Citation : 2022 Latest Caselaw 4465 Jhar
Judgement Date : 9 November, 2022
IN THE HIGH COURT OF JHARKHAND AT RANCHI
(Civil Writ Jurisdiction)
WP(C) No. 3675 of 2019
Himanchal Construction Company Pvt. Ltd. ..... ...... Petitioner
Versus
The State of Jharkhand & Ors. .... .... Respondents
------
CORAM : HON'BLE MR. JUSTICE KAILASH PRASAD DEO
-------
For the Petitioner : Mr. Shresth Gautam, Advocate For the Respondents-State : Mr. Mohan Kumar Dubey, AC to AG For the respondent nos.2 to 4: Mr. Shivam Singh, Advocate
--------
The matter is being taken up through Video Conferencing. Learned counsel for the parties have no objection with it and submitted that audio and video qualities are good.
Order No.05 /Dated: 09th November, 2022 Heard, learned counsel for the petitioner, Mr. Shresth Gautam. The writ petition has been preferred by Himanchal Construction Company Pvt. Ltd., a company incorporated under companies act, 1956 for quashing the order dated 12.06.2019 (Annexure-38) as contained in Memo No.110/17/1103 as well as the order dated 24.12.2018 (Annexure-36) as contained in Memo No.110/17/3109, whereby and where under the respondent-authority, in compliance of the order passed by the co-ordinate Bench of this Court in W.P.(C) No.433 of 2018 dated 19.06.2018, has rejected the claim of the petitioner on the ground that the executive engineer has already terminated the contract of the petitioner on 22.06.2009.
Learned counsel for the petitioner has further prayed for quashing the order dated 22.06.2009 (Annexure-37) as contained in letter no.178, passed by the executive engineer, Khunti, whereby the contract of the petitioner has been illegally cancelled.
Learned counsel for the petitioner has further prayed, that upon quashing these orders, this court may direct the respondent-authority to give effect to the directions issued by the Chief Engineer for foreclosing of the contract of the petitioner, executed for road construction under the PMGSY scheme under package no.Jh-1810 phase IV Khunti Division and declare the order dated 22.06.2009 as contained in Letter No.178, passed by the executive engineer, Khunti is bad in law.
Learned counsel for the petitioner has submitted, that in pursuance
of the Notice Inviting Tender vide Notice no.1/2006-07 for construction of rural roads, the petitioner participated in the bids for construction of roads under Package No.JH-1810 of P.M.G.S.Y. 4th phase. Thereafter the petitioner was allotted the work vide Letter No.1616 dated 18.07.2006, issued by the then Chief Engineer, R.E.O., Ranchi. The said contract is of Rs.363.749 lakhs for construction of 5 roads dated 07.08.2006 within nine months. The details of the progress of the work, and the roads to be completed may be recorded hereunder:-
SL. No. Name of Road Length
(i) Salgadih Canal to Dimbojarda 1.3 Km
(ii) Salgadih Canal to Janumpiri 4.56Km-completed
(iii) Sarjamdih to Birgaon 3.50Km
(iv) Jiling Sering to Kurkutta 3.685Km
(v) NH 33 to Gango 2.20Km-completed
Learned counsel for the petitioner has further submitted, that out of five works, two works i.e., Salgadih Canal to Janumpiri, 4.56 Km length and NH 33 to Gango, 2.20 Km length have been completed. The remaining three works were not completed as because the land for construction of road has never been acquired by the State and this is a practice in the State of Jharkhand, which has been deprecated in the judgment passed in the case of National Projects Construction Corporation Limited vs. The State of Jharkhand & Ors. In L.P.A. No.312 of 2018, passed by the Hon'ble Division Bench of this Court on 25.06.2018. Paragraphs-6 to 9 of which may be quoted hereunder.:-
"6.Thus, the State Government has not fulfilled the aforesaid two conditions. The work of the aforesaid road construction was not completed within a period of 18 months. Land acquisition is sovereign power vested in the State. Land acquisition power cannot be assigned to the contractor, and hence, unless the full site is available, full road cannot be constructed by the contractor. This aspect of the matter was neither properly appreciated by the respondents - State while issuing the impugned order dated 26.02.2018 (Annexure - 5), nor it was properly appreciated by the learned Single Judge while disposing of the writ petition being W.P.(C) No.2701 of 2018. We, therefore, quash and set aside the order passed by the learned Single Judge in W.P.(C) No.2701 of 2018, dated 07.06.2018 as well as the impugned order dated 28.02.2018, which is at Annexure- 5 to the memo of this Letters Patent Appeal.
7. No reply is filed of paragraph nos.15 & 17 of the writ petition, by the State Government. Much has been argued out by the counsel for the respondents - State that no error has been committed by the Government while
issuing the impugned order. It ought to be kept in mind that whenever any road is to be constructed, the land site must be given to the contractor free form all encumbrances. If the land acquisition is to be done, it ought to have been clear prior to the notice inviting tender.
8. It has become a fashion in the State of Jharkhand to publish a notice inviting tender for a particular work and within the time bound, schedule work is to be completed, without, obtaining clearance of the forest department or without acquiring land or without providing proper and adequate police protection in naxalite affected areas. Thus, one or other type of work is yet to be completed by the Government, a notice inviting tender is published. This case is no exception of such type of general behaviour of the Government.
9. In the facts of the present case land acquisition process is yet to be completed for few patches of land. In such eventualities notice inviting tender should not have been published at all. No work can be completed within 18 months without the land acquisition. If such type of work is completed within 18 months of road construction, the land acquisition should have been completed within 8 months by the State Government. Those who are living in a glasshouse beware of throwing stones at others. Thus, if the State Government has failed to acquire the land in question, then it should not have issued the impugned order dated 28.02.2018 (annexure - 5), hence, we also quash and set aside the impugned order."
Learned counsel for the petitioner has further submitted, that even this Court has found that roads have been constructed by the Road Construction Department in the District of Gumla, Koderma, Deoghar and Giridih but without acquisition of land work has been done, money has been spent illegally. When the matter came up before this Court in the writ jurisdiction, this Court has directed to the Chief Secretary, Government of Jharkhand to enquire into the matter that before the land is being acquired, how the roads have been constructed and how the tenders are being issued and how the funds are being allotted and released? This shows that there is organized crime in the State of Jharkhand to siphoned off the money. This Court has passed such order in W.P.(C) No.1224 of 2020 in the District of Gumla, W.P.(C) No.2847 of 2020 in the District of Koderma, W.P.(C) No.2466 of 2020 in the District of Deoghar, and W.P.(C) No.3174 of 2020 in the District of Giridih. Apart from that the Hon'ble Division Bench of this Court has already considered the same in the year 2018. This means that the State Officials are not taking any lesson from the judicial order and they are working as per their whims and fancies to siphoned off the money from the State Exchequer.
Learned counsel for the petitioner has further submitted, that before
acquisition of land a file cannot be moved for construction of road and for allotment of funds, though it has been mentioned in the Notice Inviting Tenders at Column-3 of Section 1 which is at page no.79 of the writ petition, where a wrong statement has been made by the State-authorities that the site for the work is available but it will be apparent, from their own record that the land has been never been acquired, that is why the road could not be completed in three allotted works.
Learned counsel for the petitioner placed reliance upon the letter issued by the Superintending Engineer, as contained in Memo No.454 dated 10.06.2009, where they have categorically mentioned in serial no.1-xzkeh.k ls iwNus ij crk;k x;k fd mDr Hkkx esa laosnd }kjk dk;Z fd;k tk jgk Fkk ysfdu tehu fookn ds dkj.k dk;Z ugha fd;k tk ldkA Learned counsel for the petitioner has further submitted, that all the three works which have not been completed only because of the objection made by the land lord or raiyat and thus it appears that even in the State of Jharkhand, false information are being given in the Notice Inviting Tenders and they are not taking any lesson from the judicial order passed by this Court.
Learned counsel for the petitioner has further submitted, that the Junior Engineer, Bundu has also submitted his report to the Executive Engineer, Khunti on 25.05.2012, stating therein that dzekad 4 esa of.kZr ftfyax flfjax ls dqjdqÍk iFk ds rhljs fd0eh0 esa yxHkx 100 eh0 iFkka'k jS;rh Hkwfe gS ftldk LokehRo Jh ujs'k egrks xzk0& dksMk+Mhg lksukgkrw ds iklk gSA HkwLokeh us mDr iFkk"k esa dk;Z iwjh rjg ls cUn djok fn;k gSA vusdksa ckj lEidZ djus ds ckn Hkh iFk fuekZ.k gsrq Hkweh nsus bUdkj fd;k gS lkFk gh Hkwfe ls lacaf/kr fdlh Hkh rjg dk dkxtkr fyf[kr :i esa nsus ls Hkh bUdkj fd;k gSA Learned counsel for the petitioner has thus submitted, that this itself shows that whatever the State have mentioned in their Notice Inviting Tenders at page no.79 in Column-3 of Section-1 of the writ petition the site for the work is available, is a false statement.
Learned counsel for the petitioner has further submitted, that in year 2012 the then Executive Engineer, Khunti in terms of letter no.1246 dated 24.12.2012 addressed to the petitioner, has submitted, that the work granted to the petitioner vide Argeement No.SBD No.KH01/2006-07 of Package No.JH-1810 of fourth phase under P.M.G.S.Y is foreclosed and all the earlier orders issued with this respect are hereby rectified or amended.
Learned counsel for the petitioner has submitted, that this letter is of dated 24.12.2012, but respondents are still relying upon the letter, issued under Letter No.178 dated 22.06.2009, whereby Executive Engineer xzk0dk0fo0 dk;Z izea.My] [kw¡Vh has mentioned in the last paragraph, that the agreement is hereby cancelled, the security money is confiscated and name of the company is being recommended to the higher authorities for blacklisting.
Learned counsel for the petitioner has thus submitted, that once letter no. 1246 dated 24.12.2012 has been issued by the same officer i.e., Executive Engineer, Khunti making all correction in the previous orders, the letter No.178 dated 22.06.2009 itself merges with rectification letter dated 24.12.2012.
Learned counsel for the petitioner has placed reliance upon Clause 24, 24.1, 24.2 and 24.5 of the Notice Inviting Tenders, which are at page 109 and 110 of the writ petition, to submit, that in case of any dispute there is a Dispute redressal system before the Chief Engineer.
Thus petitioner being aggrieved of such act of the respondent has filed an application before the Chief Engineer, JSRRDA, Ranchi on 23.04.2012, which was sent under speed post, which has been brought on record as Annexure-24 to the writ petition at page no.209 to 210 and thereafter the Chief Engineer, JSRRDA, Ranchi in terms of letter no. JSRRDA-84/09-1457 dated 12.05.2012 has issued notice to the v/kh{kd vfHk;ark] xzkeh.k dk;Z foHkkx dk;Z vapy] jk¡ph] dk;Zikyd vfHk;ark] xzkeh.k dk;Z foHkkx dk;Z ize.My] [kw¡Vh as well as to the petitioner esllZ fgekapy da'VªD'ku da0 iz0 fy0] 11 H/G vkn'kZuxj te'ksniqj for their appearance on 24.05.2012 at 12:30 P.M.
Learned counsel for the petitioner has further submitted, that it is surprising that thereafter a report was called for and the same has been submitted by the Junior Engineer, Bundu on 25.05.2012, which has been brought on record as Annexure-26 at page no.213 of the writ petition, whereby the Junior Engineer, Bundu in his report addressed to dk;Zikyd vfHk;ark xzkeh.k dk;Z foHkkx] dk;Z ize.My] [k¡qVh has admitted, that the land has been given for construction. The Chief Engineer, JSRRDA, Ranchi, on the basis of the materials available on record has passed an order on 15.09.2012 as contained in Letter No. JSRRDA-84/09-3136, stating therein that the agreement is foreclosed, take necessary action for resolution of land and other dispute on urgent basis so that connectivity of the target habitations be achieved and expenditure be fruitful. This letter/order has been issued with
the approval of Principal Secretary-cum-CEO, JSRRDA, Ranchi, (File No.JSRRDA-84/09-N.S. Page 22).
Learned counsel for the petitioner has further submitted, that once the agreement is foreclosed as because the land has not been acquired, there is no occasion for the respondent to confiscate the security money or to black list of the petitioner.
Learned counsel for the petitioner has further submitted, that in the counter-affidavit dated 14.11.2019, filed by Prem Nath Ram, son of Late Kashi Nath Ram, the then Executive Engineer RDD (KWA) works Division, Khunti, wherein Annexure-N at page 78 states the order passed by the Hon'ble Division Bench of this Court in W.P.(PIL) No.7015 of 2012, which was preferred by one Ranjit Kumar Mahato against the State of Jharkhand & Ors. for the work allotted to the petitioner, where they have wrongly stated that respondents have filed counter-affidavit and submitted that security money of Rs.23,20,382/- has been forfeited and the said contractor has already been black listed for which a communication dated 22.06.2009 has been given to the said contractor.
Learned counsel for the petitioner has further submitted, that this letter has already been brought on record in the writ petition as Anenxure-37, as contained in Letter No.178 dated 22.06.2009, whereby the recommendation has been with regard to black listing and subsequently the Executive Engineer, Khunti has categorically mentioned in his order, as contained in Letter No.1246 dated 24.12.2012 that all earlier orders issued with respect.
Learned counsel for the petitioner has further submitted, that the petitioner has applied under the R.T.I. Act to have a copy of the counter- affidavit filed in W.P.(PIL) No.7015 of 2012, but a wrong statement has been issued by the Executive Engineer, RDD (RWA) works Division, Khunti on 16.01.2017 which is at page no.62 of the rejoinder filed by the petitioner on 09.10.2021, whereby at column no.5 they have stated no counter-affidavit in W.P(PIL) 7015 of 2012, Ranjit Kumar Mahto v/s State of Jharkhand has been filed.
Learned counsel for the petitioner has further submitted, that it appears that in the State of Jharkhand, no law is prevailing. The State is working as per their own choice, own pleading without perusal their own
record. If the Chief Engineer has already foreclosed the account of petitioner, meaning thereby no officer below the rank of Chief Engineer can pass any order and till date no black listing order has been brought on record, but only by shouting that blacklisting has been done, the respondents have confiscated the security money of the petitioner.
Learned counsel for the petitioner has further submitted, that the counter-affidavit is being filed by the Executive Engineer without taking note of the judgment passed by the Hon'ble Division Bench of this Court in the year 2018 as well as the orders passed by this Court, whereby this Hon'ble Court has referred several matters to the Chief Secretary, Government of Jharkhand to look into the matters, where financial irregularities is being committed in the State of Jharkhand, without acquisition of land the road is being constructed and funds have been allotted but till date nothing has improved.
Learned counsel for the petitioner has further submitted, that the Secretary, Rural Works Department-cum-CEO, JSRRDA, Ranchi may be directed to file a detail counter-affidavit, so that being a senior officer he can look into the order passed by the Chief Engineer as per the agreement as well as orders of Superintending Engineer, Executive Engineer and Junior Engineer with regard to the fact and a heavy cost may be imposed upon the Executive Engineer for misleading the court and filing a fresh affidavit before this Court with regard to the counter-affidavit filed in W.P.(PIL) No.7015 of 2012.
Learned counsel for the respondents/State Mr. Mohan Kumar Dubey, AC to AG has submitted, that let the detail and fresh counter-affidavit be filed.
The Secretary, Rural Works Department-cum-CEO, JSRRDA, FFP Building, 2nd Floor, H.E.C, Campus, Dhurwa, P.O.-Dhurwa, P.S. Jagannathpur,Ranchi is directed to file detail counter-affidavit in this matter as there are conflicting orders passed by their officers like Chief Engineer, Executive Engineer and Junior Engineer. The affidavit must be filed with approval of the Chief Secretary, Government of Jharkhand within a period of four weeks.
Put up this case on 20.12.2022 under the same heading. It is made clear that if, the affidavit is not filed in compliance of the
order, this Court may withheld the salary of the Secretary of the Department.
Let a copy of this order be communicated to the Chief Secretary, Government of Jharkhand and the Secretary, Rural Works Department-cum- CEO, JSRRDA through FAX/e-mail.
(Kailash Prasad Deo, J.) Rohit/-
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!