Citation : 2022 Latest Caselaw 11569 HP
Judgement Date : 27 December, 2022
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
.
CWP No. 8073 of 2021
Reserved on: 28.09.2022
Decided on : 27.12.2022
Bali Ram Thakur ...Petitioner
Versus
The Union of India and another ...Respondents
Coram
The Hon'ble Mr. Justice Tarlok Singh Chauhan, Judge. The Hon'ble Mr. Justice Virender Singh, Judge.
Whether approved for reporting?1 No.
For the petitioner: Mr. P.S. Goverdhan, Advocate.
For the respondents: Mr. Balram Sharma, Deputy Solicitor
General of India.
Virender Singh, Judge.
Petitioner-Bali Ram Thakur, by virtue of the
present writ petition, filed under Article 226 of the
Constitution of India, has sought the indulgence of this Court
to issue the appropriate writ, order or direction, claiming the
following substantive reliefs:
Whether Reporters of local papers may be allowed to see the judgment?
"(a) To issue necessary writ, order and direction to the respondents to refer the dispute arisen between the parties to the committee of the Arbitrator with further direction to follow the procedure as
.
contemplated under Sections 325 to 330 of the
Cantonment Act, 2006, in view of clauses 25 and 30 of agreement dated 1.8.2021 Annexure P-2.
(b) To issue necessary writ and order thereby
quashing impugned order dated 14.12.2021, Annexure P-12, being wrong and illegal.
(c) To issue necessary writ, order or direction to the respondents thereby allowing the petitioner to collect
the fee at the toll barriers as per the terms of the agreement and further to complete the tenure of the contract/agreement dated 1.8.2021 Annexure P-2, till its expiry i.e. 31.3.2022, and to restore the possession
of the toll barrier in favour of the petitioner.
(d) To quash and set aside the notice dated 14.12.2021 Annexure P-13, notice dated 7.12.2021, Annexure P-15 and notice dated 27.11.2021, Annexure P-16, being wrong and illegal."
2. The petitioner has invoked the extra ordinary
jurisdiction of this Court, on the ground, that the respondents
had floated the tender, through e-auction, on 4th March, 2021,
for collection of the toll, from the vehicles, entering in the
limits of Cantonment Board Subathu, Tehsil and District
Solan, H.P., for the period, commencing from the intervening
night of 31st March, 2021 to 1st April, 2022.
3. The petitioner participated in the tender process and
had been declared as successful bidder. Accordingly, the
contract was awarded to him. The codal formalities were
completed and formal agreement (Annexure P-2), in this
regard, was reduced into writing on 1st August, 2021.
.
4. After commencement of the contractual period,
according to the petitioner, the toll collection, for the first
month, remained as normal, but, thereafter, due to the
restrictions imposed by the Central Government, and, followed
by the State Government, in the wake of COVID-19 pandemic,
collection of the toll had drastically come down, resulting huge
financial losses to the petitioner.
5. Despite suffering the huge losses, according to the
petitioner, he was under contractual obligation to pay the
tender amount to the respondents in a periodical manner, as
per Clause 1 of the agreement, dated 1 st August, 2021.
Although, the petitioner was regular in payment of the
installment in advance, but, due to the COVID-19 restrictions,
he could not pay the said amount within time. Due to the
imposition of the curfew, the petitioner represented to the
respondents to consider the loss being suffered by him, but, the
said representations were not considered by them.
6. Vide letter dated 10th May, 2021, the petitioner wrote
a letter to respondent No. 2 to permit him to either close the
toll barriers or to compensate the losses. The said letter was
also not responded by respondent No. 2. Thereafter, the
.
petitioner has made various communications, vide letters,
dated 3rd June, 2021, 8th August, 2021, 11th June, 2021, 21st
June, 2021 and 27th July, 2021. Instead of acceding to the
requests made by the petitioner, as referred to above, the
respondents had kept on demanding the installments from the
petitioner. Thereafter, he had again made representation on
4th August, 2021.
