Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Montecarlo Limited vs Regal Emporia Infratech Pvt Ltd
2021 Latest Caselaw 2782 Del

Citation : 2021 Latest Caselaw 2782 Del
Judgement Date : 6 October, 2021

Delhi High Court
Montecarlo Limited vs Regal Emporia Infratech Pvt Ltd on 6 October, 2021
$~2
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                           Date of decision: 06.10.2021
+     ARB.P. 787/2021
      MONTECARLO LIMITED                                 ..... Petitioner
                         Through      Mr. Pratyush Prasanna, Adv.

                         versus

      REGAL EMPORIA INFRATECH PVT LTD        ..... Respondent
                  Through  Mr. Alok K. Aggarwal,
                           Ms. Anushruti and Mr. Raj Duggal,
                           Advs.

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                         J U D G M E N T (oral)

1. Petitioner- M/s Montecarlo Limited has preferred the present petition

under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking

appointment of Arbitrator to adjudicate the dispute with respondent.

2. According to petitioner, respondent- Regal Emporia Infratech Pvt Ltd,

registered under the Companies Act, 1956, had invited tender for erection,

construction, execution and completion of works relating to Civil &

Structural including but not limited to other services related to civil and

structure works from start to completion for a mix use project known as

"Regal Emporia" situated at Plot No. C-02, Sector-4, Greater Naida, Gautam

Budh Nagar and petitioner, having substantial experience in the civil work

and construction activities, approached respondent and showed interest in

various services to the respondent for the said project. Respondent vide

Letter of Intent dated 11.03.2015 awarded the said work to petitioner and so,

the parties entered into an agreement dated 07.04.2015. The execution of

work commenced on 10.04.2015, which was to be completed on 10.04.2018.

3. According to petitioner, it suffered various losses due to the lapses on

the part of respondent like delay in handing over of the drawings, delay in

receipt of free issue of materials, delay in payments etc. and also due to

situation beyond the control of the petitioner like Covid pandemic.

Therefore, vide e-mail dated 04.06.2020, petitioner sent an email to the

respondent seeking extension for completion of project which was granted

and the date of completion was extended to 05.04.2021. The petitioner vide

its letter dated 18.03.2021 claims to have submitted interim claim of

Rs.41,03,45,815.15/- to respondent due to prolongation of project upto

01.03.2021. Since respondent failed to reply to the aforesaid letter dated

18.03.2021 and make payment of interim claim, petitioner issued a notice of

dispute dated 30.03.2021 regarding the underutilized claim amounting to

Rs.41,03,45,815.15/- for a period of July 2016 till March 2021.

4. It is further averred in the petition that several joint discussions

between representative of both the sides to amicably resolve the disputes

took place like on 09.10.2020 and 28.01.2021, however, parties could not

resolve it. Therefore, in accordance with General Conditions of the Contract

as well as Clause- 21 of the Contract Agreement, petitioner vide Notice

dated 30.03.2021 referred the dispute to Managing Director of the

respondent. Once again vide letter dated 03.04.2021, petitioner sought

extension of time for completion of the project till 03.08.2021 citing reasons

for Force Majeure, however, respondent vide its letter dated 05.04.2021

refused to grant any further extension and also referred to Clause 20 (b) and

20 (c) of the Contract Agreement, which provides for termination of

Contract Agreement by giving 30 days' time in writing. Thereafter,

petitioner vide letter dated 13.04.2021 requested respondent to clear all dues

and reimburse the claims.

5. Petitioner further claims to have sent letter dated 26.06.2021

informing respondent of commencement of arbitration and proposed name

of a former Judge of Supreme Court of India as sole Arbitrator and sought

respondent's consent. In reply to the aforesaid, vide letter dated 01.07.2021

respondent declined to the proposed name of Arbitrator by the petitioner and

further, vide letter dated 28.07.2021 issued a letter to the petitioner

informing that it is under the process of selecting an Arbitrator.

6. The stand of petitioner is that since respondent is an interested party,

against which petitioner has raised claims, therefore, respondent has no right

to propose or appoint the Arbitrator. In support of aforesaid averment,

reliance is placed upon decision in Perkins Eastman Architects DPC v.

HSCC (India) Ltd. 2019 SCC Online SC 1517. Next, since respondent has

not yet proposed/nominated any name of Arbitrator pursuant to Clause -21

of the Contract Agreement, therefore, the present petition deserves to be

allowed.

7. At the hearing, learned counsel appearing on behalf of respondent

disputed the claims raised by the petitioner, however, very fairly conceded

that the disputes inter se parties can be resolved through arbitration and

prayed this Court that this Court may appoint sole Arbitrator.

8. This Court has heard the submissions advanced by both the sides.

9. Upon hearing, this Court finds that counsel representing both the sides

have not disputed existence of Contract Agreement dated 07.04.2015 and

also that there are disputes inter se parties, which could not since be

resolved through conciliation, therefore, are required to be resolved through

arbitration. Reliance placed by petitioner's counsel upon Hon'ble Supreme

Court's decision in Perkins Eastman (Supra) to submit that respondent has

vested rights and so, be not permitted to appoint its Arbitrator, does not

appeal to this Court, as in the said decision it has been categorically stated

that "in cases where one party has a right to appoint a sole arbitrator, its

choice will always have an element of exclusivity in determining or charting

the course for dispute resolution. Naturally, the person who has an interest

in the outcome or decision of the dispute must not have the power to appoint

a sole arbitrator." Therefore, though it does not meet the contention so

raised above by petitioner's counsel but is very well placed upon in the

present case. The afore-noted dictum of Hon'ble Supreme Court in Perkins

Eastman (Supra), has been followed by Coordinate Benches of this Court in

Proddatur Cable Tv Digi Services Vs. Siti Cable Network Limited 2020

SCC OnLine Del 350 and VSK Technologies Private Limited and Others

Vs. Delhi Jal Board 2021 SCC OnLine Del 3525 and also in various

decisions passed by this Court in unequivocal terms. Thus, concurring with

the decision in Perkins Eastman (Supra), the present petition is allowed.

10. Accordingly, Mr. Justice (retd.) A. Ramalingeswara Rao (Mobile:

8330969969 & 9391002170) is appointed sole Arbitrator to adjudicate the

disputes between the parties.

11. The fees of the learned Arbitrator shall be according to Fourth

Schedule of the Arbitration and Conciliation Act, 1996.

12. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

13. The present petition is accordingly disposed of.

14. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE OCTOBER 6, 2021 rk/r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter