Citation : 2022 Latest Caselaw 161 Del
Judgement Date : 17 January, 2022
$~2
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 17.01.2022
+ ARB.P. 1085/2021
SUBHASH CHANDER ..... Petitioner
Through Mr. Bhupesh Narula, Adv.
versus
DELHI DEVELOPMENT AUTHORITY ..... Respondent
Through Mr. Akshay Chandra, Advocate on
behalf of Ms. Shobhna Takiar,
Standing Counsel
CORAM:
HON'BLE MR. JUSTICE SURESH KUMAR KAIT
J U D G M E N T (oral)
1. The present petition has been filed under Section 11(6) of the
Arbitration and Conciliation Act, 1996 seeking appointment of sole
Arbitrator to adjudicate the disputes inter se the parties.
2. As per the averments made in the present petition, petitioner is a
construction contractor. Respondent had invited the tender for the work of
"D/o main land including 60 Mtr. & 45 Mtr. Master Plan road in Dwarka
project phase-II (D/o Sector-23B, 24, 25 & 26) Subhead: Providing and
laying peripheral sewer line sector-25 Dwarka Phase-II." The work was
awarded to the petitioner through acceptance letter No. F31(1695)EE/WD-
3/DDA/A/958 dated 09.11.2017 and agreement to the same effect was on
14.11.2017. Respondent is the custodian of the said agreement and as per the
contract, the stipulated dates of commencement and completion for the
above work were 19.11.2017 and 17.05.2018 respectively. However,
according to petitioner, the work could not be completed within the
stipulated time due to various hindrances on the part of the respondent, i.e.
non-availability of site and breaches of contact attributable to the
respondent. For these reasons, the work which was to be completed on
17.05.2018 was completed belatedly on 06.09.2018. Petitioner further
claims that the work was completed on 06.09.2018 to the satisfaction of the
respondent, which was duly accepted by respondent by issuing completion
certificate.
3. It was next submitted that the respondent had granted extension of
time to the petitioner but for the extended time period, no additional
compensation was given. Further, as per the agreement, petitioner was
required to submit final bill on or before 05.12.2018, however, respondent
made it impossible for the petitioner to submit the same by the due date as it
had completely failed to jointly record the final measurements in terms of
the agreement and also not provided the copies of sanctioned
extra/substituted and deviated items without which submission of final bill
was not possible. Learned counsel submitted that as per Clause 9 of the
agreement, respondent was to release the final payment to petitioner within
6 months after the completion of work i.e. on or before 05.03.2019 but the
same was not done. Thereafter, disputes arose between the parties. Since
Respondent was not releasing payments, the petitioner invoked arbitration
clause 25 of agreement and vide notice dated 31.07.2019 requested
respondent to appoint an arbitrator.
4. Thereafter, the Engineer in charge called upon the petitioner for a
meeting on 20.12.2019 and informed that he had prepared and passed the
final bill without disclosing the amount. However, he informed that the
amount of the bill was to the tune of 1.25 crore and showed his helplessness
to release the payment unless the petitioner withdraws the application for
appointment of Arbitrator. Subsequently, the petitioner agreed upon and
withdrew the said application. Thereafter, disputes again arose between the
parties and the petitioner once again invoked arbitration on 12.07.2021 and
referred the disputes to the Chief Engineer for adjudication, however, the
Chief Engineer failed to resolve the dispute within statutory period i.e. 30
days, provided under the arbitration clause of agreement. Petitioner further
on 16.08.2021 and 15.09.2021, requested the Engineer Member of the
respondent to appoint Arbitrator, which was not done. Hence, the petitioner
has filed the present petition.
5. During the course of hearing, learned counsel appearing on behalf of
respondent has disputed the averments made in the present petition,
however, submitted that the issues are triable and this Court may appoint an
Arbitrator to adjudicate the dispute between the parties subject to all issues
remain open before the learned Arbitrator.
6. Accordingly, Mr. Amar Nath, DHJS (Retd.) (Mobile: 9958697030)
is appointed sole Arbitrator to adjudicate the dispute between the parties.
7. The fee of the learned Arbitrator shall be governed by the Fourth
Schedule of the Arbitration and Conciliation Act, 1996.
8. The learned Arbitrator shall ensure compliance of Section 12 of
Arbitration and Conciliation Act, 1996 before commencing the arbitration.
9. The present petition stands disposed of accordingly.
10. A copy of this order be sent to the learned Arbitrator for information.
(SURESH KUMAR KAIT) JUDGE JANUARY 17, 2022/rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!