Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Amr-Bbb Consortium vs Bharat Coking Coal Ltd.
2022 Latest Caselaw 130 Del

Citation : 2022 Latest Caselaw 130 Del
Judgement Date : 13 January, 2022

Delhi High Court
Amr-Bbb Consortium vs Bharat Coking Coal Ltd. on 13 January, 2022
$~6
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                             Date of decision: 13.01.2022
+     ARB.P. 1247/2021
      AMR-BBB CONSORTIUM                                    ..... Petitioner
                          Through       Mr.Rajeeve Mehra, Sr. Adv. with
                                        Mr.Keshav Sehgal, Adv.

                          versus

      BHARAT COKING COAL LTD.               ..... Respondent
                  Through  Mr.Amit Sharma, Adv.

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                          J U D G M E N T (oral)

The hearing has been conducted through video conferencing.

1. The present petition has been filed under Section 11(6) read with

Section 10(2) of the Arbitration and Conciliation Act, 1996 seeking

appointment of sole Arbitrator to adjudicate the disputes inter se the parties.

2. Petitioner is a Consortium comprising of two companies i.e. AMR

India Limited, a company registered under the Companies Act, 1956 {AMR

Construction Limited} and Building Business Bridges UK Limited {BBB}

and the Consortium Agreement was entered into between AMR and BBB on

16.09.2011 and 12.12.2012 for participating in the tender process and

development, mining and extraction of the Kapuria Block. As per clause 5 &

6 of the agreement dated 16.09.2011, AMR was the lead partner of the

petitioner consortium.

3. According to the petitioner, respondent is a public sector undertaking

and a subsidiary of Coal India Limited and engaged in the business of

mining of cooking coal and operating the Jharia and Raniganj coalfields in

the State of Jharkhand and produces bulk of cooking coal mined in the

country.

4. As per the averments made in the present petition, vide letter of

acceptance dated 10.09.2011 by the respondent, petitioner was awarded to

undertake the work under Contract for the "Development of Kapuria Block

& extraction of coal by mass production technology package for a minimum

guaranteed production of 2.0 million ton per Year on turnkey basis'', for the

amount of Rs. 798.82 crores as capital cost for development phase-I, and Rs.

1427.25 crores as Revenue cost for phase-II. Accordingly, in terms of

Clause 4.1.l(xxxiii) of the Contract, the scope of Work included preparation

of a Detailed Project Report ("DPR") & EMP by the Petitioner for the

development and extraction of coal from the mine for commercial

production period of nine (9) years (APP). The Geological Reports were

provided by the respondent to the petitioner for preparation of DPR as per

scope of work and in return, petitioner prepared a comprehensive DPR and

submitted to the respondent for approval. The aforementioned DPR was

examined over a period of 8 months and communicated to the petitioner

vide letter dated 11.07.2013 with the directions to start the work as per this

approved DPR after getting the Environmental clearance and other statutory

approvals. Consequent to the approved DPR, petitioner furnished a

Performance Bank Guarantee ("PBG") equivalent to 1 % of the Contract

Value, in terms of Clause 4.1.4 of the Agreement dated 18.04.2012

amounting to Rs. 12,78,49,970/- drawn on Oriental Bank of Commerce;

prepared the Mining Plan for extraction of coal reserves; and conducted an

Environmental Impact Assessment and the Environmental Management Plan

and submitted to the respondents through various communications.

Moreover, the Petitioner sought approvals including but not limited to

mining plans, Environmental Clearance, shaft sinking plans and also

furnished Bank guarantees for import of Plant and Machinery, which are as

follows:

i. Bank Guarantee dated 25.09.2014 for Rs. 6,40,75,203/- issued by

ICICI bank

ii. Bank Guarantee dated 29.09.2014 for Rs. 20,00,00,000/- issued by

SBI Bank;

iii. Bank Guarantee dated 30.09.2014 for Rs. 14,79,00,000/- issued by

Bank of Baroda.

5. However, respondent failed to establish letters of credit in favour of

petitioner to import plant and machinery for the purpose of extraction of

coal and also failed to clear the payments under different invoices. Many

other disputes arose between the parties and in order to resolve the issues,

various communications took place between the parties, but those were of

no avail. Thereafter, petitioner vide letter dated 10.11.2020 invoked

arbitration in terms of clause 4.1.31.2 of the Contract.

6. Learned counsel further submits that petitioner approached

International Chambers of Commerce, Paris on 18.12.2020 to appoint an

arbitrator in accordance with the contract but the institution has also failed

to act in accordance with Clause 4.1.43 .2 of the Contract. ICC vide payment

request dated 02.09.2021 demanded to deposit $ 78,000 from all parties i.e.,

Petitioner as well as Respondent and the additional parties. Since there was

no compliance, therefore the ICC, on 14.09.2021 treated the claims as

withdrawn and eventually petitioner also withdrew its claims. However,

petitioner made another attempt to amicably resolve the disputes and called

upon the respondent to join in the appointment of Arbitrator by its letter

dated 29.09.2021, which was not responded to by the Respondent. Hence,

the present petition has been filed.

7. On the other hand learned counsel for respondent has opposed the

present petition submitting that petitioner- Consortium has deliberately and

mala fidely suppressed certain material and relevant facts from this Court.

Learned counsel has pointed out that the Notice dated 10.07.2020 for

cancellation of the Contract was sent to petitioner, as it had prepared DPR

based on limited data available and had not taken up additional exploration

work and rather granted 15 days' time to come up with its submissions,

failing which the contract shall be cancelled. In response to the aforesaid,

petitioner vide letter dated 23.07.2020, sought settlement of the disputes

through 'Conciliation'. Thereafter, vide communication dated 10.11.2020,

respondent asked the petitioner to submit specific disputes, questions,

differences upon which conciliation was intended. However, instead of

replying to said communication, petitioner invoked arbitration. According to

learned counsel for respondent, even after a chain of communications,

petitioner did not come forward for conciliation. In the meantime,

respondent was informed by the Secretariat of the International Court of

Arbitration of the International Chamber of Commerce (ICC) that on

18.12.2020 it had received a request from petitioner for arbitration.

However, due to default of payment to ICC International Court of

Arbitration by the petitioner despite repeated communications, ICC sought

the parties to pay the balance amount. However, again petitioner gained time

from ICC to make payment. Lately, respondent received a communication

dated 29.09.2021 from the petitioner wherein it was informed that petitioner

had withdrawn request for arbitration before the ICC and now, petitioner has

filed the present petition seeking appointment of Arbitrator. Learned counsel

submitted that having approached the ICC, petitioner has already exhausted

its arbitral remedy and therefore, the present petition deserves to be rejected.

8. On the asking of this Court, learned counsel for respondent fairly

submitted that disputes are arbitrable and it has no objection if this Court

appoints an Arbitrator.

9. In view of above, the present petition is allowed. Accordingly, Mr.

Justice (Retd.) T.S. Thakur, former Chief Justice of India (Mobile:

8800309969) is appointed sole Arbitrator to adjudicate the dispute between

the parties.

10. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration

The learned Arbitrator shall decide the fee after consulting with he parties.

11. The present petition stands disposed of accordingly.

12. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE JANUARY 13, 2022/ab

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter