Citation : 2025 Latest Caselaw 6314 Guj
Judgement Date : 4 September, 2025
NEUTRAL CITATION
C/CA/923/2025 ORDER DATED: 04/09/2025
undefined
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/CIVIL APPLICATION (FOR CONDONATION OF DELAY) NO. 923 of
2025
In
F/FIRST APPEAL NO. 29066 of 2024
With
F/FIRST APPEAL NO. 29066 of 2024
With
CIVIL APPLICATION (FOR STAY) NO. 1 of 2024
In F/FIRST APPEAL NO. 29066 of 2024
==========================================================
UNION OF INDIA THROUGH EXECUTIVE ENGINEER
Versus
M/S. PRIYANKA CONSTRUCTION (BARODA) PVT. LTD.
==========================================================
Appearance:
MR HARSHEEL D SHUKLA(6158) for the Applicant(s) No. 1
MR PARV S GUPTA(11850) for the Respondent(s) No. 1
MR SP MAJMUDAR(3456) for the Respondent(s) No. 1
==========================================================
CORAM:HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE
SUNITA AGARWAL
and
HONOURABLE MR.JUSTICE D.N.RAY
Date : 04/09/2025
ORAL ORDER
(PER : HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE SUNITA AGARWAL)
1. The present appeal under Section 37 of the Arbitration
and Conciliation Act, 1996 (for short "the Act, 1996") has
been filed on behalf of the Union of India through the
Executive Engineer, Central Public Works Department,
Vadodara Central Division, Vadodara, challenging the Arbitral
Award dated 30.03.2015 passed by the learned sole Arbitrator
as also the judgment and order dated 10.05.2024 passed by
NEUTRAL CITATION
C/CA/923/2025 ORDER DATED: 04/09/2025
undefined
the Commercial Court/4th Additional District Judge, Vadodara
in rejecting the application under Section 34 seeking to set
aside the Arbitral Award.
2. The delay of 61 days in filing the present appeal is
sought to be explained in the application seeking condonation
of delay dated 23.09.2024 filed along with the present appeal.
In a vague manner, it was stated in paragraph No. '2' of the
said application that the impugned judgment under Section 34
of the Act, 1996 was passed on 10.05.2024 and the same was
received by the applicant-appellant on 31.07.2024. Upon
receiving the copy of the said order, the same was analyzed at
appropriate organisational hierarchies and after detailed
examination of the impugned order and other relevant
documents, the decision was taken to file an appeal invoking
Section 37 of the Act, 1996. The matter was then placed
before the Additional Solicitor General of India on 06.08.2024
and, thereafter, the appeal was prepared and verification was
done on 23.09.2024. The submission, thus, is that the delay of
61 days is a procedural delay and was unintentional and
purely administrative in nature.
NEUTRAL CITATION
C/CA/923/2025 ORDER DATED: 04/09/2025
undefined
3. Having considered these submissions made in the
application seeking condonation of delay, by the order dated
22.07.2025 noticing that no sufficient cause has been shown
in the application seeking condonation of delay, two weeks
time was granted to the learned advocate appearing for the
appellant to file a better affidavit. The additional affidavit
dated 08.08.2025 was then filed giving a date chart as to the
manner in which the preparation of the appeal had proceeded
from the date of passing of the impugned order under Section
34 proceedings.
4. From a perusal of the date and event chart extracted in
the affidavit dated 08.08.2025, pertinent is to note that after
the order dated 10.05.2024 was passed in the Commercial
Civil Misc. Application No.74 of 2022, under Section 34 of the
Act, 1996, a letter No. 964-H dated 26.06.2024 stated to have
been written to the learned advocate requesting for the
certified copy of the judgment and his opinion. The further
assertions are about the communications between the
Department and the learned advocate, as also some inter-
departmental communications etc., but none of the aforesaid
communications/letters have been brought on record with the
NEUTRAL CITATION
C/CA/923/2025 ORDER DATED: 04/09/2025
undefined
said affidavit.
5. Noticing the above, by another order dated 12.08.2025,
we have granted time to the learned advocate to file a further
better affidavit giving explanation of day to day delay in the
presentation of the present appeal. The third affidavit dated
19.08.2025 has been filed as additional affidavit to the
application seeking condonation of delay wherein various
communications have been brought on record.
6. Pertinent is to note the assertions in paragraph No. '2'
of the third affidavit, wherein it is stated that the impugned
order was passed on 10.05.2024 in Commerical Civil Misc.
Application No. 74 of 2022 by the Commercial Court,
Vadodara and the said date was the last working day before
the summer vacation of this Court. The submission is that the
period from 10.05.2024 to 09.06.2024 was of Court vacations
and, therefore, the applicant could not procure the copy of the
impugned order. The order was, thereafter, obtained and
the applicant then wrote the letter no. 964-H dated
26.06.2024, a copy of which is appended at page No. '80' of
the paper-book.
NEUTRAL CITATION
C/CA/923/2025 ORDER DATED: 04/09/2025
undefined
7. From the abovenoted averments made in the third
additional affidavit, pertinent is to note that there is
complete silence as to when the applicant came to know about
the order passed on 10.04.2024 by the Commercial Court. The
letter dated 26.06.2024 brought on record, was adressed to
the learned advocate seeking his opinion/comment on the
Court Judgment. The averments of the said letter do not
indicate as to when the appellant got knowledge of the
passing of the impugned judgment by the Commercial Court.
Even the date when the certified copy of the judgment was
applied for has not been indicated therein. However, from the
certified copy of the judgment and order dated 10.05.2024,
available on the record, we could notice that the certified copy
of the judgment of the Commerial Court was applied by the
appellant through the learned advocate on 01.07.2024. The
copy was prepared and delivered on 30.07.2024.
8. It is, thus, evident that even as per the assertions
made in Paragraph No.'2' of the additional affidavit dated
19.08.2025, the certified copy was applied after a period of
one month of the date, i.e. 09.06.2024, when allegedly the
NEUTRAL CITATION
C/CA/923/2025 ORDER DATED: 04/09/2025
undefined
Court vacations was over. Thus, as per the averments in
three affidavits, the period of approximately 22 days
remained explained. Moreover, we may note that there is no
Court vacations in the Civil Court from 10.05.2024 to
09.06.2024 and the period of vacation as stated in Paragraph
No.'2' of the additional affidavit could be said to be about the
Court vacations of the High Court of Gujarat. In any case, the
vacations do not completely shut down the working of the
office/Registry, even in the High Court.
9. As there is no Court vacation in the District Court,
the explanation offered in third affidavit about the delay in
applying the certified copy of the order, for the period of
approximately two months from 10.05.2024 to 01.07.2024,
remained unexplained.
10. Further, after getting the certified copy on
30.07.2024, pertinent is to note that the letter seeking legal
opinion from the Additional Solicitor General was received on
06.08.2024 and, thereafter, process for approval for filing the
appeal has been initiated which has taken further time and
appeal was presented only on 07.10.2024.
NEUTRAL CITATION
C/CA/923/2025 ORDER DATED: 04/09/2025
undefined
11. From the abovenoted facts, it is more than evident
that the deponent of the affidavits namely the Executive
Engineer, CPWD, Vadodara has not given correct and
complete facts for explanation of the delay of 61 days in
presentation of the present appeal. The statements made in
three affidavits filed on behalf of the appellant as noted
hereinabove are misleading in nature. The delay of 61 days in
filing the present appeal, therefore, has not been explained to
the satisfaction of the Court and hence cannot be condoned.
The delay condonation application is accordingly, rejected.
Resultantly, the appeal stands dismissed. Consequently, all
the connected Civil Application stand disposed of. No order as
to costs.
(SUNITA AGARWAL, CJ )
(D.N.RAY,J) BINA SHAH
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!