily contending that the fault lied at the
       manufacturing end of the shaft and petitioner-Company was not
       responsible for the same. Petitioner was thereafter again issued notice vide
       letter no. 102/2021, dated 31.01.2024, asking therein as to why the losses
       suffered to JTDC on account of Lease Rent, Charges for Air Rescue by the
       Indian Air Force and the Estimated expenses for repair and maintenance
       of the ropeway to make it re-operational, be not recovered from the
       Company. This show-cause was replied by the petitioner-Company vide
       letter dated 09.02.2024. When reply of the petitioner-Company was not
       found satisfactory, the impugned order was passed and the same need no
       interference. Petitioner-Company has not been able to prove as to how the
       findings of the expert committee was perverse.

RC                                       12                        W.P.(C) No. 3858 of 2024
  27.          To buttress his arguments, learned counsel has placed reliance upon
       the following Judgments:
       (i)     Navneet Kaur Harbhajansing Kundles alias Navneet Kaur Ravi
               Rana Vs. State of Maharashtra and others reported in 2024 SCC
               OnLine SC 494
       (ii)    State of Odisha and others Vs. Panda Infraproject Limited and
               another analogous case reported in (2022) 4 SCC 393;

       ARGUMENTS ON BEHALF OF STATE
 28.          Mr. Piyush Chitresh, AC to learned Advocate General opposes the
       contention of Mr. Prashant Pallav regarding different reports and further
       submits that there is only one report i.e. the report regarding greasing and
       report regarding shaft by two independent agencies and both are two
       different components. Learned counsel further adopts the arguments
       advanced by Mr. Sumeet Gadodia, learned counsel representing
       respondent no. 2 and justifies the impugned order. The loss to the life and
       property is serious issue and the agency involved cannot be left scot free
       on the ground that it was a rarest of the rare accident and could have
       happened due to technical lapses. Such an excuse cannot be accepted in
       view of reports and involvement of the Petitioner-Company cannot be
       overlooked. The serious issue of laches on part of Petitioner-Company
       resulted into serious injuries and death of innocent people. Learned
       counsel submits that there is no illegalities or any infirmities and as such
       the writ petition is fit to be dismissed.
       DISCUSSION AND CONCLUSION
 29.          Heard rival submission of the parties across the bar. Before delving
       deep into the matter, it would be appropriate to examine the important
       issues involved in the instant writ petition:
       (I)     Whether the impugned order was passed without following the
               cardinal principles of natural justice?
       (II)    Whether it was incumbent upon the Expert Committee before
               coming to the finding to hear the petitioner?
       (III) Whether before passing the impugned order, any adequate
               opportunity of hearing was given to the petitioner?

RC                                         13                        W.P.(C) No. 3858 of 2024
        (IV) Whether petitioner can be held responsible and was rightly inflicted
               punishment in view of the manner in which occurrence took place
               and the reasons behind the occurrence as per the enquiry report?
       (V)     Whether in view of report of the Expert Committee, petitioner can
               be directly held responsible for the incident?
       (VI) Whether the report of the Expert Committee is perverse on the face
               of it in absence of any opportunity of hearing to the petitioner?
 30.          It is an admitted fact that the occurrence took place due to
       entrapment of hydrogen in the shaft. After the fatal incident which resulted
       into death and fatal injuries to many people, vide Notification No. 25,
       dated 09.04.2022, a Committee was constituted by the Department of
       Tourism, Art, Culture, Sports & Youth Affairs, Government of Jharkhand
       to inquire into the cause which led to accident on 10.04.2022. The
       constitution of the Enquiry Committee was to inquire into the cause of the
       accident and was never prejudiced against the petitioner-Company. A
       detailed investigation was done and one of the major cause for the
       accident was found to be breakage of the return shaft. It was reported by
       the Expert Committee that there was the manufacturing defect in the shaft
       which was admittedly replaced by the petitioner-Company in the year
       2016 in terms of the agreement as a part of its operation and maintenance
       activity, which is clear from Clause-5 of the Agreement dated 28.05.2014.
       It would be relevant to quote clause 5 of the said agreement, which reads
       as under:
             "5. Scope of operation & maintenance work for the Trikut Ropeway
             to be undertaken by the Operator/DRIL.
              (a) The Operator/DRIL shall run, maintain the ropeway system to
                  ensure steady, smooth operation under the supervision of the
                  Owner/ JTDCL or his representative.
              (b) The entire ropeway system including building and complex
                  appurtenant thereto with terminal building will be maintained by
                  Operator/ DRIL.
              (c) The Operator/ DRIL shall maintain attendance register of their
                  employees and all employees shall wear uniform with identity
                  Card.
              (d) The annual maintenance of ropeway systems for about 15 to 20
                  days may be taken up and the period shall be decided on
                  mutually agreed basis during the lean season.
RC                                        14                         W.P.(C) No. 3858 of 2024
      (e) In the annual maintenance all the steel structures and cabins are
         to be painted before the month of October every year with two
         coats of paint approved by the Owner/ JTDCL
     (f) The monthly maintenance of ropeway shall be carried out on a
         fixed date of every month (or) as instructed by the Owner/
         JTDCL.
     (g) It shall be the responsibility of the Operator/ DRIL to replace
         all spares including rope and any other material as may be
         required at his own cost in maintenance of the ropeway. All
         cabins should be maintained periodically.
     (h) The Operator/ DRIL shall engage his own personnel to carry out
         the operation and maintenance activity with prescribed uniform
         and DRIL shall provide contributory Provident Fund, ESI
         Coverage, minimum wages duly complying with the Labour
         Laws.
     (i) The maintenance of the equipment is to be carried out in
         conformity of BIS (Bureau of Indian Standards) of Ropeways.
     (j) The Operator/ DRIL should maintain necessary maintenance
         records, log books and history sheets concerning the various
         equipment, change of spares and consumables details etc.
     (k) The Operator/ DRIL agrees to comply with all laws, rules and
         regulations applicable to the nature of work and any reasonable
         suggestions or instructions issued by the officials of the Owner/
         JTDCL/ Safety Committee.
     (l) The Operator/ DRIL shall maintain the Gen-Set also.
     (m) The Operator/ DRIL shall maintain electrical fixtures in both
         station buildings.
     (n) The Operator/ DRIL agrees to take insurance policies to all
         ropeway plant/ machinery/ equipment/system/ passengers/ other
         personnel and meet all labour liabilities & claims during
         operation & maintenance during the period of agreement.
     (o) The Operator/ DRIL shall provide and maintain First aid facility
         at site.
     (p) The Operator/ DRIL is entirely responsible for any loss or
         damage, mishappenings to passsengers, Owner/ JTDCL plant &
         machineries due to any deficiency/negligence on the part of the
         DRIL in operation and maintenance until the plant is taken over
         by the Owner/ JTDCL.
     (q) The Operator/ DRIL agrees to take insurance to cover the
         ropeway plant & machines.
     (r) The Operator/ DRIL will take passenger insurance also.
     (s) Operator/ DRIL will arrange facilities like ticketing, security,
         traffic control, Housekeeping, building maintenance etc. during
         operation & Maintenance period.
     (t) The expenditure towards maintenance, running of DG sets shall
         be borne by the DRIL.
     (u) The Operator/DRIL shall properly maintain the cleanliness of the
         premises, restaurant building and public amenities/ facilities at
         its own cost.
RC                              15                        W.P.(C) No. 3858 of 2024
             (v) If any tax, levy or duty is imposed by the Central/State
                Government, the same will be paid by the Operator/ DRIL.
            (w) Operator/DRIL agreed to provide effective communication
                system between LTP and UTP.
            (x) To run operate, maintain the restaurant at LTP on is own and to
                get the required licenses for compliance of the issues relating to
                operation of the restaurant.
            (y) To cooperate the officials of Owner/ JTDCL or the safety
                committee formed by the Owner/ JTDCL for inspection of the
                ropeway system and any equipment used or to be used in
                operation of the ropeway.
            (z) To provide complete manning of daily operations and all
                maintenance shut downs.
            (aa)     To provide consumable like brake oil, gear oil eye, diesel,
                welding rods, greases, gases for oxy acetylene cutter, ropes and
                any other consumable for day-to-day maintenance of spares
                required.

 31.        From Clauses (g) and (i) hereinabove, it is apparent that it was the
       responsibility of the Operator/ DRIL to replace all spares including rope
       and any other material as may be required at his own cost in maintenance
       of the ropeway and all cabins had to be maintained periodically. The
       maintenance of the equipment was to be carried out in conformity of
       Bureau of Indian Standards of Ropeways. It is an admitted fact that the
       Enquiry Committee consisting the experts from the CSIR and other
       agencies, reported that there was manufacturing defect in the shaft due to
       entrapment of hydrogen which was present more than the permissible
       quantity and could have been detected at the time of manufacturing itself.
       From Clause 6(n) of the said agreement, it is crystal clear that it was
       responsibility of the Petitioner-Company for carrying out Ultrasonic
       Testing (NDT) for all critical equipment. Clause 6(n) reads as under:
            "6.     The Operator/ DRIL also agreed to perform the work
            mentioned below:
                n. Carrying out Ultrasonic Testing (NDT) for all critical
                components (to be mutually decided with Owner/JTDCL)
                and Non-destructive Testing for rope with defectograph,
                annually."

            It further appears that the Committee, after examination of reports of
       Ultrasonic Testing submitted by the petitioner-Company, which was also
       examined by the experts from CSIR and other agencies, it was opined that

RC                                      16                        W.P.(C) No. 3858 of 2024
        such defects in manufacturing of shaft should have been detected in the
       Ultrasonic Testing reports, which were carried out subsequently by the
       Petitioner-Company. From the reports, it was found that admittedly there
       was manufacturing defect in the shaft but even the said manufacturing
       defect was not detected in subsequent Ultrasonic Testing reports submitted
       by the petitioner.
 32.        As regard opportunity of hearing to the petitioner is concerned, a
       show-cause notice vide letter no. 426/2023, dated 04.05.2023 was issued
       with respect to the report submitted by the Investigating Committee of the
       Trikut Ropeway, Deoghar acceded on 10.04.2022. After report of the
       investigating committee, Petitioner-Company was confronted with the
       report of the Investigating Committee and was directed to give comments/
       written explanation to the findings of the investigating report. From the
       aforesaid, it can comfortably be gathered that the principles of natural
       justice were duly complied with and proper opportunity of hearing was
       granted to the Petitioner-Company. From reply to the show-cause notice
       letter no. 426/2023, dated 04.05.2023, it can comfortably be inferred that
       the Petitioner-Company was given ample opportunity to meet specific
       finding of the investigating committee and also the JSTDC before passing
       of the impugned order. From the impugned order it appears that due
       consideration was given to the reply submitted by the Petitioner-Company
       and thereafter a decision was taken to blacklist the Petitioner-Company for
       five years. It further appears that the Committee was an independent
       Committee and independent investigation for coming to the conclusion
       regarding the cause of accident, it was not required to hear the Petitioner-
       Company as the same was not directed against the petitioner-Company but
       was constituted in order to inquire into the cause of accident and as such,
       contention of Mr. Prashant Pallav, learned counsel that the Investigating
       Committee did not consider proper to hear the petitioner while coming to
       the finding, is not acceptable to this Court.
 33.        Petitioner-Company is also aggrieved by the imposition of penalty
       and as such whether imposition of penalty is justified or not, has to be
       looked into. Admittedly, the accident took place due to sheer negligence
RC                                        17                       W.P.(C) No. 3858 of 2024
        on part of the Petitioner-Company. Due to the accident, operation of the
       ropeway has been suspended with effect from 10.04.2022 and the
       respondent-Corporation is suffering loss of yearly royalty amount. Apart
       from that, great loss has been caused towards the reputation of the
       Corporation. The Corporation has further suffered loss towards repair of
       the Ropeway and to make it operational, loss of lives and loss during
       operation of rescue system. As per Clause 6(h), it appears that the
       Operator/DRIL had agreed to perform the work towards operation of
       rescue system and its maintenance. Thus, the respondent - Corporation
       was justified in imposing cost.
 34.        This Court has to examine whether there is any perversity in the
       impugned order and whether there is any reappraisal of the evidence.
       Admittedly, in view of settled principles of law, this Court would not sit in
       appeal to reappraise the evidence for holding the petitioner guilty, from
       the independent findings of the investigating committee and after
       affording ample opportunity of hearing to the Petitioner-Company and
       giving show-cause reply, this Court is of the view that neither report is
       perverse nor there is any appraisal of evidences. What has been derived by
       the investigating committee, the Petitioner-Company cannot be left scot-
       free in view of the admitted facts that it was the duty and responsibility of
       the Petitioner-Company to maintain operation in view of terms and
       conditions of the agreement. Petitioner-Company itself being a
       manufacturer since the year 2009 and while changing the shaft in the year
       2016, was very much aware that the said incident may take place and the
       petitioner cannot shirk from the responsibility. The shaft which was
       replaced in the year 2016, was of the inferior quality which led to the
       accident. The report of Central Mechanical Engineering Research Institute
       (CMERI) also clearly reveals that the fractured surface had significant
       curvature from periphery towards centre. It further reveals that no surface
       flaw could lead to such catastrophic failure and the final fracture occurred
       from the interior which led to rapid/fast fracture. The entrapped hydrogen
       was therefore investigated using an CHNS (Carbon-hydrogen-nitrogen-
       sulphur) analyzer and was found to be 5.62 ppm, which is much higher
RC                                       18                         W.P.(C) No. 3858 of 2024
        than the acceptable range of 2-3 ppm. The concentration of hydrogen is
       responsible to generate flakes within the material. The report says that in
       the instant case the hydrogen content in the steel was approximately 87%
       more than the permissible limit. The entrapped hydrogen molecules also
       produce flaky surfaces which are extremely weak and produces network
       of cracks (numerous sub-surface cracks, possibly due to generation of a
       critical stress state by hydrogen trapped at inclusions). Such evidences
       were seen on the fracture surface. Hydrogen has a tendency to get
       entrapped during manufacturing stage of the shaft and is generally
       removed by vacuum degassing. It may be possible that the degassing
       process was not done appropriately. The report further says that the
       presence of such flaw in components should have been detected using
       more sensitive NDT equipment (Ultrasonic equipment). The chances of
       overlooking such planer defects always remain, if the equipment's
       sensitivity does not match as per requirement. The NDT reports (provided
       by JTDC Officials for 2019 and 2021) did not reveal presence of such
       planner defects possible due to location or may be due to procedure
       undertaken (Calibration) by the NDT Personnel, being not fully perfect. It
       is evident from all the analysis made, that the hydrogen gas got entrapped
       during manufacturing of the raw material of shaft itself which colluded
       with large number of inclusions present and created an elliptical flaw in
       the central region. The elliptical flaw once reached to critical size after
       certain years of operation thereafter it failed instantaneously. The mobility
       of the tensioning devises was to be ensured at all times but the same was
       not complied with.
 35.        Nowhere it has been disputed by the Petitioner-Company that they
       were not aware of the enquiry report. It was only after handing over
       enquiry report and going through the reply, the impugned order was
       passed. So, it can be inferred that ample opportunity was afforded to the
       petitioner and there was no breach of principles of natural justice. From
       the reply, nowhere it is reflected that the Petitioner-Company had taken
       the stand that opportunity of hearing was not given by the original enquiry
       committee.
RC                                       19                         W.P.(C) No. 3858 of 2024
  36.        Here it is relevant to quote the findings arrived at by the Expert
       Committee on the basis of report of CSIR and other agencies, which reads
       as under:
            "From the above it can be concluded that the cause of accident of
            Trikut Ropeway on 10.04.2022 was the failure/breaking of return
            shaft during operation. The failure/breaking of shaft caused the bull
            wheel to shift from its position and impacted the existing front
            structure. It also resulted in the dislocation of the rope from the
            return bull wheel. As the rope was dislocated, at the same time a
            cabin leaving the return station (UTP) was unable to grip/catch the
            rope at the UTP station's end point, which resulted in fall of the
            cabin to ground due to which one person died and another was
            seriously injured. The dislocation of the rope also led to stopping of
            the Ropeway which resulted in the passengers being stranded in air
            who had to be evacuated by personnel of Indian Army and Indian
            Air Force in a span of nearly 2 days. It is to be noted that shaft was
            tested earlier multiple times. It was tested twice in 2016, once in
            2018, once in 2019 and once in 2021 but on any of these five
            occasions the abnormalities which have been reported by CSIR-
            Central Mechanical Engineering Research Institute, Durgapur were
            not reported/detected. The test reports submitted by ID & RL in
            2016 and 2018 itself mentions that 100% shaft was not tested."
            Thus, the enquiry Committee, on the basis of the report of the experts
       from the premier institutions of metallurgy of the Government of India,
       formed an opinion that there was manufacturing defect of the shaft which
       was admittedly replaced by the petitioner and further, the enquiry
       committee observed that not only there was manufacturing defect but the
       said manufacturing defect would not be detected in the Ultrasonic Test
       Reports submitted by the petitioner as the said Ultrasonic Test Reports
       were obtained from the institutions which did not deploy more sensitive
       NDT Equipment (Ultrasonic Equipment) and thus, the chances of
       overlooking planner defects remained. The said committee also obtained
       the opinion of M/s. RITES Limited on 'graphite grease and came to the
       conclusion as under:
            Ïn the above reproduced report it is mentioned that Graphite
            flake content of grease has been observed to be 0.96 against the
            specified value of minimum 6. The significance of grease lies in
            its role in reducing friction between the shaft & beatings and
            inside the bearings. Reduced flake content of the grease may lead
            to enhanced friction between the shaft & bearings and inside the
            bearings which may in turn cause enhanced stress on the shaft.
RC                                      20                         W.P.(C) No. 3858 of 2024
             This appears to be an operation and maintenance issue."
            The said Committee also examined the practice of operation and
       maintenance undertaken by the Petitioner-Company and in terms of Code
       of Practice framed by Bureau of Indian Standard, observed as under:
            "2.      Clause 4.1(a) of the Code of Practice for Operation and
            Maintenance of all types of Ropeways intended for transportation
            of passengers is 17234:2019 states that "Deployment of trained
            operating personnel." Clause 4.2.8 of the Code stages that "Rescue
            operation should be carried out by trained personnel only and with
            utmost safety." The educational qualification of the manpower has
            not been specified in the Code. Damodar Ropeway & Infra limited
            has not provided the training details of the personnel who were
            engaged in the Trikut Ropeway operation. However, from the
            perusal of the above reproduced document, it appears that most of
            the maintenance personnel were not adequately qualified. It is
            pertinent to note that quality of human resources deployed may
            have an impact on the quality of operation and maintenance of the
            Ropeway."

 37.        The Hon'ble Apex Court in the case of State of Odisha and others
       Vs. Panda Infraproject Limited and another analogous case reported in
       (2022) 4 SCC 393 has held that the findings recorded by the inquiry
       committee can be said to be the basis for initiating the action of
       blacklisting against the contractor. The findings recorded by the inquiry
       committee can be said to be a prima facie opinion while initiating the
       proceedings for blacklisting. Merely because show-cause notice was
       issued and the blacklisting order was passed on consideration of the
       inquiry report, that by itself it cannot be said that the blacklisting order
       was pre-decided. Paragraps-17 to 20 of the said Judgment reads as under:
             "17. Merely because the show-cause notice was issued after the
             inquiry committee report was considered and thereafter the State
             Government took the decision to initiate proceedings for
             blacklisting, that by itself cannot be said that the order of
             blacklisting was pre-determined as observed by the High Court.
             The communication dated 10-10-2017 by the State Government to
             the Chief Engineer can be said to be a proposed decision to
             initiate the proceedings for blacklisting. In the communication
             dated 10-10-2017, it has been specifically mentioned that the
             action be taken for blacklisting after following the procedure as
             per the OPWD Code.
             18.     Before any show-cause notice is issued for any action
             when a tentative decision is taken, it cannot be said that
RC                                      21                         W.P.(C) No. 3858 of 2024
              subsequent decision followed by a show-cause notice and the
             proceedings as per the OPWD Code can be said to be pre-
             determined. Before initiation of any proceedings for blacklisting,
             there can be a tentative decision on the basis of the material
             available forming a tentative/prima facie opinion that action is
             required.
             19.     In the instant case a committee submitted a detailed report
             which was the basis for issuance of the show-cause notice to the
             respondent. The action initiated against the respondent was not in
             a vacuum but after considering the committee's report and after
             following the due procedure as required. Therefore, the High
             Court has erred in holding that the blacklisting order was pre-
             determined.
             20.     So far as the findings recorded by the High Court that the
             blacklisting order was in breach of principles of natural justice is
             concerned, it is to be noted that the blacklisting order was passed
             after issuing a show-cause notice to which the respondent
             contractor was called upon to reply and show cause as to why he
             be not blacklisted. A detailed show-cause notice was issued with
             specific allegations to which the respondent contractor submitted
             a detailed reply. After considering the allegations in the show-
             cause notice, considering the reply and also by considering the
             material available on record the order of blacklisting was passed.
             We fail to appreciate, how in such a case the blacklisting order
             can be said to be in breach of principles of natural justice.
             21. In Grosons Pharmaceuticals (P) Ltd. v. State of U.P. [Grosons
             Pharmaceuticals (P) Ltd. v. State of U.P., (2001) 8 SCC 604] , the
             order of blacklisting was challenged by the contractor on the
             ground that the contractor was not supplied with all the materials
             on the basis of which charges against him were based. It was the
             case on behalf of the contractor that non-supply of such material
             resulted in violation of principles of natural justice. To that, this
             Court observed that it was sufficient requirement of law that an
             opportunity of show cause was given to the appellant before it was
             blacklisted. This Court observed that the contractor was given an
             opportunity to show cause and it did reply to the show-cause to the
             State Government and therefore the procedure adopted by the
             Government while blacklisting the contractor was in conformity
             with the principles of natural justice."

 38.       The question which is posed for consideration of this Court is,
       whether, in the facts and circumstances of the case the contractor was
       required to be debarred/blacklisted. In Kulja Industries [Kulja Industries
       Ltd. v. Western Telecom Project BSNL, (2014) 14 SCC 731], Hon'ble
       Supreme Court has observed that "debarment" is never permanent and the
       period of debarment would invariably depend upon the nature of the
RC                                      22                         W.P.(C) No. 3858 of 2024
        offence committed by the erring contractor. In the said decision this Court
       emphasised on prescribing guidelines by determining the period for which
       the blacklisting should be effective. It is observed and held by this Court
       that while determining the period for which the blacklisting should be
       effective, for the sake of objectivity and transparency it is required to
       formulate broad guidelines to be followed. It is further observed that
       different periods of debarment depending upon the gravity of the offences,
       violations and breaches may be prescribed by such guidelines. The
       duration of blacklisting cannot be solely per offence. Seriousness of the
       lapse and the incident and/or gravity of commission and omission on the
       part of the contractor which led to the incident should be the relevant
       considerations. In a given case, it may happen that the commission and
       omission is very grave and because of the serious lapse and/or negligence,
       a major incident would have taken place. In such a case, it may be the
       contractor's first offence, in such a case, the period/duration of the
       blacklisting/banning can be more than three years. However, as the said
       guidelines are not under challenge, it is upon the State Government to
       suitably amend and/or modify the said office memorandum. However, the
       observations made herein can be a guide while determining the period of
       debarment/blacklisting.
 39.        In the case of Navneet Kaur Harbhajansing Kundles alias Navneet
       Kaur Ravi Rana Vs. State of Maharashtra and others reported in 2024
       SCC OnLine SC 494, the matter relating to factual issues has been dealt
       with. It has been held that the High Courts as well as the Supreme Court
       should refrain themselves from deeper probe into factual issues like an
       appellate body unless the inferences made by the concerned authority
       suffers from perversity on the face of it or are impermissible in the eyes of
       law. It has been held that the writ of certiorari is expended as a remedy
       and is intended to cure jurisdictional error, if any, committed by the
       Courts/ forums below. It should not be used by superior Court to substitute
       its own views by getting into fact-finding exercise unless warranted. The
       findings of fact recorded by a fact-finding authority duly constituted for
       the purpose and which ordinarily should be considered to have become
RC                                       23                         W.P.(C) No. 3858 of 2024
         final, cannot be disturbed for the mere reason of having been based on
        materials or evidence not sufficient or credible in the opinion of the writ
        Court to warrant those findings at any rate, as long as they are based upon
        such materials which are relevant for the purpose or even on the ground
        that there is yet another view which can be reasonable and possibly
        undertaken.
  40.         It appears that three show-cause notices were given to the petitioner
        i.e. on 04.05.2023 and 31.01.2024 followed by 31.01.2024 regarding
        financial and other loss to the Corporation in view of Clause - 5 and 6 of
        the agreement, which has not been denied by the petitioner.
  41.         In view of backdrop of findings of the investigating committee as
        well as the reasonings assigned by the respondents and observations made
        by this Court hereinabove, this Court cannot shut its eyes in considering
        seriousness of the incident in which due to omission and commission
        wholly on part of the petitioner-Company, the incident took place causing
        death, injury, loss to life and property and reputation of the Corporation.
        The manner in which occurrence took place caused loss to life and
        property and reputation of the Corporation due to callous and lethargic
        approach of the petitioner, the impugned order is fully justified and
        warrants no interference.
  42.         On thoughtful consideration to submission and after going through
        the materials available on record, this Court is of the considered view that
        no interference is warranted in the instant writ petition. Accordingly, this
        writ petition stands dismissed. The issues framed are inter-related and as
        such answered accordingly.
  43.         Pending Interlocutory Application, if any, also stands disposed of.



                                                        (Dr. S.N. Pathak, J.)

Navneet Kumar, J.

(Navneet Kumar, J.) Jharkhand High Court, Ranchi Dated : November 12, 2024

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter