Thursday, 14, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

State Of Gujarat vs Ghanshyam R Patel
2021 Latest Caselaw 3261 Guj

Citation : 2021 Latest Caselaw 3261 Guj
Judgement Date : 25 February, 2021

Gujarat High Court
State Of Gujarat vs Ghanshyam R Patel on 25 February, 2021
Bench: A. P. Thaker
        C/FA/1400/1996                                        JUDGMENT



       IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

                  R/FIRST APPEAL NO. 1400 of 1996


FOR APPROVAL AND SIGNATURE:


HONOURABLE DR. JUSTICE A. P. THAKER

==========================================================

1    Whether Reporters of Local Papers may be allowed                    No
     to see the judgment ?

2    To be referred to the Reporter or not ?                             Yes

3    Whether their Lordships wish to see the fair copy                   No
     of the judgment ?

4    Whether this case involves a substantial question                   No
     of law as to the interpretation of the Constitution
     of India or any order made thereunder ?

==========================================================
                         STATE OF GUJARAT & 1 other(s)
                                   Versus
                            GHANSHYAM R PATEL
==========================================================
Appearance:
MR. SOAHAM JOSHI, AGP (1) for the Appellant(s) No. 1,2
MR BS PATEL(602) for the Defendant(s) No. 1
MRS RANJAN B PATEL(646) for the Defendant(s) No. 1
==========================================================

 CORAM: HONOURABLE DR. JUSTICE A. P. THAKER

                              Date : 25/02/2021

                              ORAL JUDGMENT

1. Being aggrieved and dissatisfied with the judgment and decree passed by the learned Civil Judge (S.D.), Valsad on 16.12.1995 in Special Civil Suit No.16 of 1989, the defendant has preferred this Appeal under Section 96 of the Civil Procedure Code.

C/FA/1400/1996 JUDGMENT

2. For brevity and convenience the parties are referred to herein as per their status before the trial Court.

3. The defendant has contended that the learned trial Judge has erred in holding that non­carrying out of work of Pump house amounts to breach of contract committed by the department. It is stated that even without the Pump house, the plaintiff could have carried out the other items in the contract in the absence of pump house. It is also contended that the plaintiff had not completed the work of fish Farm for which the site was provided within the stipulated time. It is also contended that the learned trial Court has erred in holding that the work of rolling and watering was to be carried out by the department. It is further contended that as per the terms of the agreement, the plaintiff was to carry out the work of watering and consolidation. It is also contended that the trial Court has committed error in holding that the department could not have imposed penalty under clauses 2 and 3 as well as holding that the time was not the essence of the contract.

3.1 It is also submitted that error has been committed by the learned trial Court in holding that the department has failed to prove that the plaintiff did not complete the work within the stipulated period due to its own fault. It is the contention of the defendant that the learned trial Court has not properly interpreted Exh­55 letter dated 4.1.1988 written by the plaintiff, which clearly indicates that the Contractor has

C/FA/1400/1996 JUDGMENT

abandoned the work and, therefore, he is not entitled to any damage. The defendant has also stated that the observation of the learned trial Court regarding entitlement of the plaintiff to the tune of Rs.1,04,905/­ towards overstay and overhead account as well as Rs.52,000/­on account of loss of profit and Rs. 2 lakhs towards work done and not paid as well as awarding interest at the rat of 15% to the plaintiff. According to the defendant, the learned trial Court has failed to appreciate that the plaintiff itself has committed breach of the contract by not completing the work within stipulate period mentioned in the contract agreement and, therefore, he is not entitled to any compensation. According to the defendant, the learned trial Court ought to have held that that the plaintiff has abandoned the work as per letter Exh­

55.

3.2 It is further contended that the learned trial Court has failed to appreciate that Section 13 of the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 puts a bar on the Civil Court to deal with or decide any question, which the Tribunal is empowered to deal with and decided uner the said Act. It is contended that the learned trial Court has committed jurisdiction error as well as did not appreciate oral as well as documentary evidence in proper perspective and wrongly passed the impugned judgment and decree in favour of the plaintiff and against the defendant.

4. Heard Mr. Soaham Joshi, learned AGP for the Appellant and

C/FA/1400/1996 JUDGMENT

Mr. B.S.Patel, learned Senior Counsel with Mr. C.B. Patel, learned advocate for the respondent­original plaintiff through video­conferencing.

5. Mr. Joshi, learned AGP has vehemently submitted the same facts which are narrated in the Appeal memo. While referring to the oral evidence on record, he has submitted that there is no dispute as to the execution agreement for carrying out the work in question. He has submitted that the work was to be completed in a stipulate period. However, the plaintiff has not completed the same and has abandoned the work by letter at Exh­55. Mr. Joshi has also submitted that as the plaintiff did not complete the work in stipulated period, the Executive Engineer has issued letter for final measurement and it was carried out. While referring to the original plaint regarding the claim of money on various grounds and the reasons of granting thereof by learned trial court, the learned AGP has submitted that all these facts have not been properly appreciated by the learned trial Court. He has also submitted that the evidence clearly suggest that the breach of contract was made by the plaintiff and the time was essence of the contract. According to Mr. Joshi, learned AGP, as the plaintiff has committed breach of contract, no decree ought to have been passed against the defendant. He has also contended that item­wise programme was to be fixed by the Contractor and not by the defendant department. He has also contended that approach road was to be prepared by the Contractor and he did not do so. Mr. Joshi has also submitted that there was

C/FA/1400/1996 JUDGMENT

no extension of period of contract after 16.11.1986. While referring to the letters by the plaintiff, he has submitted that it does not mean that the defendant has not considered time as an essence of the contract. According to him, the plaintiff has abandoned the contract by stoppage of the work.

5.1 Mr. Joshi, learned AGP has further submitted that the entire judgment of the trial Court is based on assumption and presumption and there is over­riding of the claim as the claim was overhead charges and expectation of loss of profit is already covered in other heads. According to him, even if it is believed that he is entitled to damages for overhead and overstay then there cannot be such amount granted for the entire period of contract. Learned AGP has also submitted that for arriving at decision on Claim 4, the learned trial Court has made guess work, which cannot be resorted to for granting damages. According to him, there must be some cogent and convincing evidence for granting damages. He has also submitted that the claim Nos. 6 and 7 would go hand to hand and there cannot be any separate damages for over head charges and expected loss of profit. He has also submitted that the learned trial Court has not framed issue on the ground of abandonment of the Contract and without framing of such issue burden has been shifted on the shoulders of the defendant­department. He has also submitted that there is no iota of evidence for awarding Rs. 2 lakhs. The learned trial Court has awarded the same without any basis. He has also contended that the interest component

C/FA/1400/1996 JUDGMENT

of 15% is on higher side. Learned AGP has vehemently submitted that the impugned judgment and decree passed by the learned trial Court is perverse and it requires to be interfered with. He has prayed to allow the present Appeal and set­aside the judgment and decree and pass necessary order for dismissing of the suit of the plaintiff.

6. Mr. B.S. Patel, learned Senior Counsel with Mr. C.B.Patel, learned advocate for the respondent­original plaintiff has vehemently submitted that there is no dispute regarding the execution of the contract between the parties. He has also submitted that the department has not prepared any detailed programme and has not supplied item­wise programme to the plaintiff. While referring to the agreement, he has submitted that as per the clauses of the agreement, such item­wise programme was to be approved by the department. He has also submitted that at the relevant time no item­wise programme was in existence. While referring to the impugned judgment of the trial Court, he has submitted that the trial Court has considered each and every aspect of the matter and has arrived at right conclusion and there is no need of interference by this Court.

6.1 Mr. Patel, learned Senior Counsel has also submitted that it was the duty of the department to provide approach road for carrying out the work but that approach road was not provided by the defendant authority. He has also submitted that there was legitimate expectation of the contractor to

C/FA/1400/1996 JUDGMENT

have profit and cooperation from the department. He has also submitted that can department itself make the allged work without any approach road. He has also submitted that the contractor had applied for extension of time, but, it was not decided by the defendant side though the same was recommended by the local authority to the higher ups. He has also submitted that pending the proposal for extension of contract, the contract was terminated by the department. He has also contended that the finding of the learned trial Court as to whether time was essence of the contract, is proper one and no factual and legal error has been committed by the trial Court. He has also submitted that no measurement sheet has been prepared in presence of the plaintiff by the defendant in the matter. According to him, no such measurement is also produced in the matter.

6.2 Regarding granting of Rs. 2 Lakhs is concerned, Mr. Patel learned Senior Counsel has submitted that the version as has been put up by the plaintiff has not been denied by the defendant since no evidences as to final measurement is produced. He has also submitted that so far as point regarding "overstay" and "overhead" is concerned, the learned trial Court has not committed any error in granting damages. He has also submitted that considering the work contract, rate of interest i.e. 15% is proper. He has also submitted that profit is to be calculated after deduction of all the expenses and, therefore, expenses cannot be treated as a profit. According to him, there is no overlapping for damages for

C/FA/1400/1996 JUDGMENT

"profit" and "overhead" and "overstay". He has also contended that the alleged suit of 1995 filed by the department before other Civil Court has no consequences and pendency thereof cannot affect this Suit filed by the plaintiff.

6.3 Mr. B.S. Patel, learned Senior Counsel has relied upon the decison rendered in case of McDermott International Inc. v. Burn Standard Co. Ltd. and Another, reported in (2006) 11 SCC 181, especially para no. 96, 97 and 98, which read as under:

"96. The arbitrator has noticed that the claim of MII arose only after it has been satisfactorily proved that the invoices in respect of each of these claims were issued and had become due for payment before reference to arbitrator. It furthermore appears that para 23 of the partial award and the claim for compensation on the aforementioned head are not identical. Para 23 of the partial award dealt with the claim in respect of WI­9 to WI­S pipeline laying. So far as para 24 of the said award is concerned, the learned arbitrator noticed the specific invoices issued against Change Order Nos. 2, 3 and 7 relating to delay and disruptions. It is, therefore, in our considered opinion, not correct to contend that the invoice is the only base whereby and where under a claim can be made. There is no legal warrant for the said proposition. A claim can also be made through correspondence or in meetings.

97. A claim for overhead costs resulting in decrease in profit or additional management costs is a claim for damages.

98. An invoice is drawn only in respect of a claim made in terms of the contract. For raising a claim based on breach of

C/FA/1400/1996 JUDGMENT

contract, no invoice is required to be drawn".

6.4 Learned Senior Counsel has also submitted that though the contractor plaintiff has approached the defendant authority for extension of time period of the contract, the same was not decided in time. He has also submitted that the plaintiff has sent notice to the defendant, and therefore, there is no question of any abandonment of contract by the plaintiff. He has contended that for overhead and overstay expenses, 10% is permissible as per the law and the rate of interest prevalent at the time is proper.

7. On perusal of the pleadings before the trial Court, it transpires that the dispute has arise between the parties for non­performance of the contract. According to the plaintiff, he could not complete the work as no item­wise programme and approach road and other ancillary item was provided by the department to carry out the work. It is the case of the plaintiff that he was ready and willing to perform his part of contract and had also sought for extension of time. As alleged by the plaintiff, the local authority had recommended for extension of time but the higher­ups in the department had not decided the same in time and ultimately the higher­ups had directed the plaintiff for stoppage of the work. According to the plaintiff, at the time of execution of contract, he has paid security of Rs.21,420/­ and thereafter remaining amount of Rs. 21,420/­ had also been deducted by the

C/FA/1400/1996 JUDGMENT

Government from the amount of running bills. It is also contended that the contract between the parties create reciprocal contractual obligation and in the present case, the defendant fails to perform their part of contract agreement. The allegations made by the plaintiff is to the effect that the defendant have committed several breaches of the terms and conditions of the agreement. According to the plaintiff, the work of rolling and watering was to be done by the department but the department failed to do so. It is also the case of the plaintiff that approach road for the site was also not made available to the plaintiff by the defendant and due to that the plaintiff could not execute the work during monsoon season. It is further the case of the plaintiff that the Pump house work was to be carried out by the department which they did not do so. He has also alleged that there was shortage of funds and the department failed to make payment regularly to the plaintiff. It is also contended that the department has illegally imposed penalty under Clause 2 and 3 of the agreement and impliedly terminated the contract illegally. The plaintiff has contended that due to the breach committed by the department, he has suffered damages on various accounts. The plaintiff has claimed Rs. 4,49,256/­ on account of work done not paid, Rs.50,000/­ on account of saving in tender quantity, Rs.42,840/­ in form of security deposit, Rs.1,04,905/­ in the form of overstay and overhead, Rs. 25,000/­ towards the price of the materials at site, Rs.65,000/­ on account of extra items of gate, Rs.1,20,000/­ towards the loss of profit and Rs. 32,137/­ on account of

C/FA/1400/1996 JUDGMENT

interest and damages and thus in all Rs.8,89,138/­ with interest at the rate of 18% per annum and the costs of the suit.

8. The suit has been resisted by the defendant by filing Written statement wherein it has accepted the execution of agreement between the parties and entrustment of the work to the plaintiff. But it has been alleged that the work was to be completed within 18 months and as contract was executed on 17.5.1985 which was to be completed on 16.11.1986. However, during this period, the plaintiff did not complete the work. The defendant has also raised the contention that the work of rolling and watering was to be done by the plaintiff and the approach road was not to be made available by the department as the plaintiff himself had visited the site before placing the tender. According to the defendant, they had given ground level to the plaintiff and on the basis of that level and working plan, the plaintiff was in a position to calculate the top level of the farm. It is also alleged that the plaintiff had to execute so many items of the contract agreement which had no relevancy with the pump house. According to the defendant, as per the terms and conditions of the agreement, the item­wise programme was to be prepared by the Contractor which was to be approved by the department but no such exercise was carried out by the Contractor. It is further contended by the defendant that progress of the work was very slow and the work executed by

C/FA/1400/1996 JUDGMENT

the plaintiff was also defective and inspite of instruction given by the department, the plaintiff failed to improve the defective work. It is further contended that the plaintiff could not complete the work in stipulated time due to their own fault and, therefore, the department has exercised its right under Clauses 2 and 3 of the Agreement. It is also contended that the action on the part of the department for terminating the contract is legal and valid and the plaintiff is not entitled to get any relief in form of security deposit or any other amount as being claimed.

9. On the basis of the pleading of both the parties, learned trial Court has framed the following issues:

1) Whether the plff proves that it could not complete the work within stipulated period due to breaches committed by the deft?

2) Whether the plff proves that the deft's action of levying the compensation is illegal?

3) Whether the plff proves that its contract agreement is illegally terminated by the defts?

4) Whether the plff proves that it is entitled to recover Rs.8,89,138/­ from the deft?

5) Whether the plff is entitled to get interest? Yes, at what rate?

     6)      What is due to the plff?

     7)      What order and decree?






         C/FA/1400/1996                                JUDGMENT




10. It appears from the record that after perusal of the pleadings of the parties as well as oral and documentary evidence produced by both the sides and after hearing both the sides, the learned trial Court has answered the aforesaid issues as under:

      1)     In the affirmative.

      2)     In the affirmative.

      3)     In the affirmative.

      4)     Rs.3,90,406/­.

      5)     Yes, 15% simple interest.

      6)     Rs.3,90,406/­.

      7)     As per final order.

11. The following points arise for determination of the present Appeal:

1) Whether the observation of the trial Court that breach of contract has been committed by the defendant is proper?

2) Whether the contract agreement has been illegally terminated by the defendant?

3) Whether the trial Court has committed error of facts and law in awarding Rs.3,90,406/­ as compensation?

4) Whether the trial Court has committed any error in granting interest at the rate of 15% ?

      5)     What order and decree?






         C/FA/1400/1996                                  JUDGMENT




12. My findings on the above points, for the reasons given below, are as under:

      1)     In the affirmative.

      2)     In the affirmative.

      3)     Partly in affirmative.

      4)     In the affirmative.

      5)     As per final order.


                               REASONS


13. Since all the issues are inter­connected, instead of discussing point wise, all are discussed herewith together.

14. It is admitted fact that the plaintiff has not challenged the impugned judgment and decree though his suit is partly allowed and no damages is allowed (i) on account of saving in tender quantity; (ii) claim on account of extra item and

(iii) claim on account of material on site. Thus, the decision of the learned trial Court on this count is accepted by the original plaintiff.

15. At this stage, it is pertinent to note that one of the grounds raised in the Appeal by the defendant regarding availability of the remedy under the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 is concerned, the

C/FA/1400/1996 JUDGMENT

same is not applicable in the present case. Admittedly, the said tribunal Act has come into existence in the year 1992 whereas the agreement to execute the work in the present matter is of 1985 and the Suit has been filed in the year 1989. Therefore, when the Suit was filed, there was no such tribunal in existence.

16. On perusal of the impugned Judgment and decree, the particulars regarding item­wise relief of amount by the plaintiff coupled with the facts of granting amount on those heads may be shown in the tabular form as under:

      Item                 Amount claimed       by Amount awarded                      by
                           the plaintiff           the trial Court
      Claim on account                 Rs.50,000.00                                   Nil
      of   saving     in
      tender quantity
      Claim on account                 Rs.42,840.00                   Rs.17,751.00
      of       security
      deposit
      Claim on account              Rs.1,04,905.00                 Rs.1,04,905.00
      of overstay and
      overhead
      Claim on account                 Rs.65,000.00                                   Nil
      of extra item
      Claim on account              Rs.1,20,000.00                   Rs.52,734.30
      of expected loss
      of profit
      On account of                    Rs.25,000.00                                   Nil
      material on site
      On account of                 Rs.4,49,256.00                Rs. 2,00,000.00
      what work done
      but not paid





         C/FA/1400/1996                                     JUDGMENT



      On account         of             Rs32,137.00                   Rs.15015.70
      interest           as
      damages
                                Total:8,89,138.00             Total:3,90,406.00


17. On perusal of the Record and Proceedings of the suit it appears that the plaintiff Ghanshyambhai R. Patel has examined himself at Exh­44 and he has also produced certain documents at Exh­45, 46, 49 to 68. Whereas defendant has examined one Shri Shankerbhai Khemabhai Patel at Exh­91. The defendant has produced the documentary evidence at Exh­74 to 83. On perusal of the entire evidence on record, it transpires that in view of the pleadings the issue as to who has breached the contract is involved in the matter. Now, it is alleged by the plaintiff that defendant has committed breach of contract and, therefore, it was for the plaintiff to prove this fact. It appears from the record that the plaintiff has categorically stated in his deposition that burden lies on the plaintiff to prove this fact. At the same time, the defendant has also contended that the plaintiff has committed breach of contract. In view of this fact, on perusal of the evidence on record, it transpires that essentially work for Pump House Bore was to be carried out by the department. But it has failed to carry out the same work within the period of contract and, therefore, the plaintiff failed to complete the said work.

18. The other dispute is regarding the item wise programme.

C/FA/1400/1996 JUDGMENT

Both the sides have contended that the other side had to provide the item­wise programme. Now, in view of the pleadings of the parties, essentially WS of the defendant at Exh­14, there is acceptance on the part of the defendant­ department that no item­wise programme had been given by the department to the plaintiff. This fact is also narrated by the witness Shankarlal in his deposition and also during his cross­examination that no item­wise programme was provided to him by the department is established. However, according to the defendant as per Clause 2 of the tender agreement, the item­wise programme was to be fixed by the contractor and the department had to approve such item­wise programme. At this stage, it is worthwhile to note that as per Clause­2 of the Tender Agreement Exh­50, it is mentioned that in the event if the contractor failed to comply that condition, then he shall be liable to pay as compensation the amount equivalent to 1% of such smaller amount as the Superintendent Engineer may decide of the said estimated cost of the whole work for everyday with due quantity of the work remained incomplete. It also appears from the Schedule­B at Page­59 which provides that the quantity item­ wise and this quantity are to be bifurcated into the work to be carried on day­to­day so that on its work it can be compared with the work done actually on site and any incomplete un­ executed quantity in that particular item on the site. It can be compared and linked with clause­2 for working out insufficient quantity compared with the item­wise programme to be provided. Thus, it is crystal clear that it was for the

C/FA/1400/1996 JUDGMENT

department to provide item­wise programme to the plaintiff. Therefore, non preparing item­wise programme and not approving and supplying to the contract, the item­wise programme by the department, is the fault of the department. Under this circumstance, the department is at fault and this fact has directly affected the execution of the contract agreement. Therefore, there was breach of contract of the department.

19. Regarding the work of rolling and watering is concerned, it is alleged by the plaintiff that work of rolling and watering was to be carried out by the department. Whereas it is submission of the defendant department that same work was to be carried out by the plaintiff. Now, on perusal of the evidence on record which includes letters written by the plaintiff dated 17.2.1986, 14.11.1986, 14.4.1987, 4.1.1988, etc. (Exh­52, 62, 63 and 55) for non­supplying of roller and tanker at the relevant time and when this fact has not been controverted by the defendant the version of the plaintiff could be believed. However, it appears that the defendant­ department has first time raised such contention in their pleadings. It is admission on the part of witness of the department (Exh­91) that rolling and watering in respect of the work of Item No.3 was to be carried out by the department. Thus, on this count also the department has committed breach of contract agreement.

20. So far as the dispute regarding approach road is concerned, it

C/FA/1400/1996 JUDGMENT

appears that there is no provision made in the tender agreement regarding the approach road. However, considering the contract, it is on the part of the department to provide approach road to the plaintiff, but, so far as the internal road is concerned, it was for the plaintiff to carry out the same. Considering the evidence on record, it is clearly evident that due to non­providing of approach road the plaintiff could not execute the work in monsoon season.

21. So far as the pont of shortage of funds is concerned, it appears from the oral as well as documentary evidence which consist of letters (Exh­55, 56, 64 and 67) written by the plaintiff to the department, it clearly appears that the defendant failed to make the payment of the work done by him. Thus, the department has failed to make payment regularly and due to that reason the plaintiff could not complete the work within time.

22. It is pertinent to note that there is also dispute regarding providing design and drawing by the defendant to the plaintiff. It appears especially from Clause 13 of the Agreement which provides that defendant ­ department was bound to supply three sets of the work drawings, etc. to the contractor i.e. plaintiff free of cost along with work order. It also appears from the record that the plaintiff has written many letters to the department, however, it appears that in those letters the plaintiff has not raised the point regarding non­supply of design and drawing. It also appears that the

C/FA/1400/1996 JUDGMENT

plaintiff has carried out work as per the contract. It shows that he has with him the drawings and design otherwise, he might not have carried out any work as per the contract. Therefore, the point of providing of design and drawing by the defendant is not established by the plaintiff by leading cogent evidence.

23. It also appears from the record that there was dispute regarding the top level of the farm and the plaintiff has alleged that the same was not given to the plaintiff for executing the work and it is admitted by the defendant in its W.S. that ground level of the farm had already been given by the department to the plaintiff and the plaintiff could easily calculate the top level by adding necessary levels given in the plan, drawings, etc. Now the plaintiff's witness has admitted in his cross­examination at Exh­44 that the department had given ground level of the farm to him and on that basis the plaintiff was in a position to know the top level of the farm. Now, as per the provisions of tender agreement the department has to record the level in the Field Book day­to­ day during the execution of the work. Now, no such Field Book has been produced in the present case though written notice was issued by the plaintiff to the defendant for producing the said Field Book. Considering this ground and other grounds as discussed hereinabove, this point is also one of the reasons for breach of contract.

24. The main contention raised by the defendant in this matter is

C/FA/1400/1996 JUDGMENT

regarding that the time was essence of the contract. At this stage it is worthwhile to refer to the decision of the Hon'ble Apex Court in case of M/s. Hind Construction Contractors v. State of Maharashtra, reported in AIR 1979 SC 720 has specifically observed in Para­7 and 8 that the question whether or not time was essence of contract would essentially be a question of the intention of the parties to be gathered from the terms of the contract. Even where the parties have provided that time is essence of the contract, such a stipulation have to be read along with other provisions of the contract and such other provisions may, on the construction of the contract, exclude the inference that the completion of the work by a particular date was intended to be fundamental, for instance, if the contract were to include clause provided for extension of time in certain contingency or for payment of fine or penalty for every day or week the work undertaken remains unfinished on the expiry of the time provided in the contract such clauses would be construed as rendering ineffective the express provision relating to the time being of the essence of contract.

25. But now considering the decision of the Hon'ble Supreme Court to the effect when there is provision in the Contract agreement regarding extension of time then it would be not a case that time was essence of the contract. In the present case, considering the facts and circumstances and documentary evidence on record, especially contract agreement, it is crystal clear that time was not the essence of

C/FA/1400/1996 JUDGMENT

the contract. It also appears from the record that due to breach of contract by the defendant, the plaintiff could not execute the work. It also appears from the record that the plaintiff has not avoided the work rather than the defendant has directed stoppage of work and has prepared the final measurement.

26. Now, considering the evidence on record and discussion made by the learned Judge awarding the compensation as referred to hereinabove on various counts, it appears that the learned trial Court has committed serious error of facts and law in granting Rs.1,04,905/­ under the head of "overstay" and "overhead". The trial court has calculated the said amount for the entire period of contract. In the considered opinion of this court, no such amount for entire stipulated period and thereafter on extra time would be available to the plaintiff. The damages for the overhead and overstay is permissible only for the period after expiration of the stipulated period of the contract. Now, in this matter the stipulated period for completing the contract was of 18 months, therefore, for the duration of stipulated period no damages on account of overhead and overstay is permissible. As such, on this count only amount for 1 and 1/2 months could be awarded to the plaintiff. For calculating the damages on this count, the formula adopted by the learned trial Court for granting overhead and overstay at the rate of 5,400 per month is proper. Therefore, the amount for 1 and 1/2 month would come to Rs.8,100/­ Thus, the learned trial

C/FA/1400/1996 JUDGMENT

Court has committed serious error of facts and law in granting the amount of Rs.1,04,905/­ for overhead and overstay. The plaintiff contractor is only entitled to get Rs.8,100/­ under this head. Therefore, the amount of compensation is required to be reduced on this count.

27. On perusal of the entire material on record, it clearly appears that the learned trial Court has considered the evidence on record in proper perspective and has not committed any serious error of facts and law in awarding Rs.52,734.30 ps for expected loss of profit and on account of interest on damages Rs.15,015.70 ps, Rs.17,751.00 for Security deposit and Rs.2,00,000/­ on account of work done but not paid. However, the learned trial Court has committed error of fact and law in granting Rs.1,04,905/­ for overhead and overstay. The excess amount on the count of "overhead" and "overstay" needs to be modified. Therefore, the amount awarded by the learned trial Court is required to be modified to the following extent:

      Claim Particulars          Amount of claim Amount of claim
                                 granted by trial granted by this
                                 Court            Court
      Claim On account of           Rs.2,00,000.00        Rs.2,00,000.00
      No.1 work done but
            not paid
      Claim On account of                       Nil                           Nil
      No.2 saving in tender
            quantity
      Claim Towards security            Rs.17751.00               17,751.00
      No.3 deposit





         C/FA/1400/1996                                       JUDGMENT



      Claim On account of            Rs.1,04,905.00                    8100.00
      No.4 overhead   and
            overstay
      Claim On account of                         Nil                           Nil
      No.5 material on site
      Claim On account         of                 Nil                           Nil
      No.6 extra items         of
            iron gates
      Claim On account of               Rs.52,734.30                52734.30
      No.7 expected loss of
            profits
      Claim On account of               Rs.15,015.70                15,015.70
      No.8 interest    as
            damages
                                               Total:
                                         3,90,406.00             2,93,601.00

28. Regarding awarding of interest is concerned, at the relevant point of time, it is contention of the plaintiff that it was the general practice of granting interest at the rate of 15% was in existence. However, considering the facts of the case, the interest granted by the learned trial Court at the rate of 15% is on higher side which is required to be modified to the extent that the plaintiff is entitled to get interest at the rate of 12% simple interest from the date of filing of the suit till the date of filing of the appeal and after filing of this appeal, the rate of interest would be 9% till realisation of the amount. At the same time the direction of releasing of deposit of Rs.22,000/­ does not warrant any interference.

29. In view of the aforesaid reasoning, the judgment and decree passed by learned Civil Judge (S.D.), Valsad on 16.12.1995 in

C/FA/1400/1996 JUDGMENT

Special Civil Suit No.16 of 1989 is hereby modified to the extent that plaintiff is entitled to recover Rs.2,93,601/­ instead of Rs. 3,90,406/­ with the interest at the rate of 12% simple interest from the date of filing of the Suit till the date of filing of the Appeal and thereafter rate of interest would be 9% from the filing of the Appeal till realisation of the amount. The direction to release deposit of Rs.22,000/­ is hereby confirmed. No order as to costs. Decree to be drawn in this Appeal accordingly.

30. Registry to send R&P to the learned trial Court along with a copy of this judgment as well as decree forthwith.

(DR. A. P. THAKER, J) SAJ GEORGE

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter