Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Third Wave Services vs M/S Selene Constructions Limited ...
2021 Latest Caselaw 3174 Del

Citation : 2021 Latest Caselaw 3174 Del
Judgement Date : 23 November, 2021

Delhi High Court
M/S Third Wave Services vs M/S Selene Constructions Limited ... on 23 November, 2021
$~3(2021)
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                            Date of decision: 23.11.2021
+     ARB.P. 967/2021
      M/S THIRD WAVE SERVICES                ..... Petitioner
                   Through: Mr. Sandeep Sharma,
                            Mr.AmitChoudhary, Ms.Kanchan
                            Semwal & Mr.Gurjas S. Narula,
                            Advocates

                         Versus

      M/S SELENE CONSTRUCTIONS LIMITED & ANR.
                                               ..... Respondents
                    Through: Mr. Dhruv Mohan, Advocate for
                             respondent No.2

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                         J U D G M E N T (oral)

1. The present petition has been filed by petitioner seeking appointment

of a Sole Arbitrator under the provisions of Section 11(6) of the Arbitration

and Conciliation Act, 1996.

2. Petitioner, a private limited company, claims to be registered under

the Micro Small and Medium Enterprises Development (MSMED) Act,

2006, claims to be engaged in the diverse businesses pertaining to providing

permanent Civil, electrical and Mechanical infrastructure.

3. According to petitioner, respondent No.1 is a public limited company

engaged in real estate activities, who develops offices, housing, hotels and

othr industrial projects. Respondent No.2 is also engaged in real estate

development services.

4. Petitioner claims to have received a work order No. 3228105854

dated 12.07.2013 for work of internal electrical works of Building G1,2,3,

K1,2,3, B & EWS at Centrum Park, Phase-ll, Gurgaon from respondent

No.2 (as a sub-contractor) for a contractual amount of Rs.8,76,05,494.61/-,

which was later enhanced to Rs.9,16,24,074.35/-. It is further claimed that

the work was to commence on 01.07.2013 and the stipulated time for

completion of work was 12 months i.e. till 30.06.2014. However, due to late

handing over of site by respondent No.2, the work period had to be extended

time to time i.e. from 31.03.2016 till 31.03.2017. Also, the work order was

amended and enhanced on 07.06.2017 to Rs.9,33,18,103.05/.

5. At the hearing, learned counsel for petitioner has submitted that due to

implementation of the Goods and Services Tax Laws, the terms and

conditions of work had to be reassessed and revised vide post GSI Work

Order No. 0330110049 and under the amended contract, respondent No.1

became the employer and petitioner the contactor, instead of respondent

No.2. Further submits that owing to failure on the part of respondents in

adhering to the terms and conditions of the agreement, the work was delayed

and time ceased to be essence of the contract and therefore, work to the tune

of Rs.2,96,52,939.32, as against the awarded value of Rs.9,18,72,965.59,

could be executed by the petitioner.

6. It is further submitted by learned counsel that respondent vide its

email dated 22.03.2018, admitted the claim of petitioner, however,

respondent has agreed to pay only Rs.70,00,000/-, whereas in the

'completion certificate' issued by respondent No.1, the work executed by

petitioner has been mentioned as "good". It is also averred on behalf of

petitioner, that against the final bill dated 05.04.2019 amounting to

Rs.1,32,50,052.21, respondent No.1 approved amount of Rs.1,05,94,359.07

and out of the said amount too, amount of Rs.56,70,074.00 only was

released to petitioner till 14.02.2020 and out of the remaining amount of Rs.

49,24,285.07, further amount of Rs.11,83,311/ was released by respondent

No.1, leaving the balance amount of Rs. 37,40,974.07 still unpaid.

7. Petitioner claims to have sent various e-mails to the respondent No.1

for clearance of outstanding dues, however, upon failure to make the

payment, petitioner invoked arbitration vide notice dated 10.06.2021. In

response to the aforesaid notice dated 26.06.2021, respondent unilaterally

appointed its Arbitrator, which is impermissible in law and hence, the

present petition has been filed.

8. To the contrary, learned counsel appearing on behalf of respondents

has opposed the present petition while submitting that the claims raised by

the petitioner in the present petition are frivolous and this petition deserves

to be dismissed. However, learned counsel has not disputed invocation of

arbitration vide Notice dated 10.06.2021 and also that any dispute inter se

parties have to be resolved in terms of Clause-37(b) of the amended post

GST Work Order No. 330110049.

9. Upon hearing learned counsel appearing from both the sides this

Court finds that disputes between the parties are required to be adjudicated

by an Arbitrator in terms of Clause-37(b) of the amended post GST Work

Order No. 330110049. Vide notice dated 10.06.2021, petitioner has invoked

arbitration, however, respondent has gone ahead appointing Arbitrator of its

choice, which in the considered opinion of this Court cannot be permitted.

10. The Hon'ble Supreme Court's in Perkins Eastman Architects DPC &

Anr. vs. HSCC (India) Ltd. 2019 SCC Online SC 1517, has categorically

stated that no single party can be permitted to unilaterally appoint the

Arbitrator, as it would defeat the purpose of unbiased adjudication of

dispute between the parties. The aforesaid decision in Perkins (Supra) has

been followed by a Coordinate Bench of this Court in Proddatur Cable TV

Digi Services Vs. Citi Cable Network Limited: (2020) 267 DLT 51. Thus,

the Arbitrator either has to be appointed with the consensus of the parties or

by this Court.

11. Concurring with the decisions as noted above, the present petition is

allowed. Accordingly, Ms. Madhrima Panwar Mridul, Advocate (Mobile

9810175151) is appointed sole Arbitrator to adjudicate the dispute between

the parties.

12. The fee of the learned Arbitrator shall be governed by the Fourth

Schedule of the Arbitration and Conciliation Act, 1996.

13. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

14. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE NOVEMBER 23, 2021 r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter