Citation : 2022 Latest Caselaw 3427 Jhar
Judgement Date : 29 August, 2022
-1-
IN THE HIGH COURT OF JHARKHAND AT RANCHI
Commercial Appeal No.4 of 2021
----
Senbo Engineering Ltd., a company registered under the provisions of the Companies Act, 1956, having registered office at 87, Lenin Sarani, P.O. & P.S. Lenin Sarani, District- Kolkata-700013, West Bengal ... ... Appellant Versus East Central Railway, represented through the General
Manager, Having office at Zonal Office Road, P.O. & P.S.
Hajipur, District-Hajipur, Bihar-844102
... ... Respondent
-------
CORAM : HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE SUJIT NARAYAN PRASAD
------
For the Appellant : Mr. Nand Kishore Singh, Advocate For Respondent : Mr. Pratyush Kumar, C.G.C.
--------
C.A.V. on 11.05.2022 Pronounced on 29.08.2022
Per Dr. Ravi Ranjan, C.J.
The instant appeal has been preferred under Section 13 of
the Commercial Courts Act, 2015 assailing the order/judgment
dated 06.01.2021 passed in Commercial Revocation Case No.07
of 2019, by which, an arbitral award dated 23.02.2019 passed
by the sole Arbitrator, has been set aside in entirety.
2. The brief facts of the case, required to be considered in
this appeal, stand enumerated as under:-
A notice inviting tender was issued by the East Central
Railway through its General Manager for construction of seven
bridges between Tori to Shivpuri (Km 23.00 to Km 44.00) in
connection with construction of Tori Shivpur new BG Rail line
project in Latehar district of Jharkhand State and the work was
awarded to the respondent vide LOA
No.ECR/CAO/Con/WT/S/165/13616 dated 03.06.2014. The
value of the work was estimated to the tune of
Rs.82,80,54,283.78 and the work was to be completed within
24 months from the date of issuance of acceptance letter i.e.,
till 02.06.2016. A formal contract/agreement was entered into
in between the parties on 31.10.2014. However, the work could
not have been completed within the stipulated time. Thereafter,
the East Central Railway vide its letter dated 11.07.2016 issued
letter for termination of contract. Thus, the dispute arose
between the parties and the claimant-respondent-appellant
filed an application before this Court for appointment of an
Arbitrator to adjudicate upon the dispute and this Court vide
order dated 28.07.2017 passed in Arbitration Application No.16
of 2017 has appointed Hon'ble Mr. Justice D.G.R. Patnaik, a
Former Judge of this Court as Arbitrator and the dispute was
referred for arbitration.
The award was passed in favour of the appellant holding
the termination of the contract to be illegal and has passed the
order allowing the claim to the extent of Rs.28,45,90,777.56
under different heads as under:-
Sl No. Description Amount Allowed
1 Item No.I:-Refund of encashed Rs.8,59,08,325/-
Bank Guarantees
2 Item No.2:-Compensation for Rs.2,44,85,062/-
loss of on going work
3 Item No.3:-Compensation for Rs.36,00,000/-
loss suffered on Batching Plant
4 Item No.7:- Loss of profit Rs.9,63,19,088.13/-
Compensation for expenses
incurred in purchase, supply
and cutting, bending, fixing
TMT Bars and for procurement,
fabrication of structural steel
as per relevant clause of the
contract
7 Item No.9:- Payment of interest Rs.5,49,39,600.47/-
(I) Interest on Item
No.1=Rs.4,12,35,996/-
(ii) Interest on item nos.2, 10
and 11=Rs.1,37,03,604.47/-
(iii) Interest on item No.7:- it To be calculated
shall be calculated @ 12 % per
annum from the date of award
till the date of actual payment
made on the amount of loss of
profit to the tune of
Rs.9,63,19,088.13
Total Rs.28,45,90,777.56/-
The respondent East Central Railway, being aggrieved with
the award, assailed the same by invoking the jurisdiction
conferred under Section 34 of the Arbitration and Conciliation
Act, 1996 (hereinafter referred to as the 'Act'), 1996.
The Court below, after hearing the application filed under
Section 34 of the Act, 1996 has considered the aforesaid award
to be incorrect, as would appear from paragraphs-26, 27 and
28 of the order passed by the concerned Court. The finding
recorded by the concerned court dealing with the application
under Section 34 of the Act, 1996 as referred under
paragraphs-26, 27 and 28 read as under:-
"26. In the present case award to the extent of Rs.8,59,08,325.00 has been made towards refund of encashed bank guarantee and security deposit vide item no 1 and further vide item no.9 (I) award has been made towards interest on item no.1. In this regard, I find that clause 29 and 30 of the Tender document stipulates, that both the BG and security deposit was to be released only after physical completion of the work where as in the present case only 4 % of the work has been executed by the contractor. Further both these clauses specifically bars payment of interest on BG and Security deposit but interest has been paid on both the items and therefore the claim awarded under item no 1 and item no 9 (I) is in
contravention of Clause 29 and 30 of the tender document.
27. Further vide item no 2, 3 and 7 the claim has been awarded towards compensation for loss of on-going work, compensation for loss suffered in batching plant and loss of profit. In this regard I find that clause 51 and 52 of the Tender Document specifically bars this claim wherein it envisages that:-
Clause 51-No claim whatsoever will be entertained by the railway on account of any delay or hold up of the works(s) arising out of delay in approval of drawings, changes, modifications, additions, omissions and site lay out plan or detailed drawings and designs and or late supply of such materials as are required to be arranged by the railway or due to any other factor on railway account.
(Emphasis added)
Clause 52 reads-No claim for idle labour, or idle machinery etc on any account will be entertained. Similarly no claims shall be entertained for business loss and any such loss.
28. So far as item no 11 and 12 are concerned, I find that the same has been awarded towards compensation for expenses incurred in purchase, supply and cutting, bending, fixing TMT bars and for procurement of structural steel as per relevant clause of contract. The learned Counsel for the petitioner submitted that even assuming that the contractor has purchases these articles but the articles were never supplied nor were used at the site and therefore no claim could have been granted for the articles which are in the claimants
possession. This claim has been dealt with the learned Tribunal at page 45 of the award wherein in the Tribunal has held "From perusal of the documents on record, it appears that the Claimant has filed its Rejoinder to the defence statement submitted by the Respondents and while reiterating the items for its claim for compensation, it has also put forth its claim for the aforesaid two items mentioned at serial no 11 and 12 of the summary of claims. Though the respondents have received a copy of the claimant's rejoinder, they have not controverted this portion of the Claimant's claim. In absence of any denial either specific or even general, it has to be deemed that the claimant has incurred the expenses under these two heads and is therefore entitled to claim payment for the same. In this regard I find that claim under Item no 11 and 12 has been awarded only because the petitioner/respondent did not controverted this claim either specific or in general and there is no discussion as to what was the evidence which was adduced by the claimant in support of this claim. I find that no reasons has been assigned by the Tribunal in awarding this part of the claim save and except that the petitioner respondent did not convert the claim. In Associate Builders case ((2015) 3 SCC 49) it has been held that "if an arbitrator gives no reasons for an award in contravention of Section 31(3) of the 1996 Act, such award is liable to be set aside."
The appellant, being aggrieved with the order/judgment
dated 06.01.2021 passed in Commercial Revocation Case No.07
of 2019, has preferred the instant appeal invoking the
jurisdiction conferred to this Court under Section 13 of the
Commercial Courts Act, 2015.
3. Mr. Nand Kishore Singh, learned counsel appearing for
the appellant, made following submissions:-
(i) The Court below has not exercised the power conferred
under the Arbitration and Conciliation Act, 1996 in a proper
manner, since several issues have been raised by the appellant
in support of the finding recorded by the learned sole
Arbitrator, but, no finding has been recorded either way i.e.,
discarding the same, therefore, the Court below has passed the
order in a mechanical manner, since, no consideration about
the plea raised before it in defence of the award has been
answered by recording the finding to that effect on the basis of
the ground agitated on behalf of the appellant, therefore,
submission has been made that since the judgment has been
passed by the concerned Court in exercise of power conferred
under Section 34 of the Arbitration and Conciliation Act, 1996
which having not considered the factual aspect agitated on
behalf of the appellant and as such, it cannot be said that the
judgment has been passed after giving proper consideration of
the factual aspect vis-à-vis the legal position as has been
agitated on behalf of the appellant and hence, the
judgment/order dated 06.01.2021 is not sustainable in the eye
of law.
(ii) The submission has been made that the award has
been passed by the sole Arbitrator after considering the fact
that there was non-cooperation on the part of the respondent
which led the appellant in not concluding the work within the
time frame. The aforesaid fact has been agitated before the
concerned Court dealing with the application under Section 34
of the Act, 1996, but, it would be evident from the bare reading
of the judgment/order dated 06.01.2021 (impugned) that no
such finding has been recorded about non-cooperation of the
respondent, which is the main ground taken by the sole
Arbitrator in non-conclusion of the work within the stipulated
time, therefore, the order passed by the concerned Court is not
sustainable in the eye of law.
(iii) The concerned Court has reversed the finding
recorded by the sole Arbitrator, in exercise of power conferred
under Section 34 of the Act, 1996, but while doing so, he has
exceeded its jurisdiction in reversing the fact finding recorded
by the sole Arbitrator in the award.
Submission has been made on behalf of the learned
counsel for the appellant that the concerned Court in exercise
of power conferred under Section 34 of the Act, 1996 can
reverse the fact finding recorded by the sole Arbitrator, but, the
same can only be done, if the award is based upon the perverse
finding. But, it would not be evident from the order impugned
that the concerned Court has considered this aspect of the
matter, rather, the Court has travelled into the principle of
public policy.
4. According to the learned counsel for the appellant, it is not
a case where the applicability of the principle of public policy is
applicable, which led the concerned Court to reverse the finding
recorded by the sole Arbitrator in the award.
5. Learned counsel for the appellant has relied upon the
judgment rendered by the Hon'ble Apex Court in J.G.
Engineers Pvt. Ltd. Vs. Union of India & Anr., (2011) 5 SCC
758 to fortify his argument that the reason shown for reversal
of the fact finding recorded in the award by the Court in
exercising the power conferred under Section 34 of the Act,
1996 which was based upon the non-consideration of the terms
and conditions of the agreement, since, the learned sole
Arbitrator has considered the accountability in non-conclusion
of the work within the stipulated period and exactly in the
similar circumstances, the Hon'ble Apex Court in the aforesaid
case, has decided the issue, as to whether the appellant was
responsible for the delay in execution of the work, was
arbitrable.
The aforesaid aspect of the matter was considered and the
matter has finally been settled by the Arbitrator and in such
circumstances, the Hon'ble Apex Court has came to the
conclusion that once it is held that the issues relating to who
committed breach and who was responsible for delay were
arbitrable, the findings of the arbitrator that the contractor was
not responsible for the delay and that the termination of the
contract is illegal, would not be open to challenge.
- 10 -
It has been submitted that in the case in hand also the
appellant was ready to execute the work within time but it is
due to non-cooperation on the part of the respondent
concerned, the work could not have been completed and as
such, the learned Arbitrator after considering this aspect of the
matter has passed the award, which cannot be said to suffer
from perversity, as has been held by the concerned court in
exercising the power conferred under Section 34 of the Act,
1996.
Learned counsel for the appellant has further submitted
that once the award has been passed, based upon the reason,
the same is not required to be interfered with by the concerned
Court in exercise of power conferred under Section 34 of the
Act, 1996 that too without taking into consideration the plea
agitated before it.
6. Per contra, Mr. Pratyush Kumar, learned C.G.C. appearing
for the respondent-East Central Railway has submitted that
there is no infirmity in the order passed by the concerned Court
under Section 34 of the Act, 1996, reason being that the
concerned Court has considered the terms and conditions of
the contract, as per which, there is no condition stipulated
therein for refund of amount to the extent of Rs.8,59,08,325.00
towards refund of encashed bank guarantee and security
deposit.
Since, as per the conditions stipulated under Clause 29
and 30 of the Tender document which stipulates, that both the
- 11 -
bank guarantee and security deposit were to be released only
after physical completion of the work whereas in the present
case only 4% of the work has been executed by the contractor.
Further, the concerned Court has considered that there is
no condition stipulated in the contract for issuance of direction
for payment of interest but even then, the award was passed
directing the respondent to pay interest.
7. According to the learned counsel for the respondent-East
Central Railway, since the work has not been concluded, rather
only 4% of the work could be completed, therefore, this aspect
of the matter ought to have been considered by the learned sole
Arbitrator, however, without considering this aspect of the
matter and without answering the implication of the specific
condition stipulated in the agreement, held that the amount of
bank guarantee and the security deposit to the extent of
Rs.8,59,08,325.00 are to be released since the same was only
to be paid, in case of conclusion of the work and as such, the
learned sole Arbitrator since has directed for disbursement of
the amount contrary to the terms and conditions of the
agreement. Therefore, the said order has been considered to be
against the public policy by the Court dealing with the
application filed under Section 34 of the Act, 1996, as such, the
aforesaid finding cannot be said to be incorrect, reason being,
when the parties have agreed and came into an agreement, the
terms and conditions bind them and once the terms and
conditions have been accepted, they cannot be allowed to
- 12 -
retract back and claim the amount along with due
compensation as also that the order for refund of bank
guarantee and security deposit amount to be refunded with the
interest.
8. Therefore, According to the learned counsel for the
respondent-East Central Railway, the Court, dealing with the
application under Section 34 of the Act, 1996 has reversed the
award on the aforesaid ground as referred in the preceding
paragraph, which cannot be said to suffer from any illegality.
9. In the aforesaid backdrop of the facts, he further submits
that since an issue has been raised on behalf of the appellant
that there point of view was not considered, it would be a fit
case to remit the matter before the concerned Court for
consideration of the issue raised by passing a fresh order.
10. We have heard the learned counsel for the parties,
perused the documents available on record as also considered
the finding recorded by the concerned Court dealing with the
application filed under Section 34 of the Act, 1996.
11. The undisputed facts in this case are that the agreement
has been entered in between the parties for execution of the
work for construction of seven bridges between Tori to Shivpuri
(Km 23.00 to Km 44.00) in connection with construction of Tori
Shivpur new BG Rail line project in Latehar district of
Jharkhand State. The work could not have been completed, the
same has taken to be a ground for termination of the contract
and accordingly, the dispute arose in between the parties.
- 13 -
The dispute was finally referred before the learned sole
Arbitrator by virtue of order dated 28.07.2017 passed by this
Court in A.A. No.16/2017, by which, Hon'ble Mr. Justice
(Redt.), D.G.R. Patnaik, Former Judge of this Court was
appointed as sole Arbitrator for resolution of the dispute.
The said award has been questioned by the respondent-
East Central Railway by invoking the jurisdiction conferred to
the concerned Court under Section 34 of the Act, 1996.
The concerned Court has passed the order by reversing
the award vide impugned judgment dated 06.01.2021 passed in
Commercial Revocation Case No.07 of 2019, which is the
subject matter of the instant appeal.
12. The submission has been made on behalf of the learned
counsel for the appellant that there is no infirmity in the award
but without appreciating that aspect of the matter, the award
has been reversed, which cannot be said to be proper and
therefore, the impugned order is fit to be quashed and set
aside.
The sole argument agitated by referring to the impugned
order/judgment is that whatever point has been considered by
the learned sole Arbitrator and even though the ground in
defence of the award was agitated before the concerned Court,
it would be evident from the impugned order that there is no
consideration at all. Merely the submission of the appellant has
been referred but no finding has been recorded either way.
Learned counsel for the appellant, therefore, submits that
- 14 -
the order impugned is nothing but a cryptic and mechanical
order.
Learned counsel, in the backdrop of the aforesaid fact, has
submitted that the order/judgment impugned is fit to be
quashed and set aside and the award dated 23.02.2019 is fit to
be restored.
It has been submitted that so far as the interest part is
concerned, the appellant is ready to forgo, since there is no
condition to that effect in the agreement. However, so far as the
other claims are concerned, as directed to be paid, as would
appear from the tabular chart, referred hereinabove, the
appellant was legally entitled to get the same. Since, it was the
respondent who had come in the way in non-conclusion of the
work within the stipulated period, the same was taken as a
ground before the sole Arbitrator which has been considered in
the right perspective noticing about non-cooperation of the
respondent, the award has been passed in favour of the
appellant directing the respondent to make payment as per the
tabular chart under different heads.
13. On the other hand, learned counsel for the respondent-
East Central Railway, has submitted that the learned Arbitrator
has not appreciated the terms and conditions of the agreement
rather travelled beyond the terms and conditions, interest has
been awarded as also the bank guarantee and security deposit
have been directed to be refunded, even though, there was
specific bar in releasing the said amount. The said amount can
- 15 -
only be refunded in a case where the work is concluded within
the stipulated time.
14. This Court, for appreciating the aforesaid arguments
advanced on behalf of the parties, is required to consider the
following issues:-
(i) Whether the court having jurisdiction under Section 34
of the Arbitration and Conciliation Act, 1996, is required to
consider the ground agitated in defence of the award and what
would be its result if there is non-consideration on the said
ground by the concerned Court?
(ii) Whether the impugned judgment passed by the Court
in exercising the power conferred under Section 34 of the Act,
1996, is held to be not sustainable due to non-consideration of
the ground agitated and in case of such decision, will it be
appropriate for this Court in exercise of power under Section 13
of the Commercial Courts Act, 2015 to restore the award
instead of remanding the matter to the concerned Court to pass
a fresh order after consideration of the factual aspect which has
been agitated before it?
Since both the issues are intertwined, as such are being
considered together and being answered.
15. There is no dispute about the settled position of law that if
an opportunity is being provided to the party and the same has
been responded, it is the bounded duty of the concerned Court
or the authority to deal with such pleading and answer it in
either way.
- 16 -
16. It is in these circumstances only, it can be said that there
is proper consideration of the factual aspect placed before the
concerned Court or the authority.
17. The meaning of 'consideration' is the active application of
mind of the factual aspect, as per the definition of
'consideration' given by the Hon'ble Apex Court in Chairman,
Life Insurance Corporation of India & Ors. Vs. A.
Masilamani, (2013) 6 SCC 530, wherein, at paragraph-19, it
has been held by the Hon'ble Apex Court as under:-
"19. The word "consider" is of great significance. The dictionary meaning of the same is, "to think over", "to regard as", or "deem to be". Hence, there is a clear connotation to the effect that there must be active application of mind. In other words, the term "consider" postulates consideration of all relevant aspects of a matter. Thus, formation of opinion by the statutory authority should reflect intense application of mind with reference to the material available on record. The order of the authority itself should reveal such application of mind. The appellate authority cannot simply adopt the language employed by the disciplinary authority and proceed to affirm its order. (Vide Indian Oil Corpn. Ltd. v. Santosh Kumar [(2006) 11 SCC 147 : (2007) 1 SCC (L&S) 388] and Bhikhubhai Vithlabhai Patel v. State of Gujarat [(2008) 4 SCC 144 : AIR 2008 SC 1771] ."
18. This Court has considered the finding recorded in the
award by the learned Arbitrator and found therefrom that the
consideration has been given regarding casting accountability
upon the respondent for non-conclusion of the work within the
- 17 -
stipulated period. That has led the learned Arbitrator to come to
the conclusion and passing the award in favour of the
appellant. However, the said award was questioned on the
ground that the learned Arbitrator had passed the award
deviating from the specific terms and conditions of the
agreement, wherein, even though, there is no Clause pertaining
to payment of interest, the award for payment of interest has
been passed.
Further, other amounts have been directed to be paid as
per the tabular chart, as quoted and referred hereinabove,
inclusive of the refund of bank guarantee and security deposit.
But, it is the plea of the respondent that such directions
contained in the award is contrary to the terms and conditions
of the agreement as per which the amount could only be
directed to be paid under the said heads in the case where the
work is concluded in entirety whereas records show that only
4% work could be completed.
19. In response to the same, learned counsel for the appellant
has taken the ground, referring to the reasons assigned by the
learned Arbitrator in passing such direction even contrary to
the agreement, that the learned tribunal has came to the
conclusion about accountability in not allowing the work to be
concluded within the stipulated time.
It appears from the judgment/order impugned that even
though, the appellant has raised this specific issue before the
Court below and the same has been noticed by it but no finding
- 18 -
has been recorded and simply on going through the terms and
conditions of the agreement, the award has been held to be
illegal.
20. The question is that 'what is the meaning of notice and
what is the meaning of providing an opportunity of hearing'
that too, if any order has been passed in favour of the party,
which is the subject matter of consideration by the Higher
Forum.
Once the notice is issued to the party, which itself
suggests that the opportunity is being given to defend the order
which has been passed in favour of the party and if the party
appears and takes plea in defence of the impugned order before
the Forum, it would be the bounded duty of the concerned
Forum to give a specific finding either in discarding or
accepting the same. That would be required to be based on
reason. Only then, it could be said that there is proper
consideration of the factual aspect raised by the parties.
Otherwise, if the plea has been taken by the party but no
finding discarding the same is available in the order, the same
will have to be held to be cryptic and mechanical order.
The plea which is being taken before the concerned Forum
is required to be considered and 'consideration' means a proper
application of mind, as has been held in Chairman, Life
Insurance Corporation of India & Ors. Vs. A. Masilamani
(supra).
It is not disputed by the respondent-East Central Railway
- 19 -
that there is no consideration of the factual aspect pleaded by
the appellant before the Court dealing with the application
under Section 34 of the Arbitration and Conciliation Act, 1996.
21. So far as the argument advanced on behalf of the learned
counsel for the appellant that the issue may be decided on
merit by this Court in the appeal itself instead of remitting the
matter before the concerned Court, this Court is of the view
that since this Court is sitting in an appeal and since the issue
of consideration of factual aspects, which were raised before the
learned Arbitrator, have been placed before the Court dealing
with the issue under Section 34 of the Act, 1996, that Court is
required to deliberate upon the same considering the relevant
documents or evidence for its proper appreciation, it would not
be proper for this Court to exercise such power under the
appellate jurisdiction rather this Court deems it fit and proper
to remit the matter before the concerned Court.
22. This Court sitting under the appellate jurisdiction is of the
view that the order/judgment impugned requires interference.
23. Accordingly, the order/judgment impugned dated
06.01.2021 passed in Commercial Revocation Case No.07 of
2019, is hereby quashed and set aside.
24. In the result, the instant appeal is allowed.
25. In consequence thereof, the matter is remitted to the
Court concerned for passing an order afresh in accordance with
law preferably within the period of three months' from the date
of receipt/production of copy of this order.
- 20 -
26. Pending interlocutory application(s), if any, also stands
disposed of.
(Dr. Ravi Ranjan, C.J.) I agree
(Sujit Narayan Prasad, J.) (Sujit Narayan Prasad, J.)
A.F.R.
Rohit/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!