Citation : 2022 Latest Caselaw 676 Guj
Judgement Date : 20 January, 2022
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/SPECIAL CIVIL APPLICATION NO. 2606 of 2016
With
CIVIL APPLICATION (FOR DIRECTION) NO. 1 of 2019
In R/SPECIAL CIVIL APPLICATION NO. 2606 of 2016
With
R/SPECIAL CIVIL APPLICATION NO. 2608 of 2016
FOR APPROVAL AND SIGNATURE:
HONOURABLE MR. JUSTICE A.Y. KOGJE
===============================================================
1 Whether Reporters of Local Papers may be allowed
to see the judgment ?
2 To be referred to the Reporter or not ?
3 Whether their Lordships wish to see the fair copy
of the judgment ?
4 Whether this case involves a substantial question
of law as to the interpretation of the Constitution
of India or any order made thereunder ?
================================================================
YUSUFBHAI TEHERBHAI BADRI
Versus
SURAT MUNICIPAL CORPORATION
===============================================================
Appearance:
MS KJ BRAHMBHATT(202) for the Petitioner(s) No. 1
MS VARSHA BRAHMBHATT(3145) for the Petitioner(s) No. 1
MR HS MUNSHAW(495) for the Respondent(s) No. 1
===============================================================
CORAM:HONOURABLE MR. JUSTICE A.Y. KOGJE
Date : 20/01/2022
ORAL JUDGMENT
[1] Rule. Learned advocate Mr. H.S.Munshaw waives service of
rule on behalf of respondent-corporation.
[2] This group of petitions are filed against the judgment and order
passed in Regular Civil Appeals by the 9th Additional District Judge,
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
Surat by which the compensation awarded under the provisions of
Bombay Municipal Corporation Act (for short "the Act") and the
interest calculated was called in question. By way of these writ
petitions, the judgment and order passed by the District Court in the
appeals filed both by claimants as well as acquiring body namely
Surat Municipal Corporation is challenged.
[3] The issue pertains to award of compensation to the petitioner
whose land was acquired for the purpose of widening of the road.
The corporation through its Commissioner had awarded the amount
of compensation, against which the Municipal Reference was
preferred by the petitioner and the Principal Senior Civil Judge, Surat
decided the reference.
[3.1] The reference was subject matter by separate appeals
preferred both by the claimants as well as the Surat Municipal
Corporation and by common judgment, the respective appeals came
to be decided. Each appeal filed by the claimant and the municipal
corporation was decided by a common judgment hence, the
petitioner has preferred two writ petitions, pertaining to the same
plot, part of which was taken up for the purpose of road widening.
All these petitions were heard jointly however, to avoid confusion,
separate orders are passed as per the property number.
[4] The present petitions pertains to property Ward No.7 Nondh
No.278/A/1/7/2 situated at Sufibaug, Station Road, Surat City, where
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
acquired land is admeasuring 190.8224 Sq.Mtrs to widen the
existing 50 feet road to 60 feet road by the Surat Municipal
Corporation under Section 210 read with Section 212(2) of the Act.
The commissioner on 10.12.2002 under Section 390 awarded the
compensation for the land is Rs.7689/- per sq.mtr.
[4.1] Thereafter, the petitioner filed Municipal Reference which was
partly allowed vide order dated 23.09.2010, whereby granted
additional compensation of Rs.6349.51 and hence total
compensation of Rs.14,038.51 per sq.mtr with interest at the rate of
15% per annum from the date of taking possession i.e. 01.03.2002
till realization of the same.
[4.2] Thereafter, against the aforesaid order, separate appeal filed
by both the claimant seeking enhanced compensation, rate of
interest, date of granting interest from the date of possession till
realization and Surat Municipal Corporation seeking reduction rate
of interest. In both the appeals, vide common judgment and order
dated 21.11.2015, the appeal preferred by the SMC was partly
allowed and reduced the rate of interest to 9% payable from the
date of order of Reference Court dated 23.09.2010, whereas the
appeal preferred by the petitioner is dismissed.
[4.3] Special Civil Application No.2606 of 2016 is filed by the
petitioner against the order passed in Regular Civil Appeal No.63 of
2010, whereas the Special Civil Application No.2608 of 2016 is filed
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
by the petitioner against the order passed in Regular Civil Appeal
No.78 of 2010.
[5] Learned advocate for the petitioner submitted that the lower
appellate Court has committed grave error by reducing the rate of
interest from 15% per annum awarded by the Reference Court to
9% per annum on the ground that it is excessive. it is submitted
that in a different proceedings regarding road widening The learned
Principal Senior Civil Judge, Surat vide judgment and order dated
29.09.2008 in Municipal Reference No.5 of 1997, awarded rate of
interest at 15% per annum and against the said award, the
respondent-Municipality has preferred Regular Civil Appeal No.30 of
2010, wherein the District Court at Surat reduced the rate of
interest at 12% per annum from 15% per annum. The SMC accepted
the said judgment and no further proceedings were filed by the SMC
against the said judgment. Hence, the petitioner is also entitled to
receive interest at least at the said accepted rate of interest being
12% by respondent-Municipality. It is submitted that the levy of
betterment charges is not only bad but unjust, improper,
unreasonable and erroneous inasmuch as widening of said already
existing 50 feet road to 60 feet road has not added any further air
and light facilities or appreciated value of remaining property of the
petitioner. On the contrary, with said widening the petitioner has
lost valuable property under compulsory acquisition. If has reduced
the property to be occupied, used and owned by the petitioner.
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
Despite the said glaring fact, the respondent Municipality committer
error by levying Betterment Charges that too at the rate of Rs.200/-
per sq.mrt on the remaining property and therefore, the trial Court
properly observed and directed to return said Betterment Charges
with interest to the petitioner. However, in absence of any evidence
being adduce qua any benefits to have accrued to the petitioner by
said acquisition by the respondent Municipality, the Appellate Court
has committed error by giving finding that under section 216(2) of
Act, the respondent Municipality is entitled to recover Betterment
Charges. Said findings is without any evidence on record of the case
and erroneous and therefore the impugned Judgment requires
requires to be quashed and set aside. The lower Appellate Court has
failed to appreciate that the property of the petitioner is already on
existing 50 feet road and out of it some portion came to be acquired
by the respondent Municipality for the purpose of widening the said
existing road further by 10 feet i.e. making 50 feet road to 60 feet.
[5.1] It is submitted that the appellate court has committed error in
not interfering with the market value fixed by the Trial court on the
ground that the market value of the property as calculated earlier @
Rs.14038.51 per sq. m. Is close (near about)amount to market value
shown in Government Jantri @ Rs.15000/per sq/m. That the Trial
Court has taken market value @ Rs.13150.81 per sq. m. As per 1
sale instance and has added Rs.887.70 per sq.m. towards
construction cost for arrivıng at compensation amount. That the
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
appellate Court has erred in holding that the trial court has fixed
market value of property @ Rs.14038.51 Ps. Sq. m. In fact it iss the
amount of total compensation of property arrived at by fixing
market value of land: @ Rs.13150.81 per sq. m. Plus construction
cost of RS.887.70 per sq.m.. It is rightly held that Government Jantri
rate at Rs.15,000/per sq.m. is proper, adequate and reasonable for
fixing market value of said property, the appellate court has
committed error in holding that Market value fixed by Trial Court @
Rs.14038.51 is close to market value shown in Government Jantri.
The Trial Court has fixed market value of said property at
Rs.13150.81 only.
[6] With regards to the interest awarded by the appellate Court at
the rate of 9%, learned advocate for the petitioner has referred to
judgment in Regular Civil Appeal No.30 of 2010, where the appellant
is the Surat Mahanagarpalika and in this judgment, the Appellate
Court has reduced the interest rate awarded by the Reference Court
from 15% to 12% and that the interest rate of 12% was accepted by
the Surat Municipal Corporation and therefore, in the present case,
where the interest rate is reduced to 9% by the appellate Court from
what was awarded by the Reference Court at 15%, is required to be
interfered with.
[7] As against this learned advocate for the respondent-corporation
submits that compensation determined by the SMC is as per market
value of the property and the same is fair and reasonable. The SMC
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
has also considered the compensation taking into consideration all
requisite aspects like sale instance and locality of the acquired
property. The SMC has acquired the land for the public purpose and
therefore the award passed by the SMC is passed taking into
consideration public interest at large. The SMC has further stated
that the petitioner has been benefited by the acquisition of the land
ventilation of the petitioner's property is increased. Not only that,
but the petitioner has been benefited many other facilities therefore
the petitioner not entitled to recover betterment charges from the
amount of compensation and therefore betterment charge
recovered by the petitioner is according to law hence the petitioner
is not entitled to recover betterment charges from the respondent.
[8] The Court has considered the submissions made by learned
advocates and perused the documents placed on record. The first
issue raised before this Court in the petitions during the course of
arguments is that the petitioner has not been given adequate
compensation as the compensation awarded does not contain the
component of compensation towards the existing construction on
the land which was acquired for the road widening.
[9] The other question which is raised is with regards to reduction
in the rate of interest by the appellate forum from 15% awarded in
the Municipal Reference to 9% awarded by the Appellate Court.
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022 [10] In the present case, the details regarding acquisition
proceedings and the compensation awarded at various stages are
already recorded in the preceding paras.
[11] The acquisition was proposed under Section 210 read with
Section 212 of the Act and after following due procedure, an award
was passed by the Commissioner under Section 390 of the Act.
From the record, it appears that while passing the award, all
necessary provisions of law were complied with and there is no
challenge in so far as procedural aspect is concerned.
[12] The Municipal Reference was filed by the claimants on the
ground of inadequate compensation calculated by the
Commissioner while passing the award. The Municipal Reference
was partly allowed enhancing the compensation by taking into
consideration the evidence in the form of sale deeds of surrounding
areas and additional compensation was granted. Alongwith the
compensation, the reference Court also decided upon the rate of
interest by calculating the same at the rate of 15% from the date of
taking of possession. Being aggrieved by the judgment and order of
the Municipal Reference Court, both the Municipal Corporation and
the claimants preferred Regular Civil Appeals. The Surat Municipal
Corporation challenged the judgment and order of the reference
Court for awarding higher rate of interest at the rate of 15% per
annum, whereas the claimants preferred the appeal for not granting
the adequate compensation. Both the appeals were dealt by the
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
appellate forum jointly. While allowing the appeal of the corporation
reduced the rate of interest from 15% to 9%, whereas dismissed the
appeal of the claimants maintaining the compensation awarded by
the Municipal Reference Court.
[13] The Commissioner had awarded compensation of Rs.7689/- per
sq.mtr. The Municipal Reference Court considered the evidence on
record and come to the conclusion that the compensation is
required to be awarded is to be Rs.14038.51 per sq.mtr, thereby
granted additional compensation of Rs.6349.51. The Municipal
Reference Court also granted the compensation with rate of interest
of 15% from the date of taking over the possession i.e. from
01.03.2002. In the appeal, the appellate forum maintained the
compensation at the rate of Rs.14,038.51 per sq.mtr, but reduced
the rate of interest to 9% and that too payable from the date of
order of the reference Court i.e. from 23.09.2010.
[14] The Court first deals with the compensation arrived at by the
Reference Court and confirmed by the appellate Court. The
Municipal Commissioner had considered the rate of compensation
by considering the value of the land at Rs.7689 per sq.mtr.. While
challenging such value of the land, the claimants had produced on
record evidence in the form of sale deeds of nearby areas and
claimed that value of the land ought to have been considered at
Rs.23000 per sq.mtr. and in this regard, three sale instances were
placed on record. Over and above, the sale instances, the market
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
rate fixed by the Jantri (Annual Statement of Rates) was also placed
on record which indicated the market price of the land in the area to
be 15000 sq.mtr. The Government Jantri of the property situated in
city survey No.278/A/1/7/3 was placed on record vide mark 3/13.
[15] Thereafter, by relying the decision of the Supreme Court,
proceeded to hold that every kind of land is required to be
compensated, accepted the principal of compensating the claimant
for the purpose of construction and accepted an amount of
Rs.887.70 per sq.mtr as compensation for the construction.
However, inspite of considering the Jantri rate at the rate of 15000
per sq.mtr., the Reference Court proceeded to consider
compensation at the rate of Rs.13,150.81 to be appropriate rate of
compensation by placing reliance on sale instances which was
produced vide mark 3/8.
[16] The logic for treating Rs.14,038.51 per sq.mtr,, to be adequate
compensation by considering the sale instances and adding the
compensation for existing construction to be adequate as it is
coming to Rs.14,038.51 per sq.mtr. which is the figure very near to
the Jantri price fixed by the Government at the rate of 15000/- per
sq.mtr. This in the opinion of the Court is an error which has crept
in. In the opinion of the Court, the Government Jantri placed on the
record would reflect the true and correct market value as against
the sale instances which were also placed by the petitioner on
record. There is nothing brought on record by the corporation to
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
contend that the reliance on the sale instances would be more
appropriate than the market rate as per the Government Jantri and
therefore, the logic placed by the Reference Court in considering the
value as per the sale instances, adding the cost of construction per
sq.mtr and holding such valuation being near to the Government
fixed Jantri would actually result in not considering the component
of the compensation towards existing construction which otherwise
was treated at the rate of Rs.887.70 per sq.mtr.
[17] The compensation for the existing construction has to be
awarded is a settled position of law and is not disputed by the
respondent-corporation. The reason for awarding such
compensation obviously is because the individual who losses his
portion of land for the purpose of road widening will also have to
loose construction on which such individual would have made some
investment. Not only that, but having reduced such investment to
"Zero", will also have to make further investment to make over loss
of construction area for which again an individual have to make
investment in monetary terms. Therefore, separate compensation
for the loss of construction over the land acquired for road widening
is an acceptable norm. The only issue is that on one hand, the
Municipal Reference Court as well as Appellate Court considered this
principal, but adding some cost only to the value of the land arrived
at on the basis of sale instance No.1 and by adding these two
figures, accepted the total compensation to be adequate since it
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
was near to the Government Jantri. The Jantri Exh.3/13 would only
consist of the value of open land and would not consist of the
enhanced compensation of the land on the basis of the construction
existing on such land and therefore, though principally the
compensation calculated by the Reference Court and the Appellate
Court may appear to be within the frame work, but cannot be
treated to be a adequate compensation. The Court therefore, holds
that adequate compensation is reacquired to be considered at
Rs.15000/- plus Rs.887.70 per sq.mtr, which is the value of the
construction on the land and total value of the land the construction
is 15,887.70 per sq.mtr. and therefore, the petitioner is entitled to
additional compensation of Rs.1849.19 per sq,mtrs.
[18] With regards to the argument for the rate of interest, the Court
has taken into consideration the issue of interest in two aspects. The
first being the rate of interest and other being the date from which
such rate of interest is to be calculated. In so far as the rate of
interest is concerned, the Reference Court has awarded the rate of
15% interest from the date of taking the possession which was
reduced by the appellate Court to 9%. Not only that, the appellate
Court has also made the rate of interest applicable from the date of
order of the Reference Court i.e. from 23.09.2010.
[19] The only submission made by the petitioner is that the
respondent-corporation in one of the proceedings of similar kind of
acquisition for road widening has accepted the award of the
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
Appellate Court, which has reduced the interest from 15% per
annum to 12% per annum and therefore, in the present case, the
interest rate of 9% granted by the appellant Court may not be
enhanced to at the rate of 15% as granted by the Reference Court,
but at least should be increased to 12%. The proceedings under the
BPMC Act are governed by the separate statute which is different
from the provisions of Land Acquisition Act, where the rate of
interest is provided under the acquisition itself. The proceedings of
acquisition under the BPMC Act will have to be governed by the
Code of Civil Procedure as provided for under Section 434. Section
434 of the Gujarat Provincial Municipal Corporation Act provides for
application of Civil Procedure Code and Sub-Section 2 provides for
application of the same to all other matters for which no specific
provision has been made under this Act which shall be governed by
such Rules, as the State Government may from time to time make
after consultation with the High Court. There is no provision with
regards to the interest in GPMC however, Section 34 of the CPC
would apply which provides for the rate of interest, not exceeding
6% per annum. However, as the corporation is not challenging the
rate of interest as prescribed by the appellate Court, the Court is not
inclined to interfere with to change the rate of interest. On the
challenge made by the claimants to enhance the rate of interest
from 9% to 12% or 15%, no interference is called for in so far as the
rate of interest is concerned.
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
[20] With regards to the aspect of period of applicability of the rate
of interest, the relevant date, as per the opinion of the Court, would
be the date on which the possession is taken over which, in the
instant case is 01.03.2002 till the date of taking of possession. The
reason for interfering to the limited extent is the Reference Court
has granted the rate of interest from the date of taking the
possession by assigning cogent reasons however, when the
appellate Court reduced the period from the date of taking over the
possession to the date on which the Reference Court had
pronounced the judgment and order dated 23.09.2010, no reasons
had been adduced in doing so and therefore, by maintaining the
judgment and order in this regard by the Reference Court, this Court
is of the view that the rate of interest of 9% may be applicable from
the date of taking over of possession. The petitioner is therefore
entitled to receive additional compensation of the Rs. 1849.19/- with
interest at the rate of 9% from the date of taking of possession of
the lands of petitioner.
[21] The respondent corporation has made a feeble attempt to
argue that the nomenclature in the petition indicates the petition
being filed under Art.227 of Constitution of India and therefore the
scope of interference for this Court is limited. in view of the
discussion in the foregoing paras it is apparent that the Judgment
and Order of the Appellate Court is final and there is no statutory
provision to agitate the grievance. moreover, the error is committed
C/SCA/2606/2016 JUDGMENT DATED: 20/01/2022
by the subordinate Court where on one hand has accepted on
record the evidence of Govt Jantri to decide the market value but
does not take the same in consideration while giving weightage to a
sale instance. therefore the court deems it fit to interfere.
[22] With the aforesaid extent, the petitions stand allowed. Rule is
made absolute to the aforesaid extent.
[23] In view of the order passed in the main matter, the Civil
Application No.1 of 2019 in Special Civil Application No.2606 of
2016 does not survive. Hence, the Civil Application stands
disposed of.
(A.Y. KOGJE, J) SIDDHARTH
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!