Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vivaan Solar Pvt. Ltd. vs Northern Central Railways & Anr.
2021 Latest Caselaw 2459 Del

Citation : 2021 Latest Caselaw 2459 Del
Judgement Date : 9 September, 2021

Delhi High Court
Vivaan Solar Pvt. Ltd. vs Northern Central Railways & Anr. on 9 September, 2021
$~1
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                           Date of decision: 09.09.2021
+     ARB.P. 191/2021
      VIVAAN SOLAR PVT. LTD.                   ..... Petitioner
                   Through: Mr. Arun Doodawat, Advocate

                         Versus

      NORTHERN CENTRAL RAILWAYS & ANR. ..... Respondents
                  Through: Mr. Jagjit Singh, Senior Standing
                            Counsel, Mr. Preet Singh &
                            Mr. Vipin Chaudhary, Advocates
      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT
                  J U D G M E N T (oral)

The hearing has been conducted through video conferencing.

1. The present petition has been filed by petitioner seeking appointment

of a Sole Arbitrator under the provisions of Section 11(6) of the Arbitration

and Conciliation Act, 1996.

2. Petitioner, a private limited company, claims to have vast experience

in development of Solar Power Park, Roof Top Plants and in generation of

renewable source of energy in solar, having been registered under the Micro,

Small and Medium Entrepreneurs Department and claims to be entitled to all

the benefits and privileges available under the provisions of Micro, Small

and Medium Entrepreneurs Act 2006. Petitioner had submitted a bid with

respondents towards a tender bearing No. No. NR/SPV/RFP/01/2015 to

execute design, manufacture, supply, erection, testing and commissioning of

5 MWP of Solar Rooftop Project including operation and maintenance for a

period of 25 years at Railway Stations of Northern Railways under PPP

Model.

3. According to petitioner, vide letter dated 28.10.2016, respondents

awarded the work in question to petitioner, which was accepted by petitioner

vide letter dated 28.10.2016. A Power Purchase Agreement dated

16.11.2016 was entered into between the parties, wherein terms and

conditions of work ancillary thereto, were recorded. The petitioner had

concluded the work/project on 09.11.2017 and respondents after due

satisfaction had issued completion certificate on 22.11.2017.

4. It is further averred that during execution of the work, several

grievances were raised by petitioner, however, respondents failed to meet

out the same such like regular generation loss, providing security of the

equipment for rooftop solar plant, which was within the ambit of

respondents, which resulted in regular thefts and ultimately causing loss to

the petitioner and thereby, respondents failed to fulfil its part of contractual

obligations in terms mentioned in Article-19.1.4 of the Power Purchase

Agreement in question.

5. At the hearing, learned counsel for petitioner has submitted that

respondents has also failed to comply with the Article- -30.1 towards change

of law in GST; 15.1.7 towards repairs of the roof of the premises; 16.5

toward supply of electricity besides other over heads e.g. module removal;

shifting ACDB panel, cables and modules etc.

6. It is further averred in Para-21 of the petition that out of total CFAS

amount of Rs.5.6175 crores, an amount of Rs.5.37 crores have already been

paid by the respondents and amount of Rs.24,75,000/- is still unpaid towards

CFA to petitioner, which is claimed with 15% interest from respondents.

Petitioner has further claimed a termination payment of Rs.43,23,72,000/-

vide Notice dated 24.08.2020 with a further letter dated 17.09.2020 to Chief

Electrical General Engineer of the Northern Railways under the provisions

of Article-33.2 of the Power Purchase Agreement. However, no steps have

been taken by the respondents to resolve the grievances. Therefore,

petitioner has invoked Article-33.4 of the Power Purchase Agreement

invoking arbitration vide its communication dated 15.10.2020 and since no

reply was received thereto, petitioner has filed the present petition seeking

appointment of an Arbitrator to adjudicate the disputes between the parties.

7. On the contrary, the present petition is opposed by learned senior

standing counsel appearing on behalf of respondents, who submits that in

terms of Clause- 33.1 and 33.2 of the Power Purchase Agreement, the

disputes can be amicably resolved under the aegis of Railway Arbitrator

appointed by the General Manager and the petitioner without making an

attempt to resolve the dispute amicably and following the due procedure, has

approached this Court rather than fulfilling it's part of obligations.

8. Learned senior standing counsel for respondents further submits that

respondents have already made the payments as per tariff of the Power

Purchase Agreement in question. In addition, to submit that the appointment

of Arbitrator at the behest of respondent is as per law, reliance is placed

upon a decision of the Hon'ble Supreme Court in Central Organization for

Railway Electrification vs. M/s. ECI-SPIC-SMO-MCML (JV) A Joint

Venture Company 2020(14) SCC 712 wherein it has been held that

Railways has an expressed power to constitute the arbitral tribunal. Further

submits that in the case in hand, since the purported Notice dated 17.09.2020

has not been received by the respondents, they have a right to appoint the

Arbitrator.

9. The aforesaid submission of learned senior standing counsel for

respondents is refuted by learned counsel for petitioner who submits that the

decision in Central Organization for Railway Electrification (Supra) has

been referred to the Larger Bench and is thus, not applicable to the present

case.

10. This Court has heard learned counsel for the parties and has gone

through the petition and written submissions filed on behalf of both the sides

as well as decisions relied upon. During the course of hearing, learned senior

standing counsel appearing on behalf of respondents has not disputed

existence of the Power Purchase Agreement entered between the parties and

arbitration clause mentioned therein.

11. Further, the submission of learned senior standing counsel for

appearing on behalf of respondents that the respondents have a right to

appoint the Arbitrator does not stand, as the Hon'ble Supreme Court in

Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd. 2019 SCC

Online SC 1517 has categorically stated that "in cases where one party has

a right to appoint a sole arbitrator, its choice will always have an element of

exclusivity in determining or charting the course for dispute resolution.

Naturally, the person who has an interest in the outcome or decision of the

dispute must not have the power to appoint a sole arbitrator."

12. The afore-noted dictum of Hon'ble Supreme Court in Perkins

Eastman (Supra), has been followed by Coordinate Benches of this Court in

Proddatur Cable Tv Digi Services Vs. Siti Cable Network Limited 2020

SCC OnLine Del 350 and VSK Technologies Private Limited and Others

Vs. Delhi Jal Board 2021 SCC OnLine Del 3525 in unequivocal terms.

13. Concurring with the decisions as noted above, the present petition is

allowed.

14. Accordingly, Justice Ajit Prakash Shah, former Chief Justice of

Delhi High Court (Mobile: 9910160007) is appointed sole Arbitrator to

adjudicate the dispute between the parties. The arbitration shall be

conducted under the Delhi International Arbitration Centre (DIAC).

15. The fee of the Arbitrator shall be in accordance with the Schedule of

Fees prescribed under the Delhi International Arbitration Centre (DIAC)

(Administrative Cost and Arbitrators Fees) Rules, 2018.

16. A copy of this order be sent to the learned Arbitrator as well as Delhi

International Arbitration Centre (DIAC) for information.

17. With aforesaid directions, the present petition is accordingly disposed of.

(SURESH KUMAR KAIT) JUDGE SEPTEMBER 09, 2021/r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter