Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ms Bn Infra Llp Ripl Jv vs The Union Of India And Othrs
2025 Latest Caselaw 7676 Gua

Citation : 2025 Latest Caselaw 7676 Gua
Judgement Date : 26 September, 2025

Gauhati High Court

Ms Bn Infra Llp Ripl Jv vs The Union Of India And Othrs on 26 September, 2025

Author: Devashis Baruah
Bench: Devashis Baruah
                                                                     Page No.# 1/8

GAHC010220822025




                                                              undefined

                             THE GAUHATI HIGH COURT
  (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

                               Case No. : WP(C)/5796/2025

          MS BN INFRA LLP RIPL JV
          OFFICE AT- AMBAGAN ROAD, BYE LANE, WARD NO. 8, TEZPUR TOWN,
          DISTRICT-SONITPUR, ASSA - 784001 REPRESENTED BY ITS AUTHORISED
          PERSON HAREN NATH, AGED ABOUT 55 YEARS, SON OF JOGESWAR
          NATH.



          VERSUS

          THE UNION OF INDIA AND OTHRS
          THROUGH THE SECRETARY, MINISTRY OF RAILWAYS, RAIL BHAWAN,
          RAISINA ROAD, NEW DELHI-110001

          2:THE RAILWAY BOARD
          THROUGH THE MEMBER ENGINEERING
           RAIL BHAWAN
           RAISINA ROAD
           NEW DELHI1100 01

          3:THE GENERAL MANAGER
           NORTHEAST FRONTIER RAILWAY CONSTRUCTION
           MALIGAON
           GAUHATI-781011

     For the Petitioner(s)    : Mrs. G.J. Rautruy, Advocate
                                Ms. D. Thakur, Advocate
                                Ms. B. Chouwdhury, Advocate
                                Ms. Imsenkala, Advocate

     For the Respondent(s) : Ms. R. Devi, CGC
                                                                Page No.# 2/8


                                BEFORE
                 HONOURABLE MR. JUSTICE DEVASHIS BARUAH

                                  ORDER

Date : 26.09.2025

Issue notice making it returnable on 27.10.2025.

2. Ms. R. Devi, the learned CGC appears on behalf of the respondent Nos. 1 to 3 and accepts notice.

3. Extra copies of the writ petition along with the documents enclosed therewith be served upon her during the course of the day.

4. The petitioner herein is aggrieved by the communication dated 17.09.2025 whereby the Respondent Authorities terminated the contract and initiated steps for the invocation of the Bank Guarantee which was kept with the Respondent Authorities in the form of performance security and retention money.

5. It is the case of the petitioner that they were awarded a contract for Engineering, Procurement and Construction of BG formation including side drains, retaining walls, other protection works, minor, major and important bridges, RUB/LHS, station building, platforms, FOBs, development of circulating areas and other passenger amenities including Electrical General works for commissioning of Doubling of BG Railway track between Katihar Page No.# 3/8

and Kumedpur-28.885 Km {CH-1.388 Km to 30.273 Km}. Amongst various Terms and Conditions of the said contract, Clause 4.3 of the Scope of the Project i.e. Part II of the Bid Documents pertains to Environmental and Forest Clearances. The said Clause 4.3 being relevant, is reproduced here in under:

"4.3 Environmental and Forest Clearances

Environmental and forest clearances are not required for this project

The Authority represents and warrants that the environmental clearance and Forest clearance for the project is not required. In the event of any delay, the Contractor shall be entitled to Time Extension for the period of such delay in accordance with the provisions of Clause 10.4 of this Agreement and shall also be entitled to Damages calculated as if the Right of Way for and in respect of such sections of the New BG Railway line Project has not been provided in accordance with the provisions of Clause 8.2 and as a consequence thereof, the Contractor shall be entitled to Damages under and in accordance with the provisions of Clause 8.3. For the avoidance of doubt, the present status of forest clearances is specified in Schedule-A."

6. A perusal of the above quoted Clause categorically shows that in respect to the project in question Environmental and Forest clearance was not required. It further stipulates that in the event of any delay, the contractor on account of Environmental and Forest clearances, shall be entitled to time extension for the period of such delay in accordance with the provisions of Clause 10.4 of the Agreement and shall also be Page No.# 4/8

entitled to damages calculated as if the Right of Way for and in respect of such Sections of the New BG Railway line Project has not been provided in accordance with the provisions of Clause 8.2 and as a consequence, the contractor shall be entitled to damages under and in accordance with the provisions of Clause 8.3. Pursuant to the said contract, which was awarded to the petitioner, the work continued. However, the Supreme Court in the case of Noble M. Paikada Vs. Union of India reported in (2024) 12 SCC 363 observed that there would be a requirement

for Environmental Clearances in respect to projects similar to the project executed by the petitioner.

7. The materials on record further show that on account of the judgment passed by the Supreme Court in the case of Noble M. Paikada (supra), steps were being taken by the Respondent Authorities for carrying out Environmental Clearances. In such circumstances, admittedly, there has been some delay, which the petitioner claims that the petitioner is entitled to an extension and damages in terms with Clause 4.3 as referred to hereinabove.

8. Be that as it may, the Respondent Authorities had issued a 15 days show cause notice dated 26.08.2025 whereby the concerned authority conveyed its intention to initiate termination proceedings and advised the petitioner to submit Page No.# 5/8

any representation within the stipulated period of 15 days from the date of issuance. It is the further case of the petitioner that on 09.09.2025, a request was made for an extension to submit a detailed reply. Immediately thereafter, on 16.09.2025, the petitioner submitted a detailed reply. However, without considering the detailed reply dated 16.09.2025 and on a mere technicality that the petitioner did not submit the representation within 15 days, the impugned termination letter dated 17.09.2025 was issued.

9. The learned Counsel appearing on behalf of the petitioner submitted that if the Respondent Authorities would have considered the detailed Reply submitted on 16.09.2025 wherein due details have been provided, the Respondent Authorities may not have taken drastic measures of issuance of the termination letter dated 17.09.2025. The non-consideration of the reply dated 16.09.2025 violates the petitioner's right under Article 14 and Article 21 of the Constitution of India inasmuch as it violates the principles of natural justice. The learned counsel therefore submitted that taking into account that the order of termination dated 17.09.2025 has already been passed, the petitioner would not seek an interim direction as regards stay of the said order of termination. However, as the termination is apparently illegal, pending notice, the Page No.# 6/8

consequences which would fall upon the petitioner on the basis of the order of termination dated 17.09.2025 be stayed.

10. Ms. R. Devi, the learned CGC appearing on behalf of the respondents submitted that she needs to obtain necessary instruction(s). She further submitted that one aspect is very clear that the said termination order dated 17.09.2025 duly contained detailed reasons, for which, the petitioner's contract has been terminated. She further submitted that no interim directions should be passed without giving an opportunity to the respondents to place the necessary instruction(s).

11. This Court had perused the materials on record as well as the judgment passed by the Supreme Court in the case of Noble M. Paikada (supra).

12. From the materials on record, it appears that when the contract was initially awarded to the petitioner, there was no requirement of any Environmental or Forest Clearance. In view of the judgment passed by the Supreme Court in the case of Noble M. Paikada (supra), the necessity had arisen for obtaining the Environmental Clearance. This Court further takes note of that the petitioner had duly submitted a request on 09.09.2025 which is also mentioned in the termination order dated 17.09.2025 seeking further time for the purpose of submission Page No.# 7/8

of a detailed reply. The petitioner further had submitted a detailed reply on 16.09.2025. The said reply, however, was not considered as is very much apparent from a perusal of the termination order dated 17.09.2025, inasmuch as there is no reference to the petitioner's reply dated 16.09.2025.

13. The question whether the respondents could have permitted the petitioner to submit the reply beyond the period of 15 days requires deliberation. This Court had also perused the reply dated 16.09.2025 and prima facie is of the opinion that before taking the drastic steps for termination, the respondents could have dealt with the reply submitted on 16.09.2025, more so, when the impugned order is passed after the submission of the reply dated 16.09.2025. This Court is also aware that an order of termination cannot be stayed and as such, the question of staying the termination order does not arise.

14. Be that as it may, this Court however directs the Respondent Authorities not to invoke the Bank Guarantee being BG No. 33060ILG001523 amounting to Rs. 14,83,00,000/- issued by the Punjab National Bank, MG Road, Tezpur, Assam till the next date.

15. The above directions are passed taking into consideration that if such directions are not passed, the petitioner would Page No.# 8/8

suffer irretrievable injury. Additionally, this Court finds more than a prima facie case at this stage.

16. This Court shall consider whether the interim order is to be extended or not on the next date.

17. The question of maintainability of the writ petition is kept open.

18. The respondents are directed to bring on record their stand by filing the affidavit on or before 22.10.2025.

19. Liberty is given to the petitioner to the file the reply, if so advised.

20. List accordingly.

JUDGE

Comparing Assistant

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter