Citation : 2025 Latest Caselaw 1506 Guj
Judgement Date : 30 July, 2025
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/FIRST APPEAL NO. 2975 of 2004
FOR APPROVAL AND SIGNATURE:
HONOURABLE MR. JUSTICE HEMANT M. PRACHCHHAK
================================================================
Approved for Reporting Yes No
================================================================
STATE OF GUJARAT & ANR.
Versus
SOLANKI CONSTRUCTION THRO' SOLANKI BHALJIBHAI AMARSINH-
================================================================
Appearance:
MS ROSHNI PATEL, ASST. GOVERNMENT PLEADER for the Appellant(s)
No. 1,2
MR PARAS SUKHWANI FOR MR KG SUKHWANI(871) for the Defendant(s)
No. 1
================================================================
CORAM:HONOURABLE MR. JUSTICE HEMANT M.
PRACHCHHAK
Date : 30/07/2025
ORAL JUDGMENT
1. The present First Appeal is filed under Section 96 of the Civil Procedure Code, 1908 at the instance of the appellant - State being aggrieved and dissatisfied with the judgment and decree dated 28.11.2003 passed by the learned Joint Civil Judge (S.D.), Dhrangadhra (herein after referred to as "the trial court") in Special Civil Suit No. 5 of 1992, whereby, the learned Judge partly allowed the suit filed by the respondent herein and directed the appellant to pay decreetal amount of Rs.6,12,500/- with interest @ 6% per annum from the date of the suit till realization.
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
2. Brief facts leading to the present appeal are as under :-
2.1 The respondent filed a suit for the recovery of Rs.13,50,038/- as follows:
Claim No. Amount Description
1. Rs. 500/- On account of time limit deposit
2. Rs. 12000/- On account of the excess approval
pending
3. Rs. 5300/- On account of the 53 loads washout
of sands
4. Rs. 30000/- Idle establishments charges
5. Rs. 1032238/- On account of price escalation
2.2 It is the case of the appellant that, the respondent
entered into contract of work of strengthening Viramgam -
Dhrangadhra - Malvan Road Sect. Dhrangadhra Malvan by providing 37.5 MM Lean Caccamam between K.M. 44/0 to 66/8 Km. Hot Mix Plant and Pava Finisheer. That, the estimated cost of the work was Rs.45,02,612.66 paise and respondent's tender amounted to Rs.60,10,496.89 paise, 33.49% above the estimated cost. That, the work order was issued to the respondent on 27.3.1990 and the work was required to be completed as stipulated within time limit prescribed i.e. on or before 28.11.1990.
2.3 It is the case of the appellant that, since the respondent could not complete the said work within time limit, he applied for extension of limit. As a matter of fact that the respondent had started his work on 25.05.1990 only because it was obligatory to start work within 60 days from the work order. Thereafter, as per government notification, no asphalt work to
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
continue during monsoon season i.e. from 15 th June to 15th October, he was directed to stop the work. That, taking under advantage of this direction and blaming the department for not completing the road side surface racing, he demanded the extension. Even then, authorities had considered and allowed extension, so that the respondent could complete the work order. However, the respondent did not complete the work even within the extended time limit. That, there was no condition for price escalation yet the respondent claimed huge amount on account of price escalation. Without considering the evidence on record in proper perspective the learned Civil Judge allowed the suit as aforesaid vide judgment and decree dated 28.11.2003.
3. Being aggrieved and dissatisfied with the impugned judgment and award dated 28.11.2003 passed by the learned Joint Civil Judge (S.D.), Dhrangadhra in Special Civil Suit No. 5 of 1992, the appellant - State has preferred this appeal.
4. Heard learned Assistant Government Pleader Ms. Roshni Patel, appearing for the appellant - State and learned advocate Mr. Paras Sukhwani, appearing for the respondent - Company.
5. Learned AGP Ms. Patel has submitted that the impugned judgment and award passed by the trial court is contrary to the provisions of law, facts and evidence available on record of the case. She has submitted that so far as the amount of deposit is concerned, they have no objection to pay back the amount of deposit. She has further submitted that they had tried their
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
level best and worked with full care and caution and no breach on their part or any negligence on their part was committed. She has submitted that the respondent was granted extension and the proposal for Diesel, Cement, Petrol were also sent to the concerned department time to time as per the working condition of the respondent, however, the respondent himself has abandoned the work and did not fulfill as contractual obligation. She has further submitted that the appellant had never stopped the respondent from performing contract, however, the trial court has erred in holding that the appellant was responsible for the delay occurred. She has submitted that the trail court has erred in granting idle establishment and price escalation, which were not part of the contract between the parties and therefore, the award of this amount is without jurisdiction and contrary to the terms of contract. She has submitted that the impugned judgment and order passed by the trial court suffers from the patent illegality inasmuch as it granted price escalation without assigning any reason.
5.1 Learned AGP Ms. Patel has submitted that the respondent has not completed the work within the time limit stipulated in the contract and thus, the respondent has committed breach of terms of contract and therefore, he is not entitled to seek any damages as claimed in the suit. She has further submitted that the delay was at the instance of the respondent and therefore, he is not entitled to seek any escalation in price, however, the trial court has awarded Rs.5 Lac towards escalation of price which is on very higher side. She has submitted that the trial court has also awarded Rs. 1 Lac
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
towards idle establishment, Rs.500/- towards time limit deposit and Rs.12,000/- towards excess approval pending, which is also on very higher side without there being any cogent and material evidence led by the respondent, which is erroneous, illegal and unjust thus, the trial court has committed a serious error while allowing the suit of the respondent. In support of her submissions, learned AGP Ms. Patel has referred and relied upon the decision of the Hon'ble Ape Court rendered in case of NTPC Ltd. vs. M/s. Deconar Services Pvt. Ltd., reported in [2021] SCC OnLine 498, more particularly, paragraphs 17, 18 and 20 and urged that the present appeal be allowed and the impugned judgment and award passed by the trial court be quashed and set aside.
6. Per contra, learned advocate Mr. Paras Sukhwani, appearing for the respondent Company, has submitted that the trial court has passed the impugned judgment and award after considering all the relevant aspects that the work could not be commenced due to the delay on the part of the appellant in handing over the site in time and the appellant had not provided material within stipulated time and therefore, the time was extended by the appellant without there being any condition stipulated at the time of extension of time and therefore, now they cannot take shelter on the ground of delay. He has submitted that the on the contrary, the respondent had claimed Rs.10,32,238/- towards price escalation, however, the trial court has awarded only Rs. 5 Lac and thus the trial court has not committed any error while passing the impugned judgment and award. Referring to
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
paragraphs 11, 12 and 13 of the impugned judgment and award, learned advocate Mr. Sukhwani has submitted that the trial court has considered the facts and the documents produced on record including the documents at Exh.-78, 79 and 80 and the document at Exh.-117, which clearly shows that time was extended by the appellant from 27.11.1990 to 06.06.1991, wherein there was no condition stipulated. He has further submitted that after appreciating the documentary evidence at Exh.-79 and 80 while discussing the claim of the respondent in paragraphs 15 to 19, the trial court has rightly passed the impugned judgment and award in favour of the respondent and therefore, the no interference is required to be called for in the present appeal and the present appeal be dismissed.
6.1 In support of his submissions, learned advocate Mr. Sukhwani has referred and relied upon the decisions of the Hon'ble Apex Court as follows :
[I] Hyderabad Municipal Corporation vs. M. Krishnaswami Mudaliar and another, reported in AIR 1985 SC 607, paragraph 2, which reads as under :
"2. Under Ex. A-1 drainage work for CSIR Laboratory at Uppal was entrusted to the respondent-plaintiff and under the terms of the contract the work was to be completed by the plaintiff within a period of one year, i.e., from 26th March 1951 to 25th March 1952. Admittedly at the instance of the Executive Engineer, P.W.D. due to financial difficulties-less budget having been provided for in the year 1951-52 the plaintiff was requested to spread over the work for two years more, that is to say to complete the same in three years but the respondent-plaintiff was agreeable to spread over the
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
work for two years more as suggested on condition that extra payment will have to be made to him in view of increased rates of either material or wages. The Government did not intimate to the respondent-plaintiff that no extra payment on account of increased rates would be paid to him or that he will have to complete the work on the basis of original rates. In fact no reply was sent by the Government and a studied silence was maintained by the Government in regard to the respondent-plaintiff's demand for extra payment, in spite of several reminders in that behalf, till the plaintiff actually completed the work during the spread over period and only when after completion of work the plaintiff-respondent submitted his final bill claiming 20 per cent extra over and above the rates originally agreed upon between the parties the Government stated that he was not entitled to increased rates. After considering the correspondence exchanged between the parties and the other material on record the High Court has taken the view that the Government was liable to make extra payment for the work done as there was no dispute that the rates of material, etc. had increased during the extended period of two years and plaintiff was entitled to such extra payment. After considering the relevant material on record we are of the view that both in equity and in law the plaintiff contractor is entitled to receive extra payment and the High Court was right in deciding the question in respondent-plaintiff's favour. Since subsequent to the entering into the agreement Ex. A-1 the Drainage Division was transferred from P.W.D. to Hyderabad Municipal Corporation the liability to make this extra payment in our view has been properly saddled on the appellant Corporation."
[II] P.M. Paul, Appellant vs. Union of India, reported in AIR 1989 SC 1034, paragraph 12, which reads as under :
"12. In the instant case, it is asserted that the extension of time was granted and the arbitrator has granted 20% of the escalation cost. Escalation is a normal incident arising out of gap of time in this inflationary age in performing any contract. The arbitrator has held that there was delay, and he has further referred to this aspect in his award. The arbitrator has noted that Claim I related to the losses caused due to increase in prices of materials and cost of labour and transport during the extended period of contract from 9.5. 1980 for the work under phase I, and from 9.11.80 for the work under phase II. The total amount shown was Rs.5,47,618.50. After discussing the evidence and the sub- missions the arbitrator found that it was evident that there was escalation and, therefore, he came to the conclusion that it was reasonable to allow 20% of the compensation under Claim I, he has accordingly allowed the same. This was a
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
matter which was within the jurisdiction of the arbitrator and, hence, the arbitrator had not misconducted himself in awarding the amount as he has done."
[III] Food Corporation of India vs. M/s. A.M. Ahmed and Co. and Anr., reported in AIR 2007 SC 829, Head Note-B, which reads as under :
"Head Note-B : Arbitration Act (10 of 1940), S.30 - Award - Setting aside of - Misconduct - Contract with Food Corporation of India - Escalation of costs due to statutory wage revision - Arbitrator has jurisdiction to go into said question - By awarding wage revision costs, arbitrator cannot be said to have misconducted himself - No error apparent on record - Award held, valid."
[IV] M/s. Associated Construction vs. Pawanhans Helicopters Pvt. Ltd., reported in AIR 2008 SC 2911, Head Note-A, which reads as under :
"Head Note-A : Arbitration Act (10 of 1940), (since repealed) S.30, S.33 - Powers of Court - Award of contract - Delay in completion by contractor attributed to respondents - Time was essence of contract
- Terms of contract providing no escalation during pendency of contract - However, such embargo would not be carried beyond period of completion of contract - Award of arbitrator awarding price escalation to contractor - Not so unconscionable that it required interference - Moreso, as Court does not sit as one in appeal over award of the arbitrator."
[V] NTPC Ltd. vs. M/s. Deconar Services Pvt. Ltd., reported in AIR OnLine 2021 SC 251, paragraphs 18 to 20 and 25, which reads as under :
"18. The second issue pertains to the grant of escalation charges for work done by the respondent beyond the scheduled period of the contract. It is significant to note herein that the Arbitrator only allowed a part of the claim made by the respondent under this head. In Civil Appeal No. 6483 of 2014, the Arbitrator awarded a sum of Rs. 17,86,212/ against a claim of Rs. 66,98,773/, while in Civil Appeal No. 6484 of 2014, the Arbitrator awarded a sum of Rs. 3,03,419/ as against a claim of Rs. 42,20,261/. The Arbitrator took a view on the construction of the clauses of the contract that the firm price clause operated only with respect to the period for which the
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
contract subsisted, and would not subsist beyond the scheduled period of the contract. The Arbitrator also noted that the appellant accepted the work undertaken by the respondent beyond the period of the contract without objections. The Arbitrator also carefully assessed the period of delay attributable to the appellant and awarded escalation to the respondent only for the same.
19. With respect to the question of law as to whether the Arbitrator could order such an escalation, this Court has, in a catena of judgments, upheld the same. A threeJudge Bench of 11 this Court in Assam State Electricity Board v. Buildworth Private Limited, (2017) 8 SCC 146, was faced with almost identical circumstances. In that case, the Arbitrator granted escalation charges beyond what was permissible under the contract between the parties, which prescribed a cap on the same. Upholding such an award, the Court in that case held as follows:
"13. The arbitrator has taken the view that the provision for price escalation would not bind the claimant beyond the scheduled date of completion. This view of the arbitrator is based on a construction of the provisions of the contract, the correspondence between the parties and the conduct of the Board in allowing the completion of the contract even beyond the formal extended date of 691983 up to 3111986. Matters relating to the construction of a contract lie within the province of the Arbitral Tribunal. Moreover, in the present case, the view which has been adopted by the arbitrator is based on evidentiary material which was relevant to the decision. There is no error apparent on the face of the record which could have warranted the interference of the court within the parameters available under the Arbitration Act, 1940. The arbitrator has neither misconducted himself in the proceedings nor is the award otherwise invalid."
(emphasis supplied)
20. We are of the opinion that the above holding of this Court is directly applicable to the present case. The Arbitrator in the present case has constructed the present contract, and the fixed price clause, in the same manner. This construction was on the basis of the evidence on record and the submissions of the counsel before him. The Arbitrator has carefully delineated the period of delay attributable to the appellant, and has granted the claim of the respondent only to that limited extent.
25. It is clear from the above analysis that any decision regarding the issue of whether an arbitrator can award a particular claim or not, will revolve on the construction of the contract in that case, the evidence placed before the arbitrator and other facts and circumstances of the case. No general principle can be evolved as to whether some claim can be granted or not. The judgments placed on record by the appellant, wherein claim for escalation was
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
denied, have to therefore be read in the context of their facts, and cannot be read in isolation. It is clear that all the judgments cited by the appellant can be distinguished on facts."
7. I have heard the learned advocates appearing for the respective parties and perused the material placed on record. I have also perused the impugned judgment and award passed by the trial court, the issues framed by the trail court at Exh.- 18 referred in para-4 and answered in para-5. On perusal of the Record & Proceedings and on examining and verifying the documentary as well as oral evidence led before the trial court, it appears that the trial court after considering the facts while deciding the issue Nos.1 and 2 has given elaborate details and recorded the reasons in the said paragraph and huts, I do not find any infirmity in the impugned judgment and award passed by the trial court. The trial court while allowing the claim of the respondent on the contrary has awarded Rs.5 Lac towards price escalation and has not awarded total amount as prayed for by the respondent in the suit which is just and adequate amount towards price escalation for the period of seven months and hence I am of the opinion that the trial court has not committed any error and there is no any infirmity or any illegality committed by the trial court in passing the impugned judgment and award. On perusal of the aforesaid decisions cited by the learned advocate Mr. Sukhwani and the ratio laid down by the Hon'ble Apex Court in the said decisions, I am of the opinion that the present appeal is required to be dismissed and no interference is required to be called for in the impugned judgment and award passed by the trial court.
NEUTRAL CITATION
C/FA/2975/2004 JUDGMENT DATED: 30/07/2025
undefined
8. In the result, the present appeal being devoid of any merits, deserves to be dismissed and accordingly, it is dismissed. The judgment and decree passed by the trial court is hereby upheld. No order as to costs.
9. At this juncture, learned AGP Ms. Patel has produced on record communication addressed by the Executive Engineer, Surendranagar and submitted that 50% of the decreetal amount alongwith interest @ 6% p.a. has been deposited by the appellant before the trial court concerned.
10. In view of above, the appellant is hereby directed to deposit remaining 50% of the decreetal amount alongwith interest before the trial court concerned, within a period of eight (8) weeks from the date of receipt of copy of this order. Once the amount is deposited by the appellant, the same shall be disbursed in favour of the respondent, after proper verification and after following due procedure, through RTGS/NEFT. Decree be drawn accordingly. Record and proceedings, if any, be sent back to the concerned Court forthwith.
(HEMANT M. PRACHCHHAK,J)
Dolly
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!