Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Umesh Choudhary @ Umesh Kumar ... vs The State Of Jharkhand
2023 Latest Caselaw 1089 Jhar

Citation : 2023 Latest Caselaw 1089 Jhar
Judgement Date : 13 March, 2023

Jharkhand High Court
Umesh Choudhary @ Umesh Kumar ... vs The State Of Jharkhand on 13 March, 2023
                                              1

                  IN THE HIGH COURT OF JHARKHAND AT RANCHI
                            Cr.M.P. No. 107 of 2008
            1.   Umesh Choudhary @ Umesh Kumar Choudhary, son of Late Surya
                 Narayan Choudhary, the then Project Officer, Karma Project, South
                 Eastern Coalfields Limited, Ambikapur, Chattisgarh
            2.   Niraj Kumar Sinha, son of Sri Akhileshwar Prasad, Manager, Karma
                 Project of M/s. Central Coalfields Limited, Ramgarh
                                                                ... Petitioners
                                          -Versus-
            1.   The State of Jharkhand
            2.   Baijnath Thakur, Forest Guard, Ramgarh          ... Opposite Parties
                                               With
                                    Cr.M.P. No. 1251 of 2015
                 J.P. Sharma @ Jai Prakash Sharma, son of Late R.K. Sharma, resident
                 of 214, DK-2, Danish Kunj, Kolar Road, Bhopal ... Petitioner
                                          -Versus-
            1.   The State of Jharkhand
            2.   Divisional Forest Officer, Ramgarh              ... Opposite Parties
                                          -----
            CORAM:       HON'BLE MR. JUSTICE SANJAY KUMAR DWIVEDI
                                          -----

For the Petitioners : Mr. Anoop Kumar Mehta, Advocate (In both cases) For the O.Ps. : Mr. Shashi Kumar Verma, A.P.P. (In Cr.M.P.-107/08) Mr. Bhola Nath Ojha, A.P.P. (In Cr.M.P.-1251/15)

-----

15/13.03.2023 Both the cases have been heard together since common question of

fact and common complaint case and order taking cognizance are under

challenge.

2. Heard Mr. Anoop Kumar Mehta, learned counsel for the petitioners

and Mr. Shashi Kumar Verma and Mr. Bhola Nath Ojha, learned counsel for

the opposite parties.

3. These petitions have been filed for quashing the entire criminal

proceedings in connection with Case No. G-165 of 2003/T.R. No.452 of 2007

including the order taking cognizance dated 22.10.2005 passed by the

learned Chief Judicial Magistrate, Hazaribagh, whereby cognizance under

Section 33 of the Indian Forest Act and Section 2 of the Forest

(Conservation) Act has been taken against the petitioners, pending in the

court of the learned Judicial Magistrate, 1st Class, Hazaribagh.

4. The opposite party no.2 lodged a written report dated 05.08.2003 in

the court of the learned Chief Judicial Magistrate, Hazaribagh. The case was

filed alleging therein that while the opposite party no.2 along with other

witnesses was on patrolling duty of Sugia reserved forest on 05.08.2003 at

about 04:00 p.m., he found that at the direction of the accused persons,

forest lands within the Sugia protected forest was being cleared and mining

work was being carried out since before. It was also alleged that on the

directions of the accused persons, the provisions contained in the Indian

Forest Act, 1927 and the Forest (Conservation) Act, 1980 were being

violated openly and the work was being carried for the benefit of the project

as a result of which about 0.66 hectares of forest land, 31.95 hectares of

reserved forest land and 102.03 hectares of Jungle-jhari was destroyed. The

offence report of opposite party no.2 was forwarded to the learned Chief

Judicial Magistrate and on receipt of the offence report, Case No. G-165 of

2003 has been registered.

5. Mr. Anoop Kumar Mehta, learned counsel for the petitioners submits

that at the relevant time, petitioner nos. 1 and 2 in Cr.M.P. No.107 of 2008

were the Project Officer, Karma Project and Manager of Karma Project

respectively and the petitioner in Cr.M.P. No.1251 of 2015 was the Chairman

cum Managing Director of M/s. Central Coalfields Limited. He further

submits that the petitioners are not the owner of the mine as the owner of

the mine is either the Director (Technical) or the Director (T) OP under the

Mines Act, 1952. He also submits that the petitioners did not issue any

order or direction in respect of working of a coal mine. He further submits

that the petitioner in Cr.M.P. No.1251 of 2015 has tendered his resignation

as Chairman cum Managing Director of M/s. Central Coalfields Limited,

which was duly accepted and he was relieved in the month of August, 2004

itself. He also submits that on the own showing of the opposite party no.2,

the forest in question is a protected forest and notified as such in the year

1952. 30 years period has since expired in the year 1982 and thereafter

there has been no re-notification made by the Government. He further

submits that an application was made by the M/s. Central Coalfields Limited

for diversion of forest lands of Karma Open Cast Project measuring an area

of 134.64 Hectare, which was subsequently revised to 132.28 Hectare and

subsequently vide letter dated 01.09.2003, proposal was submitted seeking

prior approval of the Central Government. The proposal was thereafter

considered by the Central Government and the Central Government agreed

in principle for diversion of 132.28 Hectare of forest lands for Karma Open

Cast Mining Project. He also submits that M/s. Central Coalfields Limited

complied with the conditions laid down in letter dated 12.01.2005 for the

purpose of grant of Stage-I clearance granted by the Ministry of

Environment and Forest for diversion of 132.28 Hectare of forest lands and

also made payment of the revised demand, contained in Annexure-3 of

Cr.M.P. No.1251 of 2015 and thereafter clearance report was submitted by

the State Government vide letter dated 21.04.2008, whereupon the Central

Government granted approval as required under Section 2 of the Forest

(Conservation) Act, 1980 for diversion of 132.28 Hectare of forest land.

6. Learned counsel for the opposite parties submit that there is violation

and that is why the case has been lodged.

7. In view of the above facts and considering the submissions of the

learned counsel for the parties, the Court finds that it is an admitted fact

that underground mining activities were being carried out by M/s. Central

Coalfields Limited beneath the forest area since long. So far as the

allegation made in the offence report is concerned, save and except

inclusion of the name of the petitioners in the column of accused, there is

no specific or direct allegation against them of committing any offence

under Section 33 of the Indian Forest Act . There is no concept of vicarious

liability under the Indian Forest Act and the petitioners cannot be made

vicariously liable for any offence committed by the company itself. A

reference may be made to the judgment passed in Maharashtra State

Electricity Distribution Company Limited and another v. Datar

Switchgear Limited and others; [(2010) 10 SCC 479] and in

Fasiuddin & others v. State of Bihar (now Jharkhand); [2012 (3)

JCR 602 (Jhr.)] as also the order dated 31.07.2014 passed in Cr.M.P.

No. 800 of 2009 in Krishna Kumar Poddar v. State of Jharkhand . In

Maharashtra State Electricity Distribution Company Limited (Supra), it has

been held as follows:-

"30. It is trite law that wherever by a legal fiction the principle of vicarious liability is attracted and a person who is otherwise not personally involved in the commission of an offence is made liable for the same, it has to be specifically provided in the statute concerned. In our opinion, neither Section 192 IPC nor Section 199 IPC incorporate the principle of vicarious liability, and therefore, it was incumbent on the complainant to specifically aver the role of each of the accused in the complaint. It would be profitable to extract the following observations made in S.K. Alagh:

"19. As, admittedly, drafts were drawn in the name of the company, even if the appellant was its Managing Director, he cannot be said to have committed an offence under Section 406 of the Penal Code. if and when a stature contemplates creation of such a legal fiction, it provides specifically therefor. In absence of any provision laid down under the statute, a Director of a company or an employee cannot be held to be vicariously liable for any offence committed by the company itself." "

8. In Krishna Kumar Poddar and others v. State of Bihar (Now

Jharkhand) (Cr. M.P. No. 800 of 2009) , while considering the order passed in

the case of the Fasiuddin & others v. State of Bihar (now Jharkhand) &

another (supra), it was held in paragraph-6 as follows:-

"6. After having heard the learned counsels for both sides and upon going through the records, I find that the case of the petitioner is fully covered by the decision of this Court in Md. Fasiuddin's case (supra). It is apparent from the offence reports dated 30.4.2005, 2.5.2005 & 25.4.2005 that the petitioner was not present at the place of occurrence and there is no allegation against him therein, nor is he named therein. Only in the prosecution reports the petitioner had been made accused, being the proprietor of Chotanagpur Graphite Industries, without making any specific averment or allegation against him."

9. Similar is the present case inasmuch in the prosecution report/

offence report there is no averment made with respect to the active/

direct involvement of the petitioners in the commission of forest offence.

Merely because the petitioners happen to be Project Officer, Manager

and Chairman cum Managing Director of M/s. Central Coalfields Limited at

the time of the incident, the same by itself would not make them liable to

face criminal prosecution. Moreover, the application for diversion of

forest lands of Karma Open Cast Project was allowed and subsequent

to that, amount of Rs.13,43,10,707/- has already been paid and,

thereafter, the State Government has allowed the M/s. Central Coalfields

Limited to work.

10. Considering that the amount received by the Government and there is

no direct complicity of the petitioners in the forest offence, these petitions

deserve to be allowed. In view of the judgments of the Hon'ble Supreme

Court referred herein above and in absence of any vicarious liability, the

prayer made in the petitions are allowed.

11. In view of the above facts, reasons and analysis, the entire criminal

proceedings in connection with Case No. G-165 of 2003/T.R. No.452 of 2007

including the order taking cognizance dated 22.10.2005 passed by the

learned Chief Judicial Magistrate, Hazaribagh, pending in the court of the

learned Judicial Magistrate, 1st Class, Hazaribagh is, hereby, quashed.

12. Accordingly, these petitions are allowed and disposed of.

(Sanjay Kumar Dwivedi, J.) Ajay/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter