Citation : 2023 Latest Caselaw 4596 Del
Judgement Date : 28 March, 2023
$~8
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 3499/2023
M/S. SKYLINE AIR-CONDITIONING
ENGINEERS P. LTD. ..... Petitioner
Through: Mr. Ashok Kumar, Advocate (M:
9015946273)
versus
PUBLIC WORKS DEPARTMENT ..... Respondent
Through: Mr. Satyakam, ASC with Ms. Pallavi
Singh, Advocate.
CORAM:
JUSTICE PRATHIBA M. SINGH
ORDER
% 28.03.2023
1. This hearing has been done through hybrid mode.
2. The Petitioner- M/s. Skyline Air-Conditioning Engineers Pvt. Ltd. was awarded a work for 'Comprehensive Maintenance of Electrical, Civil & Horticulture Operation relating Day to Day Maintenance, Special repair etc of Ch. Brahm Prakash Ayurved Charak Sansthan ('CBPACS'), Khera Dabar, Najafgarh, Delhi' during the years 2022-23 & 2023-24, vide Award Letter dated 7th July 2022 ('the work contract). The Petitioner has challenged the letter dated 7th February 2023, issued by Respondent - Public Works Department, GNCTD wherein the works contract entered into between the Petitioner and Respondent has been terminated.
3. According to the Petitioner, the work was executed by the Petitioner but the Respondent repeatedly sent communications from dated 24th August 2022 to 18th January 2023 to the Petitioner, raising various grievances related to the work contract. Thereafter, vide letter dated 24th January 2023, the Petitioner submitted their bills to the Respondent for processing of payment.
4. According to the Petitioner, the admitted amount due in terms of the submitted bills is not being paid by the Respondent, and further, vide letter dated 7th February, 2023, Respondent has issued a final notice for termination of the work contract.
5. Mr. Satyakam, ld. Counsel for the Respondent, who has sought instructions submits that, insofar as the admitted amounts which are due and payable, the same would be paid by the Respondent. The ld. Counsel for the Respondent also points out that the work contract provides for settlement of disputes by Conciliation and Arbitration as per clause 25 of the General Conditions of Contract 2020 (GCC 2020), which applies in the present case. Accordingly, ld. Counsel submits that there were various deficiencies and discrepancies in the manner in which the Petitioner was executing the works contract and hence the Respondent had no option but to terminate and take action in terms of the contract.
6. Heard counsel for the parties. A perusal of the notice dated 7th February, 2023 shows that the Respondent has relied upon Show-Cause Notice issued on 2nd November, 2022 and the reply of the Petitioner to the same, dated 7th November, 2022. After considering the same, the work contract has been terminated. The relevant portions of the said letter/notice dated 7th February 2023 reads as under:
"Dear Sir (s), Whereas under Clause-3 of the aforesaid agreement the Engineer-in-charge shall have powers to take action under clause 3 in the event of delay & suspension in the execution of the aforesaid work by the contractor so that in the opinion of the Engineer- in-charge (which shall be final and binding) the contractor will be unable to secure completion of the
work by the stipulated date of completion, whereas you have delayed and suspended the execution of aforesaid work and as per the opinion of the undersigned, the Engineer-in-charge (which is final and binding), you will be unable to secure the completion of the work by stipulated date of completion and whereas, you were served with show cause in this regard under this office No.54(PWD/EMD South West/M-152/22-23/2347 dated 02.11.2022. Your reply vide no. Nil dated
07.11.2022 was received in response to above show cause was considered but no improvement in working was observed.
You were once again served with show cause in vide this office No.54 (PWD/EMD/South West/M-152/2022- 23/142 dated 18.01.2023. Your reply vide No. Nil dated 24.01.2023 received in response to above show cause has been considered carefully but not found to the satisfaction of Engineer-in-Charge.
Therefore under powers delegated to me under sub-clause 3(a) & (b) I, Moti Lal Meena, the Engineer- in-charge for the aforesaid work under the aforesaid agreement, for and on behalf of the President of India, hereby
(i) Determine the contract as aforesaid upon which determination your security deposit already recovered and Performance Guarantee stand absolutely forfeited to the Government and shall be absolutely at the disposal of Government, and
(ii) Take out such part of the work out of your hand, as remains unexecuted, for giving it to another contractor to complete the work, and you shall have no claim to compensation for any loss sustained by you by reasons of your having purchased or procured any materials or entered into any engagements or made any advances on account of or with a view to the execution of the work or the performance of the contract. You are also hereby served with notice to the effect that the work
executed by you will be measured up on 20.02.2023 for which you are asked to attend for joint measurement failing which the work will be measured by the department unilaterally in your absence and result of measurement will be final and will be binding on you.
(iii) You shall not be allowed to participate in the tendering process for the balance work. This is without prejudice to Government's right to take action under any other clauses or sub-clauses of the agreement and to realize Government dues and losses and damages whatsoever under such clauses or sub-clauses."
7. The above letter/notice issued by the Executive Engineer (E), SW Electrical Division, PWD captures the following aspects:
i. That the work contract shall stand terminated, and the security deposit and performance guarantee submitted by the Petitioner has been forfeited to the GNCTD.
ii. No claim to compensation for losses of the Petitioner would be entertained by the Respondent.
iii. That in terms of the work contract which has been executed, a joint measurement shall be conducted, and in terms thereof, further steps would be taken.
iv. The Petitioner shall not be allowed to participate in the tendering process for the balance work.
8. Further, a perusal of the modified clause 25 of the GCC 2020 shows that there is a possibility of conciliation by a Conciliator who can look into the matter. The said clause reads as under:
"Clause 25 Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the
specifications, design, drawings and instructions here- in before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter.
(i) If the contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record or decision given in writing by the Engineer-in-Charge or if the Engineer in Charge considers any act or decision of the contractor on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable and is disputed, such party shall promptly within 15 days of the arising of the disputes request the Chief Engineer/ CPM, or Where there is no Chief Engineer/CPM, the Additional Director General/Special Director General (CE/ADG/SDG) who shall refer the disputes to Dispute Redressal Committee (DRC) within 15 days along with a list of disputes with amounts claimed if any in respect of each such dispute. The Dispute Redressal Committee (DRC) give its decision within a period of 60 days extendable by 30 days by consent of both the parties from the receipt of reference from CE/CP/ADG/SDG. The constitution of Dispute Redressal Committee (DRC) shall be as indicated in Schedule 'F'.
Provided that no party shall be represented before the Dispute Redressal Committee by an advocate/legal counsel etc.
The DRC will submit its decision to the concerned ADG/SD for acceptance. ADG/SDG in a time limit of 30 days from receipt of DR decision will convey acceptance or otherwise on the said decision if the Dispute Redressal Committee (DRC) fails to give its decision within the aforesaid period or the ADG/SDG fails to give his acceptance in the aforesaid time limit or any party is dissatisfied with the decision of Dispute Redressal Committee (DRC) ADG/ SDG theneither party may within a period of 30 days from the receipt of the decision of Dispute Redressal Committee (DRC), ADG/ SD or on expiry of aforesaid the time limits available to DRC/ ADG/SDG may give notice to the Chief Engineer/CPM, CPWD, in charge of the work or if there be no Chief Engineer/ CPM, the Additional Director General /Special Director General of the concerned region of CPWD or if there be no Additional Director General/ Special Director General, the Director General, CPWD for appointment of arbitrator on prescribed proforma as per Appendix XVII under intimation to the other party.
It is a term of contract that each party invoking arbitration must exhaust the aforesaid mechanism of settlement of claims/disputes prior to invoking arbitration.
The CE/CPM/ADG/ SDG shall in such case appoint the sole arbitrator or one of the three arbitrators as the case may be within 30 days of receipt of such a request and refer such disputes to arbitration. Wherever the Arbitral Tribunal consists of three Arbitrators, the contractor shall appoint one arbitrator within 30 days of making request for arbitration or of receipt of request by Engineer-in-charge to CE/ADG/ SDG /DG for
appointment of arbitrator, as the case may be, and two appointed arbitrators shall appoint the third arbitrator who shall act as the Presiding Arbitrator.
In the event of
(a) A party fails to appoint the second Arbitrator, or
(b)The two appointed Arbitrators fail to appoint the Presiding Arbitrator, then the Director General, CPWD shall appoint the second or Presiding Arbitrator as the case may be.
(ii) Disputes or difference shall be referred for adjudication through arbitration by a Tribunal having sole arbitrator where claimed amount is Rs. 20 Crore or less. Where claimed Value is more than Rs. 20 Crore, tribunal shall consist of three Arbitrators as above. The requirements of the Arbitration and Conciliation Act, 1996 (26 of 1996) and any further statutory modification or re-enactment thereof and the rules made there under and for the time being in force shall be applicable.
It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed, if any, in respect of each such dispute along with the notice to appointment of arbitrator and giving reference to the decision of the ADG/ SDG on the finding / recommendation of DRC.
It is also a term of this contract that member(s) of the Arbitration Tribunal shall be Graduate Engineer with experience in handling public works engineering contracts, are further he shall have earlier worked at a level not lower than Chief Engineer equivalent (i.e. Joint Secretary level of Government of India). This shall be treated as a mandatory qualification to be appointed as arbitrator.
Parties, before or at the time of appointment of Arbitral Tribunal may agree in writing for fast track arbitration as per the Arbitration and Conciliation Act, 1996 (26 of 1996) as amended in 2015.
Subject to provision in the Arbitration and Conciliation Act, 1996 (26 of 1996) as amended in 2015 whereby the counter claims if any can be directly filed before the arbitrator without any requirement of reference by the appointing authority. The arbitrator shall adjudicate on only such disputes as are referred to him by the appointing authority and give separate award against each dispute and claim referred to him and in all cases where the total amount of the claims by any party exceeds Rs. 1,00,000/-, the arbitrator shall give reasons for the award.
It is also a term of the contract that fees payable to arbitral tribunal shall be as approves by DG, CPWD, OM issued vide no. 2/2006/SE(TLC)/CSQ/137 dated 19-11-2019 (or its latest amendment as approved by DG, CPWD). This fee shall be shared equally by parties.
The place of arbitration shall be as mentioned in Schedule F. In case there is no mention of place of arbitration, the arbitral tribunal shall determine the place of arbitration.
The venue of the arbitration shall be such place as may be fixed by the Arbitral Tribunal in consultation with both the parties. Failing any such agreement then the Arbitral Tribunal shall decide the venue."
9. The clause as extracted above, also contemplates arbitration in case conciliation fails. From the submissions made by the parties today, it is clear that the joint measurement is currently going on, thus, for the work executed, the Petitioner would be entitled for payment. Insofar as the forfeiture of performance guarantee and security deposit is concerned, unless and until the Respondent finds that there has been complete breach by
the Petitioner, the same ought to await the outcome of conciliation. Moreover, the said forfeiture can be effected only in terms of the contract between the parties.
10. Let the matter including the above mentioned three aspects be considered by the Conciliator, and payment concerning the admitted amounts which are due and payable, be made to the Petitioner by Respondent-PWD, GNCTD. If there are any outstanding dues of the Petitioner, initially conciliation shall be explored and if the same fails, arbitration, as per the GCC 2020 shall be resorted to. If there are any outstanding RA bills, the Conciliator shall look into the same and the payments shall be released.
11. Let the Petitioner appear before the Conciliator-Principal Chief Engineer (Maintenance and Flyover) on 17th April, 2023 at 11:00 a.m.
12. With these observations, the present petition, along with all pending applications are disposed of.
PRATHIBA M. SINGH, J.
MARCH 28, 2023 dj/dn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!