Citation : 2021 Latest Caselaw 834 Jhar
Judgement Date : 22 February, 2021
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI
L.P.A. No. 149 of 2020
With
I.A. No. 3106 of 2020
With
I.A. No. 902 of 2021
With
I.A. No. 903 of 2021
------
M/s The Base Enterprises having its office at Ground Floor, Ram Janki Enclave, Obaria Road, Hatia, P.O Hatia, P.S. Hatia, District Ranchi, through its Proprietor Shri Amit Kumar Pandey, aged about 38 years, son of Dinesh Kumar Pandey, resident of Ramjanki Niwas, Dinkar Nagar, Station Road, Hatia, P.O. Hatia, P.S. Hatia, District Ranchi (Jharkhand).
..... Appellant
Versus
1.Heavy Engineering Corporation Limited through its Senior DGM (BCD & Disposal), having its office at Room No. 28, 1st Floor, Headquarter Building, HEC Limited, Dhurwa, P.O. Dhurwa, P.S. Dhurwa, District Ranchi (Jharkhand).
2.Chief of Township, Heavy Engineering Corporation Limited, having its Plant Plaza road, P.O. Dhurwa, P.S. Dhurwa, District Ranchi (Jharkhand).
3.Deputy General Manager, Town Administration Division, Heavy Engineering Corporation, having its Office at Plant Plaza Road, P.O. Dhurwa, P.S. Dhurwa, District Ranchi (Jharkhand). ... ... ... Respondents
----
CORAM: HON'BLE THE CHIEF JUSTICE HON'BLE MR. JUSTICE SUJIT NARAYAN PRASAD
-----
For the Appellant : Mr. P.N. Shahi, Sr. Advocate Mr. Indrajit Sinha, Advocate For the Respondents : Mr. Anil Kumar Sinha, Sr. Advocate Mr. Mukesh Kumar, Advocate
-------
Oral Judgment Order No. 04 : Dated 22nd February, 2021:
With consent of the parties, hearing of the matter
has been done through video conferencing and there is no
complaint whatsoever regarding audio and visual quality.
I.A. No. 3106 of 2020
2. Perused the Office Note.
3. Defect as pointed out by the office, regarding
legibility of Annexure-19 to I.A. No. 3106 of 2020, is
ignored.
L.P.A. No. 149 of 2020
4. The instant intra-court appeal has been preferred
against the order/judgment dated 25.02.2020 passed by
learned Single Judge in W.P. (C) No. 4445 of 2019, by
which the writ petition was dismissed. Learned Single
Bench declined to interfere with the letter as contained in
Ref. No. TA/REV/RB/2017/2019-338 dated 16.08.2019
issued under the signature of respondent no. 3-the
Deputy General Manager, T.A. division, Heavy
Engineering Corporation Ltd., (herein after referred to as
"HEC") whereby the Letter of Intent No. HQ/BDC &
Disp/NRB-NIT/2016-187 dated 31.10.2016 issued in
favour of the writ petitioner was terminated with
immediate effect and it was directed to vacate the
premises and to clear the pending dues as well as to
complete the formalities relating to handing over the
premises to the respondent-HEC on or before 14.09.2019.
Further, the writ Court had declined to issue any
direction upon the respondents to execute a formal
agreement/contract of lease for a period of ten years
commencing from 31.10.2016 with respect to Rajendra
Bhawan, Sector-II, HEC.
5. The brief facts of the case, which are required to be
enumerated herein for proper adjudication of the lis, are
as under:
The respondents-HEC had come out with a Notice
Inviting Tender ( in short 'NIT') dated 18.04.2016 inviting
applications from intended bidders for leasing out nine
buildings of diverse nature with associated land in HEC
Township. The writ petitioner participated in the said
tender and furnished the bid for three non-residential
buildings and it was declared technically qualified,
however, after opening of the price bids, the writ
petitioner was not allotted any non-residential building
on the ground that the price quoted by it did not match
the reserve price set by the respondents.
Thereafter, the respondents floated another tender
for leasing out six non-residential buildings with
associated land in the HEC Township vide Tender No.
HQ/BDC & Disp./NRB-NIT/2016/06 dated 05.09.2016.
The petitioner again participated in the second tender
process and quoted the bid only for one non-residential
building i.e. Rajendra Bhawan, Sector-II, HEC with its
associated land. The technical bid of the writ petitioner
was found responsive and thereafter when the financial
bid was opened, the writ petitioner was declared
successful with respect to its bid for Rajendra Bhawan,
Sector-II, HEC along with its associated land. The Senior
D.G.M. (BCD & Disposal) issued Letter of Intent (in short
'LOI') in favour of the petitioner vide letter as contained in
Reference No. HQ/BDC & Disp/NRB-NIT/2016-187 dated
31.10.2016 for a period of ten years, subject to renewal
for another period of ten years on the decisions and terms
and conditions of the management of the respondents-
HEC.
The respondents also handed over the possession of
the said building in favour of the writ petitioner vide letter
dated 20.03.2017. Pursuant to the tender notice and its
terms and conditions, the petitioner deposited a total
amount of Rs. 2,21,21,000/-and service tax of
Rs.33,18,150/-on 30.11.2016. It also paid a sum of
Rs.3,48,405/- on 30.03.2017 towards annual rent which
was accepted by the respondents-HEC. The writ
petitioner further paid the required rent for the financial
year 2018-19 and 2019-2020 to the respondents and the
same was also accepted. The writ petitioner invested Rs.
4.7 crores during the period between 29.11.2016 to
20.08.2019. The respondent no. 2 issued a notice vide
letter dated 20.10.2017 indicating inter alia that some
irregularities might have been done towards the allotment
of the said building i.e. Rajendra Bhawan, Sector-II, HEC,
in favour of the petitioner and as such it was advised not
to continue with any construction/activity in the said
building/complex as the investigation of matter was going
on at appropriate level.
The respondent no. 2 thereafter issued a notice vide
letter dated 08.11.2017 mentioning inter alia that the
construction/renovation work of the said
building/complex was still going on in spite of the
direction to discontinue any construction/renovation
activities and thus the writ petitioner was again asked to
comply the directions as issued earlier. In response
thererto, the writ petitioner submitted its reply to both
the notices on 11.11.2017 stating that it had already
deposited the required amount as mentioned in the
tender document and thereafter invested huge amount of
money in order to fulfil the terms and conditions as
mentioned in the tender notice. The writ petitioner made
requests to the respondents to allow it to continue with
the construction/renovation work and thereafter to
execute the agreement with it as huge recurring loss was
being suffered every day, but the respondent no. 2 vide
letter dated 29.09.2018 again issued a notice directing
the writ petitioner to submit all the relevant documents
based upon which three affidavits were given in favour of
the petitioner. In response thereto, the writ petitioner
submitted its reply on 09.10.2018.
It is the case of the writ petitioner that the
respondent no. 3 again issued a show cause notice to it
on 22.10.2018 directing the writ petitioner to submit
reply on or before 22.11.2018 bringing on record all the
required documents failing which suitable action as per
the terms and conditions of the NIT/LOI and existing
laws/rules, would be initiated including cancellation of
LOI /allotment.
The aforesaid notice was responded by the writ
petitioner by submitting reply vide letter dated
21.11.2018 stating inter alia that it never breached any
terms and conditions as put forth by the respondents. It
was also stated that the petitioner had already submitted
all the documents as per the requirement of NIT. The
respondent no. 3 after lapse of nine months of submitting
reply, issued letter as contained in Ref. No.
TA/REV/RB/2017/2019-338 dated 16.08.2019 whereby
the Letter of Intent dated 31.10.2016 issued in favour of
the petitioner was terminated with immediate effect and it
was directed to vacate the premises, clear the dues and
complete the formalities relating to handing over the said
premises to the respondents on or before 14.09.2019.
The writ petitioner in the backdrop of these factual
aspects has approached the writ Court by invoking the
writ jurisdiction of this Court under Article 226 of the
Constitution of India, wherein ground has been agitated
that the writ petitioner was found to be successful bidder
after finding the writ petitioner eligible from all corner. It
was further submitted that it's bid was found to be
technically qualified twice and, therefore, direction of the
respondents-HEC to furnish the documents at such a
belated stage, which were not required at the time of
submission of bid, is nothing but a colorable exercise of
power. It was further submitted that it is settled position
of law that sole proprietorship firm has no separate legal
existence from its proprietor. Further submission was
made that after being fully satisfied with the documents
submitted by the writ petitioner, the respondents-HEC
issued Letter of Intent and pursuant thereto the writ
petitioner came in possession of the said building, on
which, the writ petitioner invested more than Rs.4.7
crores and as such the respondents-HEC cannot be
allowed to turn around and declare the writ petitioner as
ineligible as per the terms and conditions of the tender
notice. It was further submitted that the writ petitioner
used the said premises for the same purpose which was
mentioned by it in its vision and mission document as
submitted along with the tender.
The writ petitioner has further raised the issue that
when the Technical Evaluation Committee accepted the
documents as submitted by the writ petitioner and
consequent thereupon the LOI was issued, the same
cannot be terminated by the said Technical Evaluation
Committee as even accepting that the petitioner had not
submitted any documents as required in the tender
notice, the respondents during evaluation of the
documents could have issued show cause notice and
could have asked the writ petitioner for submission of the
required documents, but once the LOI has been issued it
became a concluded contract as such the respondents
cannot be allowed to violate the terms and conditions of
the LOI.
The respondents-HEC appeared and contested the
case by filing counter affidavit stating therein that the
tenderers had submitted affidavits with the tender
document claiming that all the information furnished by
it with respect to fulfilment of eligibility criteria and
information given in the tender were complete and true.
The respondent-HEC in order to verify the documents
had insisted upon the writ petitioner to submit certain
documents but such documents were never produced by
the writ petitioner and, therefore, even after issuance of
LOI, which is not a final document, as per the terms and
conditions mentioned therein that after issuance of LOI
an agreement has to be made in between the bidder and
the respondents within a period of 30 days but, since the
writ petitioner had not provided the required document,
the agreement could not be reached. It has further been
submitted that the stand of the writ petitioner that
once LOI has been issued, the same became the
concluded agreement, is absolutely incorrect and illegal.
The writ petitioner without entering into the agreement as
per the terms and conditions of the LOI/NIT has started
renovation of the building and further started
construction therein for the purpose of changing the
entire structure and to that effect several notices were
issued but it avail no effect, therefore, the respondents-
HEC after taking into consideration that without entering
into the agreement the writ petitioner has started
construction over the premises even by making addition,
had issued several notices/letters to stop the renovation
work but that was not given any heed to, therefore, the
respondents-HEC took a decision to terminate the
contract after following the principles of natural justice,
and as such the action of the respondents-HEC cannot be
said to be arbitrary and colorable exercise of power rather
the same has been done after following the principles of
natural justice and as per the terms and conditions of the
NIT/LOI.
The writ Court, after appreciating the submissions
advanced by learned counsel for the parties and
considering the power of writ Court in exercising judicial
review under Article 226 of the Constitution of India did
not interfere with the decision taken by the respondents-
authority in terminating the LOI of the writ petitioner and
dismissed the writ petition, which is the subject matter of
present intra-court appeal.
6. Mr. P.N. Shahi, learned senior counsel assisted by
Mr. Indrajit Sinha, learned counsel for the appellant-writ
petitioner assailed the impugned order by making
submission that the learned Single Judge has not
appreciated the fact that once the LOI has been issued
with the condition stipulated therein that the renovation
work will be carried out, it goes to suggest that the LOI
has not become simple LOI rather it gets the shape of
concluded contract.
The monthly rental has also been paid to the
respondents-HEC along with the requisite money
required to be paid as per the condition stipulated in the
NIT and the same has been accepted without any demur,
therefore, it is inaction on the part of the respondent-HEC
in not reaching out the agreement.
It has further been submitted that all required
documents were submitted with the bid document, which
were scrutinized by the Tender Evaluation Committee and
after being satisfied with the documents, the writ
petitioner was found technically qualified and it is only
thereafter the price bid documents of the writ petitioner
along with others were opened, in which, the writ
petitioner was found to be eligible and thereafter the LOI
was issued in favour of the writ petitioner but
subsequently the respondents-HEC terminated the LOI
which cannot be said to be justified action on the part of
the respondents-HEC.
It has further been submitted that it is incorrect to
say that the writ petitioner has not entered into the
agreement rather it is the laches on the part of the
respondents-HEC in not entering into agreement, even
after the repeated requests made by the writ petitioner in
this regard. According to learned senior counsel all these
facts have not been taken into consideration by the
learned Single Judge while passing the impugned order
rather the learned Single Judge has gone into wrong
perception of fact of contract not being a concluded
contract and further violation of terms and conditions of
the LOI and dismissed the writ petition, which cannot be
said to be proper in the eyes of law.
7. Per contra, Mr. Anil Kumar Sinha, learned senior
counsel being assisted by Mr. Mukesh Kumar, learned
counsel for the respondents-HEC has submitted that
there is no error in the impugned order as in the terms
and conditions of the NIT, there is specific condition that
in order to verify the eligibility criteria the bidder has to
produce all documents for its scrutiny, however, the
Tender Evaluation Committee has found documents
produced by the writ petitioner to be satisfactory
whereupon the writ petitioner was found to be eligible
bidder and in consequence thereof LOI was issued but in
order to enter into the agreement, as per the condition of
the NIT as also LOI, the documents were sought for inn
order to verify about fulfillment of the eligibility criteria
and in response thereto affidavits sworn before the Notary
Public were filed but no document was filed to
substantiate the affidavits, more particularly about
requisite working experience in rendering such services
for which NIT was issued and therefore, the respondents-
HEC asked for the documents so that the agreement may
be entered into between the writ petitioner and
respondents-HEC but the writ petitioner failed to do so,
therefore, agreement could not be entered into rather it
came to the knowledge of the respondents-HEC that the
writ petitioner, by suppressing the fact, has managed to
get LOI in its favour and, therefore, show cause notices
were issued for termination the LOI, to which, though
writ petitioner replied but being found not satisfactory,
the respondents-HEC terminated the letter of Intent.
It has been submitted that the writ petitioner on
its own without entering into the agreement in utter
violation of terms of the NIT/LOI started renovation work
as also addition thereto over the premises, which cannot
be said to be justified on the part of the writ petitioner.
Even though the severe objection has been made by the
respondents but to avail no effect as the writ petitioner
continued to make such renovation work.
It has further been submitted, refuting the
contention of learned counsel for the writ petitioner that
money which was required to be deposited in terms and
conditions of the NIT as also the monthly rental has been
accepted, that acceptance of the rent is only on account
of the fact that possession of the premises having been
handed over to the writ petitioner subject to the condition
of entering into the agreement within a period of one
month from the date of issuance of LOI, however, since
the writ petitioner has not furnished the evidence to the
satisfaction of its eligibility, the agreement could not be
entered into. Therefore, in the absence of agreement the
carrying out of renovation work in the existing premises
is contrary to the terms and conditions of the NIT, as
such the decision of the respondents-HEC for termination
of the LOI cannot be said to be unjustified one.
Learned senior counsel for the respondents-HEC
has further submitted by referring to the documents
annexed with I.A. No. 3106 of 2020, with respect to
initiation of proceeding under Section 5-A of the Public
Premises (Eviction of Unauthorized Occupants) Act, 1971
[herein after referred to as 'Act, 1971'], whereby and
whereunder power has been conferred upon the authority
to remove unauthorized constructions etc. and Section 5-
A (2) of the Act, 1971 confers power to sell unauthorized
construction and in pursuance to the said provision,
proceeding has also been initiated and order has also
been passed by the Estate Officer but the writ petitioner
as on date has never questioned the said proceeding
before appropriate forum.
According to learned senior counsel the learned
Single Judge, after taking into consideration all these
aspects of the case, has rightly not interfered with the
decision of the respondents-HEC and as such the
impugned order/judgment may not be interfered with.
8. We, after having heard learned senior counsel for
the parties and on perusal of the materials available on
record along with the annexures appended thereto and
findings recorded by the learned Single Judge, are of the
view that for proper adjudication of the lis, following
issues are required to be decided:
(I).Whether mere issuance of LOI can be termed as
concluded contract without entering into an
agreement?
(II).Whether on the basis of LOI any right has been
accrued upon the bidder?
(III).Whether termination of LOI due to non-
compliance of the terms and conditions as stipulated
in the Notice Inviting Tender (NIT) as also LOI can be
said to be unjustified?
(IV).Whether non-furnishing of documents, that was
asked for to justify the eligibility, can be said to be
unjustified?
9. This Court, before proceeding to deal with the issue
and answering the same, deem it fit and proper to record
certain admitted facts, which is available on record.
Admittedly, herein the Notice Inviting Tender vide
Tender No. HQ/BDC & Disp./NRB-NIT/2016/06 dated
05.09.2016 was floated for leasing out six non-residential
buildings with associated lands of HEC Township. The
intent to leasing out of the premises was as an
opportunity to undertake commercial, innovative and new
projects meant for schools, educations purposes and skill
development. The subsistence of the period of lease
initially was for ten years, which was renewable for other
period of 10 years on the decision and terms & conditions
of the HEC management with a condition to deposit the
earnest money. It would be evident from Clause 7 (b) of
the 'Detailed Tender Notice' that the buildings and halls
will be offered on "as is where is" basis, with the further
stipulation that the successful bidder may make
premises/interiors suitable as per their requirement at
their own cost. Permanent structure(s) if constructed on
vacant land or renovated structure cannot be demolished
at the time of vacating these buildings.
Under clause 8 of 'Detailed Tender Notice', under
the caption 'Process of selection of lessee for lease
agreement', of NIT, it has been stated that:
"8.Process of selection of lessee for lease agreement
a.The bidders expressing interest against the notice inviting tender shall be selected based on:
-Fulfillment of Eligibility Criteria.
-Completeness and attractiveness of the proposal to develop and utilize the premise & buildings. Organization's Vision &Mission for the proposed premise/Building.
-The proposal for utilization of the proposed premises should be acceptable to HEC.
b.Bidders shall be required to participate in open tender proceeding involving financial criteria and other details. c.HEC will sign an agreement with the best evaluated party for each premise (based on tender) for a period of 10 years only.
It would be evident from definition clause, in
particular Clause 1.6 of the 'General terms and
conditions' of NIT, wherein definition of contract has been
given, which is quoted hereunder as:
'The "contract" shall mean the tender as accepted by the Lessor and the formal agreement executed between the Lessor and lessee together with the documents referred as contract document.'
Clause 1.9 of the 'General terms and conditions' of
NIT stipulates about Letter of Acceptance of Tender,
which says that:
"The Letter of Acceptance of Tender (LOA)" means letter giving intimation to the lessee that his/her/their tender has been accepted in accordance with the provisions contained in that letter.'
Clause 2 of the 'General terms and conditions' of
the 'Detailed Tender Notice' stipulates that "the Lessee
shall enter into & execute contract agreement in the
prescribed form. The cost of the required stamp papers for
the contract agreement shall be borne by the Lessee".
Clause 6 of the General Terms & Conditions under
the caption 'Cancellation of Contract', stipulates as
under:
"6.Cancellation of Contract:
HEC in addition to other remedial steps to be taken as provided in the conditions of contract, reserves the right to cancel the contract in full or in part, in the following cases:
a)If the Lessee commits default in proceeding with the services with due diligence and continues to do so even after a notice in writing from the Officer-in-Charge, then on the expiry of the period as specified in the notice.
Or
b)If the lessee commits default/breach in complying with any of the terms and conditions of the contract and do not remedy it or fails to take effective steps for the remedy to the satisfaction of the Officer-in-charge, then on the expiry of the periods as may be specified by the Officer-in-charge in a notice in writing.
Or
c)If the lessee obtains a contract with the Lessor as a result of ring tendering or other non-bonafide methods of competitive tendering.
Or
d)If the lessee shall offer or give or agree to give any person in the service of the Lessor or to any other person on his behalf any valuable gift or consideration of any kind as an inducement or reward for act/acts of favour or disfavor in relation to the obtaining or execution of this or any other contract of HEC.
Or
e)If the lessee transfers, sublets, assign the entire work or any portion thereof without the prior approval in writing from the Officer-in-charge HEC Ltd. The Officer-in-charge HEC Ltd. may be giving a writing notice, cancel the whole contract or portion of it which is in default.
Clause 7 speaks about cancellation of lease
agreement, which reads as under:
"7.Cancellation of Lease Agreement: The contract shall be cancelled under violation of any term and condition of lease agreement or any other general/special term & condition by giving one month notice in writing for eviction of premises otherwise legal action will be initiated as per the PP(EOUO) Act, 1971."
With the aforesaid terms and conditions, the writ
petitioner participated in the tender process by
submitting tender paper along with so-called documents.
The Technical Evaluation Committee had found the writ
petitioner eligible thereafter the bid was opened, in which,
the writ petitioner was found to be successful. In
consequence thereof, 'Letter of Intent' was issued on
31.10.2016 (Annexure 3 to the writ petition) for leasing
out Rajendra Bhawan, Sector II with the specific
condition as stipulated under Clause 6.
For the ready reference Clause 6 of the 'Letter of
Intent' is reproduced hereunder as:
"6.Terms & Conditions a.Period of Lease: 10 years.
(The period of the lease will be 10 years which is renewable for another 10 years on the decisions and terms and conditions of HEC Management.) b.The buildings and halls will be offered on "as is where is" basis. The Lessee can make premises/interiors suitable as per their requirement at their own cost.
c.Permanent structure(s) if constructed on vacant land or renovated structure cannot be demolished at the time of vacating these buildings. No claim for this on HEC shall be tenable at the time of vacating these building by the lessee. d.The lessees will be allowed to renovate the existing structures & maintain the halls and buildings properly. e.The lessee shall not sublease the premises and shall use it only for the purpose for which it has been granted. f.Cancellation of Contract: HEC reserves the right to cancel the contract in full or in part, in the following cases:
i)If the Lessee commits default in proceeding with the services with due diligence and continues to do so even after a notice in writing from the Officer-in-Charge, then on the expiry of the period as specified in the notice.
Or
ii)If the lessee commits default/breach in complying with any of the terms and conditions of the contract and do not remedy it or fails to take effective steps for the remedy to the satisfaction of the Officer-in-charge, then on the expiry of the periods as may be specified by the Officer-in-charge in a notice in writing.
Or
iii)If the lessee obtains a contract with the Lessor as a result of ring tendering or other non-bonafide methods of competitive tendering.
Or
iv)If the lessee shall offer or give or agree to give any person in the service of the Lessor or to any other person on his behalf any valuable gift or consideration of any kind as an inducement or reward for act/acts of favour or disfavor in relation to the obtaining or execution of this or any other contract of HEC.
Or
v)If the lessee transfers, sublets, assign the entire work or any portion thereof without the prior approval in writing from the Officer-in-charge HEC Ltd. The Officer- in-charge HEC Ltd. may be giving a writing notice,
cancel the whole contract or portion of it which is in default.
vi)Under violation of any term and condition of lease agreement or any other general/special term & condition by giving one month notice in writing for eviction of premises otherwise legal action will be initiated as per the PP(EOUO) Act, 1971."
g.Penalty & Compensaiton In case of delay in the lease rent payment, DPS (i.e. Delay payment surcharge) @ 2% per month of the due amount shall be imposed.
h.Agreement:
The Lessee shall enter into an agreement as per the "Proforma for Execution of Agreement" as per annexure - VI of the NIT within one month time from the date of issue of the LOI. All expenditure regarding the agreement will be borne by the Lessee.
i.All the terms and conditions will be as per General terms & conditions of NIT and GCC of HEC.
It is evident from Clause 6.(h) of the Terms &
Condition of the LOI that the Lessee shall enter into an
agreement within one month from the date of issuance of
the LOI and further all expenditure regarding the
agreement will be borne by the Lessee.
It further appears from Clause 6.(d) of the Terms &
Conditions of the LOI that the lessee will be allowed to
renovate the existing structures and maintain the halls
and buildings properly.
It appears that occupation of Rajendra Bhawan, the
premises in question, was handed over to the writ
petitioner, as would appear from 'Occupation Report'
dated 20.03.2017, Annexure 5 to the writ petition, with
the terms and conditions as mentioned in Letter of Intent,
but, when it came to the knowledge of the respondents-
HEC that some irregularities have been committed in
allotment of Rajendra Bhawan, the building in question, a
notice was served upon the writ petitioner vide letter
dated 20.10.2017 mentioning therein that "It is
gathered/noticed that some irregularities might have been
done towards allotment of Rajendra Bhawan, Sector-2 in
your favour. Since, the matter is being investigated at
appropriate level, you are, therefore advised not to
continue with any construction/activity in Rajendra
Bhawan Complex."
It further appears from letter dated 08.11.2017 that
in spite of direction as contained in letter/notice dated
20.10.2017 since the writ petitioner continued with
construction work in the premises in question, the
respondents-HEC intimated the writ petitioner, if the
direction as contained in letter/notice dated 20.10.2017
is not complied with, they will be constrained to take
stern action including cancellation of the allotment.
It further appears that the respondents-HEC in
order to verify the eligibility of the writ petitioner directed
the writ petitioner to submit relevant documents vide
letter dated 29.09.2018 based on which three affidavits
were submitted by it's three associates, to which though
the writ petitioner replied but the same was found not
satisfactory and thereafter, the respondents taking into
consideration all the correspondences made between
them as also the terms and conditions of the LOI,
directed vide letter dated 22.10.2018 to submit written
submission as to why process of cancellation of
contract/allotment should not be initiated and by way of
last opportunity, he was directed to furnish certain
documents showing his experience in the relevant
field/activities, which were supposed to do in Rajendra
Bhawan; all supporting documents showing the nature
and extent of its association with the concerned firms. In
response thereof, the writ petitioner submitted detailed
reply vide letter dated 21.11.2018 but being dissatisfied
with the reply submitted by the writ petitioner the
respondents-HEC vide letter dated 16.08.2019 terminated
the Letter of Intent dated 31.10.2016 with immediate
effect and was directed to complete the formalities related
to handing over the premises in question on or before
14.09.2019.
However, in the meanwhile, the writ petitioner has
started construction work as also started earning income
from the said premises by giving it on rent for its
purposes. When the writ petitioner has not acted in
pursuance to the notices given on administrative side to
the writ petitioner for stopping of the construction work
in the premises, the respondents-HEC resorted to the
provision of Section 5 (A) of the Act, 1971 for eviction of
the premises in question.
10. In the backdrop of these facts, submission has
been made by the writ petitioner that it is the
respondents-HEC who has failed to enter into the
agreement in spite of repeated requests being made by
the writ petitioner and, therefore, termination of LOI by
the respondents-HEC is absolutely illegal. Such argument
has been advanced on the ground that when the
Technical Evaluation Committee has already found the
writ petitioner technically fit there was no occasion for
the respondents-HEC to ask for the documents to
substantiate it's eligibility.
11. Here, the question would arise that if the Technical
Evaluation Committee, which was though constituted by
the respondents-HEC, has found writ petitioner eligible at
the time of consideration of technical bid, can it preclude
the respondents-HEC not to review its own decision by
calling upon the documents to substantiate the eligibility
criteria as provided under the terms and conditions of the
NIT/LOI and resorting to the said provision on the
principle that if anybody is not eligible, even if the
successful bidder has been technically qualified, and
such decision if is based upon incorrect fact can always
be reviewed and, therefore, letters were issued to the writ
petitioner to substantiate the eligibility as also the
supporting documents, based on which three affidavits
were furnished by the firms showing their association
with the writ petitioner and in response thereto to which
though the writ petitioner replied but the same was found
not satisfactory.
It is further evident from NIT/LOI that experience of
five years was required to assess the eligibility of one or
the other bidders and in order to substantiate on this
count the respondents-HEC directed to adduce evidence
regarding any registered deed for partnership or any
other mode of legal association to prove eligibility
substantiating the decision of the tender evaluation
committee.
But, the contention has been raised by the writ
petitioner that Technical Evaluation Committee has found
the writ petitioner eligible, therefore, such decision
cannot be reviewed whereas, the respondents-HEC has
made submission that if wrong has been committed since
its inception, the same has to be rectified and if any
decision has been taken to assess the eligibility of the
bidder same cannot be said to be unjust decision of the
respondents-HEC.
In these backgrounds, the agreement could not be
entered into even after lapse of period, as specified from
the date of issuance of LOI while the LOI reflects that the
agreement has to be entered into in between the
respondents and the writ petitioner within one month
from the date of issuance of LOI.
In these backdrop of aforesaid facts, since issue no.
(I).Whether more issuance of LOI can be termed as
concluded contract without entering into an agreement?
and Issue No. (II).Whether on the basis of LOI any right
has been accrued to the bidder?, are inter-connected, they
are taken together.
12. There is no dispute about the fact that the LOI
merely indicates the party's intention to enter into the
agreement with other party in future. Further, LOI is not
intended to bind either party ultimately to enter into any
contract.
The Hon'ble Apex Court in Rajasthan Cooperative
Dairy Federation Ltd. Vs. Maha Laxmi Mingrate
Marketing Service Pvt. Ltd & Ors, [ (1996) 10 SCC
405], has held that the Letter of Intent merely expresses
an intention to enter into a contract. If the conditions
stipulated in the Letter of Intent were not fulfilled, the
appellant shall be entitled to withdraw the Letter of
Intent.
In the said judgment, consideration has also been
made about applicability of doctrine of audi alteram
partem at paragraph 7, which reads as under:
"7.The High Court was also not right in importing the doctrine of audi alteram partem in these circumstances. If the conduct of Respondent 1 was such that it did not inspire any confidence in the appellant, the appellant was entitled to decline entering into any legal relationship with Respondent 1 as its selling agent. The Letter of Intent merely expressed an intention to enter into a contract. If the conditions stipulated in the Letter of Intent were not fulfilled by Respondent 1, and if the conduct of Respondent 1 was otherwise not such as would generate confidence, the appellant was entitled to withdraw the Letter of Intent. There was no binding legal relationship between the appellant and Respondent 1 at this stage and the appellant was entitled to look at the totality of circumstances in deciding whether to enter into a binding contract with Respondent 1 or not."
In the aforesaid judgment, the Hon'ble Apex Court
has also considered the fact of incurring heavy expenses
and by laying down the principles at paragraphs 8, it has
been held that the statement of the respondent-bidder
has to be established on evidence and admittedly in the
case at the hand, the writ petitioner has not filed any
appropriate case claiming for damages.
For ready reference, paragraph 8 of the judgment is
quoted hereunder as:
"8.Respondent 1 contends that in anticipation of entering into a contract with the appellant, Respondent 1 incurred heavy expenses. This statement of Respondent 1 has to be established on evidence. A writ petition is not an appropriate proceeding if any claim for damages based on disputed facts is required to be established. We do not wish to pronounce on the question whether, in anticipation of entering into a contract, a party which incurs expenses, can recover them from the other party if that other party ultimately, rightly declines to enter into a contract."
Likewise, the Hon'ble Apex Court in Bhushan
Power Steel Limited Vs. S.L. Seal, Additional
Secretary (Steel and Mines), State of Orissa & Ors
[(2017) 2 SCC 125] at paragraph 24 held as under:
"24.No doubt, having regard to the words "by whatever name called", the expression "letter of intent" is to be given wider connotation. It means that nomenclature of the letter would not be the determinative factor. It is the substantive nature of the letter in question that would determine as to whether it can be treated as the letter of intent. For this purpose, it is first necessary to find the meaning that has to be attributed to the term "letter of intent". As per the legal dictionary, "letter of intent" is a document that described the preliminary understanding between the parties who intend to make a contract or join together in another action. This term has come up for interpretation on few occasions before this Court."
In the aforesaid case, the Hon'ble Apex by making
reference of the case rendered in Rishi Kiran Logistics
(P) Ltd. v. Kandla Port Trust, Board of Trustees of
Kandla Port Trust & Ors (2015) 13 SCC 233 has held
that the letter of intent merely indicates a party's
intention to enter into a contract with other party in
future.
The relevant paragraph 25 of the judgment
rendered in aforesaid case is quoted hereunder as:
"25. In Rishi Kiran Logistics (P) Ltd. v. Kandla Port Trust [Rishi Kiran Logistics (P) Ltd. v. Kandla Port Trust, (2015) 13 SCC 233 : (2016) 1 SCC (Civ) 680] , relying upon an earlier decision, this Court held that a letter of intent merely indicates a party's intention to enter into a contract with other party in future, as can be seen from the following para 43 thereof, which reads as under: (SCC pp. 255-56) "43.At this juncture, while keeping the aforesaid pertinent features of the case in mind, we would take note of "the Rules and Procedure for Allotment of Plots" in question issued by Kandla Port Trust. As per Clause 12 thereof the Port Trust had reserved with itself right of acceptance or rejection of any bid with specific stipulation that mere payment of EMD and offering of premium will not confer any right or interest in favour of the bidder for allotment of land. Such a right to reject the bid could be exercised "at any time without assigning any reasons thereto". Clause 13 relates to "approvals from statutory authorities", with unequivocal assertion therein that the allottees will have to obtain all approvals from different authorities and these included approvals from CRZ as well. As per Clause 16, the allotment was to be made subject to the approval of Kandla Port Trust Board/competent authority. In view of this material on record and factual position noted in earlier paragraphs we are of the opinion that observations in Dresser Rand S.A. v. Bindal Agro Chem Ltd. [Dresser Rand S.A. v. Bindal Agro Chem Ltd., (2006) 1 SCC 751] would be squarely available in the present case, wherein the Court held that: (SCC p. 773, paras 39-40) '39. ... a letter of intent merely indicates a party's intention to enter into a contract with the other party in future. A letter of intent is not intended to bind either party ultimately to enter into any contract. ...
40.It is no doubt true that a letter of intent may be construed as a letter of acceptance if such intention is evident from its terms. It is not uncommon in contracts involving detailed procedure, in order to save time, to issue a letter of intent communicating the acceptance of the offer and asking the contractor to start the work with a stipulation that the detailed contract would be drawn up later. If such a letter is issued to the contractor, though it may be termed as a letter of intent, it may amount to acceptance of the offer resulting in a concluded contract between the parties. But the question whether the letter of intent is merely an expression of an intention to place an order in future or whether it is a final acceptance of the offer thereby leading to a contract, is a matter that has to be decided with reference to the terms of the letter.' When the LOI is itself hedged with the condition that the final allotment would be made later after obtaining CRZ and other clearances, it may depict an intention to enter into contract at a later stage. Thus, we find that on the facts of this case it appears that a letter with intention to enter into a contract which could take place after all other formalities are completed. However, when the completion of these formalities had taken undue long time and the prices of land, in the interregnum, shot up sharply, the respondent had a right to cancel the process which had not resulted in a concluded contract."
Thus, it is evident from the judgments, referred
hereinabove that the Letter of Intent merely indicates a
party's intention to enter into a contract with other party
in future and respondents had right to cancel the LOI
which had not resulted in a concluded contract.
In the case in hand, the Letter of Intent clearly
stipulates for entering into agreement within a period of
one month from the date of issuance of Letter of Intent.
Thus, when there is specific stipulation about entering
into contract/agreement within a period of one month,
admittedly agreement could not be arrived at within such
period of time, therefore, merely on the basis of Letter of
Intent the writ petitioner cannot claim that the said Letter
of Intent has taken the shape of concluded contract. The
Letter of Intent cannot be said to have taken the shape of
concluded contract. It is settled position of law that in the
absence of any agreement, the Letter of Intent would only
be an intention of the parties to enter into the contract
with the other party. As such, no right can be said to
have accrued to the writ petitioner in the absence of the
agreement.
In this regard, it would be relevant to mention the
meaning of vested/accrued right, as has been discussed
by Hon'ble Apex Court in MGB Gramin Bank Vs.
Chakrawarti Singh [(2014) 13 SCC 583] at paragraph
11, 12 and 13, which read under as:
"11. The word "vested" is defined in Black's Law Dictionary (6th Edn.) at p. 1563, as:
"Vested.--fixed; accrued; settled; absolute; complete. Having the character or given in the rights of absolute ownership; not contingent; not subject to be defeated by a condition precedent. Rights are 'vested' when right to enjoyment, present or prospective, has become property of some particular person or persons as present interest; mere expectancy of future benefits, or contingent interest in
property founded on anticipated continuance of existing laws, does not constitute 'vested rights'."
12.In Webster's Comprehensive Dictionary (International Edition) at p. 1397, "vested" is defined as law held by a tenure subject to no contingency; complete; established by law as a permanent right; vested interest.
13. Thus, vested right is a right independent of any contingency and it cannot be taken away without consent of the person concerned. Vested right can arise from contract, statute or by operation of law. Unless an accrued or vested right has been derived by a party, the policy decision/scheme could be changed.
It is, thus, evident that vested right is a right
independent of any contingency and it cannot be taken
away without consent of the person concerned. Vested
right can arise from contract, statute or by operation of
law. Unless an accrued or vested right has been derived
by a party, the policy decision/scheme could be changed.
Admitted fact of the present case is that as yet no
agreement has been arrived out in between the parties
and, therefore, the question of vested or accrued right
does not arise.
Accordingly, Issue Nos. I and II are answered
against the appellant.
13. So far issue no. (iii).Whether termination of LOI due
to non-compliance of the terms and conditions as
stipulated in the Notice Inviting Tender (NIT) as also LOI
can be said to be unjustified? and (IV).Whether non-
furnishing of documents that was asked for to justify the
eligibility can be said to be unjustified?, are concerned
since both the issues are intertwined , they are being
considered together.
It is settled position of law that condition stipulated
in NIT is strictly to be adhered to, as has been held by
Hon'ble Apex Court in AIR India Ltd Vs. Cochin
International Airport Ltd & Ors. [(2000) 2 SCC 617]
that State can fix its own terms of invitation of tender and
that is not open to judicial scrutiny.
Likewise, in Directorate of Education & Ors Vs.
Educomp Datamatics Ltd. & Ors [(2004) 4 SCC 19], it
has been held by Hon'ble Apex Court that the Court
should not interfere with the terms of the Notice Inviting
Tender unless it is shown to be either arbitrary or
discriminatory or actuated by malice. It has further been
held that while exercising power of judicial review of the
terms of the tender notice, the court cannot order for
change in them, unless it is of the opinion that the terms
stipulated were either arbitrary or discriminatory or
actuated by malice.
In the case of Kanhaiya Lal Agrawal-Vs.-Union of
India and Others [(2002) 6 SCC 315], it has been held
therein at paragraph 6 by taking note of the judgment
rendered by the Hon'ble Apex Court in the case of G.J.
Fernandez-Vs.-State of Karnataka and Ors. reported
in (1990) 2 SCC 488 as under:
"6.It is settled law that when an essential condition of tender is not complied with, it is open to the person inviting tender to reject the same. Whether a condition is essential or collateral could be ascertained by reference to the consequence of non- compliance thereto. If non-fulfilment of the requirement results in rejection of the tender, then it would be an essential part of the tender otherwise it is only a collateral term. This legal position has been well explained in G.J. Fernandez v. State of Karnataka."
The fact of the case is that admittedly the writ
petitioner was declared qualified in the technical bid and
pursuant thereto, Letter of Intent was issued with the
specific stipulation to enter into agreement within a
period of one month from the date of issuance of Letter of
Intent.
The respondents-HEC has also made
communication to the writ petitioner to justify about the
eligibility as per the condition stipulated in the NIT, upon
which though affidavits sworn before Notary Public was
submitted showing association with other firms, but, that
has been found to be insufficient compliance to
substantiate the eligibility as because the writ petitioner
has failed to place on record before the respondents-HEC
about the nature of association with other so-called
partners as to whether it was partnership firm or what is
the nature of the association etc. such document was
repeatedly asked by the respondents-HEC as would
appear from the materials available on record but no
such document was provided and as such the agreement
could not have been entered into.
Contention has been raised that at the belated
stage the respondents-HEC cannot again go into the
question of eligibility of the writ petitioner since the
eligibility condition has already been decided, but we are
not impressed with such argument as until and unless a
right is accrued such question cannot be agitated and
that right will be said to have accrued only after entering
into the agreement. Thus, in the case in hand, since no
agreement has been entered into, if any doubt has arisen
in the mind of the respondents-HEC about eligibility part
of the writ petitioner, which is a mandatory condition as
stipulated in the NIT and which is required to be adhered
to by the bidder, and if such document has been asked to
be submitted for assessing the eligibility, the same cannot
be said to be unjustified decision of the respondents-
HEC.
The matter would have been different if the writ
petitioner had valid documents in this regard but
admittedly no such document has been placed. Neither
such submission has been made before the writ Court
nor before this Court substantiating the eligibility
condition save and except the statement having been
made that after issuance of Letter of Intent since
possession has been handed over and the writ petitioner
has paid rental to the respondents-HEC, the said Letter of
Intent has taken the shape of concluded contract.
Therefore according to our considered view, since the writ
petitioner has failed to substantiate about eligibility
criteria, which is mandatory one, it cannot be allowed to
take such plea on account of the fact that the rental was
being paid to the respondents-HEC due to the possession
having been handed over to the writ petitioner with the
condition as enshrined in the Letter of Intent, i.e., within
a period of one month agreement is to be entered. Merely,
since possession has been handed over and the rental
has been paid, the Letter of intent, which is intention to
enter into the agreement in future with other party, such
Letter of Intent cannot take the shape of concluded
contract as per the ratio laid down by Hon'ble Apex Court
in the case of Rajasthan Cooperative Dairy Federation
Ltd. (Supra).
Accordingly, issue Nos. III and IV are also
answered against the appellant.
14. The learned Single Judge, after taking into
consideration the implication of the Letter of Intent and
the same being not by way of accrual of any right and if
there is violation of instruction as also activities that
pertains to the construction/renovation of such without
entering into the agreement, which is contrary to the
terms and conditions of the Letter of Intent, refused to
interfere with the order of termination of Letter of Intent.
The Hon'ble Apex Court in Rajasthan Cooperative
Dairy Federation Ltd. (Supra) has held that, while
terminating the Letter of Intent, it is not required to follow
the principles to audi alter partem, which also suggest
that merely by issuance of Letter of Intent no right
accrues to the party in whose favour Letter of Intent has
been issued. However, in the case in hand, notices were
issued to the writ petitioner, to which the writ petitioner
had replied and only thereafter Letter of Intent was
terminated.
15. Learned Single Judge has also discussed the power
of judicial review in the matter of contract and, upon
such legal position as also discussion by the learned
Single Judge, we are in agreement with the learned Single
Bench on the basis of settled position of law that in the
contractual matter, power of writ Court is least to be
exercised and it is only to be exercised if there is violation
of Article 14 of the Constitution of India or any error in
the decision making process.
In this regard, reference may be made to the
judgment rendered by Hon'ble Apex Court in Syed TA
Naqshbandi and Ors. vs. State of J&K and Ors.,
[(2003) 9SCC 592], wherein the Hon'ble Supreme Court
has observed as under: ―
"Judicial review is permissible only to the extent of finding whether the process in reaching the decision has been observed correctly and not the decision itself, as such. Critical or independent analysis or appraisal of the materials by the Courts exercising powers of judicial review unlike the case of an appellate court, would neither be permissible nor conducive to the interests of either the officers concerned or the system and institutions......‖
The Hon'ble Apex Court further in Tata Cellular
Vs. Union of India, (1994) 6 SCC 651 has been pleased
to hold that so far as the judicial review is concerned,
with reviewing not the merit of the decision in support of
which application for judicial review is made but the
decision making process itself. It is thus different from
an appeal with hearing an appeal, the court of concerned
within the merits of the decision under appeal since
before all judicial review is not an appeal from the
decision, the court cannot substitute its own decision. It
has further been held that it is not for the court to
determine whether a particular policy or particular
decision taken in the fulfillment of that policy is fair.
The Hon'ble Apex Court therefore, has laid down
the following principles:-
i.The modern trend points to judicial restraint in administrative action.
ii.The Court does not sit as a court of appeal but merely reviews the manner in which the decision was made. iii.The court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible. iv.The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tires. More often than not, such decisions are made qualitatively by experts. v.The Government must have freedom of contract. In other words a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of wednesbury principle of reasonableness but must be free from arbitrariness not affected by bias or actuated by mala fides vi.Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure.
Likewise in Raunaq International Ltd. Vrs. I.V.R.
Construction Ltd. & Ors. (1999)1 SCC 492 the scope
of judicial review has been laid down by holding therein
that the decision making process suffers from bias of
arbitrariness, the same will be scrutinized under the
power of judicial review.
In the case of Jagdish Mandal Vrs. State of
Orissa &Ors. reported in (2007) 14 SCC 517, it has
been laid down that the power of judicial review in the
contractual matters is permissible only if (i) Whether the
process adopted or decision made is mala fide or
intended to favour someone or the same is so arbitrary
and irrational that the court can say: the decision is
such that no responsible authority acting reasonably
and in accordance with law could have reached.
(ii) Whether public interest is affected.
Judgment rendered in the case of Ramana
Dayaram Shetty Vrs. International Airport Authority
of India & Ors., reported in (1979) 3 SCC 489, the
Hon'ble Apex Court observed as under in Paragraph-10
thereof:-
"10.It is a well settled rule of administrative law that an executive authority must be rigorously held to the standards by which it professes its actions to be judged and it must [21] scrupulously observe those standards on pain of invalidation of an act in violation of them."
16. It requires to refer herein that the writ petitioner
took a plea that as per the condition stipulated in the
LOI, the construction/renovation work has been
commenced but the same cannot be acceptable to this
Court for the reason that if any document is under
construction the same has to be considered in its entirety
and not the part which suits a party will be accepted and
the part that does not suit will not be accepted i.e. on the
basis of principle that one cannot be allowed to approbate
and reprobate. Herein, LOI consists certain conditions.
One of the conditions authorizes the writ petitioner to
carry out renovation work but another condition
stipulates that within a month from the date of issuance
of LOI, the agreement has to be entered into but the writ
petitioner is only placing reliance upon the condition
which authorizes the writ petitioner to carry out
renovation work leaving apart the condition that binds
the party to enter into agreement within a month from
the date of issuance of LOI.
In that view of the matter, according to our
considered view, it is not a case where any error has been
committed by the respondents-HEC in its decision
making process, therefore, as per the ratio laid down in
the judgments, as referred herein above, we are of the
view that the power conferred under Article 226 of the
Constitution of India is not fit to be exercised in the facts
and circumstances of the present case.
17. In the case at hand, the learned senior counsel for
the writ petitioner has failed to show any illegality having
been committed by the respondents, which pertains to
the decision making process rather according to our
considered view, based on appreciation of factual aspects
it appears that there is no error in the decision making
process.
Further, the writ petitioner had not brought to the
notice to the learned Single Judge about initiation of
proceeding under the Act of 1971 but before this Court,
by filing Interlocutory Application, being I.A. No. 3106 of
2020, a prayer has been made for stay of Case No. PP
Act/Rev/Evic./2019-02 initiated by the respondents in
the Court of Estate Officer, H.E.C., resorting to the
provision of sub-section (1) of Section 5-A of the Act,
1971 and further it appears that said notice has never
been questioned by the writ petitioner even though the
said notice has been issued by the respondents during
pendency of the writ petition, which is nothing but a
suppression of material fact.
18. It further appears from the impugned order that
learned Single Judge, while dismissing the writ petition
granted liberty to the writ petitioner to approach
the appropriate forum claiming damages from the
respondents, if so advised. Thus, we are of the considered
view that the case does not require any interference by
this Court.
19. Accordingly, the present intra-court appeal fails
and, is dismissed.
20. In view of the dismissal of the instant intra-court
appeal, all Interlocutory Applications, being I.A. No. 3106
of 2020, I.A. No. 902 of 2021 and I.A. No. 903 of 2021
stand disposed of.
(Dr. Ravi Ranjan, C.J.)
(Sujit Narayan Prasad, J.) Alankar/ -
A.F.R
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!