Wednesday, 22, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Himachal Pradesh Tourism ... vs M/S Modern Sanitary Engineers
2023 Latest Caselaw 17095 HP

Citation : 2023 Latest Caselaw 17095 HP
Judgement Date : 30 October, 2023

Himachal Pradesh High Court
Himachal Pradesh Tourism ... vs M/S Modern Sanitary Engineers on 30 October, 2023
Bench: Mamidanna Satya Rao, Jyotsna Rewal Dua

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA

Arb. Appeal No. 1 of 2014

Reserved on : 16.10.2023

.

Date of decision : 30.10.2023

-----------------------------------------------------------------------------------

Himachal Pradesh Tourism Development Appellant

Corporation.


                                            Versus





        M/s Modern Sanitary Engineers                                     Respondent

--------------------------------------------------------------------------------------

Coram :- r The Hon'ble Mr. Justice M.S. Ramachandra Rao, Chief Justice

The Hon'ble Ms. Jyotsna Rewal Dua, Judge

Whether approved for reporting? Yes _________________________________________________________ For the Appellants : Mr. Sumeet Raj Sharma, Advocate.

For the Respondent: Mr. J.S. Bhogal, Senior Advocate, with Ms. Swati Verma, Advocate.

----------------------------------------------------------------------------------- Jyotsna Rewal Dua, Judge

Learned Single Judge did not find any merit in the

Arbitration Case No. 52 of 2007 filed under Section 34(3) of the

Arbitration & Conciliation Act 1996 (in short the Act) by the Himachal

Pradesh Tourism Development Corporation (HPTDC) against the

award passed by the learned Arbitrator on 26.09.2007 as supplemented

on 04.07.2011. The Arbitration Case was dismissed on 01.07.2013.

.

Taking exception to this judgment, the HPTDC has filed this

Arbitration Appeal under Section 37 of the Act.

2. Brief reference to the facts leading to filing of instant

appeal may be made :-

2(i)

A notice dated 29.07.2002 was served by the respondent

upon the appellant-Corporation that despite completion of the work

awarded to it, on 31.10.1999, the payments due to it had not been

released. A request was made to appoint an Arbitrator for adjudicating

the dispute between the parties.

2(ii) In Arbitration Case No. 69 of 2002 filed by the

respondent under Section 11(6) of the Act, a retired Chief Engineer was

appointed as Arbitrator by the Court on 14.03.2003. However, in view

of the request made by the Arbitrator, so appointed, the order dated

14.03.2003 was modified on 09.07.2004 by appointing another retired

Chief Engineer as the sole Arbitrator in place of the earlier appointed

Arbitrator.

2(iii) The Arbitrator entered upon the reference. The award

was announced on 26.09.2007. The respondent/claimant had claimed

following amount in its claim petition.

.

"Claim No. 1 : On account of payment of the final bill for Rs. 8,00,000/-.

Claim No. 2 : On account of release of Security Deposit, for an amount of Rs. 1,00,000/-.

Claim No. 3 : On account of damages for the prolongation of the work for an amount of Rs. 4,32,000/-.

Claim No. 4 : On account of payment of price escalation, for an amount of Rs. 2,62,724/-.

Claim No. 5 : For allowing interest @ 24% on all the claims 1 to r 4 with effect from 30.04.2000 till date of

payment."

In the present appeal, learned counsel for the appellant

has confined his submissions only to the amount awarded by the

Arbitrator under claim No. 1. Hence, discussions made hereafter are

only in reference to claim No.1.

2(iv) The Arbitrator in his award dated 26.09.2007 allowed a

sum of Rs. 5,13,312/- to the respondent under Claim No.1.

The appellant assailed the award dated 26.09.2007 before

this Court in Arbitration Case No. 52 of 2007. The appellant's main

objection was that though the claim of the respondent was initially for a

sum of Rs. 4,00,000/-, but it was enhanced to Rs. 8,00,000/- in the

claim petition. This, according to the appellant, was not permissible. It

was contended that the learned Arbitrator had not given reasons in the

.

award for coming to the conclusion that under Claim No.1, the claimant

was entitled to a sum of Rs. 5,13,312/-.

2(vi) Learned Single Judge while deciding the Arbitration

Case found substance in the plea of the appellant/objector that

Arbitrator had not given reasons for arriving at the conclusion that the

claimant was entitled to a sum of over Rs. 5,00,000/- for claim No.1.

For that reason, vide order dated 11.09.2009, the award was remitted

back to the Arbitrator under Section 34(4) of the Act for giving reasons

in support of findings on claim No.1.

2(vii) In compliance to the directions passed in Arbitration

Case No. 52 of 2007, the Arbitrator again held proceedings and on

04.07.2011 supplemented his award dated 26.09.2007 by recording

following reasons :-

"In compliance to the orders of the Hon'ble H.P. High Court, I

give the reasons as under :-

At the time of making the Award, I had examined the statement of

the claimant in which he had claimed a sum of Rs. 6.39 lacs a shown in

Annex. C6 (page 291 of the arbitration file). I also found that the claimant,

with his letter dated 18.3.99, did not provide rate-analysis for the item of

'built-up steel', to which the respondent had objected. Therefore, I

.

considered it appropriate not to allow the amount (Rs. 55,986.00) claimed

for this 'built-up steel' item of work and rejected this item.

In the same statement, there were other items, like '1/2 brick

masonry', 'brick masonry in foundations', 'brick masonry in super-

structure', 'shutters with laminated board' and 1.25 mm thick HB sheets,

for which the clamant did not provide analyses of rates with his letter

dated 3.4.99. The total amount claimed under all these items works out as

Rs. 69,469.47. The respondent had denied the receipt of claimant's letter

dated 3.4.99 and in the absence of specific admission by the respondent, I

had decided not to allow these items.

By disallowing all the above items, the balance amount payable to

the claimant became Rs. 5.13 lacs (against claimed amount of Rs. 6.39

lacs) and after rounding off this figure, I awarded an amount of Rs. 5.00

lacs under claim No.1."

2(viii) The appellant Corporation, not satisfied with the reasons

assigned by the Arbitrator, again assailed the award before the learned

Single Judge. The learned Single Judge did not find favour in the

challenge laid by the appellant. The Arbitration Case No. 52 of 2007

was finally dismissed on 01.07.2013. Aggrieved, the HPTDC has now

invoked Section 37 of the Act in the instant appeal.

3. The points urged by learned counsel for the appellant-

.

Corporation are that firstly, the respondent-claimant having served

notice upon the appellant-Corporation for claiming a sum of

Rs. 4,00,000/- under claim No. 1 could not have enhanced its claim to

Rs. 8,00,000/- before the Arbitrator and secondly, that the award passed

by the Arbitrator allowing a sum of Rs. 5,13,312/- in favour of the

claimant under claim No. 1 is without any reason and contrary to clause

12 of the Arbitration Agreement. The learned Senior Counsel for the

respondent-claimant defended the impugned award passed by the

Arbitrator.

4. We have heard learned counsel on both sides and

considered the case record. Our observations in the matter are as

under :-

4(i) It is well settled that the Court cannot sit as an appellate

authority to re-appreciate the evidence led by the parties before the

Arbitrator. The Arbitrator is the final Arbiter for the dispute between

the parties. It is not open to challenge the award on the ground that the

Arbitrator has drawn his own conclusion or has failed to appreciate the

facts. The Court cannot substitute its own evaluation of the conclusion

of law or facts to come to the conclusion that the Arbitrator had acted

.

contrary to the bargain between the parties. Whether a particular

amount was liable to be paid, is a decision within the competence of

the Arbitrator. By purporting to construe the contract, the Court cannot

take upon itself the burden of saying that this was contrary to the

contract and as such beyond jurisdiction. Where the reasons have been

given by the Arbitrator in making the award, the Court cannot examine

the reasonableness of reasons. If the parties have selected their own

forum, the deciding forum must be conceded the power of appraisement

of evidence. The Arbitrator is the sole judge of the quality as well as the

quantity of evidence and it will not be for the Court to take upon itself

the task of being a judge on the evidence before the Arbitrator. [ see:

2018 (16) SCC 219 Oswal Woollen Mills Limited Vs. Oswal Agro Mills

Limited].

4(ii) In the instant case, the Arbitrator has recorded reasons

for allowing claim of Rs. 5,13,312/- to the respondent under claim No.

1. The Arbitrator has noted that according to the parties, there was no

dispute with regard to the quantity executed at the site except about the

market rate payable for various items. The respondent's plea was that it

had submitted its rates to the appellant-Corporation with proper analysis

.

of rates, but the appellant kept on paying lower rates, terming such rates

as payable market rates. The Arbitrator in his award dated 26.09.2007

noticed contract clause 12-A relied upon by the appellant which read ;

"in case if contractor fails to lodge claim supported by proper analysis

of rates in respect of such quantities in excess of the deviation limit, the

rates quoted by the contractor for individual items shall be binding

beyond deviation limit." The Arbitrator found that appellant had not

taken timely action to reject the rates demanded by the respondent-

claimant. That the respondent-claimant continued to carry out the work

on the presumption that the rates demanded by it were genuinely

payable and deemed to have been accepted by the appellant. The

Arbitrator allowed a claim of Rs. 5,08,465 + 4,847 = 5,13,312/- to the

respondent against claimed amount of Rs. 8,00,000/- under claim No. 1.

Pursuant to directions of the Court, the Arbitrator on 04.07.2011 gave

further reasons in support of award dated 26.09.2007. On the plea of the

appellant that the respondent had not given proper rate analysis, the

Arbitrator held that the respondent in its letter dated 18.03.1999 did not

provide rate analysis for the items of 'built up steel' to which the

appellant had objected to. For that reason, an amount of Rs. 55,986/-

.

claimed for the 'built up steel' was not allowed. Similarly, certain other

amounts claimed by the respondent were not allowed as the appellant

had objected to the rates quoted by the respondent of other items at the

relevant time. The Arbitrator held that by disallowing these specific

items, where contractor's quoted rates were objected to by the

appellant, the balance amount payable to the respondent became Rs.

5,13,312/-. The award passed by the Arbitrator cannot be said to be

unreasoned award.

4(iii) Learned counsel could not substantiate his other plea that

the respondent was debarred from claiming an amount of over Rs.

4,00,000/- merely because in the notice seeking appointment of

Arbitrator and in the application made under Section 11 of the Act,

Rs. 4,00,000/- was mentioned as the amount due to it. Notice seeking

appointment of the Arbitrator need not even quantify the amount

claimed. It is well settled that an application under Section 11 of the

Act need not set out in detail the disputes or the claims and may briefly

refer to the subject matter or broad contours of the dispute. It is not in

dispute that the respondent in its claim made before the learned

Arbitrator had claimed Rs. 8,00,000/- under Claim No. 1. After

.

consideration, this claim was allowed by the Arbitrator for

Rs. 5,13,312/-.

4(iv) There is no error apparent on the face of record/award,

which can be said to be falling under any one of the exceptions carved

out under the provisions of Section 34 of the Act. The learned single

Judge did not commit any error in dismissing the Arbitration Case

instituted by the appellant.

5. For the aforesaid reasons, we do not find any merit in this

appeal and the same is accordingly dismissed. Pending applications, if

any, also stand dismissed.





                                          ( M.S. Ramachandra Rao )
                                                 Chief Justice





     30th October, 2023 (K)                   ( Jyotsna Rewal Dua )





                                                      Judge





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter