Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Oil & Natural Gas Corporation Ltd vs David Parkar Construction Ltd C/O I B ...
2024 Latest Caselaw 4622 Guj

Citation : 2024 Latest Caselaw 4622 Guj
Judgement Date : 12 June, 2024

Gujarat High Court

Oil & Natural Gas Corporation Ltd vs David Parkar Construction Ltd C/O I B ... on 12 June, 2024

Author: Sunita Agarwal

Bench: Sunita Agarwal

                                                                                     NEUTRAL CITATION




     C/FA/322/2010                               CAV JUDGMENT DATED: 12/06/2024

                                                                                     undefined




              IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

                     R/FIRST APPEAL NO. 322 of 2010

FOR APPROVAL AND SIGNATURE:
HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE SUNITA AGARWAL                      Sd/-
and
HONOURABLE MR. JUSTICE ANIRUDDHA P. MAYEE                                     Sd/-
==========================================================
1      Whether Reporters of Local Papers may be allowed                  NO
       to see the judgment ?

2      To be referred to the Reporter or not ?                           NO

3      Whether their Lordships wish to see the fair copy                 NO
       of the judgment ?

4      Whether this case involves a substantial question                 NO
       of law as to the interpretation of the Constitution
       of India or any order made thereunder ?

==========================================================
               OIL & NATURAL GAS CORPORATION LTD
                              Versus
    DAVID PARKAR CONSTRUCTION LTD C/O I B PATEL (P A HOLDER) &
                              ANR.
==========================================================
Appearance:
MR AJAY R MEHTA(453) for the Appellant(s) No. 1
MR PR THAKKAR(899) for the Defendant(s) No. 1
MR.J P THAKKAR(7116) for the Defendant(s) No. 1
==========================================================
    CORAM:HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE
          SUNITA AGARWAL
          and
          HONOURABLE MR. JUSTICE ANIRUDDHA P. MAYEE

                             Date : 12/06/2024

                       CAV JUDGMENT

(PER : HONOURABLE MR. JUSTICE ANIRUDDHA P. MAYEE)

1. The present First Appeal under Section 37 of the

Arbitration and Conciliation Act, 1996 ('the Arbitration Act' for

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

sake brevity) impugns the judgment and order dated 31.3.2009

passed by the learned 7th Additional District Judge, Vadodara in

Arbitration Misc. Application No.160 of 2002, whereby the

learned Additional District Judge has allowed the application

under Section 34 of the Arbitration Act and set aside the award

dated 3.6.2002.

2. The relevant facts in the present case are that the

appellant herein had invited tenders through its Superintending

Engineer (Civil) for the work of construction of Multi-storied "D-

Type" (20 residential units) for ONGC Township at Vadodara.

The bid of the respondent contractor / claimant came to be

accepted. Thereafter, an agreement came to be executed

between the parties. As per the agreement, tender work was to

commence from 31.3.1985 and was to be completed on or

before 30.6.1986, and accordingly, work order dated 16.3.1985

came to be issued. That various disputes arose with respect to

execution of the work between the parties. The respondent

contractor filed Special Civil Suit No.110 of 1988 raising various

claims. The appellant herein opposed the said suit and also filed

an application stating that there was an arbitration agreement

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

between the parties and the dispute, if any, had to be resolved

through the arbitration mechanism. The said application came

to be rejected by the learned Trial Court, which came to be

confirmed by the High Court. Aggrieved, Special Leave Petition

came to be filed before the Apex Court. With the consent of the

parties, the Apex Court by its order dated 23.3.1999 in Civil

Appeal No.5015 of 1989 referred the dispute to the Sole

Arbitrator.

3. Pursuant to the reference, the respondent contractor /

claimant filed its Statement of Claim. The appellant herein filed

its reply as well as counter-claim against the respondent

contractor. The parties completed the pleadings, placed the

relevant documents on record and led the evidence in support of

their case. After hearing the arguments, the learned Arbitrator

by award dated 3.6.2002 was pleased to allow the two claims of

the respondent contractor and rejected the rest of the claims.

The learned Arbitrator also allowed the counter-claim of the

appellant with respect to the liquidated damages and ordered

the refund of the amount paid to the respondent contractor on

the ground of escalation. Further, the learned Arbitrator has

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

also awarded interest @ 12% per annum to the parties on the

amount awarded.

4. Aggrieved, the respondent contractor/ claimant preferred

Arbitration Misc. Application No.160 of 2002 in the District

Court at Vadodara. By the judgment and order dated 31.3.2009,

learned 7th Additional District Judge, Vadodara allowed the said

application under Section 34 of the Arbitration Act and set aside

the impugned award. Hence, this appeal.

5. Learned counsel Mr. Ajay R. Mehta, appearing for the

appellant herein has submitted that the learned District Judge

has gravely erred in setting aside the award on completely

untenable grounds which are in contravention to the provisions

of Section 34 of the Arbitration Act. He submits that the learned

District Judge has set aside the well-reasoned award on

extraneous grounds which are not recognized in law. He

submits that in respect of claim No.1 of the respondent

contractor, the learned Arbitrator has specifically recorded that

the advocate for the respondent contractor/ claimant had

argued few star items in claim No.1, but thereafter, it was

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

agreed between the parties that in respect of claim No.1, the

parties shall file their written submissions and on the basis of

the same, the learned Arbitrator would decide the claim No.1.

He submits that this action is not contrary to any public policy

or perverse in law and, therefore, the learned District Judge

ought not to have interfered with the said claim. He submits

that claim No.1 was decided by the Arbitrator on the basis of

the written submissions and was based on the cogent reasons.

Mr. Mehta further submits that the learned Arbitrator had

considered each claim as raised by the respondent claimant and

the same was decided on the basis of the entries made in the

measurement book maintained by the appellant and duly

countersigned on behalf of the respondent claimant. He submits

that the respondent contractor had not objected to any of the

measurements which have been duly countersigned by him and

the same were also paid in the running account bills. He

submits that the learned District Judge did not consider all

these aspects whereby the learned Arbitrator had rejected the

claims of the respondent claimant. He submits that the learned

District Judge has erred in holding that the learned Arbitrator

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

did not appreciate the difference between the items of the work

done and extra work which was done, as alleged by the

respondent claimant. The learned counsel submits that once the

measurements had become final after the same were

countersigned by the respondent, the learned Arbitrator and the

learned District Judge could not go beyond the said

measurements which was as per the contractual terms. The

learned counsel submits that the arbitral award was passed on

the basis of the readings in the measurement book which was

duly maintained by the appellant and countersigned by the

respondent contractor. He further submits that the learned

District Judge did not consider the fact that the respondent

claimant could not substantiate its claim for escalation of the

prices and no evidence was produced on record in respect of the

same. Accordingly, the learned Arbitrator has rightly rejected

such claim of the respondent claimant. He further submits that

the learned District Judge has also erred in coming to the

conclusion that the counter claim of the appellant was barred by

limitation in view of the direction of the Hon'ble Supreme Court,

which had referred the dispute to the Arbitral Tribunal for

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

adjudication with consent of the parties. He submits that the

counter claim was allowed by the learned Arbitrator in favour of

the appellant on two aspects, being liquidated damages as well

as over-payment in respect of the escalation as the same was

contrary to clause 10(c) of the contract. He submits that in the

present case, the learned District Judge has sat in appeal over

the findings recorded by the learned Arbitrator and thereby

passed the award in contravention to the provisions of Section

34 of the Arbitration Act. He submits that the learned District

Judge could not have re-appreciated the evidence on record and

sat in appeal to decide the application under Section 34 of the

Arbitration Act. He, therefore, submits that the present First

Appeal be allowed and the impugned judgment and order

passed by the learned 7th Additional District Judge, Vadodara be

quashed and set aside.

6. None appeared on behalf of the respondent at the time of

hearing.

7. We have heard the learned counsel for the appellant and

carefully perused the documents on record. In the present case,

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

it can be seen that the respondent claimant had raised a defense

of limitation, which was validly rejected by the learned

Arbitrator, that there was a bonafide litigation pending in the

Civil Court in the nature of civil suit by the respondent claimant

and, therefore, the claims, as raised, were within time. It is

further seen that the learned Arbitrator has taken note of the

relevant clauses of the contract, in particular, clauses 7 and 8

thereof, which provide for a mechanism to get measurement of

the work done and after signing of the same by both the parties,

the respondent claimant is required to furnish bills for payment.

The learned Arbitrator has also taken note of the fact that as per

the contract, if there was any dispute with respect to any item,

he must raise a dispute within a week from the date when such

measurement becomes final and binding on the contractor. As

per the contract, it was the Engineer of the appellant company

who prepared the bill after finality of the measurements in the

measurement book. The learned Arbitrator has also recorded

that the respondent claimant has not submitted a single monthly

running bill in accordance with the contract. Further, the

representative of the contractor was present at the time of

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

taking of the measurement. The company engineers had

followed the procedure as required by the contract when the

measurements are taken and thereafter, they have prepared the

monthly bills. The representative / Director of the respondent

claimant has signed the measurement books as to its

correctness and received payment of the monthly bills as

calculated on the basis of the measurement books. The learned

Arbitrator records that this procedure as per the contract is

followed till 27th running bill came to be prepared and paid in

accordance with the measurement books. That, thereafter, the

respondent claimant has submitted 28th bill on the ground of

alleged escalation, which also came to be paid by the appellant

company herein. That, thereafter, the respondent claimant has

come out with a final bill for the entire period of contract

running into 2 ½ years for the items by calling them extra work

and thereby giving a go-bye to the terms of the agreement and

the procedure envisaged under the contract. The learned

Arbitrator has also observed that this final bill was not based on

the measurement done as per the measurement book under the

contract and which was signed by the partners of the

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

respondent claimant and duly paid up by the company. The

learned Arbitrator while considering this claim of the

respondent claimant had called upon it to produce its books of

accounts regarding material, vouchers for the period of

contract, wage book, wage slips and relevant documentary

evidence to show that he had paid higher charges and to

substantiate its claim for escalation. It is specifically recorded in

the award that the respondent claimant did not produce any

material towards the proof for this claim of escalation. The

learned Arbitrator has accordingly observed that in view of the

measurements recorded for the work done, which has been duly

countersigned by the respondent claimant and which had

become final upto and including 28th bill, which was also paid up

by the appellant company in terms of clauses 7 and 8 of the

contract, the said issue had become final between the parties in

terms of the contract. Further, it is observed by the learned

Arbitrator that once an issue becomes final in terms of the

contract between the parties, the Arbitrator loses its jurisdiction

to go into such dispute, more so when no objection is raised by

the respondent contractor/ claimant as per the terms of the

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

contract executed between the parties within the stipulated

time of one week. We do not find any fault either in law or in the

facts and circumstances of the case as per the terms of the

contract that the learned Arbitrator has erred on this count. The

learned Arbitrator has rightly rejected such claim of the

respondent claimant.

8. Further, since the escalation was claimed on various

items, it was the advocate and the Power of Attorney for the

respondent claimant who had suggested that the claim No.1 be

decided on the basis of the submissions which came to be

agreed to by the appellant company and accordingly, by

consent, such a procedure was adopted to decide the claim No.1

of the respondent claimant. Such a procedure cannot be said to

be unknown to law or contrary to the public policy. Further, the

learned Arbitrator has given cogent reasons based on the

evidence before him while deciding such claim.

9. With respect to claim No.2, the learned Arbitrator has

specifically held that the claim of Rs.99,464.39 is de hors any

evidence. It is specifically recorded that the respondent

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

claimant did not produce any evidence to show that it had paid

higher prices than those prevailing on the date when the

contract was signed. Further, it is also specifically observed that

the claim in respect of escalation also fails since the condition

as prescribed by clause 10(c) of the contract has not been

complied with by the respondent claimant. Thus, we find no

infirmity in respect of the rejection of this claim by the learned

Arbitrator.

10. It is further seen that the counter-claim as made by the

appellant company herein has also been cogently dealt with by

giving proper reasons by the learned Arbitrator. The learned

Arbitrator has decided the disputes between the parties within

the parameters of the contract/ agreement executed by them

and on the basis of the evidence which is produced on record by

both the parties. We do not find any error in the award as

passed by the learned Arbitrator.

11. Coming to the impugned judgment and order, we find that

the learned District Judge has decided the application under

Section 34 of the Arbitration Act as an Appellate Court ignoring

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

the provisions of Section 34 of the Arbitration Act. The findings

as recorded by the learned District Judge are based on re-

appreciation of evidence, which is not permissible. We find that

the learned District Judge has re-appreciated all the claims,

counter-claims, documents and the evidence on record while

allowing the application under Section 34 of the Arbitration Act.

12. It is now well settled that the standard of scrutiny of

award can be done only on the grounds envisaged under Section

34 of the Arbitration Act. Judicial review and re-appreciation of

evidence are impermissible unless it is made out that the view

taken by the Arbitrator is based on patent illegality or on the

interpretation of the facts and terms of the contract, which are

absolutely perverse. The Court does not sit in appeal over the

arbitral award and can only interfere on merits on the limited

ground as provided under Section 34(2)(b)(ii), if the award is

against the public policy of India, and the award should be in

compliance with the Statutes and judicial precedents while

adopting a judicial approach and in compliance of the principles

of natural justice. Further, it is well settled by the decisions of

the Hon'ble Apex Court that patent illegality would constitute

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

contravention of the substantive law of India, contravention of

the Arbitration and Conciliation Act, 1996 and contravention of

the terms of the contract. But, the interference by Courts in an

arbitral award will not entail review on the merits of the dispute

and has to be limited only to situations where it is found that the

findings of the Arbitrator are arbitrary, perverse, shocking the

conscience of the Court and where the illegality goes to the root

of the matter. In the present case, we find that the view taken

by the learned Arbitrator was a plausible view and in terms of

the contract entered into between the parties. It is well-settled

that the awards which contain reasons, when interpreting the

contractual terms, are not to be interfered with lightly. Re-

appreciation of evidence is not permissible. The learned

Arbitrator has construed the terms of the contract in the correct

perspective and hence, it was not open for the learned District

Judge to interfere with the award.

13. Further, we find that no manifest illegality has been shown

in the award before the learned District Judge nor any finding to

that effect has been recorded by the learned District Judge.

Further, there are apparent contradictions. In overall view of

NEUTRAL CITATION

C/FA/322/2010 CAV JUDGMENT DATED: 12/06/2024

undefined

the matter, we find that the jurisdiction exercised by the learned

District Judge under Section 34 of the Arbitration Act is

contrary to the provisions contained therein, bad in law and

hence, cannot be sustained.

14. In view of the aforesaid observations, the present First

Appeal is ALLOWED. The impugned judgment and order dated

31.3.2009 passed by the learned 7th Additional District Judge,

Vadodara in Arbitration Misc. Application No.160 of 2002 is

accordingly quashed and set aside. The award dated 3.6.2002

passed by the learned Arbitrator is upheld and restored. No

order as to costs.

Sd/-

(SUNITA AGARWAL, CJ )

Sd/-

(ANIRUDDHA P. MAYEE, J.) OMKAR

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter