Citation : 2023 Latest Caselaw 2521 Guj
Judgement Date : 27 March, 2023
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/FIRST APPEAL NO. 1804 of 2016
FOR APPROVAL AND SIGNATURE:
HONOURABLE MR. JUSTICE N.V.ANJARIA
and
HONOURABLE MR. JUSTICE SANDEEP N. BHATT
==========================================================
1 Whether Reporters of Local Papers may be allowed to see the Yes judgment ?
2 To be referred to the Reporter or not ? Yes
3 Whether their Lordships wish to see the fair copy of the No judgment ?
4 Whether this case involves a substantial question of law as to No the interpretation of the Constitution of India or any order made thereunder ?
========================================================== OIL & NATURAL GAS CORPORATION (INDIA) LTD.
Versus M/S. ENVIRO ENGINEERS ========================================================== Appearance:
MR JEET B KARIA(11991) for the Defendant(s) No. 1 ========================================================== CORAM:HONOURABLE MR. JUSTICE N.V.ANJARIA and HONOURABLE MR. JUSTICE SANDEEP N. BHATT
Date :27/03/2023
CAV JUDGMENT
(PER : HONOURABLE MR. JUSTICE N.V.ANJARIA)
The present First Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 arises out of order dated
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
5.5.2016 of learned Additional District Judge, Gandhinagar passed in Civil Miscellaneous (Arbitration) Application No.115 of 2011. Thereby, the court below dismissed the said application and confirmed the award dated 29.6.2011 passed by the arbitral tribunal.
2. In the final award dated 29.6.2011 of the sole arbitrator, the following was the operative part,
"(i) Claim of the claimant for Rs.24,85,897/- (Rs.Twenty four lac eighty five thousand eight hundred and ninety seven) for deduction by respondent from bill nos.1 to 23 is allowed and the respondent - ONGC is directed to pay this amount with interest at the rate of 12% from the date of declaration of this award till realization.
(ii) The claim of Rs.10,70,000/- (Rs. Ten lac seventy thousand) for extra work and the claim of Rs.11,31,368/- (Rs. Eleven lac thirty one thousand three hundred and sixty eight) for alleged insufficient supply of effluent are rejected.
(iii) In the facts of the case, as success is almost equally divided between the parties, there should be no order as to costs."
3. The appellant Oil and Natural Gas Corporation Limited (ONGC) had entered into agreement dated 25.5.2007 with the respondent for operation, maintenance and management of ONGC Installation Effluent Treatment Plant, GGS-III, Navagam and Water Injunction Plant, Vasna. The contract was for the period of two years commencing from 4.5.2007, and to expire on 3.5.2009. It was stated that the contract specifically provided
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
the mode and manner in which the respondent was required to operate the effluent treatment plant. It also provided about the manner for making payments to the respondents. All the specifications of the effluent were mentioned in the contract.
3.1 The contractor completed the contract work on 3.5.2009. The respondent raised for the first time certain claims on 5.5.2009 thereunder various amounts were claimed from the appellant corporation. Before the arbitrator in the statement of claim the claims which were raised, included the first claim for Rs.24,85,897/- on the ground that the deduction was wrongly made by the appellant ONGC from the bill Nos.1 to 23 raised by the claimant. The second claim was in relation to extra work as per the bill No.24 dated 5.5.2009 for Rs.10,70,000/-. Third claim was Rs.11,31,368/- as per the bill No.25 in relation to short supply of effluent by ONGC on the ground that it was less than the contractual specific average quantity of the effluent per day. Fourth claim was regarding interest on the claims at the rate of 18% per annum.
3.2 In the written statement filed on 14.2.2011 before the Arbitrator it was inter alia contended that the claimant was bound to act in accordance with the contract and perform the contractual terms and conditions. It was contended that the claimant had failed to achieve the requisite standard specified in the contract and the level of Total Soluble Solids (TSS) was in excess of <or=3.5 m.g and that the deduction were made in that regard from bill Nos.1 to 23. It was contended that the deductions were made as per the terms of the contract.
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
3.3 In the final arbitral award dated 29.6.2011, the sole arbitrator found that the claim Nos.2 and 3 since were belatedly raised, were not tenable. The tribunal therefore rejected the claim No.2 which was for Rs.10,70,000/- and claim No.3 for Rs.11,31,368/-. The arbitral tribunal, however accepted the claim No.1 of the respondent by holding that the appellant was liable to pay the amount of Rs.24,85,897/- towards the amount of deduction made from the bill of the respondents for non- compliance of the parameters required to be met regarding the effluent.
3.4 It is in against and in respect of the said award passed for the said claim by the arbitrator holding the ONGC liable to pay the amount towards deduction made for not meeting with the effluent parameters, that the present appeal is addressed. The question is whether the arbitrator could have allowed the said amount of Rs.24,85,897/- which was deducted by ONGC from the bills of the respondents with regard to the not meeting with the parameters of effluent discharge required to be met under the terms of the contract.
4. Learned advocate Mr.Ajay Mehta for the appellant ONGC assailed the award of the arbitrator as well as the impugned judgment and order of learned Additional District Judge, whereby the award was confirmed by submitting that the court below in accepting the arbitral award holding the contractor entitled to Rs.24,85,897/-, committed an error. It was submitted that the court below could not have approved the conduct of arbitrator in travelling beyond the terms of the contract which was not permissible in law. It was submitted that the amount
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
granted was in respect of deductions legitimately made from respondent's bills for non-compliance with parameters required to be met with by the contractor in relation to effluent treatment.
4.1 It was submitted that award of this nature of claim was not only based on misinterpretation of the terms of the contract, but amounted to rewriting the terms, more particularly when the various clauses in the contract set out in detail the work- description and also fixed the parameters regarding effluent. It was submitted that the court below were not right in accepting the contention of the claimant contractor that TSS prescribed under contract of effluent after treatment of less than or equal to 3.5 mg was impossible or that it was not feasible in view of the effluent treatment plant of the ONGC. It was also submitted that such issue was never raised prior to filling up the tender.
4.1.1 It was next submitted that the arbitral tribunal misdirected itself in reasoning that the pollution control board had prescribed permissible level of TSS upto 10 mg and that therefore the appellant was wrong in setting the standard of less than or equal to 3.5 mg. It was submitted that it amounted to rewriting of the contract. It was erroneous to reason that condition with regard to the effluent discharge and the parameters mentioned were not fundamental. They were basic and had to be applied in conjunction of other work related parameters, it was submitted.
4.1.2 Learned advocate for the appellant submitted that appellant had to incur cost for arranging the coil tubing units for
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
clearing the production tubing and partially chocked reservoir perforation zone due to high amount of TSS which was causing low injectivity problems of the effluent disposal wells.
4.1.3 Learned advocate for the appellant relied on the decision of the Supreme Court in Ssangyong Engineering and Construction Company Limited Vs. National Highways Authority of India [(2019) 15 SCC 131], to submit that the award in question is in breach of fundamental policy of India as the arbitrator acted beyond the terms of the contract to award the claim. Decision in Satyanarayana Construction Company Vs. Union of India [(2011) SCC Online SC 1372], and several other decisions were pressed into service to emphasis that it was not open for the arbitrator to rework the contractual terms between the parties and to apply them under the cloak of interpretation.
4.2 Learned advocate for the respondent Mr.Apurv Vakil submitted that the appellant ONGC was not justified in straightway deducting the amount. It was submitted that there was no provision for deducting in such manner. According to submission of learned advocate for the respondent, if the ONGC was to deduct the amount, then Clause 7.4 of the agreement dated 25.5.2007 ought to have been followed.
4.2.1 clause 7.4 sought to be pressed into service by the respondent, stated that 'in the event of any dispute in a portion or whole of any invoice, the corporation shall make payment of undisputed portion and shall promptly notify the contractor's representative in writing for the remaining portion in contract to
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
mutually resolve the dispute and if resolved in part or full, payment shall be made to the contractor within 30 days of such settlement.'
4.2.2 it was further relied on was clause 9 of the contract which was in respect of performance, provided that 'the contractor shall undertake to perform all services under the contract with all-reasonable skill, diligence and care in accordance with the sound industry practice to the satisfaction of the corporation and accept fill responsibility for the satisfactory quality of such services as performed by them. It was further mentioned, any defect, deficiencies noticed in the contractor's service will be promptly remedied by the contractor within 10 days upon the receipt of written notice from the corporation to improve their performance failing which the corporation may terminate the contract by giving the contractor 30 (thirty) days written notice.'
4.2.3 It was submitted that in view of the above Clause, during the subsistence of the contract, if any defect or deficiency is noticed in the services rendered by the contractor, procedure as above was required to be followed. It was submitted, any defect or any deficiency was never notified by the ONGC. It was submitted that the ONGC was needed to intimate the respondent with regard to non-compliance, if any. It was submitted that on one hand it was the case of ONGC that the parameters fixed under the contract with regard to output of the effluent were not met, since the ONGC did not intimate the same, it deemed to have waived such requirement. It was further submitted that the ONGC on the contrary addressed letter in April, 2009 to offer the respondent to continue and extend the contract for a period
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
of six months.
4.2.4 Learned advocate for the respondent submitted that in the aforesaid background, the arbitrator interpreted the Clause in the contract regarding the output parameters. It was submitted that no fault could be attached to the arbitrator for resorting to the interpretative process while delivering the award. It was submitted that the condition regarding the effluent parameter was not essential part or essential condition of the contract. It was submitted that powers under Section 34 of the Act was properly exercised by the arbitrator.
4.2.5 Advancing the contentions raised above, learned advocate for the respondent relied on the decision of the Supreme Court in Navodaya Mass Entertainment Limited Vs. J.M.Combines [(2015) 5 SCC 698] to submit at the outset that in absence of any perversity the court would not substitute its own view in place of the view of the arbitrator merely because two views were possible. Learned advocate immediately proceeded to rely on another decision in National Highways Authority of India Vs. ITD Cementation India Limited [(2015) 14 SCC 21] to submit that it was permissible for the arbitrator to enter into construction of terms of the contract even if it gives rise to determination of question of law. It was submitted on the basis of such decision that the arbitrator is entitled to take view which he holds to be correct and can construe the terms of the contract in reasonable manner. It was submitted that merely because the arbitrator has construed the terms of the contract by itself, it may not be a ground to set aside the award.
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
4.2.6 Yet another decision in Associate Builders Vs. Delhi Development Authority [(2015) 3 SCC 49] was relied on. Also pressed into service was the decision in National Highways Authority of India Vs. JSC Centrodorstroy [(2016) 12 SCC 592] to submit that the arbitrator had jurisdiction to interpret the terms of the contract. The consideration on which the arbitrator award could be set aside were highlighted by learned advocate for the respondent from the decision of the Supreme Court in Haryana Tourism Limited Vs. Kandhari Beverages Limited [(2022) 3 SCC 237]. Two other decisions of the Supreme Court in General Manager Sri Siddeshwara Co-operative Bank Limited Vs. Ikbal and Others [(2013) 10 SCC 83] and Bhagwati Oxygen Limited Vs. Hindustan Copper Limited [(2005) 6 SCC 462] were pressed into service to highlight the principle of waiver or abandonment of contractual rights.
5. In light of the controversy emerging as above, the moot questions are whether it is open in law for the arbitral tribunal to proceed outside the arena of the contractual terms operating between the parties and pass the award ? It is permissible for the arbitrator to rework the contract in guise of interpretation of the terms of the contract ? Whether arbitrator can interpret the contract and to what extent ? Whether by interpreting the terms of the contract a new term could be enforced between the parties to foist rights and obligations accordingly ?
5.1 It is to be noted that the contract between the parties contained various details including the salient features of the
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
ETP- effluent Treatment Plant, GGS-III at Navagam. Amongst other details, the details of location, plant area, installed capacity, expected average throughput rate, process description, layout and the dimensions of the plant, built up area, the details of plant and machinery, utility details, safety management system were mentioned in the contract. The details were also given about the process, major equipment, major construction of the plant, instruments to be used, essential operations etc. in the different appendices.
5.2 Now, the case of the appellant ONGC- the respondent before the arbitrator was that the required standard and level of Total Soluble Solids (TSS) was specified in the contract. However, the contractor failed to maintain the level and since the level was in excess of less than 3.5 mg, the deductions were made from bill Nos.1 to 23. According to the ONGC, the directions were made in terms of the contract as the contractor has failed to achieve the standard relating to effluent. On the other hand, according to the claimant, achieving the level less than or up to 3.5 mg TSS for the effluent was impossible and for that the claimant relied upon the certificate issued by the Gujarat Pollution Control Board.
5.3 Annexure- chemical and Annexure- chemical 2 were the input parameters and the output parameters. Input parameters were for the raw effluent water brought into the effluent plant and the output parameters were of the water treated at the plant.
5.3.1 Average input parameters as given in the contract in
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
the tabular form were as under.
Sr.No. Parameter Unit Value
1 PH - 8.11-8.53
2 Total Solids mg/L 5454-6784
3 TDS mg/L 5286-6728
4 TSS mg/L 53-168
5 Oil and Grease mg/L 21-139
6 Turbidity NTU 18.5-37.0
7 Chlorides mg/L 1675-6304
8 Sulphates mg/L 37-38
9 Sulphides mg/L 5.4-9.6
5.3.2 Annexure- chemical 2 also part of the contract, gave
details of output parameters as under.
Sr.No. Parameters Operating Limits
1 Total Suspended Solids (mg/l) <3.5
2 Turbidity (NTU) <1.0
3 Filterability through 0.45 um filter, 20 psi <5.0
(ltr/30min)
4 Oil and Grease (mg/l) <10
5.4 Though the above parameters were part of the agreed
conditions incorporated in the contract, the contractor raised contention that TSS under the contract of the effluent after treatment less than or equal to 3.5 mg was on higher side and impossible to achieve. Raising a contention and advancing the case that it was not feasible to meet with the said conditions regarding parameters once the standard was erroneously set.
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
Bills in that regard were liable to be paid and the deduction effected by the appellant was not justified.
5.5 The deductions made from Bill Nos.1 to 23 was based on condition No.5.2.1 of the contract. This condition was as under.
"5.2.1 Quality and quantity checks should be regularly carried out and logged as per stipulated periodicity. In case of non- conformance to output quality for the reasons attributed to contractor's performance, ONGC may not allow dispatch and even if allowed, this quantity will not be accounted and wherever possible recycling and reprocessing will be done by the contractor without any extra cost. Shortage in quantity thus arising will attract deduction as per clause 5.1 above, in case of random check by ONGC, if quality is not found in compliance and in contradiction to reports at the plant, then entire quantity processed from the commencement of the particular shift will be deducted for arriving at actual quantity. For this purpose shift commencement time will be effective 0600/1400/2200 hours respectively. Important parameters to be monitored by sampling every two hours are listed.
Contractor will have option to either analyze each two hourly sample and log results or one composite sample can be analyzed in one shift. In case of deviation in output specifications in composite sample analysis, quantity processes since last sample will be deducted. In case of deviation in output specification in respect of parameters which are required to be analyzed on quarterly basis (like bacterial activity, corrosion rate, scaling etc) deduction would be @3.5% per parameter of the amount payable to the contractor in the previous quarter. For example if deviations are noted in the sample tested in the quarter commencing April and
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
two parameters are observed to be in deviation then deduction will be 7% of actual payment in the quarter Jan-Mar."
5.6 The arbitrator observed in its award to finally grant the claim of Rs.24,85,897/- in favor of the contractor.
"From the aforesaid facts and contractual provisions, it can be safely inferred as follows:
(i) That the parties had not intended to consider the level of TSS < OR 3.5 mg. as a fundamental condition of the contract. Had it been a fundamental terms of the contract, the respondent ONGC would have and should have exercised its contractual right to notify to the contractor and put it to notice either for termination of the contract or for remedying the defects within ten days.
(ii) There is nothing to point out on record that on account of contractor having failed to achieve the TSS leval of < or = 3.5 mg. there was any loss caused to the respondent ONGC. Contention of the respondent that it had to incur extra cost for coil and for clearing the pipes due to higher level of TSS, can not be believed for the simple reason that during the performance period of the contract, respondent never notified and declared to the claimant though it could do so, under the contract.
(iii) High level of standard, even more than what is prescribed by the Gujarat State Pollution Control Board and that too without any ceiling limit for deduction, apparently appears to be in the nature of penalty. It appears to have been provided in terrorum to secure better performance from the contractor.
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
(iv) As there is no loss to the respondent on account of higher level of TSS then specified in the contract, levy of penalty would amount to unjust enrichment.
(v) If a party accepts such standard and short supply of commodity agreed to be supplied, without avoiding the contact and if it had suffered no loss on this count and if it subsequently withholds the payments on the ground that the commodity supplied was substandard, the Courts have held that such conduct amounts to waiver of contractual rights."
6. What was observed by the Supreme Court in General Assurance Society Limited Vs. Chandumul Jain (AIR 1966 SC 1644) in relation to interpreting documents relating to insurance contract, would be the principle applicable in respect of all types of contracts, that the words in the contract should be interpreted by giving effect to the meaning and intent which emerge from the terms of the contract. It was observed that,
"...the duty of the court is to interpret the words in which the contract is expressed by the parties because it is not for the court to make a new contract, however, reasonable, if the parties have not made it themselves."
6.1 In Satyanarayana Construction Company (supra) was a case before the Supreme Court where the arbitrator was found to have awarded higher rate than rate agreed in the contract, which was held to be beyond the competency and authority of the arbitrator.
6.1.1 In Satyanarayana Company (supra), the Supreme
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
Court observed after noticing the details of rates to be applied, which were prescribed for cutting types of soils in the contract to finally hold that the High Court did not committed any error in upsetting the award of the arbitrator with regard to the claim No.4 concerned of the statement of claim.
"Thus, as per the contract, the contractor was to be paid for cutting the earth and sectioning to profile, etc @ Rs.110 per cubic meter. There may be some merit in the contention of Mr.Tandale that the contractor was required to spend huge amount on the rock blasting work but, in our view, once the rate has been fixed in the contract for a particular work, the contractor was not entitled to claim additional amount merely because he has to spend more for carrying out such work. The whole exercise undertaken by the arbitrator in determining the rate for the work at Serial No.3 of Schedule A was beyond his competence and authority. It was not open to the arbitrator to rewrite the terms of the contract and award the contractor a higher rate for the work for which rate was already fixed in the contract. The arbitrator having exceeded his authority and power, the High Court cannot be said to have committed any error in upsetting the award passed by the arbitrator with regard to claim 4."
(para 11)
6.2 In Ssangyong Engineering and Construction Company Limited (supra), the Supreme Court considered the yardstick of contravention of public policy of India as ground for challenging the arbitral award in the context of Section 32(2)(b)
(ii), 48 and 34(2-A) as they stand after the amendment of 2015.
While elucidating the expression 'Public Policy of India' proceeded to held that one of the limb thereof was fundamental principle of justice and when the arbitrator acts beyond the
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
terms of the contract resulting into alteration of contract at the hands of the arbitrator, the award would liable to be set aside.
6.2.1 Following was observed in Ssangyong (supra) in that regard.
"However, when it comes to the public policy of India argument based upon "most basic notions of justice", it is clear that this ground can be attracted only in very exceptional circumstances when the conscience of the Court is shocked by infraction of fundamental notions or principles of justice. It can be seen that the formula that was applied by the agreement continued to be applied till February, 2013 - in short, it is not correct to say that the formula under the agreement could not be applied in view of the Ministry's change in the base indices from 1993-94 to 2004-05. Further, in order to apply a linking factor, a Circular, unilaterally issued by one party, cannot possibly bind the other party to the agreement without that other party's consent. Indeed, the Circular itself expressly stipulates that it cannot apply unless the contractors furnish an undertaking/affidavit that the price adjustment under the Circular is acceptable to them. We have seen how the appellant gave such undertaking only conditionally and without prejudice to its argument that the Circular does not and cannot apply. (Para 76)
6.2.2 It was then stated by the Apex Court,
"...It is clear that the majority award has created a new contract for the parties by applying the said unilateral Circular and by substituting a workable formula under the agreement by another formula de hors the agreement. This being the case, a fundamental principle of justice has been breached, namely, that a unilateral addition or alteration of a contract can never be foisted upon an unwilling
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
party, nor can a party to the agreement be liable to perform a bargain not entered into with the other party. Clearly, such a course of conduct would be contrary to fundamental principles of justice as followed in this country."
6.2.3 It was held,
"Under no circumstance can any Court interfere with an arbitral award on the ground that justice has not been done in the opinion of the Court. That would be an entry into the merits of the dispute which, as we have seen, is contrary to the ethos of Section 34 of the 1996 Act, as has been noted earlier in this judgment."
(Para 76)
6.3 The decision in PSA SICAL Terminals (P) Limited Vs. Board of Trustees of V.O. Chidambranar Port Trust Tuticorin [(2021) SCC Online SC 508], is also a torch-bearer on the point. There was a tender contract between Board of Trustees of Chidambranar Port Trust Tuticorin and appellant PSA SICAL Terminals Private Limited. The SICAL wanted the agreement to be amended to change the 'royalty payment method' to 'revenue sharing method', to which Board of Trustees of Chidambranar Port Trust Tuticorin was opposed to. The court noted that the intention of TPT was clear from various communications as well as from its stand before the arbitrator.
The arbitral tribunal however, ignored the stand of the TPT and by substituting the royalty payment method to the revenue sharing method, a new term was thrust upon.
6.3.1 The Supreme Court observed that it was clear that the award had created a new contract of the parties by unilateral intention of SICAL as against the intention of TPT. The Supreme Court referred to Ssangyong Engineering and
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
Construction Company Limited (supra) holding that when unilateral addition or alteration of a contract has been foisted upon an unwilling party, the arbitral award thus rendered would be liable to be set aside on the ground of breach of fundamental principle of justice.
6.3.2 The court in PSA SICAL Terminals (P) Limited (supra) held, "It has been held that the role of the Arbitrator is to arbitrate within the terms of the contract. He has no power apart from what the parties have given him under the contract. If he has travelled beyond the contract, he would be acting without jurisdiction." (para 89)
6.3.3 It was also held, It has been held that an Arbitral Tribunal is not a Court of law. Its orders are not judicial orders. Its functions are not judicial functions. It cannot exercise its powers ex debito 27 (2004) 9 SCC 619 justitiae. It has been held that the jurisdiction of the arbitrator being confined to the four corners of the agreement, he can only pass such an order which may be the subjectmatter of reference. (para 91)
6.4 In Indian Oil Corporation Ltd. Vs. M/s Shree Ganesh Petroleum Rajgurunagar, Through its Proprietor, [(2022) 4 SCC 463], facts were that the appellant took a plot of land on lease from the respondent pursuant to the lease deed dated 20.9.2005 and set up at the site of retail outlet. The respondent was appointed as dealer of the said retail outlet. A separate dealership agreement was executed between the appellant and respondent. There was provision in the lease agreement to refer the disputes to the arbitrator who was to be Managing Director.
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
The dealership agreement also provided for reference of disputes to the sole arbitrator. When the disputes arose between the parties, the appellant terminated the dealership and called upon the respondent to vacate the retail outlet and to handover the peaceful possession. The arbitrator was appointed in terms of dealership agreement.
6.4.1 The Supreme Court held that the lease agreement and the dealership agreement were distinct and independent of each other. It was further held that the award of the arbitrator when it pertained to the lease rent and lease period was patently beyond the scope of competence of arbitrator appointed in terms of the dealership agreement. The award of the arbitrator was set aside to the extent that the arbitrator had increased monthly lease rent from Rs.1750/- to Rs.10,000/-.
6.4.2 In Indian Oil Corporation (supra), the Supreme Court referred to the law laid down in PSA SICAL Terminals (P) Limited (supra) while holding the award insofar as it pertained to the lease rent to be beyond the scope of the competence of the arbitrator holding thus, "The lease agreement which was in force for a period of 29 years with effect from 15th April, 2005 specifically provided for monthly lease rent of Rs.1750 per month for the said plot of land on which the retail outlet had been set up. It is well settled that an Arbitral Tribunal, or for that matter, the Court cannot alter the terms and conditions of a valid contract executed between the parties with their eyes open."
6.5 The Delhi High Court in Union Of India, Ministry Of Railways, Railway Board Vs.M/S Jindal Rail Infrastructure
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
Limited, [(2022) SCC OnLine Del. 1540], which was relied on by learned advocate for the appellant, laid down that the commercial contract between the parties cannot be avoided on the ground that one of the parties subsequently finds it commercially unviable to perform the same. The Delhi High Court found that the arbitrator had rewritten the contract of the parties. The arbitrator had interpreted the Clause 2.4 of the agreement.
7. Therefore, it has to be observed and stated that the role and function of arbitrator is to arbitrate within the terms of the contract. The four corners of the terms and conditions of the contract under which the arbitrator is appointed becomes the functional realm of the arbitrator. It defines the jurisdictional bounds of the arbitrator.
7.1 The arbitrator will be deciding the disputes between the parties which are arbitrable in nature. The disputes which are arbitrable in nature have to be there genesis to be traced only for the terms of the contract operating between the parties. It is only in the context of and by confining to the terms and agreement mutually agreed upon by and between the parties to the arbitration, that the arbitrator is required to deliver his award.
7.2 The arbitrator is concerned with the application of terms of the contract and not their interpretation. The interpretation of conditions of the contract is not the function permitted for the arbitrator. Rewriting of the contract and delivering the award is impermissible. The arbitrator cannot rework the bargain
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
between the parties. It is here that the arbitral tribunal is different from court of law in discharge of functions and in deciding the disputes.
7.3 What the court could not do while interpreting the terms of the contract, the arbitral tribunal can also certainly not do. It cannot resort to interpretative process so as to rewrite or create new contract between the parties. The task is to simple apply the terms and conditions of the agreement as agreed between the parties, while rendering the arbitration award.
8. At this stage proceeding to deal with the decisions relied on by the respondents, in Associate Builders (supra) the Supreme Court explained what is 'public policy' of India. It was highlighted that the fundamental policy of Indian Law would include compliance with the statute and judicial precedents, need for judicial approach, observance of natural justice and Wednesbury reasonableness. The interest of India, justice in modality and patent illegality are other heads and if the arbitral award is in contact with those mentioned considerations, it is liable to be interfered with. Similar principles were highlighted in Haryana Tourism Limited (supra).
8.1 The decision in General Manager, Shri Siddheshwara Co-operative Bank Limited (supra) was in the context of security interest (enforcement) Rules, 2002 in which the Supreme Court explained the expression 'written agreement' to hold that it meant mutual understanding of arrangement as to relative rights and duties of parties and that it is manifestation of mutual assent in writing. In Bhagwati Oxygen Limited
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
(supra), the principle of waiver of abandonment of contractual rights was mentioned, in the facts of the case it was found that the arbitrator was justified in making award in favor of Bhagwati Oxygen Limited (supra) allowing all its claims including all unpaid dues for oxygen that had been supplied.
8.2 In JSC Centrodorstroy (supra) the proposition that the construction of the terms of the contract was for arbitral tribunal to decide was in different context under Clause 70.8. The conditions provided for payment for additional cost or deduction of reduced cost from contract price due to change in any statute, ordinance or decree or other law or regulations or by laws of any local authority. The arbitral tribunal awarded claims as the compensation for additional cost on account of increase in service tax and insurance premium and on bank guarantee charges on the ground that the additional cost a result of revision in service tax which respondent- claimant was required to bare.
8.3 The Supreme Court held that since in light of the Clause No.70.8 of the conditions, the arbitral tribunal was entitled to construe the terms of the contract and in instant case increase in the rate of service tax in respect of the bank guarantee and insurance premium was directly relatable to the terms of the contract and performance under the contract was a possible view, there was no justification of interference by the court in the award. Thus, in that case, the arbitral tribunal had awarded additional cost on account of increase in service tax and insurance premium as was permitted in the condition of the contract itself. The facts of the said case differs from the facts of
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
the case on hand.
8.4 When in ITD Cementation India Limited (supra), the facts were different, the contract was awarded to the respondent ITD Cementation by National Highway Authority of India for widening the lanes. The State Government increased royalty on stone, sand and earth upto 30%. The respondent requested for price adjustment under Clause 70.8 of the conditions of the contract. It was denied by appellant on the ground that the said aspect was considered under price adjustment formulae under Clause 70.3, arbitral tribunal took view that provision for cost escalation based on the agreed price adjustment formulae was different from provision for compensation for additional cost resulting from a subsequent legislation. Claimant was held entitled to be compensated for additional cost. The award of the arbitrator was in the nature of applying the terms of the contract rather contractual, interpreting the same to work out new conditions.
9. From above position of law discussed, what therefore finally emerges is that generally stated the arbitral tribunal cannot travel outside the arena of terms and conditions agreed upon in the contract. The interpretation of these terms have to be on the basis of what is expressly stipulated. Express terms are the intention of the parties best expressed. The scope of interpretation of the terms and conditions of the contract would arise where the conditions are not clear or not capable of dual understanding. In this regard also the interpretation has to be in accordance with the intention of the parties to be gathered from the terms and conditions. While this cannon of interpretation of
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
contractual terms and the limitations thereof, which are true for the courts, stand equally binding to be observed by the arbitrator while giving award based on the contract between the parties.
10. In the present case, the parties had agreed about the parameters to be observed with regard to the TSS quantity in the effluent plant of the ONGC which was to be maintained and operated by the contractor. The parameter was expressly set and agreed upon by the parties forming part of the express condition of the contract which is reproduced herein above. The parameter of TSS was less than or upto 3.5 mg TSS.
10.1 When the said parameter was not observed by the contractor, the consequential deduction in the amount by the ONGC could not have been excepted by the arbitrator on the spacious ground that achieving the said standard was not feasible or possible. This condition was contractual condition agreed upon by the parties and the arbitrator was not expected to travel beyond its corners and to award the amount to the contractor which was legitimately deducted by the ONGC on the ground of breach of said parameter.
10.2 The arbitrator proceeded to interpret the said term, and virtually substituted his own applied conditions and passed award on that basis. It could be said to be an approach by the arbitrator, not just interpretation of the term to be properly apply it, but the arbitrator thereby indeed reworked the entire bargain between the parties, which was precisely not permissible in law. Interpretation of the term in the contract so
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
as to render it anew in its application and thereby to determine rights and obligations of the parties is not the jurisdiction of the arbitrator. The arbitrator has to decide and pass an award within the compass of the conditions of the contract. The conditions in the contract binds the arbitrator in rendering the award. In the instant case, the arbitrator evidently acted without jurisdiction to rework the condition about the effluent parameters.
10.3 Finally noticing, the observations of arbitrator in its award to allow the claim of Rs.24,85,897/-, which are reproduced in paragraph as above, were his own inferences, not backed by agreed by terms and conditions of the contract. The arbitrator implanted his view to award the claim. By applying the standard of the pollution control board in respect of the effluent parameter, the arbitrator clearly introduced new condition in relation to the said aspect which was not in the contract between the parties. The condition regarding the effluent parameter mentioned in the clause was discarded and it was substituted by new consideration. The approach of the arbitrator was outside the purview of his jurisdiction. The award of the claim was not based on application of the condition agreed upon but it amounted to rewriting of contract between the parties which was clearly not permissible.
10.4 In view of above principles to be applied and the position of law emerging, the appellant is entitled to succeed.
10.5 At this stage, it may be noted that this court passed following order on 9.1.2017 in Civil Application for stay No.8695 of 2016, the order was passed extracting the relevant.
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
"Having regard to the submissions made by learned advocates for the parties at the stage of considering confirmation or otherwise of ad- interim relief granted in terms of para 14(A) of this application, the applicant has already deposited the entire amount so awarded by the Tribunal and accordingly, registry of this Court is directed to invest such amount in a fixed deposit receipt of a Nationalised Bank accruing periodical interest initially for a period of three years and to be renewed from time to time till final disposal of the petition and interest which may accrue thereon shall be released in favour of respondent upon filing an undertaking within two weeks from today that in case the appeal filed by the appellant is allowed same shall be refunded as ordered by the Court finally. "
10.5.1 As the award of the award of the arbitrator as well as the impugned order of the court below confirming the same, stand liable to be set aside with the findings that the arbitrator could not have allowed the claim in question. The amount invested as per the aforementioned order in the Fixed Deposit shall be returned to the appellant.
10.5.2 In view that the claim in question is not allowed and the judgment and order is set aside, the interest earned on the said Fixed Deposit which was directed to be paid to the respondent cannot be retained by the respondents. Therefore the respondents shall pay back the interest received by it during the pendency of the appeal from the Fixed Deposit, to the appellant herein within three weeks from the date of the receipt of this order.
11. As a result of above, order dated 5.5.2016 confirming
C/FA/1804/2016 CAV JUDGMENT DATED: 27/03/2023
the award of the arbitrator, passed by learned Additional District Judge, Gandhinagar in Civil Miscellaneous (Arbitration) Application No.115 of 2011, is set aside. The respondent shall not be entitled to the amount towards claim No.3 awarded by the arbitrator. The appeal stands allowed.
(N.V.ANJARIA, J)
(SANDEEP N. BHATT,J)
FURTHER ORDER
At this stage, learned advocate Mr. Jeet Karia requested that the operation of this judgment and order may be stayed in order to enable the respondent to approach higher forum.
In the facts and circumstances of this case, the present judgment and order and the directions regarding the return of the amount deposited shall remain in abeyance for a period of four weeks.
(N.V.ANJARIA, J)
(SANDEEP N. BHATT,J)
Manshi
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!