7. When no response was given by respondent No. 2,
the petitioner was compelled to issue legal notice, dated 20 th
September, 2021, requesting the respondents to settle the
dispute by holding a meeting. The respondents were also
requested to refer the matter for arbitration as per Clause 30
of the agreement, dated 1 st August, 2021. Instead of adhering
to Clause 30, the respondents, according to the case set up by
the petitioner, replied the notice on 30 th September, 2021, in
which, the claim of the petitioner has been disputed and also
refused to adhere to comply with Clause 30 of the agreement
on the ground, that the claim of the petitioner, is not a matter,
which could be referred to the arbitration.
8. When respondent No. 2 had not adhered to Clauses
25 and 30 of the agreement, in stricto sensu, the petitioner
.
filed a petition under Section 9 of the Arbitration and
Conciliation Act, 1996, seeking the interim relief, before the
learned District Judge, Solan. The said petition was dismissed
by the learned District Judge on 14 th December, 2021, on the
ground of maintainability.
9. After the decision rendered by the learned District
Judge on 14th December, 2021, respondent No. 2 had forcibly
taken the possession of the toll collection barrier from the
petitioner without serving any notice upon him. The said act
is stated to have been done, by respondent No. 2, in violation
of the terms and conditions of the agreement (Annexure P-2),
as, instead of serving a notice upon the petitioner, they had
issued notice, dated 14th December, 2021, through whats app
message. The petitioner has informed this fact to the police
vide Annexure P-14. Now, according to the petitioner,
respondent No. 2 is threatening to re-auction the toll collection
barrier to some third person.
10. It is the further case of the petitioner that he had
already paid a sum of ₹ 68 lakh to the respondents till
November, 2021, which includes a sum of ₹ 14 lakh, as
security deposit.
.
11. Alleging against respondent No. 2, that the terms
and conditions of the agreement, dated 1 st August, 2021, have
not been adhered to, it has been pleaded that the respondents,
instead of compensating the petitioner, had taken the stand
that the matter is not liable to be referred to the Arbitrator.
As such, the said action of respondent No. 2 is stated to be in
dereliction of the provisions of Articles 325, 326 and 327 of the
Cantonment Act, 2006.
12. Similarly, the decision of the learned District Judge,
in dismissing the application under Section 9 of the
Arbitration and Conciliation act, is also stated to be in
violation of Sections 325 to 330 of the Cantonment Act, 2006.
13. On all these submissions, the petitioner has sought
the reliefs, as referred to above.
14. The writ petition has been contested by the
respondents by taking the preliminary objections qua the
maintainability of the writ petition and that the petitioner has
not approached the Court with clean hands. The factual
position regarding the auction of the barrier points of Subathu
Cantonment for collection of vehicle entry fees has not been
disputed. It has also not been disputed that the contract for
.
collecting the entry fees from the intervening night of 31 st
March, 2021 to 1st April, 2022 had been awarded to the
petitioner and possession of the barrier point was handed over
to him and the terms and conditions were reduced into writing
on 1st August 2021.
15. Elaborating
r the terms and conditions of the
agreement, it has been pleaded that the contract amount of
₹ 1,33,10,000/-, had to be paid, in six equal installments, as
per the timeline, mentioned in the agreement, but, the
petitioner could not comply with the said time schedule and
stopped the payment of the installments with effect from 1 st
August, 2021 to 15th August, 2021 on the plea to compensate
the loss caused to him due to COVID-19 restrictions.
16. According to the stand taken by the respondents,
assurance was given to him to compensate the loss, but,
despite the said assurance, the petitioner has failed to deposit
the installments, as per the agreement. When the petitioner
failed to make the payment, as such, he was asked by
respondent No. 2, vide letter, dated 30 th September, 2021, to
make payment of outstanding dues, failing which, the contract
would be terminated.
.
17. Aggrieved from the said notice, the arbitration case
was filed by the petitioner before the District Judge. In the
said proceedings, reply was filed and a committee was
constituted by the Board to assess the actual compensation to
be given to the contractor in terms of the provisions contained
in Clause25 of the contract/agreement in compliance of Court's
order, as communicated by the Cantonment Board Legal
Advisor, vide his letter, dated 21st October, 2021.
18. The said committee, after hearing both the parties,
furnished his report, dated 6th December, 2021, holding therein
that the petitioner was entitled to get relief of 35 days, as
calculated therein, during which, there was no vehicular traffic
and the said amount has been assessed by the Committee, as
₹ 12,76,301/-. The said amount is stated to be in addition to
the amount, which the petitioner had collected during those 35
days.
19. The District Judge, after going through the said
report, had dismissed the said arbitration case on 14 th
December, 2021. Thereafter, the physical possession of the
said barriers was taken on 14th December, 2021 at 6.30 p.m.
However, in compliance of the order, dated 23 rd December,
.
2021, passed by this Court, the physical possession was again
handed over to the petitioner on 24 th December, 2021 at 3.40
p.m., but, the petitioner had willingly stopped the collection of
the entry fee and again handed over the physical possession of
the said barrier of the Cantonment Board on 18 th January,
2022 at 6.00 p.m.r
20. The said action, according to the respondents, was
taken by the petitioner, in view of the letter dated 7 th January,
2022, issued by the Government of India, Ministry of Defence,
whereby collection of vehicle entry fees has been stopped to be
collected, by the Cantonment Boards, with immediate effect.
21. As regards the restrictions imposed by the
Government in the wake of COVID-19 pandemic, it has been
pleaded that the State Government of Himachal Pradesh
declared Corona Curfew after more than a month with certain
conditions on 5th May, 2021, where inter-state and intra-state
movement of public transport vehicles was restricted only up
to 50% and subject to SOP issued by the Transport
Department, however, the operation of the public stage and
contract carriage was suspended only with effect from 10 th
May, 2021, except essential services, vide order dated 8th May,
.
2021. The said restrictions remained in force up to 14 th June,
2021. The said period of 35 days was duly considered by the
Committee. As such, the compensation for the said period was
given to the petitioner.
22. Reiterating their stand that the petitioner has failed
to make the payment of the installments, as per the
agreement, Annexure P-2, it is the further stand of the
respondents that the question, with regard to the losses, which
have been suffered by the petitioner, has duly been considered
by the Subathu Cantonment Board. The meeting, in this
regard, was convened, but, the petitioner did not turn up even
after lifting of the COVID-19 restrictions.
23. The writ petition has further been contested by the
respondents on the ground that even after lifting the corona
curfew restrictions in the State, the petitioner continued
earning huge commercial gain from the said barrier. It has
not been disputed that the petitioner has not served legal
notice, dated 20th September, 2021, but, the said notice was
duly replied, vide letter, dated 30th September, 2021.
24. Reiterating that the grievances of the petitioner, if
any, fall within the purview of Clauses 24 and 25 of the
.
contract agreement (Annexure P-2), it is the stand of the
respondents that the matter would be placed before the Board
in its general/regular meeting.
25. So far as the prayer of the petitioner, qua referring
the matter to the Arbitrator, is concerned, it has been opposed
on the ground that as per Clauses 22, 24 and 25 of the contract
agreement, the said prayer cannot be accepted.
26. Filing of the case, by the petitioner, before the
learned District Judge, Solan, against the respondents, has
not been disputed. The compensation, as per Clause 25 of the
contract agreement, has already been given to the petitioner.
On the basis of the report submitted by the Committee, the
benefit of ₹ 12,76,301/-, has already been given to the
petitioner. The learned District Judge, Solan, has, thereafter,
dismissed the petition, on 14th December, 2021.
27. The physical possession of the three barriers in
Cantonment Board, Subathu, is stated to have been taken by
the respondents, as per the procedure. The petitioner is
required to deposit the remaining amount with the
respondent, as per the agreement, failing which, the stand has
been taken by the respondents, to initiate the proceedings,
.
under Section 324 of the Cantonment Act, 2006.
28. In compliance to the order passed by the learned
District Judge, Solan, the respondents had constituted the
Committee, to assess the actual losses suffered by the
petitioner, which submitted its report, dated 6 th December,
2021. The petitioner was also member of the said Committee
and signed the report, without any protest.
29. Highly relying upon Clause 30 of the contract
agreement, it is the stand of the respondents that the stand
taken by the petitioner, in the present petition, is not based
upon the actual and factual position.
30. Placing reliance on the report of the Committee,
dated 6th December, 2021, it is the stand of the respondents
that they had already published the e-auction notice on 15 th
December, 2021, for the contract, for the period 1 st January,
2022 to 31st March, 2022, as per Clause 4 of the contract
agreement, dated 1st August, 2021, as the petitioner has failed
to deposit the installments, despite repeated demands made by
the Cantonment Board.
31. On all these submissions, a prayer has been made to
dismiss the writ petition.
.
32. To controvert the stand taken by the respondents,
the petitioner has filed rejoinder, denying the stand, as taken
by the respondents, in the reply.
33. In the rejoinder, the factum of constitution of the
Committee has been denied. The petitioner, in the rejoinder,
has also denied that the alleged Committee, so constituted by
the Board, had assessed the losses suffered by the petitioner
and filed its report, dated 6th December, 2021, in the Court of
the learned District Judge, Solan. Moving a step further, the
petitioner has taken the plea that no such report has been
signed by him.
34. In view of the above factual position, it seems that
the relationship of the parties, in the present writ petition, is
governed by the contract agreement, which has been executed
between the petitioner and the respondents on 1 st August,
2021. The said agreement was for the period from 1 st April,
2021 to 31st March, 2022. The schedule of payment of the
contract fees has duly been mentioned in the contract
agreement (Annexure P-2).
35. Thus, the dispute, which has arisen, in this case, has
to be resolved, as per the provisions of this document.
.
36. As per Clause 24 of the contract agreement, in case
of a natural calamity or on account of corona curfew due to
COVID-19 pandemic, if the Government is promulgating
complete lock-down, as per the provisions of Disaster
Management Rules, 2005, then, the request of the contractor
would be placed before the Board, for consideration.
37. Clause 25 of the contract agreement provides that it
was for the Board to constitute a Committee, which would give
its report, regarding the grievances raised and to compensate
the contractor.
38. In terms of Clause 30 of the contract agreement, if
any dispute arises between the parties, which is within the
purview of this agreement, then, the matter could be referred
to the Arbitrator.
39. Clause 30 of the contract agreement, provides that
beyond this agreement, if there is any dispute/claim/any
question between the parties/any construction, commission or
omission of any kind or any other matter of any kind, which
may arise between the parties in any manner whatsoever,
Arbitrator i.e. an arbitral committee, can be constituted, under
Section 327 of the Cantonment Act, 2006. The decision given
.
by this arbitral committee will be the final decision and both
the parties will be bound to accept the decision.
40. The petitioner, as per Clause 24 of the contract
agreement, has moved the applications, on 6th May, 2021, as
well as 3rd June, 2021, demanding the compensation, on
account of the restrictions/lock-down, imposed by the State
Government, due to the COVID-19 pandemic. Apart from this,
he has moved the representations for extending the payment
schedule of the installments, as per the contract agreement,
Annexure P-2.
41. On 20th September, 2021, vide notice (Annexure P-8),
a request has been made, to respondent No. 2, to call a
meeting, within fifteen days, in pursuance of the letter, dated
9th May, 2021. The relevant portion of the notice, is
reproduced, as under:
"That you are hereby required to settle the matter and call a meeting within 15 days from the receipt of this notice so that the request of my client as requested in the letter dated 09/05/2021 be considered as assured verbally earlier and take a sympathetic view for compensating the loss suffered by my client due to the operation of law and for no fault on his part besides take note of the threats of the officials and I do hereby require not to indulge in any illegal activity of forcible
possession of the toll collection as the same shall be defended at your cost and risks, in case of default on your part in that case the matter be referred to arbitration as per the terms of the agreement and in
.
default this notice be considered as a demand notice
for arbitration proceedings."
42. Although, this notice has been replied by the
respondents on 30th September, 2021, wherein a stand has
been taken, that the issue raised by the petitioner, falls under
Clauses 22, 24 and 25 of the contract agreement, a specific
stand has been taken by the respondents that the matter
cannot be referred to the Arbitrator, in terms of Clause 30 of
the contract agreement, as the dispute, so raised, by the
petitioner, squarely falls within the purview of Clauses 22, 24
and 25 of the contract agreement (Annexure P-2).
43. Bare perusal of Clauses 24 and 25 of the contract
agreement (Annexure P-2), which governs the relationship of
the parties, clearly demonstrates that in case of natural
calamities and the lock-down, on account of COVID-19
pandemic, the application moved by the contractor would be
placed before the Board and the Board can constitute the
Committee, which may compensate the contractor.
44. Clause 30 of the contract agreement does not cover
the situation, which has been mentioned in Clause 24, as the
opening line of Clause 30 provides that 'any dispute out of the
contract can be referred to the arbitration'.
.
45. On the application of the contractor, a Committee
was constituted, consisting of two ex-elected members of
Subathu Cantt., representatives of respondents and the
contractor himself. The committee, so constituted, had
submitted its report on 6 th December, 2021, which was duly
signed by the petitioner himself.
r The relevant portion of the
report, is reproduced, as under:
"PROCEEDINGS OF MEETING HELD ON 06.12.2021 UNDER THE CHAIRMENSHIP OF .
RAVI SHARMA IN CONNECTION WITH ASSESSMENT OF LOSS CAUSED TO VEHICLE
ENTRY FEE CONTRACTOR SH. BALI RAM DUE TO CORONA CURFEW DURING MAY AND JUNE 2021.
The following members attended the meeting.
1. Sh. Ravi Sharma, House No. 92, Subathu Cantt. Ex-Elected Member & presently President, Gugga Mari Comittee, Subathu.
2. Sh. Sunit Gill, House No. 496, Ex-Elected Member, Subathu Cantt.
3. Sh. Jatin Garg rept. Of CA, Cantt. Board, Subathu
4. Sh. Bali Ram vehicle entry fee contractor himself
In continuation of earlier proceedings dated 23.11.2021 and 30.11.2021, the above committee members met today and discussed the matter at length. The contractor Sh. Bali Ram and Sh. Jatin
Garg representative of CA, Cantt. Board, Subathu have argued their sides in respect of settling the issue. The contractor has claimed 90 days rebate for the period of Corona Curfew, but he did not produce any
.
authentic document in support of his claim except an
written application dated 06.12.2021 addressed to CEO, Cantt. Board Subathu. This application was perused and discussed at length. The contractor
failed to prove his claim of compensation for 90 days and other part of his application is not tenable.
xxx xxx xxx
In view of the above documents the committee is of the view that the contractor is entitled to get relief only for 35 days as calculated above during which the vehicle traffic did not ply. Therefore the committee assessed the claim of rebate to the contractor Sh. Bali
Ram, on the basis of total contract of Rs.
1,33,10,000/- which comes to Rs. 12,76,301/- + recovery whichever the contractor has collected from the toll barriers during 35 days."
46. When the petitioner has moved the application,
which was considered by the respondents and constituted the
Committee by associating the petitioner himself, then, it
cannot lie in the mouth of the petitioner that he is entitled to
get the matter referred to the arbitrator, as per Clause 30 of
the contract agreement.
47. At the cost of repetition, the dispute, which has been
raised by way of the applications, claiming compensation, on
account of the losses suffered by him, due to the restrictions
imposed in the wake of COVID-19 pandemic, clearly falls
within Clause 25 of the contract agreement and the petitioner
is unable to make out a case, which falls within the purview of
.
Clause 30 of the contract agreement (Annexure P-2). Hence,
he is not entitled for the relief, as claimed, in the present writ
petition.
48. The petitioner has not only attended the meeting,
dated 6th December, 2021, but he had also attended the earlier
meetings, which were held on 23rd November, 2021, as well as
on 30th November, 2021. This fact has not been disclosed by
the writ petitioner, in his writ petition. Therefore, on this
count also, he is not entitled to claim any relief from this
Court.
49. Having glance of the above discussion, no ground for
interference is made out, in the instant case. Accordingly, the
writ petition is dismissed, so also the pending miscellaneous
applications, if any.
( Tarlok Singh Chauhan ) Judge
( Virender Singh ) Judge December 27, 2022 ( rajni )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!