Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Satyam Ferro-Tech (P) Ltd. A ... vs The State Of Jharkhand Through The ...
2023 Latest Caselaw 1613 Jhar

Citation : 2023 Latest Caselaw 1613 Jhar
Judgement Date : 17 April, 2023

Jharkhand High Court
Satyam Ferro-Tech (P) Ltd. A ... vs The State Of Jharkhand Through The ... on 17 April, 2023
                 IN THE HIGH COURT OF JHARKHAND AT RANCHI

                               W.P. (C) No. 2129 of 2010

            Satyam Ferro-Tech (P) Ltd. A company registered under the
            companies Act, 1956 having its registered office at Kalyani
            Apartment, 1st Floor, Gandhi Chowk, Giridih, 815301, P.O. and P.S.
            Giridih, District Giridih (Jharkhand) through its Director Binod
            Kumar Agarwala, Son of Late Vishwanath Agarwala, Resident of
            Bara Chowk, Opposite Circuit House, Giridih, P.O. and P.S. Giridih,
            District Giridih                        ...     ...      Petitioner
                                       Versus
            1. The State of Jharkhand through the Secretary, Industries
            Department, Nepal House, Doranda, P.O. and P.S. Doranda, Ranchi
            834002, District Ranchi
            2. Director of Industries, Engineer's Building, Sector-III, Dhurwa,
            P.O. and P.S. Dhurwa, Ranchi-834004 District Ranchi
            3. General Manager, District Industries Centre, Giridih, 815301
            P.O. and P.S. Giridih, District Giridih ...        ...       Respondents
                                       ---

CORAM :HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY

---

            For the Petitioner         : Ms. Aakansha Mittal, Advocate
                                         Ms. Niharika Nidhi, Advocate
            For the Respondents        : None
                                ---


09/17.04.2023         Learned counsel for the petitioner is present.
                2.    Nobody appears on behalf of the respondents.

3. Learned counsel for the petitioner submits that the matter has been listed pursuant to the order dated 22.02.2022 passed in L.P.A. No. 65 of 2011. She submits that the dispute in the present case relates to interest subsidy and the surviving grievance of the petitioner is only in relation to the financial year 2006-07 and 2007-08. She submits that so far as rest of the financial years are concerned, the grievance of the petitioner has already been redressed. She submits that there is no dispute that there has been delay in submission of application in interest subsidy for the financial year 2006-07 and 2007-08. The application for the year 2006-07 was filed on 10.12.2007and there was delay of 2 months 10 days. The application was required to be filed within a period of six months from the date of closure of the financial year. So far as 2007-08 is concerned, the same was filed on 31.10.2008 and there was delay of one month.

4. Learned counsel has submitted that reason for delay was that the required certificate from the Commercial Taxes department was

issued belatedly. She has referred to the interlocutory application to submit that the application for giving turnover and tax payment certificate for the year 2006-07 was filed on 06.09.2007 prior to expiry of the period prescribed for filing the application, but the same was made available only by memo No. 61 dated 02.03.2009. So far as period 2007-08 is concerned, the application for issuance of the turnover and tax payment certificate was filed on 19 th of August, 2008 which was also much before the expiry of the period of six months but the same was issued vide memo No. 612 dated 19.11.2008 and the application for the period 2007-08 was already filed on 31.10.2008.

5. The learned counsel submits that a letter dated 03.05.2008 was issued by the Industries Department by referring to the letter of the petitioner dated 10.12.2007 relating to the period 2006-07 mentioning therein that the required documents to be filed which included the reason for delay.

6. She submits that pursuant to the letter dated 03.05.2008 (Annexure-7) which was issued vide memo No. 124 dated 12.02.2009 as mentioned in Annexure-7 itself, the petitioner duly responded vide letter dated 13.03.2009 addressed to the General Manager, District Industry Centre, mentioning therein that the reason for delay for submission of application was that the payment certificate from the Sales Tax Authority could not be obtained within the time frame. She submits that although no separate petition for condonation of delay was filed, but the reason for delay was mentioned vide Annexure-8 itself.

7. Learned counsel submits that while rejecting the claim of the interest subsidy by the impugned order dated 22.03.2010, the reason for condonation of delay as mentioned in Annexure-8 i.e. letter dated 13.03.2009 has not been considered. She submits that the response was filed before the General Manager, District Industry Centre, Giridih i.e. through proper channel but it appears that the said letter was not considered by the Director, Industries while passing the impugned order by stating that no reason has been assigned for delay in submitting the application.

8. Learned counsel has also submitted that so far as the period 2007-08 is concerned, the required turnover and tax payment

certificate was also issued belatedly i.e. on 18.11.2008 though it was applied for within time. She submits that there has been no delay and laches on the part of the petitioner and rather the delay and laches is totally attributable to the Commercial Taxes Department who had delayed in issuance of the turn over and tax payment certificate.

9. The learned counsel submits that in view of the aforesaid facts and circumstances the impugned order dated 23.10.2010 rejecting the application of the petitioner for interest subsidy for the period 2006-07 and 2007-08 on the ground that there is no reason for condonation of delay is fit to be set aside and the petitioner is held to be entitled for the interest subsidy for the aforesaid periods. She submits that the interest subsidy amount for the period 2006-07 is Rs. 50,87,136/- and for the period 2007-08 is Rs. 49,54,842/-.

10. Post this case for judgment on 14.06.2023.

(Anubha Rawat Choudhary, J.) Binit

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter