Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S First Carbon Techologies Pvt ... vs State Of Gujarat
2021 Latest Caselaw 1438 Guj

Citation : 2021 Latest Caselaw 1438 Guj
Judgement Date : 1 February, 2021

Gujarat High Court
M/S First Carbon Techologies Pvt ... vs State Of Gujarat on 1 February, 2021
Bench: Vipul M. Pancholi
        C/SCA/3238/2011                                       CAV JUDGMENT




            IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

             R/SPECIAL CIVIL APPLICATION NO. 3238 of 2011
                                 With
    CIVIL APPLICATION (FOR VACATING INTERIM RELIEF) NO. 1 of 2020
            In R/SPECIAL CIVIL APPLICATION NO. 3238 of 2011

FOR APPROVAL AND SIGNATURE:

HONOURABLE MR. JUSTICE VIPUL M. PANCHOLI
==========================================================

1 Whether Reporters of Local Papers may be allowed to No see the judgment ?

2 To be referred to the Reporter or not ? No

3 Whether their Lordships wish to see the fair copy of the No judgment ?

4 Whether this case involves a substantial question of law No as to the interpretation of the Constitution of India or any order made thereunder ?

========================================================== M/S FIRST CARBON TECHOLOGIES PVT LTD Versus STATE OF GUJARAT & 3 other(s) ========================================================== Appearance:

MR PERCY C KAVINA, SENIOR ADVOCATE WITH MR NV GANDHI(1693)

MR RONAK RAVAL, ASSISTANT GOVERNMENT PLEADER(1) for the

MR SN SHELAT, SENIOR ADVOCATE WITH MR RD DAVE(264) for the Respondent(s) No. 2,3,4 ========================================================== CORAM: HONOURABLE MR. JUSTICE VIPUL M. PANCHOLI

Date : 1/02/2021

CAV JUDGMENT

1. In this petition, which is filed under Article 226 of the Constitution of India, the petitioner has prayed for the following reliefs:

"a) THIS HON'BLE COURT be pleased to issue writ of declaration or writ in the nature of declaration or any appropriate writ, order or direction holding and declaring that the Respondents are not entitle to withdraw 25% concessions granted towards total consideration for Plot No.D­II/12A, D­ II/12, D­II/13 & D­II/4 Dahej­II Industrial Estate;

b) THIS HON'BLE COURT be pleased to issue writ of declaration or writ in the nature of declaration or any appropriate writ, order or direction directing the Respondents to issue separate agreements for each plots without insisting payment of 25% concession granted earlier towards total considerations of the said plots;

c) THIS HON'BLE COURT be pleased to issue writ of declaration or writ in the nature of declaration or any appropriate writ, order or directions directing the Respondents to consider and grant 40 quarterly installments on balance consideration of the said plots after deducting an amount of concession of 25%, with two years moratorium including payment of interest in eight quarterly installments instead of 12 nos. and be further pleased to direct to extend the period of payment of balance amount;

d) THIS HON'BLE COURT be pleased to issue writ of declaration or writ in the nature of declaration or any appropriate writ, order or directions quashing and setting aside the Notice dated 25.11.2010 under Section 4(1) of the Gujarat Public Premises (Eviction of Unauthorized Occupants) Act, 1972 issued by Respondent No.4 - Competent Officer and Regional Manager of Respondent No.2;

e) That pending hearing and final disposal of this petition this Hon'ble Court may be

pleased to stay the operation and implementation of notice dtd. 25.11.2010 at Annexure­AA to this petition and be further pleased to restrain the Respondent from pursuing demand of Rs.23,71,69,645/­ within 3 days made vide letter dtd. 4.03.2011.

f) THIS HON'BLE COURT be pleased to grant ad­ interim relief in terms of aforesaid para­ e;

ff) THIS HON'BLE COURT be pleased to issue writ of declaration or writ in the nature of declaration or any appropriate writ, order or directions and be pleased to direct the Resp.­G.I.D.C. to calculate outstanding amount payable by the petitioner under the said OTS scheme dtd. 19.06.2020 (Annex.­ FF), and be further pleased to direct the Resp.­ G.I.D.C. to accept the same within 30 days from the date of such acceptance."

2. Factual matrix of the case is as under:

2.1 The petitioner is a Company incorporated and registered under the provisions of the Companies Act, 1956. The petitioner was intending to develop an import based industry at Vadadala, Taluka Wagra, District: Bharuch. For the said project, the petitioner through its associate firm purchased some land at Vadadala and has started construction of first phase. For the various projects stated in the memo of the petition with regard to the manufacturing of COKONYX, Board of Directors of the petitioner Company have signed Memorandum of Understanding on 12/13.01.2009 with Government of Gujarat in Vibrant­2009. The petitioner applied for

allotment of the lands in GIDC at Dahej vide application dated 02.04.2009. Pursuant to the said application, respondent No.4 gave offer­ cum­allotment letter to the petitioner. As per condition No.2 of such offer, the petitioner Company was required to send offer amount, form of agreement and acceptance­cum­undertaking within a period of 30 days from the date of receipt of the said letter. The petitioner Company was required to make upfront payment of Rs.13,18,56,400/­ being 30% of the total price of the land and balance amount of Rs.30,76,69,600/­ being 70% balance capital within 12 quarterly installments with 12.5% rate of interest and further required to pay 1% administrative charges on the said balance capital of 70% in form of Demand Draft in favour of respondent No.2­GIDC. In the said letter, other terms and conditions are also set out. As per the Policy of the respondents, 25% concession was required to be given on the land price and, therefore, the petitioner was required to pay total amount of Rs.43,95,28,000/­ as per the calculation.

2.2 It is stated that in response to the said offer­ cum­allotment letter dated 19.06.2009, the petitioner had given counter offer vide letter dated 18.07.2009 whereby the petitioner has requested for quarterly installments of balance amount in 40 numbers with 2 years moratorium

including payment of interest in 8 quarterly installments instead of 12 quarterly installments. The petitioner Company also requested for 10% down payment instead of 30%. It has also requested for additional time to pay the down payment. It is stated that the said offer was not acceptable to respondent No.4. Hence, vide letter dated 01.09.2009, the petitioner Company had given counter proposal for the allotment of plots in question. Respondent No.2 has therefore vide letter dated 02.09.2009 had given fresh offer­cum­allotment to the petitioner along with form of agreement in triplicate on the similar terms and conditions mentioned in offer letter dated 19.06.2009. It is further stated that the petitioner Company had paid down payment of Rs.4,12,66,500/­ and Rs.30,76,697/­ towards administrative charges. Thereafter, the petitioner had paid an amount of Rs.9,05,91,900/­ towards down payment. Thereafter, the petitioner has requested to reshape the said plots considering their requirement to establish 4 modules as per plan. Once again request was made to respondent No.2 for 10% down payment instead of 30% and to grant 40 installments with 2 years moratorium including payment of interest in 8 quarterly installments instead of 12 and also requested for additional time to pay the outstanding amount. Thereafter, various correspondences were

exchanged between the parties with regard to the payment of amount in question. The petitioner was asked to pay balance capital of 12 postdated cheques in favour of respondent No.2. Thereafter, respondent No.2 had given possession receipts of the plots vide letter dated 30.03.2010. The petitioner requested to give separate agreement for each of the plots.

2.3 It is stated that the petitioner Company intends to invest huge amount and at the time of taking possession of the plots in question approximately Rs.18 crores was paid and, thereafter, as per the case of the petitioner, purchase orders were issued and construction was carried out in the portion of the land in question.

2.4 It is further stated that respondent No.4 vide letter dated 08.06.2010 has intimated the decision taken in Board meeting dated 07.04.2010 withdrawing concession of 25% granted to the land price of industrial plots in large industrial estate like the petitioner and issued corrigendum order withdrawing rebate at 5% on cost of plot, the details of which are stated in the memo of the petition. The petitioner, therefore, vide communication dated 14.06.2010 made representation to the State Government to review the decision of respondent No.2­GIDC withdrawing 25% concession and pass necessary

direction to revive the same. Once again, on 19.07.2010, the petitioner has explained its difficulties and requested for reviewing the decision on 25% concession, separate agreement of each plot and additional time for repayment. It is also stated that the petitioner Company has thereafter instructed its Bank to stop the payment of cheques issued by the petitioner in favour of the respondent GIDC. Once again, various correspondences were exchanged between the parties.

2.5 It is the grievance of the petitioner that the respondent GIDC issued notice dated 25.11.2020 under Section 4(1) of the Gujarat Public Premises (Eviction of Unauthorised Occupants) Act, 1972 ("the Act" for short) threatening to make an order of eviction under Section 5 of the Act. The petitioner has, therefore, filed the present petition seeking various reliefs.

2.5 This Court has passed an interim order in the present petition on 09.03.2011, which reads as under:

"Heard Mr. Sunit Shah, learned advocate for the petitioner.

He has submitted that at the time when the letter of allotment was issued, condition for payment was that the entire payment must be made in 12 equal installments. The said condition was coupled with the benefit of 25% concession. However, the petitioner

company had requested that the company may be allowed to make the payment in 40 installments instead of 12 equal installments.

In response to the said request, the respondent - Corporation had informed the petitioner company that the 25% concession would stand withdrawn in view of the modified proposal/request by the petitioner company.

Apropos the said difference between the petitioner and the respondent Corporation, learned counsel for the petitioner company has submitted that the petitioner does not insist for 40 installments and is ready to make payment within 12 equal installments, as per the original schedule, if the GIDC also continues the original proposition of granting 25% concession in the price of land. He further submitted that in view of the fact that the respondent - GIDC has conveyed its agreement in principal with regard to four separate agreements, the only unresolved issue between the petitioner company and the respondent GIDC is about 25% concession in land price and number of installments. He has submitted hat the petitioner company will make payment within 12 equal installments.

Considering the said submission, issue Notice returnable on 28.3.2011. Direct service is permitted.

            On condition that the        parties will maintain
            status­quo, it is           directed that until
            returnable date, any        steps of evicting the
            petitioner may not be       taken."

2.6 Thereafter, the respondent GIDC filed reply and parties have filed rejoinder and sur­rejoinder.

In the meantime, this Court passed another interim order dated 30.07.2012, which reads as under:

Heard Mr. N.V. Gandhi, learned advocate for the petitioner and Mr. Alkesh N Shah, learned AGP, for respondent no. 1.

1. The issue involved in present petition as raised by the learned counsel for the petitioner is as to whether the respondents is entitled to withdraw the concession which was offered at the time when the contract was executed between the parties.

Learned counsel for the petitioner has relied on the decision passed in case of Kishorkumar Prabhudas Tanna & anr. Vs. State of Gujarat through secretary & Ors., reported in 2009 (1) GLR, 683 and the learned counsel for the respondents has relied on decision dated 22.01.2009 passed by the Division Bench in Special Civil Application No. 22102 of 2007.

In view of the contentions raised by both the parties. Rule.

2. So far as the interim relief is concerned it is necessary to take into account the relief prayed by the petitioner which reads thus:­

a) This Hon'ble Court be pleased to issue writ of declaration or writ in nature of declaration or any appropriate writ, order or direction holding and declaring that the respondents are not entitle to withdraw 25% concessions granted towards the total considerations for Plot No. D­II/12A, D­ II/13 & D­II/4 Dehej­II Industrial Estate:

b) This Hon'ble Court be pleased to issue writ of mandamus or any other appropriate

writ in the nature of mandamus or any other appropriate writ or directions directing the Respondents to issue separate agreements for each plots without insisting payment of 25% concession granted earlier towards total considerations of the said plots;

c) This Hon'ble Court be pleased to issue writ of mandamus or any other appropriate writ in the nature of mandamus or any other appropriate writ or directions directing the Respondents to consider and grant 40 quarterly installments on balance consideration of the said plots after deducting an amount of concession of 25%, with two years moratorium including payment of interest in eight quarterly installments instead of 12 nos. and be further pleased to direct to extend the period of payment of balance amount;

In para 12 (e) the petitioner has prayed for below mentioned relief:­

e) That pending hearing and final disposal of this petition this Hon'ble Court may be pleased to stay the operation and implementation of notice dated 25.11.2010 at Annexure­AA to this petition and be further pleased to restrain the respondent from pursuing demand of Rs. 23,71,69,645/­ within 3 days made vide letter dated 04.03.2011.

3. In this context, it is also necessary to note that on 9th March 2011 the below mentioned order was passed:­

"On condition that the parties will maintain status­quo, it is directed that until returnable date, any steps of evicting the petitioner may not be taken."

4. It is claimed by the learned counsel for the petitioner that the possession of the

plot in question is with the petitioner since long time. It is claimed that actually, the possession of the plot in question with the petitioner was even prior to the date of present petition. It is also claimed that the petitioner has completed substantial construction of manufacturing unit on the plot in question before the impugned decision and also before the petition came to be filed. The said submissions are not disputed by the respondent corporation.

5. In the light of aforesaid statement, it is clear that the possession of the plot is with petitioner before the date on which the petition came to be filed. It is also clear that the order dated 9th March,2011 granted by this Hon'ble court, has been in operation, since about 16 months.

6. Therefore, so far as the petitioner's request for interim relief is concerned, in modification of the said order, it is directed that the petitioner as well as respondent shall maintain status­quo. The petitioner will not alinate or transfer the property in question in any manner whatsoever, and the petitioner will make payment of the entire amount as demanded by the respondents. The allotment, occupancy and possession of the plot in question, in the hands of the petitioner, will be subject to final order passed in this petition. The construction and usage after and pursuant to and during the pendency of this petition will not create any right or equity in favour of the present petitioner.

The order is passed in the light of the petitioner's submission, that contract was executed between the parties and the respondent corporation handed over the plot to the petitioner before the date of impugned decision and before the date on which the petition came to be filed."

2.7 It is further revealed from the record that during the pendency of this petition, the respondent GIDC floated One Time Settlement Scheme on 19.06.2020. Pursuant to the said Scheme, the petitioner vide E­mail dated 11.07.2020 requested the respondent GIDC to unlock their on­line account so that outstanding dues can be known to the petitioner. The petitioner has shown its readiness and willingness to avail benefit of OTS Scheme and to make payment of the outstanding dues. Once again the petitioner shown readiness and willingness to clear outstanding amount as per OTS vide communication dated 06.10.2020. It is the grievance of the petitioner that though such request is made, no reply is given by the respondent GIDC and, therefore, the petitioner requested to allow the draft amendment, which eventually allowed and the petition has been amended. The petitioner has now prayed for further relief that the respondent GIDC be directed to calculate the outstanding amount payable under OTS Scheme and further direction be given to accept the said amount within 30 days from the date of such acceptance.

3. Heard learned Senior Advocate Mr.Percy C. Kavina assisted by learned advocate Mr.N.V. Gandhi appearing for the petitioner, learned Assistant Government Pleader Mr.Ronak Raval for respondent No.1 and learned Senior Advocate Mr.S. N. Shelat assisted by

learned advocate Mr.R.D. Dave appearing for respondent Nos.2 to 4.

4. Learned Senior Advocate Mr.Percy C. Kavina assisted by learned advocate Mr.N.V. Gandhi appearing for the petitioner has mainly contended that once the Policy was framed by the respondents whereby it was decided to give 25% concession on land price and pursuant to which, offer­cum­allotment letter was issued by respondent No.2 to the petitioner, the respondent ought not to have withdrawn the said concession by changing the Policy. Thus, in the present case, principle of promissory estoppel would be applicable. It is urged that the respondent should be estopped from withdrawing the promise given to the petitioner. It is also submitted that on the basis of the said promise given by the respondents, the petitioner has acted and paid the amount of approximately Rs.18 crores and, therefore, possession of the plots in question has been given to the petitioner. The petitioner has carried out construction on the certain portion of the land in question and, therefore, now the notice issued by the respondents under the Act for vacating the premises in question is to be set aside. Learned Senior Advocate would further submit that the petitioner was ready and willing to pay the outstanding amount in 40 quarterly installments as per the counter offer given by the petitioner. However, when no reply was received from the respondents, the petitioner instructed Bank to stop the payment of the postdated

cheques given by the petitioner to the respondents.

4.1 Learned Senior Advocate Mr.Kavina would further contend that even during the pendency of this petition, when OTS Scheme is floated by the respondent GIDC, the petitioner has shown willingness to avail the benefit of the said scheme. However, no reply is given by the respondent GIDC. Even on 18.01.2021, the petitioner has tried to give the cheque to the respondent GIDC. However, said cheque was not accepted. It is, therefore, urged that impugned proceedings initiated under the Act be quashed and set aside and the respondent GIDC be directed to give benefit of OTS to the petitioner.

4.2 Learned Senior Advocate Mr.Kavina has placed reliance upon a decision rendered by the Honourable Supreme Court in the case of Manuelsons Hotels Private Limited Vs. State of Kerala and others reported in 2016(6) SCC 766.

5. On the other hand, learned Senior Advocate Mr.S.N. Shelat appearing for respondent Nos.2 to 4 has vehemently opposed this petition and referred the averments made in the affidavit­in­reply, additional affidavit­cum­sur­rejoinder, further affidavit as well as affidavit­in­rejoinder filed by the respondent in connected Civil Application No.1 of 2020. It is submitted that the petitioner was under an obligation as per Clause­10 of the offer­cum­ allotment letter dated 19.06.2009 to get the building

plans approved by the competent authorities within three months from the date of possession of land, to commence construction work of factory within 12 months and to start commercial production within a period of 3 years from the date of allotment letter. However, the petitioner has intentionally flouted the said conditions. It is submitted that as per the Policy, initially, the concession of 25% was given on the land price and as per offer­cum­allotment letter and Policy, the petitioner was required to make upfront payment of Rs.13,18,58,400/­ being 30% of the total price of the plot and balance amount of Rs.30,76,69,600/­ being 70% balance capital within 12 quarterly installments with 12.5% rate of interest and further required to pay administrative charges on the said balance capital of 70% in form of Demand Draft in favour of GIDC. However, the petitioner requested for quarterly installment of balance payment in 40 installments with 2 years moratorium including payment of interest in 8 quarterly installments instead of 12. The petitioner Company also requested for 10% down payment instead of 30%. The said proposal was not acceptable to the respondent GIDC and, therefore, counter proposal was given. Thus, on one hand, the petitioner is placing reliance upon the Policy of the Government to give 25% concession on land price and on the other hand, the petitioner was not agreeable for the other conditions with regard to the mode of payment.

5.1 It is further submitted that thereafter,

possession of the land in question was given to the petitioner on certain conditions and the petitioner issued postdated cheques in favour of the GIDC. However, in the meantime, before further agreements were executed between the parties, the Government has changed the Policy whereby 25% concession on price of the land was withdrawn. It is thus contended that it cannot be said that on the basis of the promise given by the respondent, the petitioner has acted in accordance with said promise and, thereafter, the respondent has withdrawn the said promise. Thus, the principle of promissory estoppel would not be applicable.

5.2 Learned Senior Advocate Mr.S.N. Shelat has thereafter contended that conduct of the petitioner is also required to be seen by this Court before granting any equitable relief in favour of the petitioner. Learned Senior Advocate has referred the interim order dated 30.07.2012 passed by this Court in the present petition, wherein in Paragraph­6, this Court has directed that the petitioner will not alienate or transfer the property in question in any manner whatsoever and the petitioner will make a payment of the entire amount as demanded by the respondents. It is submitted that though the said order was passed in July, 2012, the petitioner failed to make any payment to the Bank and on the contrary, cheques issued by the petitioner were dishonoured.

5.3 It is submitted that in fact, the present

petition itself is not maintainable and no vested right is created in favour of the petitioner. Even there is no contractual right existed in favour of the petitioner. The petitioner did not execute the lease deed. It is further submitted that if there is a breach of condition of any agreement entered into between the parties, it is always open for the petitioner to file Civil Suit before the competent Civil Court.

5.4 At this stage, learned Senior Advocate Mr.Shelat would further submit that OTS is floated by the respondent GIDC because of COVID­19. It is submitted that as on 31.10.2020, huge amount of Rs.166,88,96,985/­ is outstanding. It is submitted that during the period between 2011­12 to 2020, the respondent GIDC has introduced various OTS schemes. However, at no point of time, the petitioner has applied for OTS. Thus, in fact, the petitioner has no intention to avail such scheme and on the contrary, the petitioner has after getting interim relief in the present petition, has enjoyed the land in question without making any further payment as per the original scheme. It is also pointed out from the record that there are six industrial companies, namely, (1) Adani Power Dahej Ltd., (2) Gujarat State Fertilizer Company, (3) GNFC, (4) SFR Ltd., (5) Alkalies & Chemicals Ltd. and (6) Action Petrochem Pvt. Ltd. were allotted huge industrial plots without any concession like the petitioner and all the said Companies have successfully established their

industries. However, so far as the petitioner is concerned, after getting possession of the huge parcel of land admeasuring 12,45,746 sq. meters, it has not made payment as per the original Policy of the respondents. Thus, it is contended that the petitioner is not entitled to claim any equitable relief from this Court.

5.5 Learned Senior Advocate Mr.Shelat has placed reliance upon the following decisions:

(1) Nidus Enterprises Pvt. Ltd. Vs. State of Gujarat reported in 2014(3) GLH 66 (2) The Rajasthan State Industrial Development and Investment Corporation and Anr. Vs. Diamond and Gem Development Corporation Ltd. and Anr. reported in AIR 2013 SC 1241 (3) Gohil Jesangbhai Raysangbhai Vs. State of Gujarat reported in AIR 2014 SC 3687 (4) Raj Mineral Through Proprietor Sharad L.

Vyas Through POA Vs. State of Gujarat and Ors. reported in 2011(3) GLH 257

6. Having heard learned counsel appearing for the parties and having gone through the material placed on record, it would emerge that the petitioner Company have signed Memorandum of Understanding on 12/13.01.2009 with Government of Gujarat in Vibrant­ 2009. The petitioner applied for allotment of the lands in GIDC at Dahej vide application dated

02.04.2009. Pursuant to the said application, respondent No.4 gave offer­cum­allotment letter to the petitioner. The petitioner Company was required to make upfront payment of Rs.13,18,56,400/­ being 30% of the total price of the land and balance amount of Rs.30,76,69,600/­ being 70% balance capital within 12 quarterly installments with 12.5% rate of interest and further required to pay 1% administrative charges on the said balance capital of 70% in form of Demand Draft in favour of respondent No.2­GIDC. It is the case of the petitioner that as per the Policy of the respondents, 25% concession was required to be given on the land price and, therefore, the petitioner was required to pay total amount of Rs.43,95,28,000/­ as per the calculation. The petitioner thereafter had given counter offer vide letter dated 18.07.2009 whereby the petitioner has requested for quarterly installments of balance amount in 40 numbers with 2 years moratorium including payment of interest in 8 quarterly installments instead of 12 quarterly installments. The petitioner Company also requested for 10% down payment instead of 30% and requested for additional time to pay the down payment. The said proposal was not acceptable to respondent No.4. Further, counter proposal for allotment of plots in question was given by the petitioner. The petitioner has thereafter made certain payments and correspondences were exchanged between the parties with regard to the amount in question. Postdated cheques were also issued by the petitioner and, therefore, respondent No.2 had given possession

receipt of the plots on 30.03.2010. It is the case of the petitioner that approximately Rs.18 crores was paid. However, it is not in dispute that respondent No.4 vide letter dated 08.06.2010 has intimated the decision taken in the Board meeting dated 07.04.2010 withdrawing concession of 25% granted to the land price of industrial plots in large industrial estate like the petitioner. In the present petition, the petitioner has raised contention that the respondents be estopped from withdrawing 25% concession granted on the total land price. It is the case of the petitioner that principle of promissory estoppel would be applicable.

7. It is pertinent to note that as per the original policy, initially, concession of 25% was given on the land price and the petitioner was required to make upfront payment of Rs. 13,18,56,400/­ being 30% of the total price of the land and balance amount of Rs.30,76,69,600/­ being 70% balance capital within 12 quarterly installments with 12.5% rate of interest. In fact, the petitioner was not agreeable for the same and the petitioner made counter proposal and requested for quarterly installments of balance amount in 40 installments with 2 years moratorium including payment of interest in 8 quarterly installments instead of 12. The petitioner also requested for 10% down payment instead of 30%. Thus, it appears that proposal and counter proposals were given by the parties and though possession of the plots in question was given to the petitioner on

30.03.2010, before further agreements were executed between the parties, the Government has changed Policy whereby 25% concession on the price of land was withdrawn in its Board Meeting dated 07.04.2010. Thus, within a period of 7 days after giving possession of the plots in question, policy decision was taken by the respondents for withdrawal of concession of 25% granted to the land price of industrial plots in large industrial estate like the petitioner. Thus, in the facts of the present case, it cannot be said that on the basis of the promise given by the respondents, the petitioner has acted in accordance with the said promise. When the petitioner was not agreeable as per the original policy to make the payment and repeatedly requested for making payment in 40 quarterly installments and to make 10% down payment only instead of 30%, this Court is of the view that the principle of promissory estoppel would not be applicable.

8. In the case of Manuelsons Hotels Private Limited Vs. State of Kerala and others (supra), upon which, reliance is placed by the learned Senior Advocate appearing for the petitioner, the Honourable Supreme Court has held that doctrine of promissory estoppel is a doctrine whose foundation is that an unconscionable departure by one party (i.e. the promisor) from subject­matter of an assumption which may be of fact or law, present or future, and which has been adopted by the other party (i.e. the promisee) as the basis of some course of conduct, act

or omission, should not be allowed to pass muster. It is further held that promissory estoppel can be the basis of an independent cause of action in which detriment does not need to be proved and it is enough that a party has acted upon the representation made. The Honourable Supreme Court has further held that for applying principle of promissory estoppel against the Government, two conditions are required to be satisfied i.e. (i) when it would be unconscionable on the part of Government to get away without fulfilling its promise and (ii) when no other consideration of overwhelming public interest exists in order that Government be justified in resiling from its promise.

Keeping in view the aforesaid decision rendered by the Honourable Supreme Court, if the facts of the present case as discussed hereinabove are examined, this Court is of the view that the aforesaid decision would not be applicable to the facts of the present case. On the contrary, the petitioner was not agreeable as per the original policy of the State Government and, therefore, counter offer was made from time to time and though the possession of the plots in question was given on 30.03.2010 as observed hereinabove, the respondent has taken decision in its Board meeting dated 07.04.2010 to withdraw 25% concession. The said policy was applicable not only to the petitioner but as per the case of the respondents, to various other industrial Companies. It is specifically stated in the reply by the

respondents that there are six industrial companies namely, (1) Adani Power Dahej Ltd., (2) Gujarat State Fertilizer Company, (3) GNFC, (4) SFR Ltd., (5) Alkalies & Chemicals Ltd. and (6) Action Petrochem Pvt. Ltd., who were allotted huge industrial plots without any concession like the petitioner and all the said Companies have successfully established their industries. Thus, when the petitioner has not acted as per the original policy, this Court is of the view that the aforesaid principle of promissory estoppel would not be applicable.

9. I have considered the two interim orders passed by this Court, which are reproduced hereinabove. In para­6 of the order dated 30.07.2012, this Court has specifically observed that the petitioner as well the respondents shall maintain status­quo. The petitioner will not alienate or transfer the property in question in any manner whatsoever and the petitioner will make payment of the entire amount as demanded by the respondents. The allotment, occupancy and possession of the plot in question, in the hands of the petitioner, will be subject to final order passed in this petition. The construction and usage after and pursuant to and during the pendency of this petition will not create any right or equity in favour of the present petitioner.

Thus, from the aforesaid observation, it is clear that the petitioner was required to make payment of the entire amount as demanded by the

respondents. However, it is not in dispute that the petitioner has failed to make any payment even after the order dated 30.07.2012 to the respondents. Thus, while considering the case of the petitioner, conduct of the petitioner is also required to be examined by this Court.

10. Thus, from the record, it appears that though the aforesaid order was passed in the year 2012, the petitioner has not made any payment to the respondents. On the contrary, it is not in dispute that the cheques issued by the petitioner were dishonoured as the petitioner had given instructions to the concerned Bank to stop the payment. Thus, while considering the request of the petitioner, this conduct of the petitioner is also required to be kept in view.

11. The next contention raised by the learned Senior Advocate for the petitioner is with regard to the availment of benefit of OTS Scheme floated by the respondents on 19.06.2020. If the aforesaid policy is carefully examined, it is revealed that because of the condition prevailing in the market pursuant to the COVID­19, OTS Scheme is introduced. As per the reply filed by the respondents, huge amount of Rs.166,88,96,985/­ is outstanding as on 31.10.2020. It is also the specific case of the respondents that during the period between 2011­12 to 2020, the respondent GIDC has introduced various OTS Schemes. However, at no point of time, the petitioner has

applied for the OTS Scheme. Thus, it can be said that the petitioner had no intention to avail the said OTS Scheme. At this stage, it is once again pertinent to note that as per the order dated 30.07.2012, the petitioner was required to clear outstanding dues at the relevant point of time. However, the petitioner has failed to make such payment in spite of the order passed by this Court. The petitioner has enjoyed the property in question during these years and now, at this stage, the request is made to grant benefit of OTS Scheme introduced in June, 2020. Hence, no direction can be issued to the respondents to grant benefit of such scheme to the petitioner.

12. At this stage, this Court would like to refer the decisions, upon which, reliance is placed by the learned Senior Advocate for the respondents. In the case of Nidus Enterprises Pvt. Ltd. Vs. State of Gujarat (supra), this Court has observed in Paragraph­6 as under:

"6. There is no gainsaying that the dispute and relief prayed for in the petition falls primarily and essentially in the realm of contract and pertains to the enforcement of contractual obligations. It is trite position of law that jurisdiction of this Court under Article 226 which is a writ jurisdiction would not be exercisable in all ordinary circumstances in respect of contractual matters. Writ jurisdiction extends to the issues of violation of fundamental right and for protection of those rights. It would be also available where statutory right is infringed and infringement is

to be remedite by enforcing the same. But contractual dispute, by their very nature, do not fall within the purview of writ jurisdiction. Whether the terms of contract between two parties are breached or not is essentially a question of fact. It would require adjudication. From this standpoint also, they are neither amenable nor fit for consideration in the writ jurisdiction. Factual adjudicatory process is outside the purview of writ powers.

13. In the case of Raj Mineral Through Proprietor Sharad L. Vyas Through POA Vs. State of Gujarat and Ors.(supra), the Division Bench of this Court has held in Paragraph­7.5 as under:

"7.5 The powers conferred by Article 226 of the Constitution of India on the High Courts are certainly very wide and confer on them discretion of a most extensive nature. That discretion, however, must, necessarily be exercised in accordance with judicial considerations and well established principles. The High Court will certainly not hesitate in issuing an appropriate direction, order or writ when necessary, but no person can claim to be entitled to such an order or writ, as a matter of course, without satisfying the High Court that the case is suitable one for the issue of such an order or writ. Thus, mere fact that an order is without jurisdiction or that, there is an error apparent on the face of the record, is not sufficient to justify the issue of a writ. In addition to that, it must be established that the order has resulted in manifest injustice. It is, therefore, open to the High Court to refuse to issue writ, if it feels that if the writ prayed for is issued, it will clearly effectuate an injustice in the case."

14. In the case of The Rajasthan State Industrial Development and Investment Corporation and Anr. Vs. Diamond and Gem Development Corporation Ltd. and Anr. (supra), the Honourable Supreme Court has observed in Paragraphs­14 and 15 as under:

"14. It is evident from the above, that generally the Court should not exercise its writ jurisdiction to enforce the contractual obligation. The primary purpose of a writ of mandamus, is to protect and establish rights and to impose a corresponding imperative duty existing in law. It is designed to promote justice (ex debito justiceiae). The grant or refusal of the writ is at the discretion of the court. The writ cannot be granted unless it is established that there is an existing legal right of the applicant, or an existing duty of the respondent. Thus, the writ does not lie to create or to establish a legal right, but to enforce one that is already established. While dealing with a writ petition, the court must exercise discretion, taking into consideration a wide variety of circumstances, inter­alia, the facts of the case, the exigency that warrants such exercise of discretion, the consequences of grant or refusal of the writ, and the nature and extent of injury that is likely to ensue by such grant or refusal.

15. Hence, discretion must be exercised by the court on grounds of public policy, public interest and public good. The writ is equitable in nature and thus, its issuance is governed by equitable principles. Refusal of relief must be for reasons which would lead to injustice. The prime consideration for the issuance of the said writ is, whether or not substantial justice will be promoted. Furthermore, while granting such a writ, the court must make every effort to ensure from the averments of the writ petition, whether there exist proper pleadings. In order to maintain the writ of mandamus, the first and

foremost requirement is that the petition must not be frivolous, and must be filed in good faith. Additionally, the applicant must make a demand which is clear, plain and unambiguous. It must be made to an officer having the requisite authority to perform the act demanded. Furthermore, the authority against whom mandamus is issued, should have rejected the demand earlier. Therefore, a demand and its subsequent refusal, either by words, or by conduct, are necessary to satisfy the court that the opposite party is determined to ignore the demand of the applicant with respect to the enforcement of his legal right. However, a demand may not be necessary when the same is manifest from the facts of the case, that is, when it is an empty formality, or when it is obvious that the opposite party would not consider the demand."

15. In the case of Gohil Jesangbhai Raysangbhai Vs. State of Gujarat (supra), the Honourable Supreme Court has observed in Paragraphs­20 and 21 as under:

"20. These two judgments answer the submission of the appellants that the amount which is being charged is not a tax but a fee. It is neither. It is a premium for granting the sanction. This is because under this welfare statute these lands have been permitted to be purchased by the tenants at a much lesser price. As held in Shashikant Mohanlal (AIR 1970 Guj 204) (supra), the tenant is supposed to cultivate the land personally. It is not to be used for non agricultural purpose. A benefit is acquired by the tenant under the scheme of the statute, and therefore, he must suffer the restrictions which are also imposed under the same statute. The idea in insisting upon the premium is also to make such transfers to non­agricultural purpose unattractive. The intention of the statute is reflected in Section 43, and if that is the intention of the Legislature there is no reason why the Courts should depart therefrom while

interpreting the provision.

21. It was submitted by the appellants that assuming that the valuation of the land is permitted to be done as per the Jantri rates, it must be so done on the basis of the rates as prevalent on the date of the application. The resultant injustice was highlighted in the case of Savitaben in Civil appeal No.4129/2012. The fact however, remains that the Section speaks of previous sanction. As noted earlier, Section 4(2) of the Bombay Paragana and Kulkarni Watans (Abolition) Act, 1950 also speaks about the previous sanction. Thus, this is the theme which runs through all such welfare agricultural enactments, and a similar provision in the said Act has been left undisturbed by the bench of three Judges of this Court. Therefore, the Jantri rate to be applied will be on the date of the sanction by the Collector, and not on the date of the application made by the party."

16. From the aforesaid decisions rendered by the Honourable Supreme Court, it is clear that generally, the Court should not exercise its writ jurisdiction to enforce the contractual obligation. It is designed to promote justice. The grant or refusal of the writ is at the discretion of the court. The writ cannot be granted unless it is established that there is an existing legal right of the petitioner, or an existing duty of the respondent. Discretion must be exercised by the court on the grounds of public policy, public interest and public good and the writ is equitable in nature and thus, its issuance is governed by the equitable principles.

17. Thus, keeping in view the aforesaid decisions,

if the facts of the present case as discussed hereinabove are examined, this Court is of the view that looking to the conduct of the petitioner, the petitioner is not entitled to claim equitable relief from this Court.

18. In view of the aforesaid discussion and in view of the overall facts and circumstances of the present case, the petitioner is not entitled to get the reliefs as prayed for in the present petition. The petition is accordingly dismissed. Rule is discharged. The interim relief, shall stand vacated. Accordingly, the connected Civil Application also stands disposed of.

(VIPUL M. PANCHOLI, J) piyush

After the judgment is pronounced, learned advocate Mr.N.V. Gandhi appearing for the petitioner requested that the stay granted by this Court may be extended for a period of four weeks so that the petitioner can file an appeal before the Higher Forum.

The said request is vehemently opposed by learned Senior Advocate Mr.S.N. Shelat, who is appearing for respondent Nos.2 to 4.

For reasons recorded in the present order and looking to the conduct of the present petitioner as

observed in the order, the request made by the petitioner is rejected.

(VIPUL M. PANCHOLI, J) piyush

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter