Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Nandi Infratech Pvt. Ltd. vs R K Bararia & Anr.
2024 Latest Caselaw 3900 Del

Citation : 2024 Latest Caselaw 3900 Del
Judgement Date : 31 May, 2024

Delhi High Court

Nandi Infratech Pvt. Ltd. vs R K Bararia & Anr. on 31 May, 2024

Author: Vibhu Bakhru

Bench: Vibhu Bakhru

                               IN THE HIGH COURT OF DELHI AT NEW DELHI
                          %                                  Judgment delivered on: 31.05.2024
                          +     FAO (COMM) 49/2023 and CMNo.9287/2023

                                M/S NANDI INFRATECH PVT. LTD.                ..... Appellant
                                                          versus
                                M/S R.K. BARARIA & ANR                       ..... Respondents
                          Advocates who appeared in this case:
                          For the Appellant        : Mr Sanjoy Ghosh, Senior Advocate with Mr
                                                   Rajesh Kumar and Mr Suresh Chand Sharma,
                                                   Advocates

                          For the Respondent       : Mr Sanjay Bansal, Advocate

                          CORAM
                          HON'BLE MR JUSTICE VIBHU BAKHRU
                          HON'BLE MSJUSTICE TARA VITASTA GANJU

                                                      JUDGMENT

VIBHU BAKHRU, J

1. The appellant (hereafter NIPL) has filed the present appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 (hereafter the A&C Act) impugning a judgment dated 19.12.2022 (hereafter the impugned judgment), whereby the learned Commercial Court rejected NIPL's application being OMP (COMM) No. 85/2021 captioned M/s Nandi Infratech Pvt. Ltd. v. M/s R.K. Bararia & Another.

2. NIPL had filed the aforementioned application [OMP (COMM) No. 85/2021] under Section 34 of the A&C Act to set aside an arbitral

award dated 07.05.2021 (hereafter the impugned award) delivered by the Arbitral Tribunal comprising of a sole arbitrator (hereafter the Arbitral Tribunal).

3. The impugned award was rendered in the context of the disputes that had arisen between the parties in connection with the Work Order dated 18.04.2018 (hereafter the VDF Contract) for executing the work relating to Vacuumed Dewatering Flooring (hereafter VDF) awarded by NIPL to respondent no. 1 (hereafter RKB).

4. The Arbitral Tribunal has awarded an aggregate sum of ₹1,44,02,313/- along with future simple interest at the rate of 10% per annum from 08.05.2021 till realization as well as costs quantified at ₹2,50,000/-, in favour of RKB.

FACTUAL CONTEXT

5. NIPL is a company incorporated under the Company Act, 1956 and is, inter alia, engaged in the business of Construction.

6. RKB is engaged in carrying on business as a civil contractor, and was awarded the contract for executing the work of "Construction of Proposed Structures for 8 towers, that is tower B, C, D, E, F, G, H and I, of Amaatra Homes" for a tentative value of ₹36,12,50,000/- by the Letter of Award dated 01.11.2014 (hereafter LoA). In the year 2016, NIPL directed RKB to construct two additional towers, that is towers A and J, increasing the scope of the contract to entail construction of 10 towers of Amaatra Homes.

7. On 18.04.2018, NIPL issued another Work Order (VDF Contract) for execution of the work of Vacuum Dewatering Flooring (VDF) of NIPL's residential project 'Amaatra Homes' at Plot No. GH- 02C, Sector 10, Greater Noida West (hereafter VDF work). The execution of the VDF work was required to be completed within a period of 60 days to be reckoned from ten days after the date of the VDF Contract, that is, on or before 27.06.2018. The value of the VDF work was fixed at ₹1,84,19,500/-.

8. RKB claims that it executed the VDF work up to 16.07.2018 with its own Ready Mix Concrete (RMC) and raised the bill for the works done, however, NIPL refused to release the payment and insisted that the work be executed by RMC supplied by NIPL. In addition to RMC, NIPL also supplied bricks.

9. The VDF work was not completed within the stipulated period and by a letter dated 09.12.2018 (hereafter the termination letter), NIPL terminated the VDF Contract alleging failure on the part of RKB to perform its obligations.

10. Prior to termination of the VDF Contract, RKB had submitted two running bills (RA Bill dated 30.06.2018 for a sum of ₹16,15,368/- and RA Bill dated 02.11.2018 for a sum of ₹68,61,940/-). RKB also submitted a consolidated bill dated 08.01.2019 for a total amount of ₹1,45,05,142/-.

11. It is RKB's case that NIPL did not pay any amount against the VDF work executed by it. NIPL disputed the same and claimed that it

had made an ad-hoc payment of ₹6,00,000/- to RKB against executing the VDF Work.

12. RKB claims that it continued to execute the work till January, 2019 and thereafter NIPL did not permit RKB to enter the site.

13. In the aforesaid circumstances, RKB invoked the arbitration agreement as contained in the VDF Contract dated 18.04.2018. RKB also requested NIPL for appointment of an arbitrator, however, it did not receive any response from NIPL.

14. Thereafter, RKB filed a petition [Arb. Pet. No. 70/2019] under Section 11 of the A&C Act before this Court for an appointment of Arbitrator. The aforesaid petition was dismissed with the direction to place the VDF Contract before the Collector of Stamps. RKB again filed arbitration petition in December, 2019, before this Court and by an order dated 06.02.2020, this Court appointed a Sole Arbitrator for adjudicating the dispute between the parties.

ARBITRAL PROCEEDINGS

15. Before the Arbitral Tribunal, RKB filed his Statement of Claims raising six claims, which are briefly summarized below:

Claim No.1 for a sum of ₹83,98,080/-:

16. RKB claimed that it had executed the total works for a value of ₹1,43,05,610/-. The same included materials (bricks, RMC and angles) of an aggregate value of ₹67,74,122/-, which were supplied by NIPL.

Thus, RKB claimed an amount of ₹75,31,488/- on account of the VDF work done. In addition, it claimed an amount of ₹8,66,592/- as the component of profit included in the value of the items supplied by NIPL computed at the rate of 15% of an amount of ₹57,77,280/-. RKB had founded the said claim on the basis that NIPL had insisted on supplying the items at a rate higher than as available in the market. Thus, RKB claimed an aggregate amount of ₹83,98,080/- (₹75,31,488/- plus ₹8,66,592/-). In addition, RKB also claimed GST at the rate of 18% of the value of work done.

Claim No.2 for a sum of ₹6,00,000/-:

17. RKB claimed that execution of the VDF work had been delayed for reasons attributable to NIPL and RKB was thus entitled to claim compensation for the prolongation of work beyond the stipulated date of completion. RKB claimed a sum of ₹6,00,000/- as compensation for prolongation of the contract. It quantified the claim at the rate of ₹1,00,000/- per month for a period of six months.

Claim No.3 for a sum of ₹5,40,758/-:

18. RKB claimed loss of profit computed at the rate of 15% of the value of the balance remaining work quantified at ₹5,40,758/-.

Claim Nos.4 and 5 for interest at the rate of 14% per annum:

19. RKB claimed interest at the rate of 14% per annum for delay in release of payments (pre-reference and pendent lite). Additionally,

RKB claimed future interest at the rate of 14% per annum on total amounts as claimed.

Claim No.6 for legal costs

20. RKB claimed legal costs and costs for arbitration.

21. NIPL disputed the aforesaid claims and also raised counterclaims. NIPL acknowledged that RKB had submitted two running bills prior to termination of the VDF Contract and had submitted a consolidated bill dated 08.01.2019 for an amount of ₹1,45,05,142/-. NIPL claimed that the said bills were exaggerated and that the value of works completed by RKB was only ₹64,01,191/- till the termination of the contract. It claimed that against the aforesaid amount it had paid an ad-hoc amount of ₹6,00,000/- and had also issued debit notes for the materials supplied aggregating ₹58,99,539.10. The said amounts were required to be adjusted against the value of work done. Thus, according to NIPL, a sum of ₹1,26,405/- was recoverable from RKB.

22. In addition, NIPL also claimed a sum of ₹9,13,475/- towards liquidated damages for delay in execution of the works.

23. On the basis of the rival pleadings, the Arbitral Tribunal framed the following issues:

"(I) To what amount the claimant is entitled against claim no. 1 of Rs.83,98,080/- and GST on Rs.1,43,05,610/- amounting to Rs.25,75,010/-?

OPC

(II) Whether the claimant is entitled to damages on account of prolongation of the work against claim no. 2 of Rs.6,00,000/-? If so, how much? OPC (III) Whether the Claimant is entitled to loss of profit due to alleged breach of contract committed by the Respondent on the balance of work not got executed from the Claimant against Claim no. 3 of Rs. 5,40, 758/-? OPC (IV) Whether the Claimant is entitled to interest? If so, at what rate, on what amount and for what period?

OPC (V) Whether the Claimant is entitled the cost of arbitration and litigation? If so, how much against Claim no. 6? OPC (VI) Whether the termination of work of contract was valid and legal? OPR (VII) Whether the Respondent had made payment of Rs.6,00,00/- to the claimant? OPR (VIII) Whether the Respondent is entitled to a sum of Rs.58,99,539/- against debit notes for supply of materials and on other counts? If so, how much?

OPR (IX) Whether the Respondent is entitled to liquidated damages for alleged breach of contract on the part of the Claimant? If so, how much against claim of Rs.9,13,475/-? OPR (X) Whether the Respondent is entitled to the counter claim of Rs.1,26,405/- being the alleged excess payment? OPR (XI) Whether the Respondent is entitled to interest? If so, at what rate, on what amount and how much?

OPR

(XII) To what relief the parties are entitled? Onus on parties"

24. Both the parties submitted their documents relied upon by them. RKB also tendered the affidavit by way of evidence of his son (Sumit Bararia - CW1), who was stated to be entrusted with the execution of the VDF work. He was also cross-examined by the counsel for NIPL. NIPL also tendered evidence by way of affidavits of Mr. Shibalak Rai (RW1), claimed to be a sub-contractor; Mr. Satindra Singh (RW2); Mr. Kunal (RW3); and, Mr. Umesh Gupta (RW4) who was the construction and financial advisor of the NIPL, for the project.

IMPUGNED AWARD

25. The Arbitral Tribunal considered the various items covered in the Final Bill and accepted RKB's claim in regard to works executed. RKB had claimed that it had executed the works amounting to ₹1,34,97,625/- as per measurements and had also made a claim of ₹8,07,985/- towards extra items of work. According to RKB, it had executed the works aggregating to ₹1,43,05,610/-. Whilst, the Arbitral Tribunal accepted the said amount, it found that RKB had computed its claim for the quality of PCC at a higher rate of ₹3,879/- instead of ₹3,800/-. Thus, the aggregate excess amount of ₹80,442/- charged on account of PCC was disallowed.

26. The Arbitral Tribunal held that RKB had executed work of an aggregate value of ₹1,42,25,168/-. The Arbitral Tribunal also accepted that RKB would be entitled to GST on the aforesaid amount calculated

at 18% of the value of work executed, which was quantified at ₹25,60,530/-. However, the Arbitral Tribunal rejected RKB's claim for a sum of ₹8,66,592/-being the element of profit on the extra items as supplied by NIPL.

27. The Arbitral Tribunal accepted that the value of items supplied by NIPL was ₹67,74,122/- (bricks of a value of ₹3,47,857/-; RMC of a value of ₹62,89,167/-; and angles of a value of ₹1,37,098/-). After adjusting the aforesaid amount, the Arbitral Tribunal found that a sum of ₹1,00,11,576/- (₹1,42,25,168/- less ₹67,74,122/- plus ₹25,60,530/-) was due and payable to RKB and had accordingly awarded the said amount against claim no.1.

28. The Arbitral Tribunal rejected NIPL's claim that it had made an ad-hoc payment of ₹6,00,000/- to RKB as payment of the said amount was not established.

29. In addition, the Arbitral Tribunal accepted RKB's claim for loss of profit for the remaining works quantified at ₹5,40,758/-. The Arbitral Tribunal held that RKB was entitled to loss of profit at the rate of 15% of the balance works of ₹41,94,332/- (total value of the work ₹1,84,19,500/- less the works executed by RKB valued at ₹1,42,25,168/-). The Arbitral Tribunal reasoned that in terms of Clause 12 of the VDF Contract an allowance of 15% was required to be factored in for ascertaining the rates of extra items and therefore the said compensation for loss of profit at the said rate was reasonable. Since, RKB's claim was for a lower amount, the same was allowed.

30. In addition, the Arbitral Tribunal awarded interest at the rate of 14% per annum on the amount withheld for the period 08.02.2019 till the date of the award (07.05.2021) quantified at ₹34,49,979/-. The Arbitral Tribunal also awarded a sum of ₹4,00,000/- towards compensation for prolongation of the works.

31. Insofar as counter claims are concerned, the Arbitral Tribunal rejected the same. It did not accept NIPL's calculation of the work done as it was not based on joint measurements. The Arbitral Tribunal also found that RKB had submitted measurement sheets along with its bills, which was not disputed at the material time. The Arbitral Tribunal faulted NIPL for the delay in execution of the works. It held that NIPL had breached the terms of the contract by withholding payments and delaying the execution of VDF work. A tabular statement setting out the amounts awarded in favour of the RKB is set out below:

                                        CLAIM                            AWARDED
                           Claim No. 1:                        Rs. 83,98,080/-
                           Claim No. 2:                        Rs. 4,00,000/-
                           Prolongation of work
                           Claim No. 3:                        Rs. 5,40,758/-
                           Loss of Profit at the rate of 15%
                           of balance work
                           Claim No. 4 & 5:                    Rs. 34,49,979/-
                           Interest at the rate of 14%









                            Claim No. 6:                        Rs. 2,50,000/-
                           Legal Cost

                          SUBMISSIONS


32. Mr. Sanjoy Ghosh, the learned counsel appearing for NIPL assailed the impugned award on several grounds. First, he submitted that the Arbitral Tribunal had grossly erred in accepting RKB's claim that it had executed the works at a value of ₹1,42,25,168/-. He contended that the Arbitral Tribunal had grossly erred in accepting that the said claim was based on measurement of the work. He submitted that in terms of the contract between the parties payments were to be released on the basis of the joint measurements. However, RKB had not cooperated with NIPL to jointly measure the work despite several requests. He submitted that Arbitral Tribunal had erred in not appreciating that NIPL had sent various e-mails to RKB to conduct joint inspections but RKB had not complied with the same. In the circumstances, NIPL had unilaterally measured the work done. It had also produced measurement sheets that were forwarded to RKB. He contended that NIPL had verified the quantum of work done and responded to RKB's e-mail on 18.04.2019 confirming that the quantum of work done was valued at ₹64,01,191/- and the same was not disputed by RKB at the material time. He submitted that the said measurement sheets required to be considered as the only basis for adjudicating any claim regarding the work done by RKB. He contended that Arbitral Tribunal had erred in simply relying on the measurement sheets as

produced by RKB and there was no basis for accepting the measurement sheets submitted by RKB except its self-serving assertions, and rejecting the measurement sheets as furnished by NIPL. He submitted that the approach of the Arbitral Tribunal was in conflict with the most basic notion of morality and justice.

33. He submitted that the award of sum of ₹25,60,530/- as GST is patently illegal as the same includes value of items on which GST is included. He submitted that admittedly items worth ₹67,74,122/- were supplied, which included an element of GST. Thus, the GST on the said amount was required to be reduced. However, in all fairness to Mr. Ghosh, he did not seriously canvass this challenge.

34. Mr Ghosh submitted that the award of compensation of ₹4,00,000/- for prolongation of the work was not sustainable. He submitted that the same was contrary to clause 14 of the VDF Contract, which expressly prohibited payment of any compensation for delay in execution of the works. He further submitted that computation of the said amount was without any basis or material. The Arbitral Tribunal had quantified the compensation on the assumption that RKB's son would be entitled to ₹1,00,000/- per month for the time spent by him in overseeing the execution of VDF work. This basis is arbitrary and unfounded.

35. He submitted that the award of loss of profits as claimed was based on no evidence as RKB had led no evidence in support of its claim for loss of profits. The Arbitral Tribunal had relied on clause 12 of the

VDF Contract, which deals with extra items and provides for an allowance of 15% on account of overheads, profits as well as establishment charges. He contended that award of loss of profits at the rate of 15% was not supported by the said clause as well.

36. Lastly, he submitted that the award of interest was unsustainable as it was not based on any evidence.

37. Mr. Ghosh also relied on the various decisions including the decision of the Supreme Court in PSA SICAL Terminals (P) Ltd. v. Board of Trustees of V.O. Chidambranar Port Trust Tuticorin: 2021 SCC OnLine SC 508; Associated Engineering Co. v. Government of Andhra Pradesh & Anr.: (1991) 4 SCC 93; and Hindustan Zinc Ltd. v. Friends Coal Carbonisation: (2006) 4 SCC 445 and the decisions of this Court in Indo Nabin Projects Ltd. v. Powergrid Corporation of India Ltd.: 2018 SCC OnLine Del 8405; National Highways Authority of India v. IRB Pathankot Amritsar Toll Road Ltd.: Neutral Citation 2023:DHC:4352-DB; Chintels India Ltd. v. Bhayana Builders Pvt. Ltd.: 2022 SCC OnLine Del 1964; and GTM Builders & Promoters Pvt. Ltd. v. Sneh Developers Pvt. Ltd.: 2018 SCC OnLine Del 9653 as well as the decision of the Bombay High Court in Edifice Developers and Projects Engineers Ltd. v. Essar Projects (India) Ltd.: 2013 SCC OnLine Bom 5.

REASONS & CONCLUSION

Quantum of work done

38. First and foremost question to be examined is whether any interference is warranted in the decision of the Arbitral Tribunal to accept RKB's claim for the quantum of work done. A plain reading of the impugned award indicates that the Arbitral Tribunal's decision to accept RKB's claim as to the quantum of work done is supported by material on record. The Arbitral Tribunal found that RKB had continued to work till 23.01.2019, which was beyond the date of termination of VDF Contract. The Arbitral Tribunal found that RKB had submitted its measurement sheets along with three bills (Bills dated 30.06.2018, 02.11.2018 and 08.01.2019). NIPL had disputed that RKB had submitted the measurement sheets along with the three bills. However, the Arbitral Tribunal found that this denial was false. The bills were sent through e-mails and on RW3 (Mr. Kunal - Engineer-in- Charge of NIPL) being confronted with the said e-mails, he admitted that the measurement sheets were received along with the three e-mails (E-mails dated 03.07.2018, 03.11.2018 and 27.01.2019) whereby the bills dated 30.06.2018, 02.11.2018 and 08.01.2019 were communicated to NIPL. Further RKB's witness (CW1) had also tendered his evidence as to the quantum of work done. He was also cross-examined but there is nothing in his testimony to discredit it. He was specifically asked whether the measurement sheets had been submitted along with the bills (Q.59) to which he answered in the affirmative. He was specifically asked as to how the quantities were measured without joint verification and who had verified the same. He responded by stating that the quantities were measured from the drawings and co-related with the

work done at site and he had himself done it. NIPL had also produced measurement sheets, which the Arbitral Tribunal did not accept. The Arbitral Tribunal found that the persons who had physically prepared the measurement sheets had not been examined. The Arbitral Tribunal also did not accept NIPL's claim that despite being called upon to jointly measure the work done, it had failed to join the said exercise. The Arbitral Tribunal found that there was no material on record to establish that NIPL had called upon RKB to jointly measure the work done.

39. There is a serious dispute as to the quantum of work done and both parties had led evidence in this regard. However, the Arbitral Tribunal had not accepted NIPL's claim.

40. NIPL, essentially, seeks that this Court to once again re-evaluate the evidence and re-adjudicate the said question. This is clearly outside the scope of proceedings under Section 34 of the A&C Act. It is settled law that this Court does not re-adjudicate or re-evaluate the disputes in considering an application to set aside the arbitral award under Section 34 of the A&C Act. The scope of examination is limited to whether the arbitral award is liable to be set aside on any of the grounds set out under Section 34(2) or under Section 34(2A) of the A&C Act. It is well settled that the Arbitral Tribunal is the final arbiter to evaluate sufficiency and merits of the evidence. This Court cannot re-evaluate the evidence and material produced by the parties and supplant its opinion in place of that of the Arbitral Tribunal.

41. Although, there is a substantial contest as to the quantum of work executed, it is clear that this is not a case where the Arbitral Tribunal's decision is based on no evidence at all. On the contrary, it is clear from a plain reading of the impugned award that the Arbitral Tribunal had evaluated and appreciated the evidence led by the parties. Its decision is based on material available on record. Further, we do not find the Arbitral Tribunal's view is not a plausible one. It is established on record that RKB had sent its bills along with measurement sheets. The same were not disputed at the material time. Although, NIPL had disputed receipt of the said measurement sheets, the evidence on record clearly established that the same were received by NIPL. The VDF Contract required that payments be made on the basis of joint measurements, however, it is RKB's case that it was not allowed to enter the site after January, 2018 and at the material time there was no dispute as to the quantum of work done.

42. In view of the above, we reject NIPL's contention that the impugned award, to the extent it accepts RKB's claim as to the quantum of work done, is required to be set aside as vitiated by patent illegality or on the ground that it is in conflict with the public policy of India. The scope of interference under the said grounds is now well settled and it does not entail re-appreciation and re-appraisal of evidence on merits of the dispute. We are unable to accept that the decision of the Arbitral Tribunal offends the basic notions of morality and justice as contended by Mr. Ghosh, learned counsel appearing for NIPL.

Award of GST

43. The next question to be examined is whether the Arbitral Tribunal has erred in awarding 18% GST on the quantum of work done. It is NIPL's case that the award of an amount of GST is contrary to Section 16 of the Central Goods & Services Tax Act, 2017 (hereafter CGST Act). It is also contended that since the quantum of work done included value of items (bricks valued at ₹3,47,857/-; RMC valued at ₹62,89,167/- and angles valued at ₹1,37,098/-) aggregating to ₹67,74,122/- which included GST, the same was required to be deducted from the value of GST on the quantum of work done. We find the said contention unmerited. GST is payable on the output goods and services. Thus, RKB's claim that it would be liable to pay GST at the rate of 18% on the total value of work executed, which the Arbitral Tribunal has quantified at ₹1,42,25,168/-, is correct. Mr. Ghosh was unable to point out any provision in the CGST Act, which restricts the liability to pay GST on output supplies, on the basis of tax paid supplies used for providing taxable goods or services. Undisputedly, a taxable entity would be entitled to claim Input Tax Credit in respect of the GST paid on input supplies. However, that does not absolve NIPL of its liability to pay GST on the supplies received by it. Admittedly, if RKB is obliged to provide NIPL credit for the value of taxable inputs supplied by NIPL, it is also entitled to claim Input Tax Credit for the same. This does not mitigate NIPL's liability to pay GST for the value of work executed by RKB.

Compensation for prolongation of work

44. The next question to be examined is whether the Arbitral Tribunal has erred in allowing compensation for damages at the rate of ₹1,00,000/- per month for a period of four months on account of prolongation of works.

45. The Arbitral Tribunal found after evaluating the evidence placed on record, including an e-mail dated 10.09.2018 sent by RKB to NIPL, that RKB had established that the execution of works was prolonged for at least four months due to unreasonable demands and lapses on the part of NIPL. Concededly, the said findings cannot be interfered with in this proceeding.

46. NIPL's challenge to the award of compensation is, essentially, on two fronts. First, that it is contrary to Clause 14 of the VDF Contract, which expressly prohibits claim of any such compensation. And second, that the quantification for such compensation is without any evidence at all.

47. At this stage it is relevant to refer to Clause 14 of the VDF Contract, which is set out below:

"14. Delay in Commencement:

The contractor shall not be entitled to any compensation (monetary only) for any loss suffered by him on account of delays in commencing or executing the work, whatever the case delays may be, including delays arising out of modification to the work entrusted to him or in any sub-contract

connected there with or delay in awarding contract for other trades of the project or in commencement of such works or in procuring Government controlled or other building materials or any other reason whatsoever and the client shall not be liable for any claim in respect thereof (time duration will be extended accordingly)."

48. It is clear that the contract in question expressly provides that RKB would not be entitled for any compensation for loss suffered on account of delay in "commencing or executing the work". The parties are bound by the terms of their contract. The Arbitral Tribunal had held that the said clause would not be applicable in respect of the delays caused by NIPL. The said conclusion clearly runs contrary to the plain language of Clause 14 of the VDF Contract, which expressly provides that no compensation shall be payable on account of delay including for "any other reason whatsoever". Section 28(3) of the A&C Act expressly requires the Arbitral Tribunal to take into account the terms of the contract. In Union of India v. Manraj Enterprises: (2022) 2 SCC 331, the Supreme Court had held that a clause of the contract prohibiting grant of interest would be binding and an award in disregard of the said clause would be liable to be set aside. A similar view was also expressed by the Supreme Court in other prior decisions as well [see: Union of India v. Ambica Construction: (2016) 6 SCC 36; Sree Kamatchi Amman Constructions v. Divisional Railway Manager (Works), Palghat & Ors.: 2010 SCC OnLine SC 919; Jaiprakash Associates Ltd. (JAL) v. Tehri Hydro Development Corporation (India) Ltd. (THDC): (2019) 17 SCC 786.

49. In Oil and Natural Gas Corporation v. Wig Brothers Builders and Engineers Pvt. Ltd.: (2010) 13 SCC 377, the Supreme Court held that the Arbitral Tribunal had exceeded in his jurisdiction in awarding compensation for delay in execution of the works, which was prohibited by the contract. The relevant extract of the said decision is set out below:

"5. ...... But clause 5A of the contract pertains to extension of time for completion of work and specifically bars any claim for damages. The said clause is extracted below :

"In the event of delay by the Engineer-in-Charge to hand over to the contractor possession of land/lands necessary for the execution of the work or to give the necessary notice to the contractor to commence work or to provide the necessary drawing or instructions or to do any act or thing which has the effect of delaying the execution of the work, then notwithstanding anything contained in the contract or alter the character thereof or entitle the contractor to any damages or compensation thereof but in all such cases the Engineer-in- Charge may grant such extension or extensions of the completion date as may be deemed fair and reasonable by the Engineer-in Charge and such decision shall be final and binding."

6. In view of the above, in the event of the work being delayed for whatsoever reason, that is even delay which is attributable to ONGC, the contractor will only be entitled to extension of time for completion of work but will not be entitled to any

compensation or damages. The arbitrator exceeded his jurisdiction in ignoring the said express bar contained in the contract and in awarding the compensation of Rs.9.5 lakhs. This aspect is covered by several decisions of this Court. We may refer to some of them.

* * * * In Ramnath International Construction (P) Ltd. v. Union of India

- 2007 (2) SCC 453, a similar issue was considered. This Court held that clause 11(C) of the General Conditions of Contract (similar to clause 5A under consideration in this case) was a clear bar to any claim for compensation for delays, in respect of which extensions had been sought and obtained. This Court further held that such a clause amounts to a specific consent by the contractor to accept extension of time alone in satisfaction of claims for delay and not to claim any compensation; and that in view of such a bar contained in the contract in regard to award of damages on account of delay, if an arbitrator awards compensation, he would be exceeding his jurisdiction."

50. In the aforesaid view, the decision of the Arbitral Tribunal to award compensation contrary to the terms of the VDF Contract vitiates the impugned award to the said extent by patent illegality.

51. We also find merit in the contention that the quantification of the amount of compensation is also not founded on any evidence. The Arbitral Tribunal has awarded a sum of ₹1,00,000/- solely on the basis that RKB's son had devoted his time for the works executed at the site

and he was a qualified engineer. There is no material on record to establish the additional expenditure incurred by RKB during the period of prolongation of the contract. The impugned award is thus based on no evidence at all.

Compensation for loss of profit

52. The next question to be examined is whether the impugned award to the extent it awards compensation for the loss of profit is sustainable. The Arbitral Tribunal had awarded an amount of ₹5,40,758 as compensation for loss of profit on the unexecuted works. The Arbitral Tribunal had found that NIPL had wrongfully terminated the VDF Contract and thus RKB would be entitled to claim loss of profit on the unexecuted works. We find no ground to interfere with this finding. However, the award of compensation is not based on any evidence or materials. It is settled law that a party claiming damages on account of breach of contract is required to establish the same. In the present case, RKB had led no evidence to establish the losses that it had suffered on account of non-execution of the balance works. There is no material whatsoever on record, which would establish that RKB would have earned 15% profit on the value of the VDF Contract. The quantum of loss is quantified solely on the basis that Clause 12 of the VDF Contract, which provides that rates of extra items would include "an all inclusive allowance of 15%". Clause 12 of the VDF Contract is relevant and is set out below:

"12. Extra Items:

If the contractor is required to any such item/work in the course of construction for which the schedule of rate has not been quoted by him, he must undertake such work and he should bring to the notice of the Engineer in charge within seven days of the occurrence. The rate for such additional work shall be determined by the Engineer in Charge as per the following:

• The rate to be derived from one of the quoted rates for similar item of work in the tender.

• Rates based on actual observation and/or analysis of labour, materials, testing and commissioning involved in such work. For this purpose the contractor shall submit to Engineer ln charge detailed analysis of the rate proposed by the Contractor supported by relevant vouchers along with the estimated quantity of work item involved. While fixing of rates for extra items an all-inclusive allowance of 15% of the cost will be provided for contractor over heads, profit and establishment charges."

53. The fact that rates of extra items would include an all inclusive allowance of 15% of costs on account of "overheads, profits and establishment charges" does not establish that RKB would have earned 15% profit on execution of the contract in question.

54. The mark up on account of overheads, profit and establishment expenses in item rates cannot form the basis of awarding compensation for loss of profits that would have been earned by execution of the contract. This is essentially for three reasons. First, that analysis of rates of an extra item is not akin to execution of the contract of the works as a whole. The value of the contract is determined on the basis of the

offer made by the contractor and there is no requirement for the contractor to align its estimated profit on the basis of analysis of rates of extra items. It is quite possible that a contractor, who has unutilized spare capacity, may agree to execute the works on marginal profits. On the other hand, a contractor that has no spare capacity may not accept a contract unless there is sufficient mark up to expand its capacity. The profit margin on which a contractor would agree to execute the works has no relation with the rate analysis for extra items.

55. Second, an inclusive allowance of 15% on the item of rates translates to an allowance of 13.04% on the value of item rate. This can be clearly illustrated by assuming the costs of a component of extra item at ₹100/-, a 15% inclusive allowance would translate to an item rate of ₹115/-. A profit mark up of ₹15/- on the item rate of ₹115/- would translate into 13.04% (₹15/115). Thus, if it is assumed that the balance work was akin to an extra item, the same would include an allowance of 13.04% on the value of the work as mark up on account of overheads, profits and establishment expenses. Thus, the assumption that the loss of profits is 15% of the remaining value of the work is ex facie erroneous.

56. Third, all inclusive allowance of 15% includes an allowance for overheads and establishment expenses in addition to an allowance for profits. RKB's claim was confined to loss of profits alone. Thus, in any event, it would not be apposite to assume a profit margin of 15% on the basis of analysis of rates for extra items. The said analysis would

inapposite as the all inclusive allowance of 15% of costs also includes establishment expenses and overheads.

57. In Edifice Developers and Projects Engineers Ltd. v. Essar Projects (India) Ltd. (supra), a Division Bench of the Bombay High Court had upheld the decision of the learned Single Judge faulting the Arbitral Tribunal in awarding the claims for overhead losses without any evidence. In the said case, the Arbitral Tribunal, following the decision in the case of AT Brij Paul Singh v State of Gujarat: AIR 1984 SC 1703 had allowed the claims for overhead losses. In the said context, the Division Bench held as under:

"10. Brij Paul Singh's case therefore does not stipulate as a doctrine of law that the formula which has been prescribed in Hudson's treatise must invariably be accepted in all cases as a measure of damages sustained on account of loss of overheads. On the other hand in the subsequent decision of the Supreme Court in McDermott International (supra), the Supreme Court has relied upon the following observations contained in the earlier decision in M.N. Gangappa v. Atmakur Nagabhushanam Setty & Co. (1973) 3 SCC 406.

"In the assessment of damages, the court must consider only strict legal obligations, and not the expectations, however reasonable, of one contractor that the other will do something that he has assumed no legal obligation to do."

11. The judgment in McDermott International (supra) considers various formulae including Hudson's Formula, Emden Formula and Eichleay Formula. As regards Hudson's Formula the Supreme Court has noted, in the following extract, that although it has received judicial support in many cases, it has been the subject matter of criticism:

"(a) Hudson Formula : In Hudson's Building and Engineering Contracts, Hudson formula is stated in the following terms:

"Contract head office overhead & contract sum period of delay" profit percentage x --------------------- x contract period In the Hudson formula, the head office overhead percentage is taken from the contract. Although the Hudson formula has received judicial support in many cases, it has been criticized principally because it adopts the head office overhead percentage from the contract as the factor for calculating the costs, and this may bear little or no relation to the actual head office costs of the contractor."

(emphasis supplied)

12. In McDermott International (supra) the Supreme Court has held that it is an accepted position that different formulae can be applied in different circumstances and the question as to whether damages should be computed by taking recourse to one or other formula, having regard to the facts and circumstances of a particular case, would fall within the domain of the Arbitrator. In the present case no other formula other than Hudson's formula has been considered in the arbitral award. In the present case the Arbitrator proceeded on the basis that it was only Hudson's Formula which was to be applied and that even though no direct evidence had been adduced on behalf of the Appellant, nonetheless the Appellant would be entitled to damages measured with reference to the aforesaid formula. This approach of the Arbitrator is manifestly in the teeth of the law laid down by the Supreme Court in McDermott International. Section 28(1)(a) requires that the Arbitral Tribunal shall decide a dispute submitted to arbitration in accordance with the substantive law for the time being in force in India. Section 28(3) requires the Arbitral Tribunal to decide in accordance with the terms of the contract and take into account the usages of the trade applicable to the transaction.

The Arbitral Tribunal under Section 28(2) can act as amiable compositeur and can decide ex aequo et bono only if parties have expressly authorized it to do so. In the present case, the Learned Single Judge was correct in coming to the conclusion that the award of the Arbitrator proceeds on the manifestly misconceived notion that a contractor is entitled to claim overhead losses even in the absence of evidence on the basis of Hudson's Formula. Similarly, the Arbitral Tribunal proceeded on a misconceived premise that this formula is invariably adopted for quantification of claims for overhead losses in India. In the present case the Appellant produced no evidence in support of its claim; this has been so stated in the Award. The award of the claim is on the misconceived basis that the Hudson's Formula must be applied despite the absence of evidence. Since the fundamental basis that has permeated the award is contrary to law, the judgment of the Single Judge cannot be faulted in setting aside the arbitral award on that aspect."

58. We respectfully concur with the aforesaid view. Thus, the impugned award, to the extent it awards compensation at the rate of 15% of the value of unexecuted works without any evidence or material, is vitiated by patent illegality.

59. NIPL has also challenged the award of interest as being patently illegal, however, we find no merit in the said contention. The award of 14% interest cannot by any stretch be considered as unreasonable. We are also of the view that the Arbitral Tribunal's decision to award future interest at the rate of 10% per annum requires no interference in this proceeding. Since, RKB has succeeded substantially, we find no ground to interfere with award of costs as well.

60. In view of the above, the appeal is partially allowed and the impugned award to the extent the Arbitral Tribunal has allowed Claims no.2 and 3 - award of compensation for prolongation of works and on account of loss of profits - is set aside.

61. The pending application, if any, is also disposed of.

VIBHU BAKHRU, J

TARA VITASTA GANJU, J MAY 31, 2024 'gsr'

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter