Citation : 2022 Latest Caselaw 1226 Guj
Judgement Date : 4 February, 2022
C/IAAP/119/2020 ORDER DATED: 04/02/2022
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/PETN. UNDER ARBITRATION ACT NO. 119 of 2020
==========================================================
SHRI MANGALAM BUILDCON NOW KNOWN AS SHRI MANGALAM
BUILDCON (I) PVT. LTD.
Versus
EXECUTIVE ENGINEER, PANCHAYAT ROAD AND BUILDING DIVISION
==========================================================
Appearance:
MR NL RAMNANI(2400) for the Petitioner(s) No. 1
MR HS MUNSHAW(495) for the Respondent(s) No. 1
==========================================================
CORAM:HONOURABLE THE CHIEF JUSTICE MR. JUSTICE
ARAVIND KUMAR
Date : 04/02/2022
ORAL ORDER
1. Heard. Petitioner is a registered
Partnership Firm having registration of AA Class
Contractor and it is duly registered with the R & B
Department, Surat, in Special Category-I and is
engaged in construction of bridges and has earned
reputation in the field of construction since last
many years. After having successfully and
satisfactorily completed various works, participated
in the tender bid invited by the respondent on
11.11.2016 for the construction of major bridge
across river Anas on Tanda Bhavani Mandir to Anas
river M.P. Border Road at Taluka and District Dahod.
The estimated cost of the tender was
C/IAAP/119/2020 ORDER DATED: 04/02/2022
Rs.15,88,57,799.11 as against which the petitioner
quoted Rs.13,03,38,173.80 and petitioner's bid being
lowest, contract was awarded and works order came to
be issued on 11.11.2016 and after completing all the
formalities including furnishing of security deposit
in the form of fixed deposit receipt, the work was
commenced and completed within the original time
limit fixed, resulting in Completion Certificate
being issued to the said effect by the competent
authority. As against total running bills submitted,
an amount of Rs.24,02,873/- was due and payable by
respondent which came to be demanded by the
petitioner and same has not been paid. Hence,
petitioner got issued a legal notice on 05.11.2020
calling upon the respondents to appoint an Arbitrator
for resolving the dispute arising under the subject
contract as mentioned in Clause 30 of the Agreement.
No reply was received. Hence, present petitioner has
been filed.
2. Respondent on being notified has filed the
reply denying the averments made in the petition
except to the extent expressly admitted thereunder.
C/IAAP/119/2020 ORDER DATED: 04/02/2022
3. Having heard Shri Narendra Ramnani, learned
counsel appearing for petitioner and Shri
H.S.Munshaw, learned advocate appearing for the
respondent, this Court is of the view that only
question that would arise is :
Whether petitioner is entitled to seek
for appointment of a sole Arbitrator ?
4. Having heard learned advocates appearing
for the parties and on perusal of the subject
contract, it would emerge therefrom that under clause
30, parties are at ad-idem on the issue of resolving
the disputes arising out of contract by alternative
dispute redressal mechanism namely arbitration.
Clause 30 reads thus :
"Clause 30 (1): Disputes to be referred to Tribunal:
The disputes relating to this contract, so far as they relate to any of the following matters, whether such dispute arise during the progress of the work or after the completion of abandonment thereof, shall be referred to the Arbitration Tribunal, Gujarat State."
5. It is the primary contention of Mr.Munshaw,
learned advocate appearing for the respondent that
C/IAAP/119/2020 ORDER DATED: 04/02/2022
under the contract dispute has been agreed to be
resolved through Arbitration Tribunal, Gujarat State
and as such parties may be relegated to the said
redressal mechanism. However, learned counsel
appearing for petitioner would vehemently oppose the
same. He would rely upon the judgment of the
coordinate Bench rendered in I.A.A.P. No.64 of 2015
disposed of on 22.01.2016 whereunder this Court
having considered similar contention was of the view
that Amreli District Panchayat is not a notified
authority in terms of clause (k) of sub-section (1)
of Section 2 of the Gujarat Public Works Contracts
Disputes Arbitration Tribunal Act, 1992, which
defines the term 'works contract'. In the teeth of
the said provision, it cannot be gainsaid by the
respondent in the instant case that arbitration
contract would mean a contract made by the State
Government or the public undertaking with any other
person for execution of any of its work relating to
construction, repair etc. and as such the arbitration
tribunal referred to in Clause 30 supra would be the
authority to adjudicate the dispute.
C/IAAP/119/2020 ORDER DATED: 04/02/2022
6. The contract in question admittedly is
entrusted to petitioner by the District Panchayat of
Dahod and not by the State Government. When there is
no privity of contract between petitioner and the
government and the contract is between petitioner and
Dahod Panchayat, this Court is of the considered view
that contention raised by Mr.Munshaw cannot be
accepted. Hence, rejecting said contention, I proceed
to pass the following :
ORDER
(i) Petition is allowed.
(ii) Shri Virendra Balwantrai Barot, retired District Judge, is hereby appointed as the sole Arbitrator to resolve the disputes between the parties in accordance with the Arbitration Centre (Domestic and International), High Court of Gujarat Rules, 2021. Both Parties would be governed by said Rules.
(iii) Registry to communicate this order to the sole Arbitrator forthwith by Speed Post.
(ARAVIND KUMAR, CJ) GAURAV J THAKER
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!