Citation : 2022 Latest Caselaw 1843 Del
Judgement Date : 3 June, 2022
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: June 03, 2022
+ O.M.P.(I) (COMM.) 173/2022, I.A. 8902/2022
M/S HFCL LIMITED ..... Petitioner
Through: Mr. Bishwajit Bhattacharya, Sr. Adv.
with Mr. Zeeshan Hashmi and Mr.
Salman Hashmi, Advs.
versus
M/S TELECOMMUNICATIONS
CONSULTANTS INDIA LTD. ..... Respondent
Through: Mr. Nikhilesh Krishnan and Mr. Jai
Pratap, Advs.
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
V. KAMESWAR RAO, J. (ORAL)
1. The petition has been filed under Section 9 of the Arbitration and Conciliation Act, 1966, inter alia seeking an ex-parte ad interim stay on tenders dated May 10, 2022, bearing nos. TCIL Tender No. - TCIL/4110008/I/22-DEF/01E, TCIL Tender No.- TCIL/41/0009/I/22- DEF/02E, TCIL Tender No.- TCIL/41/0010/I/22-DEF/03E, Tender No. - TCIL/4110011/I/22-DEF/04E, all for the state of Uttar Pradesh, as the scope of work of the impugned tenders is already within the scope of work to be performed by the petitioner under the BSNL Tender dated June 21, 2013 and Memorandum of Understanding („MOU‟, for short) dated January 30, 2014 between Telecommunications Consultants India Ltd. („TCIL‟ and the respondent herein) and Himachal Futuristic Communications Ltd. (HFCL Ltd.‟ and the petitioner herein) dated
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 1 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 January 30, 2014 read with first addendum dated September 18, 2014, BSNL Purchase Order („PO‟, for short) No. CT/P0/04/2014-15 dated September 09, 2014 ("BSNL PO"), TCIL PO No. TCIL/15/1612/1114 MM/58P dated September 19, 2014 along with its all amendments and TCIL PO No. TCIL/16/1611/I/14- MM/57P dated September 19, 2014.
2. It is the case of the petitioner and so contended by Mr. Bishwajit Bhattacharya, Ld. Sr. Counsel that BSNL published a tender bearing Tender No.-CA/CNP/NFS OFC/T- 44112013 on June 21, 2013 for procurement, supply, trenching, laying, installation, testing and maintenance of Optical Fibre Cable, PLB Duct and accessories for construction of exclusive optical NLD backbone and Optical Access Routes on Turnkey Basis For Defence Networks. A bidder could bid for one or more packages wherein each package comprises of different sets of States/UT's. The petitioner and respondent herein bid for „Package C‟, comprising of Uttar Pradesh, Rajasthan and Uttarakhand. They entered into a „Teaming Agreement‟ dated August 19, 2013, to submit a bid for Package C of the BSNL Tender. According to him, the said Teaming Agreement contained an exclusivity clause being Clause 2, which barred either party from entering into any agreement of similar nature with any third party for the bid package.
3. The petitioner and respondent entered into an MOU dated January 30, 2014 (as amended vide the first amendment dated September 18, 2014), for the purpose of bidding for the BSNL tender and to put down the terms of their relationship. The MOU delineated individual scope of work of both the parties and chalked out the responsibilities in
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 2 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 their scope of work. Specifically, Clause 7.4 of the MOU states as under:-
"AMC will be done by the respective parties related to their scope of work. However, TCIL will get 4% on the sale value of HFCL 's AMC portion of work towards the expenditure incurred on Manpower and other services." Clause 25 .1.1 0 of the BSNL Tender states "Undertaking duly signed by Lead bidder and its partner stating that both of them, shall be liable for due performance of the contract jointly and severally, shall be submitted after declaration of L1 bidder as given at Clause 13.6 and 13.7 above.".
4. It is stated that a reading of Clause 1.2 and 7.3 of the MOU and Clause 13.7 and 25.1.10 of the BSNL tender shows that the petitioner is OFC manufacturer alongwith the respondent as they are individually and independently responsible for their scope of work and also jointly and severally liable towards BSNL for the execution of the project.
5. Further, it is stated that Clause 4.3 of the MOU provides that the Annual Maintenance Contract („AMC‟) is within the scope of work of the petitioner. It states "The sole responsibility of supply of SOR material during the execution of the project shall be of HFCL. HFCL shall be entirely responsible for supply, warranty, AMC, Payments and all other terms mentioned in the teaming agreement with the other OEMs ". It is the case of the petitioner that Clause 3 of the MOU bars the respondent from entering into any agreement of similar nature with any third party with respect to Package C. Therefore, the impugned tenders are in breach
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 3 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 of the MOU, because the services being sought to be procured under the impugned tenders are the same as the services currently being provided by the petitioner and covered by the MOU.
6. He stated that the BSNL Tender also contains several clauses whereby it can be ascertained that the work for maintenance and preventive correction to be done under the AMC was part and parcel of the main tender and has to be performed by the petitioner after expiry of the warranty period. Clauses 47, 83.2, 154, 186.11.14, 189, 197 and 207 support the aforesaid fact. It is stated that the petitioner took into consideration the aforesaid clauses and the fact that AMC services will be performed by the petitioner, and fixed the cost of its products for submission of the bid while making its decision of partnering with TCIL to bid for the project.
7. Thereafter, BSNL issued a PO dated September 09, 2014 to the respondent as the contractor and the petitioner as the Teaming Agreement Partner. The said PO was issued in furtherance of the BSNL tender. Clause 32 of the PO reads as under:-
"Annual maintenance Contract:
(i) After commissioning and handing over of the network to PICG by BSNL, PICG will sign the Agreement for AMC with the successful lead suppliers as per the terms contained in section 4 and other relevant clauses of the tender. (i) the purchaser also reserves the right to blacklist the bidder in case the vendor fails to honour the AMC commitment after expiry of the warranty period"
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 4 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56
8. Subsequently, the respondent issued POs dated September 19, 2014 in favour of the petitioner for procurement of services pursuant to the issuance of the BSNL PO. He stated, the MOU has been referred to in the POs and forms a part of the TCIL POs. The petitioner performed its obligations under the agreements without demur and provided its services as per its scope of work. As per Clause 89 of the Tender and Clause 17 of the PO, the bidder had to provide warranty for 3 years for materials supplied. After completion of the warranty period, the petitioner started providing operation and maintenance services under the AMC clauses as provided for in the MOU and the Tender.
9. He stated, on January 31, 2020, the petitioner wrote a letter to the respondent informing it of its obligation to issue a PO for AMC so that the petitioner continue maintaining the network as per agreed terms. In reply, the respondent, vide letter dated February 06, affirmed its obligation of issuing PO for post warranty AMC services on back-to- back basis, upon receipt of corresponding PO from the Project Implementation Core Group in favour of the respondent. On December 31, 2020, the respondent sent a letter to the petitioner stating that they have received consent letter dated December 11, 2020 from BSNL regarding AMC services in Package C. It further stated that the AMC agreement has been sought for from BSNL and will be communicated to the petitioner as soon as the respondent receives it. The consent letter received from BSNL provided for the period from October 01, 2020 till March 31, 2020. According to Mr. Bhattacharya, the aforesaid letter
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 5 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 affirms the fact that there was no dispute on the fact that the petitioner has the right to perform AMC services.
10. The petitioner sent a letter vide email dated May 20, 2021 stating "as discussed today, please find letter regarding AMC material required for maintenance." The said email bore the subject "Letter for AMC material" Subsequently, vide email dated May 24, 2021, which bore the subject "Letter for material to be arranged by PICG for preventive maintenance and fault rectification under AMC", the petitioner stated as under:-
"this has with reference to trailing mail on dated 20th May regarding immediate support for material to be arranged by P ICG for preventive maintenance and fault rectification under AMC. Request your immediate support in this matter. "
11. He stated, the petitioner sent reminders on May 31, 2021 and June 07, 2021 stating that the petitioner will not be responsible for any unforeseen incident caused because of the absence of material. Thereafter, on June 09, 2021 the respondent replied stating "as discussed please find enclosed copy of letter written to BSNL regarding the matter for your information and necessary action.". According to Mr. Bhattacharya, the respondents had sent letters dated June 09, 2021 and July 06, 2021 wherein they admitted that after cessation of the warranty period, AMC services have been provided by the petitioner. In the letter dated June 09, 2021, the respondent referred to two letters of BSNL dated February 23, 2021 and December 11, 2020 as „AMC Letters‟. However the petitioner was not provided with a copy of these letters.
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 6
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:03.06.2022
20:34:56
12. The petitioner started providing AMC services from February 2020. It has provided the said services ever since, under the assurance of the respondent that money for such services will be paid immediately upon execution of the AMC with BSNL.
13. Thereafter, BSNL shared the AMC agreement for the duration October 2020-March 2021 with the respondent for execution between them. As per the MOU and POs, a back-to-back agreement needs to be executed between the petitioner and the respondent for AMC services to enable the petitioner to raise invoices for the work already done. It is the case of the petitioner that the respondent breaches the MOU by not executing back-to-back AMC/PO with the petitioner.
14. Mr. Bhattacharya further stated that the petitioner vide its letters bearing No. HFCL/Kanchan/HQ/2232 dated February 8, 2022 and bearing No. HFCL/Kanchan/HQ/2295 dated April 18, 2022 has raised concerns regarding rising dues for AMC services and execution of AMC, but the respondent did not respond to the said letters, either positively or negatively. It is stated that approx. ₹50 crore is due towards AMC services already provided.
15. He stated, the respondent issued the impugned tenders on May 10, 2022 with the date of opening of Technical bid as June 01, 2022 and the date for opening of financial bid to be notified later. He stated, the said tenders have been issued without affording an opportunity to be heard to the petitioner and without any fault or deficiency on the part of the petitioner. It is also stated that as on the date of issuance of the
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 7 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 impugned tenders, BSNL had imposed damages because of the fault in provision of services by the respondent.
16. He stated, the impugned tenders have been issued for providing maintenance services during AMC period for OFC based NLD and access links across the state of Uttar Pradesh. The impugned tenders clearly state that they have been issued under the BSNL Tender; however the petitioner is already providing AMC services under the said tender and is entitled under the BSNL Tender to provide the said services for the entire duration of 7 years. In protest, the petitioner sent a letter dated May 20, 2022 to the respondent and called upon them to cancel and withdraw the impugned tenders and execute the AMC.
17. In substance, the submission of Mr. Bhattacharya is that:-
(i) A valuable right to perform the AMC services had already accrued in favour of the petitioner and the respondent has acknowledged that right several times and assured the petitioner that it will abide by the terms of the agreements between them. The impugned tenders are in complete breach of the terms of the MOU and defeat the vested right in favour of the petitioner. Apart from the terms of the MOU, the respondent has recognised the petitioner‟s right for performing AMC services on several occasions.
(ii) The MOU provides for back-to-back obligations between the parties. The aforesaid obligation is not only with respect to
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 8 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 AMC services but in respect of each and every right and obligation.
(iii) Clause 5.1 of the MOU states that terms of payment and financial guarantees between the parties shall be on back-to-back basis. Clause 5.3 states the raising of invoices and the payment of such invoices is also on back-to-back basis and that payments received by the respondent from BSNL shall be released in favour of the petitioner on back-to-back basis. Clause 13.7 provides for a joint team for following-up and ensuring expeditious release of payment against invoices submitted to BSNL by the respondent.
(iv) The action of the respondent in issuing the impugned tenders dated May 10, 2022 are illegal and in absolute breach of the MOU.
(v) The respondent cannot introduce a third party into the project.
(vi) The intent of BSNL in seeking the provision of AMC services from the OFC manufacturer is clear as the manufacturer of the supplied goods would be in the best position to maintain such goods as opposed to a third party.
(vii) While formulating the bid and fixing price for supplies, the petitioner had considered the fact that AMC services will also be provided by it for which it will be paid. Clause 83.2 of the BSNL Tender also provides that the AMC quoted by the bidder will be
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 9 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 taken into consideration while evaluation of the bid by BSNL. The respondent's act of unilaterally and arbitrarily denying the petitioner the benefit to which it is legally entitled to, is not only in gross violation of the MOU but is also illegal and causes irreparable damage to the petitioner.
(viii) The actions of the respondent are actuated by mala fide as it never asked the petitioner not to provide AMC services when it sent letters and emails wherein the petitioner clearly stated that it was providing AMC services for more than a year and sought its assistance in seeking materials. The intent of the respondent is to illegally deny the petitioner the dues for providing AMC services which are due from the respondent.
18. On the other hand, Mr. Nikhilesh Krishnan, learned counsel appearing for the respondent would justify issuance of the impugned tenders. He stated that the BSNL Tender is primarily related to procurement, supply, trenching, laying, installation, testing and maintenance of Optical Fibre Cable, PLB Duct and accessories for construction of exclusive Optical NLD backbone and Optical Access Routes on Turnkey Basis for Defence Networks.
19. It is his submission that it is an important work, which cannot be delayed. He states that the petitioner has not approached this Court with clean hands and has concealed from the Court, important documents, which will show the stand of the respondent herein. He stated, no doubt the MOU has been executed between the parties with regard to executing the work / tender of BSNL including AMC but Mr.Bhattacharya has
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 10 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 conveniently not referred to Clauses 8.3 and 8.4 of the MOU, which contemplates execution of separate agreement for AMC. He states that till date, no separate agreement for AMC has been executed because of the reasons attributable to the petitioner. In this regard, Mr. Krishnan states that the respondent had written to the petitioner with regard to the AMC agreement. The petitioner vide its letter dated March 18, 2021 had raised certain issues, which were not as per BSNL tender. In fact, the respondent had vide emails / letters dated May 13, 2021 and May 21, 2021 called upon the petitioner to give its consent for accepting the BSNL, AMC agreement without change.
20. Though the petitioner had written a letter dated September 02, 2021, there is another issue of rates for providing AMC, which has cropped up between the parties. According to him, the average price in Uttarakhand and Rajasthan is ₹2218/- per km whereas the rate of AMC of the petitioner in Uttar Pradesh is ₹4800/- per km, which is on a higher side, resulting in a difference of ₹75,91,08,000/- between the price of the petitioner and recently recorded price in Uttarakhand and Rajasthan. He states that Clauses 8.3 and 8.4 contemplates that the parties shall execute an agreement, which means that if it is on mutually agreed terms, an agreement can be executed. He also states that till date, no agreement with regard to AMC has been executed by the respondent with the petitioner for the work in Uttar Pradesh. Hence, TCIL is not liable to pay the petitioner. It is only for the purpose of AMC that the tenders have been issued. He also states that the petitioner is within its right to apply against the tenders. He, on instructions, also states that if the petitioner
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 11 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 meets the rate of ₹2218/- per km, the grant of tender for AMC could be considered by TCIL / respondent.
21. That apart, it is his submission that the scope of judicial review under Section 9 of the Arbitration and Conciliation Act, 1996 is very limited. That apart, it is a discretionary relief and it is not necessary that every relief, which has been prayed for, needs to be granted.
22. That apart, he also states, in view of the provisions of the Specific Relief Act, more specifically Sections 14 (b), 41(e) and 41(h), the Court cannot interdict an ongoing infrastructure project, which is ultimately for a larger public interest. In this regard, he has referred to the judgment of a Coordinate Bench of this Court in the case of West Haryana Highways Projects Private Limited v. National Highways Authority of India and Ors., 2020 (272) DLT 446. He also relied upon the judgment of the Supreme Court in the case of M/s N.G. Projects Limited v. M/s Vinod Kumar Jain & Ors. 2022 AIR (SC) 1531.
23. Having heard the learned counsel for the parties, the issue which arises for consideration is, whether the petitioner is entitled to the relief as prayed for in the present petition. In substance, the relief sought by the petitioner is a restraint order against the respondent from proceeding ahead with the tenders issued on May 10, 2022. There is no dispute that an MOU has been executed between the parties with regard to the work referred to above, to be awarded by the BSNL. The work includes procurement, supply, trenching, laying, installation, testing and maintenance of Optical Fibre Cable, PLB Duct and accessories for construction of exclusive Optical NLD backbone and Optical Access
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 12 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 Routes on Turnkey Basis for Defence Networks and also the warranty thereof and including AMC subsequent to the warranty period. The Clauses referred to by Mr.Bhattacharya are primarily Clauses 1.2, 4.3 and 7.3 of the MOU, which I reproduce as under:-
"1.2 Whereas the Parties agree that as between themselves, each party shall be individually responsible for employing capital and resources in executing the individual Scope of Work and as a corollary be independently responsible with respect to the commercial risks associated with non-performance or negligence / or breach relating to individual Scope of Work, in accordance with the Project terms and conditions.
xxx xxx xxx
4.3 The sole responsibility of supply of SOR material
during the execution of project shall be of HFCL. HFCL shall be entirely responsible for supply, warranty, AMC, Payments and all other terms mentioned in the teaming agreement with other OEMs.
xxx xxx xxx
7.3 The Parties shall undertake joint and several
liabilities to the BSNL for the execution of the Project in respect of their obligations to the BSNL pursuant to the Project. However, irrespective of joint and several liabilities agreed between the Parties towards the BSNL, each of them expressly agrees to bear its own losses and retain profits arising from the performance of their respective work split as per Annexure I."
24. The Clauses as referred to by Mr. Bhattacharya, no doubt do contemplate that the petitioner shall have the responsibility for supply, warranty, AMC etc., but at the same time Clauses 8.3 and 8.4, of the MOU, which have been referred to by Mr.Krishnan and reproduced as
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 13 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 under, also contemplate that for the purpose of AMC, there shall be a separate agreement to be executed between the parties and concedingly no agreement has been executed between the parties till date. In the absence of any agreement between the parties, it is prima facie doubtful, whether the petitioner can claim AMC as a matter of right.
"8.3 The expiration of 36 calendar months from the Effective Date or till the successful completion of the project and warranty obligations whichever is later and period fo maintenance (AMC) for which Parties shall sign an independent Agreement.
8.4 On signing of alternate agreement, if mutually agreed between the Parties."
25. The plea of Mr.Krishnan is primarily that the petitioner had raised certain issues with regard to the BSNL agreement. That apart, it raised an issue of rates, which have been awarded by the petitioner for providing AMC, which according to Mr. Krishnan is on a higher side, as compared to the rates of Uttarakhand and Rajasthan, which is not acceptable to the respondent. On this, Mr. Bhattacharya has submitted that these rates were offered to TCIL at the time when TCIL had bid for the BSNL Tender.
26. Going by the submissions made by learned counsel for the parties, it is clear that as per Clauses 8.3 and 8.4 of the MOU, for the purpose of AMC, there has to be a separate agreement executed between the parties. Concedingly, the parties have not entered into an agreement with regard to AMC.
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 14
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:03.06.2022
20:34:56
27. A plea was taken by Mr. Bhattacharya that AMC is being carried out by the petitioner. The said plea has been contested by Mr.Krishnan by stating that no such work for Uttar Pradesh has been awarded to the petitioner. This Court is of the view, albeit prima facie, that the submission made by Mr. Krishnan based on Clauses 8.3 and 8.4 of the MOU is appealing. Till such time an agreement is executed between the parties, the petitioner cannot claim the work of AMC in Uttar Pradesh. Hence, the prayer as sought for by the petitioner cannot be granted. In other words, it shall amount to this Court directing the parties to enter into an agreement, even though the terms are not mutually agreeable. Such a direction cannot be given.
28. Mr. Krishnan is justified in relying upon the judgment in the case of West Haryana Highways Projects Private Limited (supra), wherein this Curt had considered the provisions of the Specific Relief Act, 1963, held as under:-
"46. On the other hand, I find merit in the contention of respondent no.1 that if the petitioner, notwithstanding the protestations of respondent no.1, were directed to carry out maintenance work, such a direction would undoubtedly involve an element of supervision from this Court, which is neither feasible nor permissible in the light of Sections 14(b) read with Section 41(e) of the Specific Relief Act. At this point, it is important to ask - then who shall carry out the repair and maintenance work under the Concession Agreement? The answer to this query lies in Article 17.9.1 of the Concession Agreement which vests respondent no.1 with the power to carry out remedial, operation and maintenance works on the project highway at the risk and cost of the petitioner, even during the subsistence of the agreement.
Evidently, the impugned NITs were issued by respondent
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 15 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 no.1 in pursuance of this power. Keeping in view the fact that there is a serious dispute between the parties regarding the quality of work rendered by the petitioner, any injunction granted upon these NITs could possibly impede or delay the repair and maintenance work on the highway as also have a direct impact on its safety and condition. For this reason, granting such an injunction, as rightly contended by respondent no.1, would fall foul of Section 20A of the Specific Relief Act and operate against public interest. Thus, keeping in view the fact that the NITs dated 17.04.2020 and 05.05.2020 issued by the respondent no.1 solely pertain to the execution of repair and maintenance works of the stretch of highway which comprise of the Delhi/Haryana border to Rohtak Section of NH- 10 from Km 29.700 to Km 87.000, I find no reason to restrain these NITs. For this reason, all the reliefs sought in the first petition as also the petitioner's prayer in the second petition seeking to restrain the respondent no.1 from issuing any notice/letter with regard to repair and maintenance, cannot be granted. However, it is made clear that this Court is not expressing any opinion on whether respondent no.1 is justified in issuing these NITs or whether the quality of petitioner's repair and maintenance work is adequate or not; these issues can only be determined in arbitration. Therefore, it would be open for the petitioner to agitate these issues in arbitration."
29. If the petitioner has any grievance with regard to the fact that it was entitled to the AMC work in Uttar Pradesh, surely the petitioner can seek such remedy as available in law in terms of the contract executed between the parties.
30. Insofar as the judgment in the case of M/s N.G. Projects Limited (supra) is concerned, the Supreme Court held as under:-
"23. In view of the above judgments of this Court, the Writ Court should refrain itself from imposing its decision over
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 16 Digitally Signed By:ASHEESH KUMAR YADAV Signing Date:03.06.2022 20:34:56 the decision of the employer as to whether or not to accept the bid of a tenderer. The Court does not have the expertise to examine the terms and conditions of the present day economic activities of the State and this limitation should be kept in view. Courts should be even more reluctant in interfering with contracts involving technical issues as there is a requirement of the necessary expertise to adjudicate upon such issues. The approach of the Court should be not to find fault with magnifying glass in its hands, rather the Court should examine as to whether the decision-making process is after complying with the procedure contemplated by the tender conditions. If the Court finds that there is total arbitrariness or that the tender has been granted in a malafide manner, still the Court should refrain from interfering in the grant of tender but instead relegate the parties to seek damages for the wrongful exclusion rather than to injunct the execution of the contract. The injunction or interference in the tender leads to additional costs on the State and is also against public interest. Therefore, the State and its citizens suffer twice, firstly by paying escalation costs and secondly, by being deprived of the infrastructure for which the present-day Governments are expected to work."
31. In view of my above discussion, I do not see that the petitioner has made out a case for granting the relief as prayed for in the petition. The petition is dismissed. No costs.
I.A. No. 8902/2022 (for stay) In view of my decision in the petition, this application has become infructuous. The same is dismissed as such.
V. KAMESWAR RAO, J
JUNE 03, 2022/ak
Signature Not Verified
OMP(I)(COMM) 173/2022 Page 17
Digitally Signed By:ASHEESH
KUMAR YADAV
Signing Date:03.06.2022
20:34:56
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!