Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Trf Limited vs Shiva Shakti Engineering ...
2023 Latest Caselaw 2928 Jhar

Citation : 2023 Latest Caselaw 2928 Jhar
Judgement Date : 17 August, 2023

Jharkhand High Court
Trf Limited vs Shiva Shakti Engineering ... on 17 August, 2023
             IN THE HIGH COURT OF JHARKHAND AT RANCHI
                   Commercial Appeal No. 09 of 2020

TRF Limited, a Company incorporated under the Companies Act, 1956, having
its registered office at 11, Station Road, Burma Mines, Jamshedpur, P.O. and
P.S. Burma Mines, District East Singhbhum, through its Authorized Signatory,
namely Pankaj Kumar Choubey, aged about 33 years, Son of Shri Ramawatar
Choubey, resident of 7, Namda, Golmuri, Jamshedpur, P.O. and P.S. Golmuri,
District East Singhbhum-831003 (Jharkhand)          ......           Appellant

                                       Versus

Shiva Shakti Engineering Construction through its Managing Director, having tis
office at Plot No. F-4/1, Chandaka Industrial Estate, Patia, P.O. and P.S. Patia,
District Bhubneshwar (Odisha)-751024               ...      ...         Respondent
                                        ---
    CORAM: HON'BLE MR. JUSTICE SHREE CHANDRASHEKHAR
          HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY
                                        ---
For the Appellant         : Mr. Sumeet Gadodia, Advocate
                            Mrs. Shilpi Sandil Gadodia, Advocate
                            Mrs. Aanya, Advocate
                            Mr. Prakash Narayan, Advocate
For the Respondent        : None
                                        ---
                                                                 ORDER

17th August 2023 Per, Shree Chandrashekhar, J

This Commercial Appeal has been filed by the TRF Limited (in short, Company) under section 13(1-A) of the Commercial Courts Act, 2015 to challenge the order passed in Arbitration Case No.4 of 2019 passed by the Commercial Court, East Singhbhum, at Jamshedpur.

2. This Commercial Appeal was filed on 10th June 2020 and taken up for hearing on 30th September 2020, when notice was directed to be issued to Shiva Shakti Engineering Construction (in short, claimant). The proceedings in this appeal indicate that on the request of the Company it was granted permission to serve dasti summons and an affidavit affirming service of dasti summons upon the claimant has been filed. This appeal was taken up on 27th June 2023 but on that day also no one appeared for the claimant.

3. Therefore, by an order dated 24th July 2023, the Registry was directed to transmit a copy of the order to the claimant at the address disclosed in the present appeal.

4. Notwithstanding that, no one appears on behalf of the claimant. Constrained, we have heard this appeal in absence of the claimant.

2 Commercial Appeal No. 09 of 2020

5. The challenge laid by the Company to the order dated 16th January 2020 passed in Arbitration Case No.4 of 2019 is confined to a limited issue in law that; whether or not the Arbitrator could have made the award beyond the reference?

6. Briefly stated, for "Erection and Commission of RMHS- (Package- A)" the work was awarded by Tata Steel Limited to TRF Limited (hereinafter referred to as the 'Company') on 3rd December 2012 which, in turn, invited quotations from other agencies for completing the subject work. The Company has pleaded that the subject work for a value of Rs.4,96,06,800/- was allotted to the claimant and MOM dated 16th April 2013 was issued. Raising a dispute, the claimant invoked Clause 15 and the learned Arbitrator was requested by both parties to enter upon the reference. The subject work could not be completed in time and according to the Company the blame squarely lies on the claimant. The claimant has referred to amendments in the purchase order on different dates starting from 17th December 2013 to 8th March 2016 by which the scope of work was gradually and substantially reduced. According to the Company, the purchase order was reduced to Rs.1,28,90,574.60 because the claimant was not able to perform and it had to engage another agency to finish the remaining 75% work. The learned Arbitrator issued notice to both the parties and they filed their respective claims and counter-claims.

7. The claimant raised claims under 4 heads viz. (i) Rs.93,00,844/- for unpaid bills against the work executed (ii) Rs.11,42,867/- for idle manpower and machinery (iii) Rs.25,43,152/- as loss of profit and (iv) interest @ 2% over and above SBI PLR per annum over the claim nos.1, 2 & 3.

8. For a better appreciation of the dispute before the learned Arbitrator, we would extract the claims made by the claimant under the following 4 heads which are recorded in paragraph no.13 of the award, as under:

The claimant having executed the work meeting to the conditions of the purchase order and having raised the bill against the work so executed is entitled for Rs. 93,00,844/- pertaining to unpaid bills as per abstract of payment over and above Rs. 11,42,567/- as idling cost and as Rs. 75,00,000/- towards cost of machineries forcibly detained.

Claim No. 2 - Compensation for idling of manpower and machinery The claimant has raised bill for idling of manpower of Rs. 11,42,867/- and the same has been duly certified by the representative as per the annexure marked to Exhibit-C-12. The said expenditure having been incurred is reimbursable to the claimant as per the grounds of substantiation noted below. Claim No. 3 - Loss of opportunity to earn profit.

The claimant agreed to contracted price of Rs. 4,96,06,800/- with firmed mind set to earn profit of 8% as it has been deriving from execution of similar 3 Commercial Appeal No. 09 of 2020

project in the past. Unfortunately, in spite of it being an mobilized state with manpower and machinery, the respondent for its own choice/benefit convenience did not allow the claimant to execute the work as per purchase order and MOM and stopped the work even without serving a contractual, legal and customary notice of termination assigning, the reasons of termination, if any. Resultantly, the claimant having executed work for Rs. 1,78,17,393/- in the one hand incurred substantial infructuous expenditure and in the other hand lost the opportunity of deriving profit @ 8% from executing the unexecuted value of work which is amounting to Rs. 3,17,89,407/- and @ 8% interest amounting to Rs. 25,43,152/-. The opportunity to earn the above amount of profit being lost for none of the default of the claimant this amount is required to be compensated to the claimant.

Claim No. 4 - Interest The since the bill for last payment was made on December 2014 and thereafter the work, the amount was not allowed to execute the work claimed under claim no. 1, 2 and 3 remained below with the exchequer of Respondent and the claimant met the expenditure availing finance from different sources, it is entitled for interest @ SBIPLR+2% p.a. from 1.1.2015 to actual date of release which the claimant for the time being has updated it till July, 2017."

9. The learned Arbitrator adjudicated the claim no.1 raised by the claimant for payment of Rs.93,00,844/- in paragraph no.47 of the award. The learned Arbitrator took note of the statement of defence of the Company whereunder a stand was taken that the outstanding balance amount of Rs.47,61,482/- has been wrongly shown against the bills for RA-8, RA-9, RA-1, 2 and 3 and EW-2. As regards RA-8 and RA-9, the learned Arbitrator held that those were not valid bills for payment. The learned Arbitrator further took note of the fact that the claim for extra work and alignment were not applicable. Finally, the claim no.1 has been rejected by the learned Arbitrator.

10. The learned Arbitrator has dealt with claim no.1 in the following manner:

"57. Much have been argued on behalf of the claimant and the respondent-TRF in support of their respective claims and counter claims which have already been discussed in the foregoing paragraphs.

Firstly, the claims of the claimant are taken up for consideration. The claimant has presented the actual compilation of the amount payable to the claimant giving effect to all the bills as reflected at page 202 and 205 of the State of Defence in a table which has been incorporated in paragraph 52 of this Award.

The claimant has mentioned the following items being their claims against the respondent-TRF:-

       Amount payable as admitted by respondent-              Rs. 1,18,81,917.00
       TRF
       Less: Amount paid to the claimant                      Rs. 76,14,273.00
       Net Amount payable                                     Rs. 42,67,644.00
       Add:- (i) Amount payable on account of RA-             Rs. 13,65,825.00
       1 kept as deduction & hold
       (ii) Amount payable on account of RA-2 kept
       as deduction & hold

                                                              Rs. 13,65,707.00
                                                              Rs. 69,99,176.00
       Add: Amount not paid in EW-2, Unloading                Rs. 26,49,359.00
                                               4                    Commercial Appeal No. 09 of 2020




       bill, RW-1, IR-2 & IR-1
       Amount payable to claimant-                           Rs. 96,48,535.00
       Less: - Amount claimed under Claim No. 1             Rs. 93,00,844.00
       Different of amount payable but not                  Rs. 3,47,691.00

N.B.:- (i) Claim for idled charges of Rs. 12,84,114/- not included since the same amount is claimed under Claim No. 2.

(ii) Proof of submitting R/A Bill No. and R/A Bill No. 9 are available at page 51 and 52 respectively of State of Claim

58. From perusal of the State of Defence of the respondent-TRF at page 205 (Chart), outstanding balance of the claimant has been shown Rs. 47,61,482/-. Such amount has been shown after not taking into consideration of the bills of the claimant with regard to RA-8 (Placement), RA-9 (Placement), RA-1, 2 and 3 (Alignment) and EW-2 (extra work).

The respondent-TRF though in its State of Defence has shown the bills related to RA-8 and RA-9 not being received, later on it was clarified that though such bills were presented, but it were not in consonance with the protocol requirements, hence not considered. The clause no.7 of the original Minutes of Meeting provided the procedure for presentation of bills which is mandatory in nature and the claimant had consented to follow such procedure. The provisions provided that each bill should be signed by the representatives of Tata Steel Limited, M.N. Dastur & Co., TRF Ltd and the claimant. Admittedly, the RA-8 and RA-9 bills did not bear the signatures of all the said parties to protocol. The respondent-TRF has given the logic that such bills were bogus since not signed by all the members of protocol but admittedly bills were signed by the claimants and the representative of the respondent-TRF. Yet, it were not the valid bills for payment, produced in contravention of Clause 7 of Minutes of Meeting under a valid contract and therefore, R/A Bill Nos.8 and 9 have rightly not been considered.

59. Similar is the case with EW.2 (extra work), RA-3 (alignment), RW-1, IR- 2 and IR-1 (unloading) whereunder the claimant has claimed a sum of Rs.26,49,359/-, RA-3 Bill has not been considered by the respondent-TRF on the ground that welding, which was the essential part of alignment under the contract, the claimant did not execute such welding part after alignment of machineries, as such the respondent-TRF declined for payment due to breach of contract.

As regards bills related to EW-2 (extra work), RW-1, IR-2 and IR- 1, its payments have been denied by the respondent-TRF on the ground of not being applicable. It is not a fact that the respondent-TRF has accepted such bills at page 205 of the State of Defence being the pending bills. Therefore, the above bills are not payable in view of the argument of the respondent, otherwise also, the said bills since did not follow the protocol requirement, were not considered. I find substance in the submission and therefore, no claim is made out under such head in favour of the claimant."

11. The claim no.2 was in respect of the compensation for idle manpower and machinery to the tune of Rs.11,42,867/- which has been rejected. The claim no.3 was made on account of anticipated profit which was also not accepted by the learned Arbitrator.

12. The claim nos.2 and 3 have been dealt with by the learned Arbitrator as under:

"60. With regard to Claim No.2 i.e. the idling charges, the claimant stated that it had mobilized the men, machineries and tools to the worksite, but no work front was provided since ground work for raising construction was not completed by the agency. The claimant was in readiness and preparedness for 5 Commercial Appeal No. 09 of 2020

execution of assigned contract work. The claimant further stated that since the respondent-TRF went on reducing the scope of work unilaterally, the claimant having no work, had to remain idle and hence, made his claim for a sum of Rs.11,42,857/- against the respondent- TRF.

Much has been argued on behalf of the respondent-TRF against the claimant as to how the latter adopted a lethargic approach and considerably delayed the work by not fulfilling the mandatory provision of law under the Contract Labour Act, Provident Fund, Workmen's Compensation Act, etc and last, not the least, connection of electricity to be obtained from the respondent-TRF. The claimant presented first bill RA-1 at much later stage, though there was direction to start the work immediately after signing of the original Minutes of Meeting on 16.04.2013 and purchase order on 22.04.2013. Much have been argued on behalf of the parties on this issue and to my view, the scope of the work of the claimant was reduced to 25% of the total work order for the fault of the claimant itself and in this manner, the claimant failed to prove its claim of Rs.11,42,567/- being the compensation towards idling of their men & machineries. The claimant has claimed loss of profit @8% of the remaining work worth Rs.3,17,89,407/- which was given to other agency, which amounts to Rs.25,43,152/-. Admittedly, claimant's work was reduced to 25% of the total work worth Rs.4,96,06,800/- and thereby was prevented which incurred loss of opportunity to earn profit being lost for none of the default of the claimant. Much has been argued on behalf of both the parties and Arbitral Tribunal comes to conclusion that owing to own fault of the claimant, 75% work was taken away and for that, the claimant cannot be compensated under the head "loss of opportunity to earn profit" and it is decided against the claimant. Clause 31 of the Minutes of Meeting clearly indicates that, "if progress of work is inadequate, TRF reserves the right to add other vendors at M/s Shiva Shakti's risk and cost."

13. As noticed above, claim no.4 was for grant of interest over the sums awarded under claim nos.1, 2 and 3. Therefore, once the claim nos.1, 2 and 3 stood rejected, the learned Arbitrator could not have dealt with the issue regarding the award of interest. A glance at the arbitral award dated 21st October 2018 would however reflect that misconstruing his own reference as formulated under the claim no.4, the learned Arbitrator proceeded to grant interest over a sum of Rs.47,61,482/- which, in fact, is the amount claimed by the Company, a reference of which has been made in the statement of defence vide Exhibit 16.

14. Mrs. Shilpi Sandil Gadodia, the learned counsel for the appellant has contended that the order passed by the Commercial Court at Jamshedpur ignores the fundamental defect in the award dated 21st October 2018 inasmuch as the arbitral award travels beyond the reference and issues framed himself by the learned Arbitrator. The learned counsel for the appellant seeks support from clause (iv) to sub-section (2) of section 34 of the Arbitration and Conciliation Act, 1996 (in short, AC Act) which specifically provides that the arbitral award may be set aside if it deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration.

6 Commercial Appeal No. 09 of 2020

15. From pleadings of the parties and the claims raised by the claimant, it can be easily ascertained that jurisdiction of the Arbitrator and the matter referred before him were confined to the claims as aforesaid. This is the law declared by the Hon'ble Supreme Court that where the agreement or reference to arbitration requires specific disputes to be referred to the Arbitrator such specific reference shall decide the Arbitrator's jurisdiction and he cannot travel beyond the reference nor entertain any additional claims or counter-claims which are not part of the dispute. This is also well established that where the arbitral Tribunal renders an award and decides the matters beyond the scope of the contract or beyond the dispute referred for arbitration the arbitral award shall be held beyond the scope of submission to arbitration. Clause (iv) of sub-section (2) to section 34 of the AC Act provides that the arbitral award can be set aside if it deals with the dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration.

16. Section 34(2)(a)(iv) of the AC Act reads as under:

"(2) An arbitral award may be set aside by the Court only if-- ...............................................................................................

(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or"

17. Now this is not in the realm of any doubt that an arbitral award can be set aside on the grounds provided under sub-section (2) to section 34. In "M.S.K. Projects (I) (JV) Ltd. V. State of Rajasthan" (2011) 10 SCC 573 the Hon'ble Supreme Court has held as under:

"15. The issue regarding the jurisdiction of the Arbitral Tribunal to decide an issue not referred to is no more res integra. It is a settled legal proposition that special tribunals like Arbitral Tribunals and Labour Courts get jurisdiction to proceed with the case only from the reference made to them. Thus, it is not permissible for such tribunals/authorities to travel beyond the terms of reference. Powers cannot be exercised by the Tribunal so as to enlarge materially the scope of reference itself. If the dispute is within the scope of the arbitration clause, it is no part of the province of the court to enter into the merits of the dispute on the issue not referred to it. If the award goes beyond the reference or there is an error apparent on the face of the award it would certainly be open to the court to interfere with such an award. (Vide Grid Corpn. of Orissa td. v. Balasore Technical School and DDA v. R.S. Sharma and Co.)"

7 Commercial Appeal No. 09 of 2020

18. In "Ssangyong Engineering & Construction Co. Ltd. v. NHAI"

(2019) 15 SCC 131 clause (iv) of sub-section (2) to section 34 of the AC Act has been expounded by the Hon'ble Supreme Court as under:

"68. A conspectus of the above authorities would show that where an Arbitral Tribunal has rendered an award which decides matters either beyond the scope of the arbitration agreement or beyond the disputes referred to the Arbitral Tribunal, as understood in Praveen Enterprises, the arbitral award could be said to have dealt with decisions on matters beyond the scope of submission to arbitration.

69. We therefore hold, following the aforesaid authorities, that in the guise of misinterpretation of the contract, and consequent "errors of jurisdiction", it is not possible to state that the arbitral award would be beyond the scope of submission to arbitration if otherwise the aforesaid misinterpretation (which would include going beyond the terms of the contract), could be said to have been fairly comprehended as "disputes" within the arbitration agreement, or which were referred to the decision of the arbitrators as understood by the authorities above. If an arbitrator is alleged to have wandered outside the contract and dealt with matters not allotted to him, this would be a jurisdictional error which could be corrected on the ground of "patent illegality", which, as we have seen, would not apply to international commercial arbitrations that are decided under Part II of the 1996 Act. To bring in by the backdoor grounds relatable to Section 28(3) of the 1996 Act to be matters beyond the scope of submission to arbitration under Section 34(2)(a)(iv) would not be permissible as this ground must be construed narrowly and so construed, must refer only to matters which are beyond the arbitration agreement or beyond the reference to the Arbitral Tribunal."

19. Mrs. Shilpi Sandil Gadodia, the learned counsel for the appellant has submitted that in view of the patent illegality in the arbitral award dated 21st October 2018 the rejected portion of the counter-claim is liable to be returned to the learned Arbitrator for a fresh decision. To corroborate this submission, the learned counsel for the Company has referred to the judgment passed in "NHAI v. M. Hakeem" (2021) 9 SCC 1.

20. In "M. Hakeem" the Hon'ble Supreme Court held that the powers to set aside award under section 34 of the AC Act do not include a power to modify the award. It has been further held that the Court is given the limited judicial interference on extremely limited grounds not dealing with the merits of an award and this "limited remedy" under section 34 is co-terminous with the "limited right", namely, either to set aside an award or remand the matter under the circumstances mentioned in section 34 of the AC Act. In our opinion, "Hakeem" does not lay down a law that the rejected claim(s) can be referred to the Arbitrator for a fresh determination.

21. The Company raised claims under seven heads by filing a counter- claim seeking award of Rs.29,19,27,036/- with interest @ 18% per annum over the total claim from the due date of payment till the actual date of payment. The counter-claims under seven heads included the claim for expenses and incidental 8 Commercial Appeal No. 09 of 2020

costs incurred for the remaining work, loss of goodwill, loss of profit, liquidated damages and prolongation of work period. The learned Arbitrator partly allowed the claim for loss of goodwill to the tune of Rs.10 crores and partly allowed the claim of Rs.94,46,696/- towards additional expenses and incidental costs with 18% interest per annum; the costs as per actuals. The claimant, a partnership firm, was carrying on business in infrastructural development. It was awarded a contract for Rs.4,96,06,800/- by the Company for mechanical erection of its conveyor and other related structural equipments. Under the contract, there was a provision for liquidated damages to be levied @ 5% per week for maximum of 5% of the contract value in case of delay attributable to the contractor. The case set up by the claimant is that it had mobilized manpower and machinery but site was not made available between May 2013 to November 2013. A further grievance raised by the claimant is that the Company started making deductions from the running bills and/or did not make payment of the bills for longer periods, though it executed extra work under the instructions of the Field Engineer. According to the claimant, till 29th September 2016 it continued to write letters and making requests for payment but no response came from the Company. Constrained, the claimant gave a notice for appointment of an Arbitrator for resolution of the dispute between the parties.

22. The counter-claims raised by the appellant has been dealt with by the learned Arbitrator in the following manner:

  Sl. Particulars                                  Amount (In Rs.)       Remarks of the
  No.                                                                    learned Arbitrator
  1   Claim on account of additional overhead      Rs.94,46,696/-        Partly allowed
      and other incidental cost and expenses for
      getting such remaining worm done by
      other agencies which is 25% of the
      balance job (25% of Rs. 3,77,86,784/-)
      amounting to Rs. 94,46,696/-
  2   The claim for an amount of Rs. 2.00          Rs.2,00,00,000.00     Rejected
      Crores claimed on account of cost
      incurred by the Respondent due to
      prolongation of period of work by the
      claimant.
  3   Claim on account of imposition of            Rs.24,80,340.00       Rejected
      Liquidated Damages as per the letter of
      Intent/Purchase Order terms.
  4   Claim on account of loss of goodwill.        Rs.10,00,00,000.00 Partly Allowed

  5    Claim on account of loss of profit due to Rs.16,00,00,000.00 Rejected
       loss of further orders from Tata Steel
        Total                                    Rs.29,19,27,036.00

  6    Claim on interest @ 18% per annum on                              Allowed
       the total claims from the due date of
                                                9                        Commercial Appeal No. 09 of 2020




        payment till the actual date of payment.
  7     Claim towards cost.                            As per actual.            Allowed



23. The award made in favor of the claimant for interest over a sum of Rs.46,61,462/- is no doubt beyond the reference and, thus, perverse but the disallowed claims under counter-claim of the Company cannot be sent back to the Arbitrator. This is within the scope of judicial intervention as envisaged under section 34 of the AC Act that a part of the award which is severable can be saved. While setting aside the other portions which fall under the sweep of sub- section (2), in no eventuality the disallowed claims in the claim petition or counter-claim can be remitted back to the learned Arbitrator for a fresh consideration. In "Kinnari Mullick v. Ghanshyam Das Damani" (2018) 11 SCC 328 the Hon'ble Supreme Court held that the award can be sent back to the Arbitrator only under the circumstances mentioned in section 34(4) of the AC Act, which provides as under:

"(i) there is a written request made by a party to the arbitration proceedings,

(ii) the arbitral award has not already been set aside and

(iii) the challenge to the award has been set up under S. 34 about the deficiencies in the arbitral award which may be curable by allowing the Arbitral Tribunal to take such measures which can eliminate the grounds for setting aside the arbitral award."

24. The learned Arbitrator has extensively dealt with the claims raised by the Company and disallowed the claim nos.2, 3 and 5 by recording sufficient reasons. The Commercial Court could not have re-appreciated the evidence or interfered with the findings recorded by the learned Arbitrator on these claims. This is well settled a law that in section 34 petition the Court cannot by appreciating the materials go into the merits of the matter and form a different opinion. This is also a well-settled position in law that the powers under section 13(1-A) of the Commercial Courts Act, 2015 cannot be wider than section 34 of the AC Act. In "MMTC Ltd. v. Vedanta Ltd." (2019) 4 SCC 163 the Hon'ble Supreme Court has observed as under:

"12. It is only if one of these conditions is met that the Court may interfere with an arbitral award in terms of Section 34(2)(b)(ii), but such interference does not entail a review of the merits of the dispute, and is limited to situations where the findings of the arbitrator are arbitrary, capricious or perverse, or when the conscience of the Court is shocked, or when the illegality is not trivial but goes to the root of the matter. An arbitral award may not be interfered with if the view taken by the arbitrator is a possible view based on facts. (See Associate Builders v. DDA. Also see ONGC Ltd. v. Saw Pipes Ltd.; Hindustan Zinc Ltd. v. Friends Coal Carbonisation; and McDermott International Inc. v. Burn Standard Co. Ltd. ) 10 Commercial Appeal No. 09 of 2020

13. It is relevant to note that after the 2015 Amendment to Section 34, the above position stands somewhat modified. Pursuant to the insertion of Explanation 1 to Section 34(2), the scope of contravention of Indian public policy has been modified to the extent that it now means fraud or corruption in the making of the award, violation of Section 75 or Section 81 of the Act, contravention of the fundamental policy of Indian law, and conflict with the most basic notions of justice or morality. Additionally, sub-section (2-A) has been inserted in Section 34, which provides that in case of domestic arbitrations, violation of Indian public policy also includes patent illegality appearing on the face of the award. The proviso to the same states that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.

14. As far as interference with an order made under Section 34, as per Section 37, is concerned, it cannot be disputed that such interference under Section 37 cannot travel beyond the restrictions laid down under Section 34. In other words, the court cannot undertake an independent assessment of the merits of the award, and must only ascertain that the exercise of power by the court under Section 34 has not exceeded the scope of the provision. Thus, it is evident that in case an arbitral award has been confirmed by the court under Section 34 and by the court in an appeal under Section 37, this Court must be extremely cautious and slow to disturb such concurrent findings."

25. Having regard to the aforesaid discussions, the order dated 16th January 2020 passed in Arbitration Case No.4 of 2019 is set aside to the extent the arbitral award dated 21st October 2018 in respect of the award of interest to the claimant over a sum of Rs.47,61,482/- was affirmed by the Commercial Court. Consequently, the aforesaid portion of the award as indicated in paragraph 61 of the arbitral award dated 21st October 2018 is quashed. However, as regards adjudication of the counter-claim raised by the Company the award is affirmed and the order passed in Arbitration Case No.4 of 2019 is approved to that extent.

(Shree Chandrashekhar, J.)

(Anubha Rawat Choudhary, J.) Binit/Mukul

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter