Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Hindustan Copper Ltd vs M/S Predicate Consultants ...
2023 Latest Caselaw 850 Jhar

Citation : 2023 Latest Caselaw 850 Jhar
Judgement Date : 22 February, 2023

Jharkhand High Court
Hindustan Copper Ltd vs M/S Predicate Consultants ... on 22 February, 2023
                IN THE HIGH COURT OF JHARKHAND AT RANCHI

                           Arbitration Appeal No. 7 of 2016

               Hindustan Copper Ltd.                           ...     ...      Appellant
                                      Versus
              M/s Predicate Consultants Private Limited... ...        Respondent
                                      ---

CORAM: HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY

---

              For the Appellant       : Mr. Pandey Neeraj Rai, Advocate
                                      : Mr. Rohit Ranjan Sinha, Advocate
              For the Respondent      : Mr. A.K. Das, Advocate
                                      ---

40/22.02.2023 Arguments on behalf of the Appellant On the point of jurisdiction of the learned Arbitrator, learned counsel for the appellant has submitted that initially the learned Arbitrator did not decide this issue properly and consequently, the matter was remitted back for decision on the point of jurisdiction. However, the earlier arbitrator refused to take up the matter further, the matter was referred to another Arbitrator. The decision on the point of jurisdiction of the arbitrator is also under challenge.

2. The learned counsel has relied upon the judgment passed by Hon'ble Kolkata High Court reported in AIR 1980 Cal 86 (Excalcer Vs. The State of West Bengal) to submit that the arbitration clause in the present case is similar to the one which was involved in the judgment passed by Hon'ble Kolkata High Court. He has also submitted that as per the agreement, the CMD of the appellant was the Arbitrator and he stood appointed as Arbitrator by virtue of signing of the agreement and under such circumstances, mere silence on the part of the CMD pursuant to invocation of arbitration clause has to be interpreted to mean that he was already acting as an arbitrator. The learned counsel has further submitted that in view of the aforesaid submissions, that CMD was already an arbitrator, then in case of change of arbitrator or any grievance in connection with the arbitrator, recourse was available under Section 15 (2) and Section 14 of the Arbitration and Conciliation Act, 1996 and not under Section 11 (6). He has further submitted that the law in the field is governed by the judgment of Konkan Railway which was overruled with effect from 26.10.2005 as held by the Hon'ble Supreme Court in the case of (SBP & Co. Vs. Patel Engineering Ltd. and Anr.) reported in (2005) 8 SCC 618 and therefore it was open to the appellant to contend before the

learned Arbitrator that the very order by which the arbitrator was appointed i.e., order under Section 11 (6) was not justified and the legality and validity of such order could also be examined. He has relied upon judgment passed by this Court reported in (2004) 1 JLJR 449 (HC) (Cement Corporation of India Ltd. Vs. M/s Narula Trading Corporation & 4 Ors.) and has submitted that similar view has been expressed by this Court as well. The learned counsel has further referred to the judgment passed by Hon'ble Supreme Court reported in (2016) 1 SCC 721 (Huawei Technologies Company Limited Vs. Sterlite Technologies Limited), (2006) 10 SCC 763 (National Highways Authority of India and Anr. Vs. Bumihiway DDB Ltd. (JV) and Others), (2009) 17 SCC 313 (Nimet Resources Inc. and Another Vs. Essar Steels Limited), (2022) 10 SCC 235 (Swadesh Kumar Agarwal Vs. Dinesh Kumar Agarwal and Ors.) to submit that the recourse under Section 15 (2) / 14 of the Arbitration and Conciliation Act, 1996 was available to the claimant but the order passed under Section 11 (6) appointing the arbitrator was not in accordance with law.

3. The learned counsel for the appellant has also submitted that notice for appointment of arbitrator giving 15 days' time for appointment which was sent to the appellant by the respondent was itself a vague notice and it did not specify that in case the arbitrator is not appointed, they will invoke Section 11 (6) of the Act of 1996. The learned counsel submits that in the notice, it was only stipulated that the respondent will send the matter for judicial decision and therefore, the said stipulation in the notice could only co-relate to appropriate proceedings in terms of Section 14 of the Act of 1996. Section 11 (6) was not at all contemplated.

4. On the point of jurisdiction, learned counsel for the appellant has also referred to the ground 'f' of the petition under Section 34 regarding the point of jurisdiction to submit that the invocation of bank guarantee could not have been the subject matter of consideration by the learned Arbitrator. He has submitted that the notice for request for appointment of Arbitrator was given on 17.04.2002 and the application under Section 11 was filed on 13.06.2002 and the bank guarantee was invoked thereafter on

18.06.2002. Therefore, the Hon'ble Chief Justice while making the appointment on 05.07.2002 could not appoint arbitrator straightaway to decide the dispute relating to invocation of the Bank guarantee without opportunity to Hindustan Copper Limited's Chairman-cum- Managing Director to make appointment in terms of the arbitration clause.

5. Learned counsel for the appellant on merit has submitted that the entire work was to be executed in 3 packages which constituted a composite whole. He further submits that certain certificates regarding completion/acceptance were issued, but no final certificate regarding acceptance of the work was ever issued. Learned counsel submits that whatever work the respondent had done, they were paid for it and still an amount of Rs.8,30,162/- under package 2 and withheld amount of 10% of the contract value under package 3 which amounted to Rupees 98 lakhs and odd was claimed by the respondent. He further submits that the reason for non-issuance of final acceptance certificate was that 100 days test run could not be completed and the crux of the matter is that both the parties are blaming each other for non - completion of 100 days test. He submits that the test was carried out only for a period of 68 days and no more and before the arbitral proceedings, the parties joined issue on account of non-performance of reciprocal obligations for the purposes of completion of the remaining test period. He has further submitted that the failure on the part of the respondent has been recorded by the learned Arbitrator, but no clear finding has been given and further no adverse inference has been drawn by the learned Arbitrator on account of failure on the part of the respondent to produce the necessary records in support of supply of sulphuric acid.

6. Learned counsel for the appellant has referred to paragraph 13, 15 and 16 of the award to place the factual background of the case. He has further referred to paragraph 91 read with paragraph 28 and 82 of the award to submit that there were altogether 58 failures on the part of the respondent, but this fact has not been properly considered by the learned Arbitrator, rather no finding has been recorded to that effect. He has further submitted that issue no. vi as decided by the learned Arbitrator is to be read with issue no. iv, v and vii.

7. The learned counsel has further submitted that in paragraph 91, the learned Arbitrator has recorded a finding that the failure of the further test run was on account of the appellant, but the learned Arbitrator has not backed this finding by discussion of any materials on record.

8. Learned counsel for the appellant has referred to the paragraph 21 and 89 of the award. Period of test run as stated by the appellant was from 25.06.1998 to 31.08.1998. Learned counsel for the appellant has also referred to the grounds No. 29 and 30 of the petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 and submits that relevant clause of the agreement i.e. clause 3.63.7 and 3.64 have been totally ignored by the learned Arbitrator. He submits that these clause dealt with the certification regarding completion of work and they clearly stipulate that no other certification could be binding upon the appellant. He also submits that even part payment should not be construed as an admission on the part of the appellant regarding completion of work by the respondent. Learned counsel submits that these two clauses of the agreement have not even being referred to, directly or indirectly, in the entire award passed by the learned Arbitrator. As a consequence thereof the entire contractual value of the work paid to the respondent has been rightly recovered by invocation of bank guarantee. Non consideration of relevant clauses of the agreement calls for interference by this Court. The point is not the interpretation of these clauses, the point is non consideration of these clauses by the learned Arbitrator as well as by the learned court below.

9. Arguments of the appellant is concluded.

10. Respondent has commenced their arguments. The matter remained inconclusive as the Court's time is over.

11. Post this case for further hearing tomorrow i.e., on 23.02.2023.

(Anubha Rawat Choudhary, J.) Saurav/Binit

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter